SmartLi 3.0 Quick Guide (Short-Term Backup Power)
SmartLi 3.0 Quick Guide (Short-Term Backup Power)
SmartLi 3.0 Quick Guide (Short-Term Backup Power)
1. If the battery cabinet is installed but not powered on, manually powered off, or discharged, avoid
keeping it at low SOC for an extended period. Recharge the battery cabinet in a timely manner
according to the instructions in "Power-On Commissioning > Recharge Requirements for Batteries with
Low SOC" in the user manual. Otherwise, batteries may be damaged due to overdischarge.
2. It is recommended that an independent battery room be used. Before installing battery modules,
prepare fire extinguishing facilities, such as firefighting sands and liquid carbon dioxide fire
extinguishers, according to the construction regulations. Before operation, ensure that the battery room Removing the Pallet
is equipped with a fire extinguishing system that complies with local regulations.
Remove certain
Appearance Space Planning Expansion
sealing plugs
nut
Air vent based on the
Incoming cable glands Communications cable outlet Unit: mm cable size.
3. Reinstall the sealing plugs. (The sealing plugs must be completely inserted into the gland
to facilitate the reinstallation of the gland nut.)
4. Reinstall the gland nut with a torque of 8 N·m.
1
SmartLi 3.0 Quick Guide (Short-Term Backup Power)
2
SmartLi 3.0 Quick Guide (Short-Term Backup Power)
2. Install battery modules and filler panels. • Excessive bolts will be used as spare parts.
• When installing cables, ensure that the cables do not
- + PE block the QR code on the left of the protective
• Do not open the front cover of a battery module when installing or moving cover.
it.
• Assign at least three persons or use a lifting trolley to move a battery a. Open the protective covers for the negative terminal of
module. When using a lifting trolley to move a battery module on the the battery module on the upper layer and the positive
aisle, adjust the trolley angle to facilitate installation. terminal of the battery module on the lower layer.
• Install the battery modules from bottom to top and from left to right to b. Install copper bars between battery modules. Install the
prevent falling over due to imbalance. Battery copper bar end with a round hole at the battery
• If half-capacity cabinet configuration is adopted, battery modules can be baffle plate module on the upper layer, and close the terminal
installed only on the left side. Install a filler panel at the last but one layer 7+7 7+0
of the right column only after installing battery communications cables. protective cover. Install the copper bar end with a
slotted hole at the battery module on the lower layer,
8+8 8+0 and close the terminal protective cover.
c. Repeat these two steps.
d. Open the terminal protective covers, install the battery
power cables reserved in the cabinet, and close the
terminal protective covers.
Slotted
hole
7+7 7+0 6+6 6+0 6+6 6+0
3
SmartLi 3.0 Quick Guide (Short-Term Backup Power)
4. On the UPS LCD, choose System Info. > Settings > Battery Settings and set
Battery Type to Lithium battery.
5. After the green indicator of the BCU blinks at super short intervals and the red
indicator is steady on, switch on the battery circuit breaker on the battery cabinet.
The preceding procedure applies to the single-cabinet scenario. For the multi-
cabinet scenario, see SmartLi 3.0 User Manual (Short-Term Backup Power).
4
SmartLi 3.0 Quick Guide (Short-Term Backup Power)
Not Communicating with the UPS 4. Set the language, time, date, cloud service, network parameters, and system
parameters on the Settings Wizard screen of the SmartLi.
The following operations apply to the scenario where SmartLi 3.0 does not communicate • Set the preceding parameters and retain the default values for other parameters.
with the UPS (no communications cable is connected between the SmartLi and the UPS). • The preceding parameters are described for Huawei UPS5000 series. For third-party UPSs, set the LCD Preset WebUI Preset
System User
parameters by referring to the preceding description. If parameters are different, contact technical Password Password
1. On the UPS LCD, choose System Info. > Settings > Battery Settings and set the parameters support. To ensure system
as follows (the batteries are managed as lead-acid batteries by default. The battery type • If the preceding parameters are incorrectly set, the SmartLi cannot be charged or discharged admin security, change the
000001 Changeme
displayed on the NMS is VRLA batt, but actually lithium batteries are connected to the UPS). properly. In this case, contact technical support. (administrator) preset password
operator after login.
Item Description Setting 2. Press and hold the POWER ON/OFF button on the BCU of the SmartLi cabinet for more than 2s. 000001 Changeme
(common user)
Specifies the type of batteries The green indicator of the BCU blinks at short intervals.
Battery type VRLA batt.
connected to the UPS.
Specifies the voltage of each
Single battery • The BCB off alarm (the red indicator is steady on) is displayed on the SmartLi LCD. No action is
battery that is connected in 2 12
voltage (V) required. After the battery circuit breaker is switched on, the alarm will be automatically cleared.
series in a battery string.
• The green indicator blinks intermittently. After 1 minute, the BCU starts. The green indicator blinks
9999 (maximum value) at super short intervals and the red indicator is steady on.
5
SmartLi 3.0 Quick Guide (Short-Term Backup Power)
Item Description
Specifies the SmartLi connection scenario.
Default Value Value Range
08 Power-Off
UPS, HVDC,
Application scenario Currently, the UPS and EHU scenarios are UPS Switch off the battery circuit breaker in the battery cabinet. (If multiple
EHU, SST
supported. SmartLi cabinets are connected in parallel, perform this operation on
When the SmartLi is connected to the UPS 8+8/8+0 each cabinet.)
8+8/8+0
without communication, the UPS manages scenario: 276–
scenario: 276
the SmartLi based on the lead-acid battery 300
logic. You need to set the number of lead- Press and hold the POWER ON/OFF button on the BCU for more than 5s until
acid batteries supported for the UPS on 7+7/7+0 all the three indicators blink to power off the system. (If multiple SmartLi
7+7/7+0
the SmartLi monitoring screen to ensure scenario: 240– cabinets are connected in parallel, perform this operation on each cabinet.)
Number of lead-acid scenario: 252
that the charge and discharge operating 270
batteries supported
voltage ranges of the UPS and SmartLi
(The value of this
match each other.
parameter must be • If battery modules will be stored for a long time after power-off, remove the BCU to
By default, Number of lead-acid
the same as the reduce battery discharge. This prevents battery modules from being overdischarged due
batteries supported is set based on the
setting of Batteries to storage at low SOC.
single battery voltage (2 V). If the single
in a battery string • When you hold the button to power off a cabinet, only the indicators on the cabinet
battery voltage in the UPS system is 12 V,
on the UPS 6+6/6+0 6+6/6+0 where the software version is later than V500R022C00SPC100 will blink.
convert it to 2 V before setting this
monitoring screen.) scenario: 204 scenario: 192–
parameter. For example, if the single
battery voltage is 12 V and the number of 234
batteries in a battery string is 42, the value
of Number of lead-acid batteries
supported is 252 (42 x 12/2 = 252) in the
7+7/7+0 scenario.
Specifies the number of battery cabinets
connected in parallel.
Battery cabinet
Currently, a maximum of 10 lithium 1 1–10
quantity
battery cabinets can be connected in
parallel.
≤ 1000, 1000–
Set this parameter based on the altitude of 2000, 2000–
Altitude (m) ≤ 1000
the place where the rack is used. 3000, 3000–
4000
5. After the green indicator of the BCU blinks at super short intervals and the red indicator is
steady on, switch on the battery circuit breaker on the battery cabinet.
The preceding procedure applies to the single-cabinet scenario. For the multi-cabinet
scenario, see SmartLi 3.0 User Manual (Short-Term Backup Power).