2019 Exam With Explanation
2019 Exam With Explanation
(CUNA)
However, the actual practice of roller speed for
asphalt compaction is not included in the options.
However, the closest is the 4-7 Km/h. Supposedly we
can't exceed the 6 Km/h maximum speed but since
the code did not specify, thus 4-7 Km/h is reasonable
enough as the answer. Other than this is considered
high speed.
6. The contractor shall submit
in writing a job-mix-formula
supported by laboratory test
data along with samples of
materials to the engineer for
testing requirement.
a. one week
b. two weeks
c. three weeks
d. four weeks
ITEM 307 – BITUMINOUS PLANT-MIX SURFACE
COURSE – GENERAL
307.2 Material Requirements
307.2.1 Composition and Quality of Bituminous
Mixture
(Job-Mix Formula). The bituminous mixture shall be
composed of aggregate, mineral filler, hydrated lime,
and bituminous material. At least three weeks prior to
production, the Contractor shall submit in writing a
job-mix formula for each mixture supported by
laboratory test data along with samples and sources
of the components and viscosity-temperature
relationships information to the Engineer for testing
and approval.
07. A load bearing concrete
Hollow blocks (CHB) sample
with the following data:
Width, mm ------ 150
Length, mm ------ 394
Height, mm ------ 194
Ultimate load ------ 52,300
(CUNA)
High temperatures often cause an increased rate of
hardening which makes placing and finishing difficult.
Retarders keep concrete workable during placement
and delay the initial set of concrete. Since thermal
cracking is caused by rise in temperature, thus it can
be reduced by using retarders.
11. A good grading of fine
aggregate for concrete has
fineness modulus not
exceeding?
a. 2.6
b. 2.8
c. 3.2
d. 3.4
Values of Fineness Modulus of Sand
Fineness modulus of fine aggregate varies from 2.0 to
3.5mm. Fine aggregate having fineness modulus
more than 3.2 should not considered as fine
aggregate. Various values of fineness modulus for
different sands are detailed below.
https://www.sciencedirect.com/science/article/pii/S136
4032116306050
a. 2.40
b. 2.88
c. 3.24
d. 3.67
PI = LL – PL = 39 – 21 = 18
20. Test conducted on fully
cured carbon fiber sheet (CFS)
application to determine by the
engineer, adhesion testing to
the substrate is called.
a. Compressive strength test
b. Flexural strength test
c. Pull-off test
d. None of the above
Source: ASTM-A123
three (3)
23. The most widely used
concrete chemical admixture
for ready-mixed concrete
application which has water-
reducing, high range, and
retarding properties is
classified by ASTM C 494 as:
a. type A
b. type B
c. type F
d. type G
https://www.astm.org/Standards/C494
variation in mass
= (mass of specimen - nominal mass)/mass of specimen
= (2.322 - 2.235)/2.322 = 3.75% or 4%
25. The maximum height of
reflectorized thermoplastic
rumble strips must be:
a. 5mm
b. 8mm
c. 13mm
d. 25mm
source julius
gradation and atterberg's limit
27. The stone mastic asphalt
(SMA) mixture shall be placed
at a temperature of not less
than ___ and a maximum of
____ measured in the truck
before dumping into the
spreader.
a. 105 ° C, 180 ° C
b. 125 ° C, 180 ° C
c. 105 ° C, 185 ° C
d. 135 ° C, 180 ° C
D.O. No. 13 series of 2013
Item 734 – Stone Mastic Asphalts (SMA)
734.3.3 Laying
The mixture shall be placed at a temperature of not less
than 135 ° C and a maximum of 180 ° C measured in
the truck before dumping into the spreader. The mixture
shall be spread and struck off to the grade and elevation
established. Bituminous pavers shall be used to
distribute the mixture either over the entire width or over
such partial width as may be practicable.
28. An estimated 15,200 units of
corrugated G.I. sheet will be
used in the construction of
resettlement housing project,
how many quality test are you
going to prepare?
a. 9 QT
b. 10 QT
c. 13 QT
d. none of the above
(CUNA)
For the estimated 15,200 units of corrugated G.I. sheets
for the construction of resettlement housing project, we
will be using 15200/1000 = 15.2 or 16 Quality Tests.
That is not stated in the options, so the answer is option
D. None of the Above.
29. A one-lane road, with a pavement
width of 4.0m and shoulder width of
0.5m on each side of the pavement,
was designed to have sub-base and
base courses with a combined
thickness of 300mm. If the thickness
of the sub-base is 125mm, the
spreading and compaction of the
subbase and base courses shall be
carried out in
a. 2 layers over the full width of 5.0m
b. 3 layers over the full width of 5.0m
c. 2 layers over the full width of 4.0m
d. 3 layers over the full width of 4.0m
(CUNA) / internet
no such word false slump
31. When lapping of two carbon
fiber sheet (CFS) is required, a
lap length of not less than ____
shall be provided
a. 10 cm
b. 20 cm
c. 25 cm
d. 30 cm
D.O. No. 160 series of 2016
ITEM 416 - CARBONFIBER SHEET
416.3.6 Carbon Fiber Application (First Layer)
The standard length of carbon sheet will be cut from 4 to
6 m. If standard cut length is exceeded, wrinkles will
appear and installation becomes more difficult. The CFS
shall be applied in accordance with the following
procedures.
a) Install the CFS in the longitudinal direction after the
epoxy resin application.
b) Press the CFS using a roller starting from the center
towards the edge to squeeze out
entrapped air before the epoxy resin sets.
c) When lapping of two CFS is required, a lap length of
not less than 20 cm shall be
provided.
32. The proportioning of
Bituminous Material on the
basis of total dry aggregate,
when using cut back asphalt
shall be:
a. 4.5 to 7.0 mass percent
b. 6.0 to 10.0 mass percent
c. 4.5 to 6.0 mass percent
d. 5.0 to 7.0 mass percent
internet
Rebound Hammer
34. Increasing the carbon
content when it comes to
commercial steel will also
a. Increase in hardiness
b. Increase in ductility
c. Increase in workability
d. a & b
internet
Increasing carbon commercial steel: increase in
hardiness, decrease in ductility, & workmanship
difficulties.
35. For structural concrete the
maximum size of aggregates
shall be less than
a. Equals the spacing of rebars
b. Two third the spacing of rebars
c. One-half the spacing of rebars
d. Six times the spacing of rebars
internet
aggregates shall be less than 5mm both side of the
spacing of rebars.
36. What is the material used as
solvent for rapid curing cut-
back asphalt?
a. kerosene
b. gasoline
c. diesel fuel
d. none of the above
old reviewer
Solvents of cut – back asphalts:
http://www.tigercement.com/cement-products/ordinary-
portland-cement/american-standard-astm-c-150-type-1/
412.3.2 Sampling
Sampling, testing and acceptance consideration will be
made on a lot basis. A lot shall be further defined as the
smallest number of bearings as determined by the
following criteria:
a. A lot shall not exceed a single contract or project
quantity.
b. A lot shall not exceed 50 bearings.
c. A lot shall consist of those bearings of the same type
regardless of load capacity.
For acceptance purposes, bearing from within the lot
shall be selected at random as samples for inspection
and testing. A minimum of three bearings shall be taken
from the lot for testing. If the number of bearings in the
lot exceeds 50 then for each additional 50 or part
thereof, one additional bearing shall be taken for testing.
50. The proper compaction of
an embankment material will
result to?
a. minimize compressibility
b. decrease soil permeability
c. increase shear strength and soil
stability
d. all of the above
Source: CUNA
all of the above
51. These are permeable fabrics
which when used in association
with soil, have the ability to
separate, filter, reinforce,
protect, or drain.
a. welded wire fabric
b. rip rap
c. geotextiles
d. slope protection
Source: wikipedia
geotextiles
52. These are materials used on road
signs which consist of spherical lens
elements embedded within a
transparent plastic having a smooth,
flat surface with a protective precoat
or tack free heat activated adhesive.
a. mirror sheeting
b. reflective sheeting
c. signage stickers
d. reflectorized paints
https://theconstructor.org/practical-guide/water-quality-
tests-concrete-construction/7357/
https://www.academia.edu/7532017/Marshall_Test
60 degrees
57. The grading analysis shows
the fineness modulus of sand
for concrete 3.8, can this be
allowed to be used?
a. no, it is too coarse
b. no, it will cause bleeding
c. yes, if blended with fine sand to
meet the grading requirement
d. all of the above
Source: CUNA
4
59. The test property curves of
an asphalt mix design showed
the following values:
%AC at median voids - 5.0%
%AC at minimum VMA - 5.4%
%AC at maximum stability - 4.9%
%AC at maximum bulk specific
gravity - 5.2%
what is the optimum asphalt
content?
a. 5.20%
b. 5.07%
c. 5.13%
d. 5.03%
(5.0+4.9+5.2) / 3 = 5.03%
60. Grading requirement of item 200 –
aggregate subbase course, which statement
is true?
a. The fraction passing the 0.425 mm (No. 40)
sieve shall have a liquid limit not greater than 35
and plasticity index not greater than 12
b. The fraction passing the 0.425 mm (No. 40)
sieve shall have a liquid limit not greater than 35
and plasticity index not greater than 6
c. The material passing the 0.425 mm (No. 40)
sieve shall have a liquid limit of not more than
25 and a plasticity index of not more than 12
d. The material passing the 0.425 mm (No. 40)
sieve shall have a liquid limit of not more than
25 and a plasticity index of not more than 6
3.2 mm (1/8”)
62. The contractor wish to pour
concrete for pavement but he
run-out of 2" maximum size of
aggregate, you notice that only
available are 3/4". would you
approved the concrete pouring
request?
a. Allow as long as the concrete
meets the required strength
b. Wait until the 2" maximum size
aggregates are available
c. Yes, provided the contractor is
willing to increase the cement
factor
d. none of the above
Source: Wikipedia
liquefaction
65. What is the boundary
between coarse and fine
aggregates for item 405
structural concrete
a. passing sieve 3/8"
b. passing no. 4 sieve
c. passing no. 6 sieve
d. none of the above
http://asphaltmagazine.com/understanding-asphalt-
pavement-distresses-five-distresses-explained/
shoving
98. Roughness index in excess
of the prescribed limits can be
corrected through the use of
_______.
a. diamond grinding machine
b. rotomilling machine
c. fine milling machine
d. tining machine