Hardware
Hardware
List of software
No Software Description
1 Microsoft window Windows server 2008R2
server
2 Pc(client ) OS Windows 10 pro
3 Database software SQL server 2008 R2
4 Design software Microsoft Visio 2007
5 Office package Microsoft office 2013
6 Cable (network media ) Fiber optic
7 Browser software Chrome, Mozilla Firefox….
8 Email software Email exchange
9 Utility software Kaspersky antivirus
10 Driver software Snappy 209
11 UPS 3000v
]
No Phases Activities to be performed Duration Required man Responsible body
power
1 Planning Prepare work plan 1 week 2 Project manager
Allocate budget Network technician
Identify required infrastructure and
determine human recourse
2 Identify hardware 1 week 1 Network technician
required Soft ware
Other technical equipments
3 Design Visit building site and select 2 weeks 4 Project manager
appropriate network topology Network technician
Select install design tool & network Network admin
topology and Design network model DBA admin
Design physical logical Diagram
4 Network Install network medias (Cabling) 3 week 3 Network admin
installation Configure or install hardware and Network technician
and device software requirements routers, Database admin
configuration firewalls, switches etc.
Configure all servers and each network
devices
Configure security required
5 testing Test server and client and security 1 week 3 Network admin
Test network medias (cables) and Network technician
devices Database admin
Check band width
6 Maintenance Troubleshoot network problem 1 week Network admin
Troubleshoot hardware and software Network technician
Database admin
7 Documenting Prepare troubleshooting document 1 week Network admin
& Prepare presentation for acceptance Network technician
Presentation Staff training Database admin
Implementation plan
No Phase and activity Phase and activity
Month 1 Month 2 Month 3
W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4
1 Planning
2 Identify required
3 Design
4 Network installation and device configuration
5 testing
6 Maintenance
7 Documenting & Presentation
Conclusion
The project is to be successfully completed with agreed time frame or deadline needs high and
efforts and right project management skill. This network implementation project for Textile
company has been implementing the last 4 months according to our agreement as well as plan.
Now it is operational and the users must able share resources and access internet using newly
deployed network based on your organizational policy and guideline established. At the end, we
should like to request you to approve and accept finalization the project after evaluating current
status as to fully covered the remaining budget
Hardware cost =
Software cost =
Labor cost =
Internet connectivity =
Estimated total cost of the project =