C7 - Production Scheduling

The document discusses production scheduling concepts including objectives, shop floor control, loading, sequencing, and sequencing rules. It describes loading as assigning work to limited resources. Sequencing prioritizes jobs assigned to a resource. Common sequencing rules discussed include first-come, first-served, earliest due date, minimum slack, shortest processing time, and critical ratio. Examples demonstrate applying these rules to scheduling jobs through a single process.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
129 views69 pages

C7 - Production Scheduling

The document discusses production scheduling concepts including objectives, shop floor control, loading, sequencing, and sequencing rules. It describes loading as assigning work to limited resources. Sequencing prioritizes jobs assigned to a resource. Common sequencing rules discussed include first-come, first-served, earliest due date, minimum slack, shortest processing time, and critical ratio. Examples demonstrate applying these rules to scheduling jobs through a single process.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 69

OPERATION MANAGEMENT

C7. Production Scheduling


Instructor: MBA. Nguyen Danh Ha Thai. Email: [email protected]
Office: A1-307 Zalo: 0906 613 813

1
[email protected]
LO

o Objectives in Scheduling Loading


o Sequencing
o Monitoring
o Advanced Planning and Scheduling Systems
o Theory of Constraints Employee Scheduling

2
[email protected]
Definition

Scheduling: the last stage of planning before production.

The scheduling function differs considerably based on the type


of operation:
• Process Industries (Sx theo quy trình)
• Mass production (Sx hàng loạt)
• Projects (Pert/CPM)
• Batch / Job shop production (MRP)

3
[email protected]
7.1. Objectives in scheduling
• Meeting customer due dates;
• Minimizing job lateness;
Managers have
• Minimizing response time;
multiple, conflicting
• Minimizing completion time;
scheduling
• Minimizing time in the system;
objectives.
• Minimizing overtime;
• Maximizing machine or labor utilization;
• Minimizing idle time; and
• Minimizing work-in-process inventory.

4
[email protected]
7.2. Shop floor control (SFC)
Shop floor control (SFC):
the scheduling and monitoring of day-to-day production in a job shop. It is usually
performed by the production control department.

1.Loading—checking the availability of material, machines, and labor. Production control


assigns work to individual workers or machines, and then attempts to smooth out the
load to make the MRP schedule “doable.” Smoothing the load is called load leveling.
2.Sequencing—releasing work orders to the shop and issuing dispatch lists for individual
machines. The dispatch list contains the sequence in which jobs should be processed.
This sequence is often based on certain sequencing rules.
3.Monitoring—maintaining progress reports on each job until it is completed.

5
[email protected]
Loading

Loading:
the process of assigning
work to limited resources.

6
[email protected]
7.3. THE ASSIGNMENT METHOD OF LOADING

The assignment method is a specialized


linear programming solution procedure for
deciding which worker to assign to a task, or
which job to assign to a machine.

7
[email protected]
7.3. THE ASSIGNMENT METHOD OF LOADING
The procedure for a minimization problem is outlined as follows:
1. Perform row reductions by subtracting the minimum value in each row from all other row
values.
2. Perform column reductions by subtracting the minimum value in each column from all
other column values.
3. The resulting table is an opportunity cost matrix. Cross out all zeros in the matrix using the
minimum number of horizontal or vertical lines.
4. If the number of lines equals the number of rows in the matrix, an optimal solution has
been reached and assignments can be made where the zeros appear. Otherwise, modify the
matrix by subtracting the minimum uncrossed value from all other uncrossed values and
adding this same amount to all cells where two lines intersect. All other values in the matrix
remain unchanged.
5. Repeat steps 3 and 4 until an optimal solution is reached.
8
[email protected]
Example
WebStar, Inc. has four Web projects to complete and four workers with varying degrees of
expertise in Web development for particular industries. Estimates of processing times (in
hours) for each project by each worker are shown below. Development time costs an average
of $100 an hour. Assign each worker to a project so that cost is minimized.

9
[email protected]
Example

10
[email protected]
Example

11
[email protected]
Example

12
[email protected]
Example - Excel Solver

File Excel 7.1 13


[email protected]
7.4. SEQUENCING
Sequencing:
prioritizes jobs that have been assigned to a resource.

14
[email protected]
7.4.1.
Operation SEQUENCING
Management JOBS THROUGH
ONE PROCESSES

153
[email protected]
7.4.1. SEQUENCING JOBS THROUGH ONE PROCESS

FCFS - LCFS - EDD - LPT - SPT – Slack - CR (Smallest


Critical Ratio)

16
[email protected]
7.4.1. SEQUENCING JOBS THROUGH ONE PROCESS

The simplest sequencing problem consists of a queue of jobs at one machine or process.
No new jobs arrive to the machine during the analysis, processing times and due dates are
fixed, and setup time is considered negligible.

For this scenario:


Flow time:
the time it takes a job to flow through the system.
Makespan:
the time it takes for a group of jobs to be completed.
Tardiness:
the difference between the late job’s due date and its completion time.

17
[email protected]
7.4.1. SEQUENCING JOBS THROUGH ONE PROCESS

Because of the approaching holiday season, Joe Palotty is scheduled to work seven days
a week for the next two months. October’s work for Joe consists of five jobs, A, B, C, D,
and E. Job A takes five days to complete and is due on day 10, job B takes ten days to
complete and is due on day 15, job C takes two days to process and is due on day 5, job
D takes eight days to process and is due on day 12, and job E, which takes six days to
process, is due on day 8.
There are 120 possible sequences for the five jobs. Clearly, enumeration is impossible.
Let’s try some simple sequencing rules. Sequence the jobs by (a) first-come, first-served
(FCFS), (b) earliest due date (DDATE - EDD), (c) minimum slack (SLACK), and (d)
shortest processing time (SPT).
Determine the completion time and tardiness of each job under each sequencing rule.
Should Joe process his work as is—first-come, first-served? If not, what sequencing rule
would you recommend to Joe?

18
[email protected]
FCFS

Flow time (Dòng thời gian)

19
[email protected]
EDD - DDATE

20
[email protected]
SLACK
SLACK = (due date – today’s date) – processing time

21
[email protected]
SLACK

22
[email protected]
SPT

23
[email protected]
Summary

24
[email protected]
CR
CR (Smallest Critical Ratio)

25
[email protected]
CR

The product scheduling of VinFast in 25/11/2020

Task Due day Remaining processing time


A 30 4
B 28 5
C 27 2

Task CR Sequence
A (30-25)/4 = 1,25 3
B (28-25)/5 = 0,60 1
C (27-25)/2 = 1,00 2
26
[email protected]
CR

ABC Manufacture has the product scheduling for 5 tasks


Task Processing time Due Date
(Day)
A 2 7
B 8 16
C 4 4
D 10 17
E 5 15
F 12 18

27
[email protected]
CR:

Task Processing time Due Date CR


(Day)
A 2 7
B 8 16
C 4 4
D 10 17
E 5 15
F 12 18

28
[email protected]
CR:
t=0
Task Processing time Due Date CR
(Day)
A 2 7 (7-0)/2=3,5
B 8 16 (16-0)/8 = 2,0
C 4 4 4/4 = 1
D 10 17 17/10 = 1,7
E 5 15 15/5 = 3,0
F 12 18 18/12 = 1,5

29
[email protected]
CR:
t=4
Task Processing time Due Date CR
(Day)
A 2 7
B 8 16
C - -
D 10 17
E 5 15
F 12 18

30
[email protected]
CR:
t=4
Task Processing time Due Date CR
(Day)
A 2 7 1,5
B 8 16 1,5
C - - -
D 10 17 1,3
E 5 15 2,2
F 12 18 1,17

31
[email protected]
CR:
t=16
Task Processing time Due Date CR
(Day)
A 2 7 -4,5
B 8 16 0
C - - -
D 10 17 0,1
E 5 15 -0,2
F - - -

32
[email protected]
CR:
t=18
Task Processing time Due Date CR
(Day)
A - - -
B 8 16 -0,25
C - - -
D 10 17 -0,1
E 5 15 -0,6
F - - -

33
[email protected]
CR:
t=23
Task Processing time Due Date CR
(Day)
A - - -
B 8 16 -0,875
C - - -
D 10 17 -0,6
E - - -
F - - -

34
[email protected]
CR:

Sequence Processing Completion Time Due Date Tardiness


time
C 4 4 4 0
F 12 16 18 0
A 2 18 7 11
E 5 23 15 8
B 8 31 16 15
D 10 41 17 24
Total 41 133 58
Average 6,83 22,17 9,67
35
[email protected]
7.4.2.
SEQUENCING
Operation
Management JOBS THROUGH
TWO SERIAL
PROCESSES

363
[email protected]
Johnson’s rule

Johnson’s rule:
gives an optimal sequence for jobs processed serially through
two processes.
1. List the time required to complete each job at each process. Set up a one-dimensional
matrix to represent the desired sequence with the number of slots equal to the number of jobs.
2. Select the smallest processing time at either process. If that time occurs at process 1, put
the associated job as near to the beginning (LEFT) of the sequence as possible.
3. If the smallest time occurs at process 2, put the associated job as near to the end (RIGHT)
of the sequence as possible.
4. Remove the job from the list.
5. Repeat steps 2–4 until all slots in the matrix have been filled or all jobs have been
sequenced.

37
[email protected]
Johnson’s Rule
Johnson’s Fine Restorations has received a rush order to refinish five carousel animals—an
alligator, a bear, a cat, a deer, and an elephant. The restoration involves two major processes:
sanding and painting. Mr. Johnson takes care of the sanding; his son does the painting. The
time required for each refinishing job differs by the state of disrepair and degree of detail of
each animal. Given the following processing times (in hours), determine the order in which the
jobs should be processed so that the rush order can be completed as soon as possible.

38
[email protected]
Johnson’s Rule

39
[email protected]
SEQUENCING JOBS THROUGH 3 SERIAL PROCESSES

Johnson’s rule

1. The Shortest Processing time in 1st Machine if Longer


than the Longest Processing time in 2nd Machine

2. The Shortest Processing time in 3rd Machine if Longer


than the Longest Processing time in 2nd Machine

40
[email protected]
Johnson’s rule
Task Process 1 Process 2 Process 3
A 18 9 16
B 12 3 11
C 10 2 20
D 1 4 15
(Shortest = 1) (Longest = 9) (Shortest = 11)

2nd condition. à Apply Johnson’s rule


Assume: (Just for calculation, it’s not the final answer)
- Process A: Processing time = P1 + P2
- Process B: Processing time = P2 + P3 41
[email protected]
Johnson’s rule
Task A B
A 18 + 9 = 27 9 + 16 = 25
B 12 + 3 = 15 3 + 11 = 14
C 10 + 2 = 12 2 + 20 = 22
D 1+4=5 4 + 15 = 19

D-C-A-B

42
[email protected]
Gantt?

43
[email protected]
7.4.3. GUIDELINE
1. SPT is most useful when the shop is highly congested.
2. Use SLACK for periods of normal activity.
3. Use DDATE when only small tardiness values can be tolerated.
4. Use LPT if subcontracting is anticipated so that larger jobs are completed in-
house, and smaller jobs are sent out as their due date draws near.
5. Use FCFS when operating at low-capacity levels.
6. Do not use SPT to sequence jobs that have to be assembled with other jobs at a
later date.

45
[email protected]
Operation
Management 7.5. MONITORING

463
[email protected]
7.5. MONITORING
In a job shop environment, where jobs follow different paths through the
shop, visit many different machine centers, and compete for similar
resources, it is not always easy to keep track of the status of a job.

Shop paperwork, sometimes called a work package, travels with a job to


specify what work needs to be done at a particular work center and where
the item should be routed next.

47
[email protected]
GANTT CHARTS
Gantt charts:
show both planned and completed activities against a time scale.

48
[email protected]
INPUT/OUTPUT CONTROL
Input/output (I/O) control:
monitors the input and output from each work center.

49
[email protected]
INPUT/OUTPUT CONTROL
Hall Industries has begun input /output planning for its work centers. Below are the planned
inputs and outputs for Work Center 5.
a. If production proceeds as planned, what will be the backlog at the end of period 4?
b. If actual input values are 60, 60, 65, 65 for periods 1 through 4, respectively, and output
values
cannot exceed 75, how much output can be expected from Work Center 5? c. Is there a
problem with production at Work Center 5?

50
[email protected]
INPUT/OUTPUT CONTROL

51
[email protected]
INPUT/OUTPUT CONTROL

52
[email protected]
7.6. ADVANCED
Operation PLANNING AND
Management SCHEDULING
SYSTEMS

533
[email protected]
ADVANCED PLANNING AND SCHEDULING SYSTEMS
Infinite scheduling:
loads without regard to capacity, then levels the load and sequences the jobs.

Finite scheduling:
sequences jobs as part of the loading decision. Resources are never loaded beyond capacity.

Advanced planning and scheduling (APS):


a software system that uses intelligent analytical tools and techniques to develop realistic schedules.

Genetic algorithm:
method that generates possible solutions based on genetic combinations of previous solutions.
Manufacturing Execution System (MES):
manufacturing software that monitors operations, collects data, and controls processes on the shop
floor.
54
[email protected]
Operation 7.7. THEORY OF
Management CONSTRAINTS

553
[email protected]
THEORY OF CONSTRAINTS
Theory of constraints (TOC):
a finite scheduling approach that concentrates on
scheduling the bottleneck resource.

56
[email protected]
DRUM-BUFFER-ROPE
Drum-buffer-rope:
the drum sets the pace for the production, a buffer is
placed before the bottleneck, and a rope communicates
changes.

57
[email protected]
PROCESS VS. TRANSFER BATCH SIZES
1. Identify the bottleneck.
2. Schedule the job first whose lead time to the bottleneck is less than or
equal to the bottleneck
processing time.
3. Forward schedule the bottleneck machine.
4. Backward schedule the other machines to sustain the bottleneck
schedule.
5. Transfer in batch sizes smaller than the process batch size.

58
[email protected]
Example
The following diagram contains the product structure, routing, and processing time information
for product A. The process flows from the bottom of the diagram upward. Assume one unit of items
B, C, and D are needed to make each A. The manufacture of each item requires three operations at
machine centers 1, 2, or 3. Each machine center contains only one machine. A machine setup time
of 60 minutes occurs whenever a machine is switched from one operation to another (within the
same item or between items).

Design a schedule of production for each machine center that will produce 100 A’s as quickly
as possible. Show the schedule on a Gantt chart of each machine center.

59
[email protected]
60
[email protected]
Synchronous Manufacturing

Machine 2 is identified as the bottleneck, so we schedule machine 2 first.

From the product structure diagram, we see that 3 operations are performed at machine 2—B2, C3, D2.

If we schedule item B first, B1 (5’) à B2 (3’) (Item 1 always first) à Rule 2: <= bottle neck à Reject

If we schedule item D first, D1 (10’) à D2 (8’) (Item 1 always first) à Rule 2: <= bottle neck à Reject

à Schedule C first. (C1+C2 < C3)

61
[email protected]
Synchronous Manufacturing
Gantt chart

62
[email protected]
Operation 7.8. EMPLOYEE
Management SCHEDULING

633
[email protected]
EMPLOYEE SCHEDULING
Employee scheduling has lots of options because labor is a very flexible resource.
Employee Scheduling Heuristic:
1. Let N = no. of workers available
Di = demand for workers on day i
X = day working
O = day off

2. Assign the first N - D1 workers day 1 off. Assign the next N - D2 workers day 2 off.
Continue in a similar manner until all days have been scheduled.

3. If the number of workdays for a full-time employee is less than 5, assign the remaining workdays
so that consecutive days off are possible or where unmet demand is highest.

4. Assign any remaining work to part-time employees, subject to maximum hour restrictions.

5. If consecutive days off are desired, consider switching schedules among days with the same
demand requirements.
64
[email protected]
EMPLOYEE SCHEDULING
Diet-Tech employs five workers to operate its weight-reduction facility. Demand for service
each week (in terms of minimum number of workers required) is given in the following table.
Create an employee schedule that will meet the demand requirements and guarantee each
worker two days off per week.

65
[email protected]
EMPLOYEE SCHEDULING

66
[email protected]
EMPLOYEE SCHEDULING

67
[email protected]
7.9. AUTOMATED SCHEDULING SYSTEMS
• Staff scheduling assigns qualified workers to standardize shift patterns
taking into account leave requests and scheduling conflicts. The solutions
include social constraints such as labor laws for minors, overtime
payment regulations, and holidays or religious holidays that may differ by
global location.

• Schedule bidding puts certain shift positions or schedule assignments


up for bid by workers; allows workers to post and trade schedules with
others as long as coverage and skill criteria are met.

• Schedule optimization creates demand-driven forecasts of labor


requirements and assigns workers to variable schedules (in some cases, as
small as 15 minutes blocks of time) that change dynamically with demand.
Uses mathematical programming and artificial intelligence techniques. 68
[email protected]
PRACTICES

69
[email protected]
THANKS!