01 Installation Preparations 02 Installing Cabinets Non-Secured Installation Combining Cabinets

Unpacking Adjust the anchor bolts until the castors hang in


the air, ensure that the anchor bolts fully
1. Before installation, read the user manual carefully to get familiar with product information and safety
precautions. support the cabinet, and use a level instrument
2. Use insulated tools during installation and operations. to check that the cabinet is level.
3. Only qualified professionals or trained personnel are allowed to install, commission, and maintain the
battery cabinet. Otherwise, personal injury or equipment damage may occur, and the caused battery
cabinet damage is not covered under any warranty or service agreement.

1. If the battery cabinet is installed but not powered on, manually powered off, or discharged, avoid
keeping it at low SOC for an extended period. Recharge the battery cabinet in a timely manner
according to the instructions in "Power-On Commissioning > Recharge Requirements for Batteries with
Low SOC" in the user manual. Otherwise, batteries may be damaged due to overdischarge.
2. It is recommended that an independent battery room be used. Before installing battery modules,
prepare fire extinguishing facilities, such as firefighting sands and liquid carbon dioxide fire
extinguishers, according to the construction regulations. Before operation, ensure that the battery room Removing the Pallet
is equipped with a fire extinguishing system that complies with local regulations.

Model Weight Configuration Type Do not transport a


SmartLi-512V-162Ah-F With an LCD (master cabinet) cabinet with
< 1100 kg battery modules
SmartLi-512V-162Ah-S Without an LCD (slave cabinet)
installed. If the If the cabinet is installed against a wall, install only the front connecting plates.
cabinet needs to
7+7, 7+0, 8+8, and 8+0 Scenarios be transported or
moved, remove
03 Installing a Ground Cable
Output 200 kW < Output 250 kW < Output the battery 1. Remove the PDU cover and the ground cable gland nut and sealing plugs.
Item Power/Cabinet ≤ Power/Cabinet ≤ 250 Power/Cabinet ≤ 300
200 kW kW kW
modules first.
Recommended cable +/(N)/- 150 185 240
Battery
size (mm2) PE 70 95 120
Connection mode: cable crimped with a DT terminal
Bolt specifications for +/N/-: M16x50 mm (120 N·m); bolt specifications for PE: M12x30 mm (47 N·m)
The bolt specifications in the table apply only to one end of the SmartLi cable. For details about the bolt specifications Secured Installation
for the other end, see the corresponding UPS manual.

6+6 and 6+0 Scenarios


Output 170 kW < Output 210 kW < Output M12 bolt
Item Power/Cabinet ≤ Power/Cabinet ≤ 210 Power/Cabinet ≤ 250 Spring
170 kW kW kW washer
Recommended cable +/(N)/- 150 185 240 Flat washer
Battery 2
size (mm ) PE 70 95 120 2. Install a ground cable.
Unit: mm Expansion Concrete
Connection mode: cable crimped with a DT terminal floor Site ground bar
sleeve
Bolt specifications for +/N/-: M16x50 mm (120 N·m); bolt specifications for PE: M12x30 mm (47 N·m)
The bolt specifications in the table apply only to one end of the SmartLi cable. For details about the bolt specifications
for the other end, see the corresponding UPS manual.

Remove certain
Appearance Space Planning Expansion
sealing plugs
nut
Air vent based on the
Incoming cable glands Communications cable outlet Unit: mm cable size.

Battery circuit breaker


Monitoring interface unit
BCU MDU
Fuse Against a Wall Not Against a Wall
Carbon
monoxide After installing expansion bolts, reinstall the tray.
gas sensor Supported Cable Diameter
(optional) Gland Sealing Plug to Be Recommended Cable
Rubber (Including the Insulation Layer,
Model Removed Size (Unit: mm2)
Document holder plug Unit: mm)
MCCB Innermost layer (white) 10–16 -
auxiliary
Slots for installing M40 (10–32)
lever Innermost layer (white),
battery modules Rubber 16–22 70, 95, 120
second-to-last layer (red)
Carbon plug
monoxide The single-core 90°C-resistant flexible copper cable is used as an example in the table to illustrate which
gas sensor sealing plugs need to be removed. The sealing plugs to be removed depend on the actual cable
(optional) diameter (including the insulation layer). Remove sealing plugs only when necessary. Otherwise, the
sealing performance will be affected.

3. Reinstall the sealing plugs. (The sealing plugs must be completely inserted into the gland
to facilitate the reinstallation of the gland nut.)
4. Reinstall the gland nut with a torque of 8 N·m.

1
SmartLi 3.0 Quick Guide (Short-Term Backup Power)

04 Installing Output Power Cables


Preparing Power Cables Installing Output Power Cables 3. Reinstall the sealing plugs. (The sealing plugs must be completely inserted into the gland
to facilitate the reinstallation of the gland nut.)
1. Remove the cable glands and sealing plugs based on site requirements. 1. Set the switch based on the actual load. 4. Reinstall the gland nut with a torque of 10 N·m (M50) or 12 N·m (M63).
7+7, 7+0, 8+8, and 8+0 Scenarios
Connecting Communications Cables
250 kW < Load of a
single battery
cabinet ≤ 300 kW
• When reinstalling the communications cable box, prevent the cable box
from pressing the cables.
• RS485 cables and FE cables must be shielded cables.
200 kW < Load of a • If more than eight SmartLi cabinets are connected in parallel, a maximum
single battery of four 15 m parallel communications cables are supported.
cabinet ≤ 250 kW

Communications cable route


Load of a single battery
2. Cut cables and crimp terminals. cabinet ≤ 200 kW
a. Measure the cable length and mark the position where a cable needs to be
cut and the direction of the DT terminal. (Ensure that the installation surface
of the DT terminal is parallel to the copper bar.)
Mark the DT 6+6 and 6+0 Scenarios
terminal direction.
210 kW < Load of a
single battery
cabinet ≤ 250 kW
Mark the cable
cutting position.

170 kW < Load of a


b. Remove certain gland sealing plugs. Route the cable through the gland nut and single battery
sealing plugs. cabinet ≤ 210 kW

Connecting Communications Cables


(UPS Communication Involved, Using Three Parallel Cabinets as an Example)
Load of a single battery
cabinet ≤ 170 kW
Supported Cable Diameter Recommended
Gland
Sealing Plug to Be Removed (Including the Insulation Cable Size
Model
Layer, Unit: mm) (Unit: mm2) 2. Install power cables. Master SmartLi cabinet Slave SmartLi cabinet
Innermost layer (white) 18–24 150 (with an LCD) (without an LCD)
UPS Without a Neutral Wire
Innermost layer (white), second- Terminal Terminal
24–30 185, 240
M63 to-last layer (red) Spring Spring
Nut Nut
(18–44) Innermost layer (white), second-
washer washer
Bolt Bolt
to-last layer (red), and third-to- 30–37 - Flat Flat
last layer (orange) washer washer

Innermost layer (white) 16–20 -


Innermost layer (white), second-
20–26 150
M50 to-last layer (red)
(16–38) Innermost layer (white), second-
to-last layer (red), and third-to- 26–32 185 UPS With a
last layer (orange) Neutral Wire
Connect cables correctly
Connecting Communications Cables
The single-core 90°C-resistant flexible copper cable is used as an example in the table to
to avoid battery short (UPS Communication Not Involved, Using Three Parallel Cabinets as an Example)
illustrate which sealing plugs need to be removed. The sealing plugs to be removed depend
on the actual cable diameter (including the insulation layer). Remove sealing plugs only circuits and sparks.
when necessary. Otherwise, the sealing performance will be affected.

c. Strip the cable and crimp the DT terminal. Terminal Terminal


Spring
Nut Spring washer Nut
washer
Bolt Bolt
Flat washer Flat
washer

Marked cable cutting Marked DT terminal


position direction

2
SmartLi 3.0 Quick Guide (Short-Term Backup Power)

05 Installing Battery Modules


1. Pull out the BCU. 3. Check the insulation performance of the battery 4. Install battery communications cables. 5. Install battery copper bars and power cables. (7+7 8. Attach PP sheets to the notches of the battery
modules and secure the modules. (7+7 scenario scenario used as an example) modules on the top layer to prevent foreign
used as an example) 8+8 matter from falling into the cabinet. (7+7
8+0
It is recommended that you use the DC voltage scenario used as an example)
mode of a multimeter to measure the voltage
between the ground point and the positive and • Do not open the protective covers for the positive
negative terminals of each battery module and negative terminals of a battery module at When attaching PP sheets, align them with
respectively. If the readings are less than 6 V DC, the same time. Close the protective covers for the the edge of the front cover of battery
the insulation is good. Otherwise, contact terminals where copper bars have been installed. modules and ensure that the front cover can
Pull it out for technical support engineers. • After removing the safety cap from a power be opened and closed properly after PP sheets
about 10 cm. cable, install the cable immediately to prevent are attached.
the exposed terminal from touching the shell,
which may cause sparks or burns.

2. Install battery modules and filler panels. • Excessive bolts will be used as spare parts.
• When installing cables, ensure that the cables do not
- + PE block the QR code on the left of the protective
• Do not open the front cover of a battery module when installing or moving cover.
it.
• Assign at least three persons or use a lifting trolley to move a battery a. Open the protective covers for the negative terminal of
module. When using a lifting trolley to move a battery module on the the battery module on the upper layer and the positive
aisle, adjust the trolley angle to facilitate installation. terminal of the battery module on the lower layer.
• Install the battery modules from bottom to top and from left to right to b. Install copper bars between battery modules. Install the
prevent falling over due to imbalance. Battery copper bar end with a round hole at the battery
• If half-capacity cabinet configuration is adopted, battery modules can be baffle plate module on the upper layer, and close the terminal
installed only on the left side. Install a filler panel at the last but one layer 7+7 7+0
of the right column only after installing battery communications cables. protective cover. Install the copper bar end with a
slotted hole at the battery module on the lower layer,
8+8 8+0 and close the terminal protective cover.
c. Repeat these two steps.
d. Open the terminal protective covers, install the battery
power cables reserved in the cabinet, and close the
terminal protective covers.

Round 9. Reinstall the BCU.


hole

Slotted
hole
7+7 7+0 6+6 6+0 6+6 6+0

10.Select the corresponding model on the


nameplate of the cabinet based on the number of
installed battery modules. (The figure uses 14
battery modules as an example.)
6. Check the insulation between the battery
strings and the cabinet.
It is recommended that you use the DC voltage mode
of a multimeter to measure the voltage between the
battery tray and the positive and negative terminals of
each battery string respectively. If the readings are less
than 6 V DC, the insulation is good. Otherwise, contact
technical support engineers.

7. After checking that the battery strings are well


insulated, close the front cover of each battery module.

3
SmartLi 3.0 Quick Guide (Short-Term Backup Power)

06 Verifying the Installation 07 Power-On


Item Acceptance Criteria 3. Set the language, time, date, cloud service, network parameters, and system
• Turn on the ready switch on the BCU. parameters on the Settings Wizard screen of the SmartLi.
Cabinet
The cabinet is securely installed and does not tilt due to vibration. • Ensure that the UPS runs stably in normal mode and the rectifier shown in the energy flow diagram is started.
installation
Neat arrangement The adjacent cabinets are neatly arranged and secured with connecting kits. LCD Preset WebUI Preset
Status of Indicators on the BCU Description System User
Password Password To ensure system security,
Cable layout Cables are routed properly as required by the customer.
The green indicator blinks at 4 Hz (at short intervals). Status after the switch button is pressed. admin (administrator) 000001 Changeme change the preset
Cable labels Both ends of a cable are labeled. Labels are concise and easy to understand. password after login.
The green indicator blinks on for 1s and off for 4s The SmartLi circuit breaker cannot be switched on, operator (common user) 000001 Changeme
Cable ties Cable ties are secured evenly and no burr exists. (intermittently). and the UPS cannot be cold started.
Cable or copper Battery cables or copper bars are securely connected, the spring washers are The green indicator blinks at 10 Hz (blinking at super The SmartLi circuit breaker can be switched on, but
bar connections crimped properly for cables secured by screws, and the cables are intact. short intervals), and the red indicator is steady on. the UPS cannot be cold started.
The resistance between the cabinet ground bar and the equipment room The green indicator blinks at 1 Hz or is steady on
Grounding The UPS can be cold started.
ground bar is less than 0.1 ohm. (blinking at long intervals).
1. The cabinet is correctly connected to the UPS.
Battery cable
2. Battery cabinets in parallel are correctly connected.
connections Communicating with the UPS
3. The battery neutral wire (if any) is correctly connected.
Short-circuit at Check whether there is a short circuit between the positive, neutral, and The UPS supports communication with SmartLi 3.0 and a communications cable is correctly
the upstream and negative cables for circuit breakers, between copper bars, and between the connected between the UPS and the SmartLi.
downstream of cables, copper bars, and enclosure. If there is a short circuit, check whether 1. Press and hold the POWER ON/OFF button on the BCU of the SmartLi cabinet for more than 2s. The
circuit breakers the cables are damaged or short-circuited. If yes, repair the cables. green indicator of the BCU blinks at short intervals.
The inside and outside of the cabinet are free from conductive dust or other
sundries.
1. There is no foreign matter (such as copper wires and screws) on the top • The BCB off alarm (the red indicator is steady on) is displayed on the SmartLi LCD. No action is
Foreign matter required. After the battery circuit breaker is switched on, the alarm will be automatically cleared.
of the cabinet.
cleaning inside • The green indicator blinks intermittently. After 1 minute, the BCU starts. The green indicator blinks at
2. There is no foreign matter on the copper bar terminals.
the cabinet super short intervals and the red indicator is steady on.
3. There is no foreign matter around circuit breaker terminals.
4. There is no foreign matter on the bottom plate of the cabinet.
5. There is no foreign matter on the rear module subrack. 2. Obtain the startup password through the app. After the application is approved, enter the startup
password on the screen to complete battery cabinet authorization.
Cover installation All the covers are reinstalled after checks are performed.
After the installation is complete, do not store the equipment in an
Storage environment where the temperature and humidity are uncontrollable for a
environment long period of time. Otherwise, the equipment may be damaged due to
condensation.
Insulation The battery cabinet output cables are intact. The insulation resistance of the
resistance of positive, negative, and neutral output cables to the ground and that
output power between the positive, negative, and neutral output cables are greater than 2
cables megohms (using a 500 V megohm meter). Default
Item Description Value Range
Value
If batteries are not powered on after installation, take dustproof and anti-
Installation condensation measures (for example, using a dust cover, plastic film, or Specifies the SmartLi connection
protection fabric cloth) to prevent battery condensation or dust corrosion. Remove the scenario. UPS, HVDC,
Application scenario UPS
protective material when batteries need to be used. Currently, UPS scenarios are EHU, SST
supported.
Specifies the number of battery
cabinets connected in parallel.
Battery cabinet
Technical support engineers can obtain the service authorization code through the app. For details, Currently, a maximum of 10 lithium 1 1–10
Do not remove the dust cover quantity
see the Data Center Facility Deployment Guide. battery cabinets can be connected
before power-on.
in parallel.

4. On the UPS LCD, choose System Info. > Settings > Battery Settings and set
Battery Type to Lithium battery.

5. After the green indicator of the BCU blinks at super short intervals and the red
indicator is steady on, switch on the battery circuit breaker on the battery cabinet.

The preceding procedure applies to the single-cabinet scenario. For the multi-
cabinet scenario, see SmartLi 3.0 User Manual (Short-Term Backup Power).

4
SmartLi 3.0 Quick Guide (Short-Term Backup Power)

Not Communicating with the UPS 4. Set the language, time, date, cloud service, network parameters, and system
parameters on the Settings Wizard screen of the SmartLi.
The following operations apply to the scenario where SmartLi 3.0 does not communicate • Set the preceding parameters and retain the default values for other parameters.
with the UPS (no communications cable is connected between the SmartLi and the UPS). • The preceding parameters are described for Huawei UPS5000 series. For third-party UPSs, set the LCD Preset WebUI Preset
System User
parameters by referring to the preceding description. If parameters are different, contact technical Password Password
1. On the UPS LCD, choose System Info. > Settings > Battery Settings and set the parameters support. To ensure system
as follows (the batteries are managed as lead-acid batteries by default. The battery type • If the preceding parameters are incorrectly set, the SmartLi cannot be charged or discharged admin security, change the
000001 Changeme
displayed on the NMS is VRLA batt, but actually lithium batteries are connected to the UPS). properly. In this case, contact technical support. (administrator) preset password
operator after login.
Item Description Setting 2. Press and hold the POWER ON/OFF button on the BCU of the SmartLi cabinet for more than 2s. 000001 Changeme
(common user)
Specifies the type of batteries The green indicator of the BCU blinks at short intervals.
Battery type VRLA batt.
connected to the UPS.
Specifies the voltage of each
Single battery • The BCB off alarm (the red indicator is steady on) is displayed on the SmartLi LCD. No action is
battery that is connected in 2 12
voltage (V) required. After the battery circuit breaker is switched on, the alarm will be automatically cleared.
series in a battery string.
• The green indicator blinks intermittently. After 1 minute, the BCU starts. The green indicator blinks
9999 (maximum value) at super short intervals and the red indicator is steady on.

Specifies the capacity of each • If a third-party UPS is connected, set


Single battery
battery that is connected in this parameter to the maximum value.
capacity (Ah)
series in a battery string. • If the UPS from the Company is 3. Obtain the startup password through the app. After the application is approved, enter the startup
connected, set Batt. charging capacity password on the screen to complete battery cabinet authorization.
mismatch to Disable on the WebUI.

8+8/8+0 scenario: 8+8/8+0 scenario:


Recommended value: Recommended
276 value: 46
Value range: 276–300 Value range: 46–50
7+7/7+0 scenario: 7+7/7+0 scenario:
Batteries in a Specifies the number of Recommended value: Recommended
battery string batteries in a battery string. 252 value: 42
Value range: 240–270 Value range: 40–45
6+6/6+0 scenario 6+6/6+0 scenario
Recommended value: Recommended
204 value: 34
Value range: 192–234 Value range: 32–39
Specifies the number of
Number of
battery strings connected in 1
battery strings
parallel.
Cell float Specifies the battery float
2.3 Technical support engineers can obtain the service authorization code through the app. For details,
voltage (V/cell) charging voltage.
see the Data Center Facility Deployment Guide.
2.3

The UPS from the Company requires that


Cell equalized Specifies the battery equalized the equalized charging voltage be higher
volt. (V/cell) charging voltage. than the float charging voltage, so the
equalized charging voltage should be 0.01
V higher. For third-party UPSs, comply with
5
similar requirements if applicable.

Dis. cur. 0.1C Specifies the EOD threshold


EOD (V/cell) when the discharge current is 1.8
0.1C, 0.3C, 0.5C, or 1.0C
Dis. cur. 0.3C
respectively.
EOD (V/cell)
Dis. cur. 0.5C 1.8
EOD (V/cell) If a third-party UPS is
connected and the EOD is 1.75
Dis. cur. 1.0C not distinguished by rate, set
EOD (V/cell) this parameter to 1.8 V/cell. 1.75

5
SmartLi 3.0 Quick Guide (Short-Term Backup Power)

Item Description
Specifies the SmartLi connection scenario.
Default Value Value Range
08 Power-Off
UPS, HVDC,
Application scenario Currently, the UPS and EHU scenarios are UPS Switch off the battery circuit breaker in the battery cabinet. (If multiple
EHU, SST
supported. SmartLi cabinets are connected in parallel, perform this operation on
When the SmartLi is connected to the UPS 8+8/8+0 each cabinet.)
8+8/8+0
without communication, the UPS manages scenario: 276–
scenario: 276
the SmartLi based on the lead-acid battery 300
logic. You need to set the number of lead- Press and hold the POWER ON/OFF button on the BCU for more than 5s until
acid batteries supported for the UPS on 7+7/7+0 all the three indicators blink to power off the system. (If multiple SmartLi
7+7/7+0
the SmartLi monitoring screen to ensure scenario: 240– cabinets are connected in parallel, perform this operation on each cabinet.)
Number of lead-acid scenario: 252
that the charge and discharge operating 270
batteries supported
voltage ranges of the UPS and SmartLi
(The value of this
match each other.
parameter must be • If battery modules will be stored for a long time after power-off, remove the BCU to
By default, Number of lead-acid
the same as the reduce battery discharge. This prevents battery modules from being overdischarged due
batteries supported is set based on the
setting of Batteries to storage at low SOC.
single battery voltage (2 V). If the single
in a battery string • When you hold the button to power off a cabinet, only the indicators on the cabinet
battery voltage in the UPS system is 12 V,
on the UPS 6+6/6+0 6+6/6+0 where the software version is later than V500R022C00SPC100 will blink.
convert it to 2 V before setting this
monitoring screen.) scenario: 204 scenario: 192–
parameter. For example, if the single
battery voltage is 12 V and the number of 234
batteries in a battery string is 42, the value
of Number of lead-acid batteries
supported is 252 (42 x 12/2 = 252) in the
7+7/7+0 scenario.
Specifies the number of battery cabinets
connected in parallel.
Battery cabinet
Currently, a maximum of 10 lithium 1 1–10
quantity
battery cabinets can be connected in
parallel.
≤ 1000, 1000–
Set this parameter based on the altitude of 2000, 2000–
Altitude (m) ≤ 1000
the place where the rack is used. 3000, 3000–
4000

5. After the green indicator of the BCU blinks at super short intervals and the red indicator is
steady on, switch on the battery circuit breaker on the battery cabinet.

The preceding procedure applies to the single-cabinet scenario. For the multi-cabinet
scenario, see SmartLi 3.0 User Manual (Short-Term Backup Power).

Copyright © Huawei Digital Power Technologies Co., Ltd.

6
2022. All rights reserved.

You might also like