2017 Winter Model Answer Paper
2017 Winter Model Answer Paper
2017 Winter Model Answer Paper
(Autonomous)
(ISO/IEC-27001-2005 Certified)
: Indicator (1 Mark)
MAHARASHTRA STATE BOARAD OF TECHNICAL EDUCATIOD
(Autonomous)
(ISO/IEC-27001-2005 Certified)
6) Large temples
7) Auditorium
8) Cinema theaters
9) Show-rooms etc.
i) Name the starters used for following motors: (i) 15hp, 3phase squirrel cage induction
motor. (ii D.C. shunt motor
Ans: Name the starters used for following motors : ( Each Name of Starter : 1 Mark)
i) Star-Delta Starter OR ii) Auto transformer starter OR iii) Soft start starter.
j) State the meaning of following terms: (i) Security deposit (ii) Earnest money
Ans: i) Security Deposit (SD):- (1 Marks)
Security deposit is amount or deposit given by the contractor to the owner till
satisfactory completion of the project work. Generally it is a 5 to 10 % of the total
estimated cost.
ii) Earnest Money deposit (EMD) :- (1 Marks)
EMD is a deposit taken as a guaranty from the bidder if the tender is accepted by
the owner and if the contractor (bidder) refuses to accept that work in that case the EMD
is not returned to that party it is generally 2 to 5 percent estimated cost. It is refundable to
every unsuccessful (not considered) bidder.
8. All incandescent lamps, unless otherwise required, are to be hung at a height of 2.5
meters above the floor level. And ceiling fans are to be hung 2.75 meters above the
floor.
9. Lights and fans may be wired on a common circuit. Each sub-circuit is not to have
more than a total ten points of lights, fans and socket-outlets. The load on each sub-
circuit is to be restricted to 800 watts.
10. No fuse and switch is to be provided in earthed conductor.
11. Every circuit or apparatus is to be provided with a separate means of isolation such
as a switch.
12. All circuit or apparatus requiring attention are to be provided with means of access
to it.
13. In any building, light and fan wiring and power wiring are to be kept separate.
14. In 3-Phase, 4-wire installation the load is to be distributed equally on all phases.
15. No additional load is to be connected to an existing installation unless it has been
ascertained that the installation can safely carry the additional load and that the
earthing arrangements are adequate.
16. Lamp holders used in bath rooms are to be constructed or shrouded in insulating
materials and fitted with protective shield and earth continuity conductor is not to be
size less than 7/0.915 mm.
17. The metal sheaths or conduits for all wiring and metal coverings of all consuming
apparatus or applications is to be properly earthed in order to avoid danger from
electrical shock due to leakage or failure of insulation.
18. Each sub-circuit is to be protected against excessive current (that may occur either
due to over load or due to failure of insulation) by fuse or automatic circuit breaker.
19. All light conductors are to be insulated or otherwise safe guarded to avoid danger.
After completion of work the installations are to be tested (the test are to be carried
out as described) before energisation.
20. Earth Resistance :should be very low for domestic installation it should be equal to
or less than 5 ohm to 8 ohm
21. Insulation Resistance between conductor : should be very high for domestic
installation it should be equal to or more than 1 mega ohm or it should be not be
50 M
less than =
Number of outlet
MAHARASHTRA STATE BOARAD OF TECHNICAL EDUCATIOD
(Autonomous)
(ISO/IEC-27001-2005 Certified)
c) State any four advantages and two disadvantages of underground service connection.
Ans: Four advantages of underground service connection:
(Any Four point expected: 1/2 each point)
1. Repairing and maintenance is less
2. Appearance is good
3. Normally it is preferred for Residential commercial and Industrial consumers
4. Armoured cables are preferred
5. More safety
6. Chances of lightning stroke are less
Two disadvantages of underground service connection : (Any Two expected: 1Mark each)
1. Cost is more
2. Repairing and maintenance is difficult.
3. Space required is more.
One light point, one ceiling fan, one 5A socket outlet are to be wired. Switches are to be
e) provided on a single switch board. Draw the following: (i) Wiring diagram in looping -
in system, (ii) Single line diagram for (i)
Ans: Wiring diagram for 1 fan, 1 tube and one light socket looping system : (2Marks)
or equivalent fig
Single line diagram for 1 light point, 1 Ceiling fan and 1 light socket : (2 Marks)
or equivalent fig
f) Draw a labelled diagram for underground service connection.
Ans: Underground service connection: (Diagram : 4 Marks )
or equivalent figure
MAHARASHTRA STATE BOARAD OF TECHNICAL EDUCATIOD
(Autonomous)
(ISO/IEC-27001-2005 Certified)
OR
Total No.of power po int s
No. of power Sub circuits
1000 W or 2000 W
or equivalent figure
MAHARASHTRA STATE BOARAD OF TECHNICAL EDUCATIOD
(Autonomous)
(ISO/IEC-27001-2005 Certified)
e) Define the following terms as per IS : (i) Wiring diagram. (ii) Schematic diagram
Ans: (i) Wiring diagram : (2 Marks)
A wiring diagram shows the connection of an installation or part of installation. It
shows how the connections are actually made and also gives layout of wiring.
For example:
f) Draw the details of distribution board having separate energy meter for lighting load
and power load.
Ans: Distribution board having separate energy meter for lighting load and power load:
( 4 Marks)
6. A switch board is to be installed so that its bottom lies 1.25 to 1.5 meters above the
ground floor.
7. A plugs and socket-outlets are to be of 3-pin type, the appropriate pin of socket
being connected permanently to the earthing system.
8. All incandescent lamps, unless otherwise required, are to be hung at a height of 2.5
meters above the floor level. And ceiling fans are to be hung 2.75 meters above the
floor.
9. Lights and fans may be wired on a common circuit. Each sub-circuit is not to have
more than a total ten points of lights, fans and socket-outlets. The load on each sub-
circuit is to be restricted to 800 watts.
10. No fuse and switch is to be provided in earthed conductor.
11. Every circuit or apparatus is to be provided with a separate means of isolation such
as a switch.
12. All circuit or apparatus requiring attention are to be provided with means of access
to it.
13. In any building, light and fan wiring and power wiring are to be kept separate.
14. In 3-Phase, 4-wire installation the load is to be distributed equally on all phases.
15. No additional load is to be connected to an existing installation unless it has been
ascertained that the installation can safely carry the additional load and that the
earthing arrangements are adequate.
16. Lamp holders used in bath rooms are to be constructed or shrouded in insulating
materials and fitted with protective shield and earth continuity conductor is not to be
size less than 7/0.915 mm.
17. The metal sheaths or conduits for all wiring and metal coverings of all consuming
apparatus or applications is to be properly earthed in order to avoid danger from
electrical shock due to leakage or failure of insulation.
18. Each sub-circuit is to be protected against excessive current (that may occur either
due to over load or due to failure of insulation) by fuse or automatic circuit breaker.
19. All light conductors are to be insulated or otherwise safe guarded to avoid danger.
After completion of work the installations are to be tested (the test are to be carried
out as described) before energisation.
20. Earth Resistance : should be very low for domestic installation it should be equal to
or less than 5 ohm to 8 ohm
MAHARASHTRA STATE BOARAD OF TECHNICAL EDUCATIOD
(Autonomous)
(ISO/IEC-27001-2005 Certified)
21. Insulation Resistance between conductor : should be very high for domestic
installation it should be equal to or more than 1 mega ohm or it should be not be
50 M
less than =
Number of outlet
Draw a single line diagram for 15hp, three phase, 440V, Induction motor to be
b)
operated on suitable start.
Ans: Single line diagram 15hp, three phase, 440V, Induction motor - (4 Mark)
S Main Fuse
ICTP - 32A/450V
I
15 HP 3 Ø Induction motor OR
M
Wiring diagram –
or equivalent figure
MAHARASHTRA STATE BOARAD OF TECHNICAL EDUCATIOD
(Autonomous)
(ISO/IEC-27001-2005 Certified)
At first envelop No.1 of all parties are opened and comparative statement of all
parties done.
The rejected party of whose envelope No.1 is invalid there envelope No.2 are not
opened it is freezed.
For all reaming parties envelope No.2 opened and detailed comparative
statement is done.
For lowest eligible bidders the contract is handed over.
d) State any four factors on which selection of contract depends.
Ans:
Four factors on which selection of contract depends:
( Any Four Expected: 1 Mark each)
1) Previous experience
2) Financial position
3) Machinery & man power
4) Quoted Rates
5) Works in hand
6) Reputation
7) Valid Licenses
8) Taxes clearance certificate
State any four important factors, which should be considered for economical execution
f)
of electrical installation work.
Ans: (Any four types expected 1-Mark each)
1. Prepare project execution plan (PEP) & map.
2. Make design of electrical installation work optimum (good design)
3. Use appropriate labour as per project work requirement whether skilled, semi-
skilled or unskilled. Do not use too-much labour . only use the labour which are
actually required.
4. Choose wire/cable size as per requirement, do not use higher size of wire/cable.
5. Use recommended illumination level as per Indian standard. Do not use higher
illumination level.
6. Complete the electrical installation work within specified time do not use more
time.
7. For laying of cable use shortest route.
8. Before finalizing labour charges it should be compare with market values.
9. Before finalizing material purchase it should be compared with other equivalent
quality material other companies.
10. Select type of installation according to application.
11. Select correct method of execution
i) Total load in Hall 1120 420 1400 2940 watt ---------------------- (1 Mark)
2940
Total load in Amps 12.78 13 Amp assu min g p. f . 1 ------ (1 Mark)
230
2940
ii) No. of Sub circuit 3.675 4 Nos lighting sub circuit ------------ (1 Mark)
800
35
According to po int No. of Sub circuit 3.5 4 Nos lighting sub circuit
10
iii) Rating Main switch: - since rated input current is 25 A. -------------------- ( 1 Mark)
Assumed that Staring current = 1.5 times rated current
So starting current = 1.5x 13 = 19.5 A
1) layout and show the position of lamps, fans etc: ------------ (2 Mark)
Or equivalent diagram
MAHARASHTRA STATE BOARAD OF TECHNICAL EDUCATIOD
(Autonomous)
(ISO/IEC-27001-2005 Certified)
What is industrial load? Compare it with residential load on any two points. Also write
b)
any five important points of motor wiring.
Ans: i) Meaning of Industrial Load: (Any Four points expected: 1/2 Mark each)
In industrial load power load, electrical machines load is more than lighting load.
3-ph load is more than single phase load.
Power factor of the load is less than unity, it should be improved.
The tariff of industrial load is different.
The all safety precausions e.g. MCB, MCCB, ELCB, Fuses should be installed.
The earthing resistance should be maintained, the size of earth wire is 8SWG
copper or 6 SWG GI
4) The motor should be earthed at two distinct terminals by 8 SWG copper wires.
5) The voltage drop in the cable should be with the tolerance limit + or – 5 %
OR
(Any Three points expected 1 Mark each)
1. The supply to every motor is controlled by main switch. Main switch may be ICDP
for single phase machine and ICTP for 3-ph machine.
2. Starter is required to start the motors, if the capacity of the motor is less than 5 HP
then DOL starter can be used and if it is more than that, star-delta starter,or auto
transformer starter, or rotor resistance starter etc. (depends upon types of motor) can
be used.
3. The size and core of cable is also decided Size of the cable is decided by the starting
current of every machine, generally starting current is assumed two times of rated
input current of every machine
3. Type of the cable is decided by the type of supply of the machine, if the machine is
single phase then two core cables is used and if the machine is three phase delta
connected then three core cable is selected.
If the machine is star connected then 3.5 cores or 4- core cable is selected
4. The path and mounting of cable is selected such that it should be a shortest route and
convenience to distribute the power to the machine.
5. Armaoured cable can be selected for indoor power machine and unarmored cables
can be selected outdoor power machine.
c) Draw the wiring diagram for the industrial load shown in Figure No. l show all TCTP,
MAHARASHTRA STATE BOARAD OF TECHNICAL EDUCATIOD
(Autonomous)
(ISO/IEC-27001-2005 Certified)
starters cables with ratings. Assume suitable power factor and efficiency and squirrel
cage induction motors.
Ans: NOTE: Single 1-Ph Induction motor voltage should be 230V but in numerical 400V is
given so assume any one and marks should be given
(Diagram: 4 Mark)
Following Ratings for ICTP, Starters, Cables with rating: (Rating: 4 Mark)
S.No Motor rating ICTP/ICDP Type of Cable Size & P.F Efficiency
Starter Core of cable of Motor
1 For 3-Ph 20 450V, 63A Star- 3.5 core x 6 0.8 0.8
HP 400V I.M: Delta Sqmm
2 For 3-Ph 10 450V, 32A Star- 3.5 core x 4 0.8 0.8
HP 400V I.M: Delta Sqmm
3 For 3-Ph 5 HP 450V, 16A DOL 3.5 core x 2.5 0.8 0.8
400V I.M: Sqmm
4 For 1-Ph 1 HP 250V, 6A DOL 2 core x 2.5 0.8 0.8
230V I.M: Sqmm
OR
MAHARASHTRA STATE BOARAD OF TECHNICAL EDUCATIOD
(Autonomous)
(ISO/IEC-27001-2005 Certified)
HP 735.5
1. For 20HP machine current I L ----------------------(1/2 Marks)
3 VL Cos
20 735.5 14710
Rated input current I L
3 440 0.8 0.8 443.392
Rated /Full load Current in Motor:- = 33.17 Amp ---------------(1/2 Marks)
It is assumed that starting current is two times rated input current.
Starting current = 2 x 33.17 = 66.34 Amp ------------------- (1/2 Marks)
HP 735.5
2. For 10HP machine current I L
3 VL Cos
10 735.5 7355
Rated input current I L
3 440 0.8 0.8 443.392
Rated /Full load Current in Motor:- = 16.585 Amp ---------------(1/2 Marks)
HP 735.5
3. For 5 HP machine current I L
3 VL Cos
5 735.5 73553677.5
Rated input current I L
3 440 0.8 0.8 443.392
1 735.5 735.5
Rated input current I L
230 0.8 0.8 147.2
1 735.5 735.5
Rated input current I L
3 400 0.8 0.8 256
Main Switch for Four Motor = Starting Current of highest rated m/c = full load current of
remaining all m/c
= 66.34 +16.585 + 8.29 + 5
= 96.215 Amp
Rating of Main switch for all Motors = 100 Amps, 415 Volt------------------------- (1/2 Mark)
So use, 6.0 Sqmm , 3 ½ core cable Aluminum 1/ 2.80 mm , 600V grade should
be selected rating of SFU, ICTP switch is 16A, 450V grade should be selected.
Justification: (1 Marks)
This is for single squirrel cage induction motor for single sub-circuits and it is
repeated for other four Motors also after the ICTP (Main switch)
S Main Fuse
ICTP
Λ / Δ starter
M
15 HP 3 Ø Induction motor
OR
Wiring diagram – --------------------------------------------------------------------(1Marks)
b) Also state the procedure to calculate motor current in any industrial installation.
Ans: Following the procedure to calculate motor current in any industrial installation:-
Total output power Total H .P 735.5 (1 Mark)
HP 735.5
Rated input current I L
3 VL Cos
.H .P 735.5
Rated input current I L
3 415 efficency P. f
= …….. Amp (2 Mark)
It is assumed that starting current is two times rated input current.
Starting current = 2 x …….. = …….. Amp by this ampere rating the size and
type of cable is decided. The fuses are also selected for this current. (1 Mark)
c) In a workshop 10 h.p.(metric), 415 V, three phase, 50 Hz motor is to be installed.
MAHARASHTRA STATE BOARAD OF TECHNICAL EDUCATIOD
(Autonomous)
(ISO/IEC-27001-2005 Certified)
Prepare the estimate required for the motor installation assuming PVC surface
conduct type of wiring. The detailed plane is as shown in Figure No. 2.
Ans: Note: Credits may be given step wise for numerical problems. In some cases, the
assumed constant values may vary and there may be some difference in the
candidate’s answers and model answer.
Assuming height of Ceiling if 3 m from the floor.
Motor is installed 1 M away from the nearest wall.
Height of Main Switch is 1.2 M from the floor
Step No. 1:- The out power of induction motor = 10 x 735.5 = 7355 W----------- (1/2 Mark)
Step No. 2:- Input power of I. M = output power of I M / efficiency of IM motor.(1/2 Mark)
Assuming efficiency of I.M is 80 %
Input power of induction motor = 7355 / 0.8 = 9193.75 W
Step No. 3:- To determine the rated current for I.M ---------------------------------- (1/2 Mark)
P 3 VL I LCos VL 400 V
P
IL
3 VLCos
9193.75
IL Cos 0.8 assumption
3 400 0.8
I L 16.587 Amp Rated current 16.587 Amps
Step No. 4:- To determine the size & core of cable:- -------------------------------- (1 /2Mark)
Starting current is assumed two times rated input current for starting surge,
momentary short circuit & overload. Starting current = 2 x 16.587 = 33.175 Amps
So use,
16 Sqmm 4 core cable for the I.M.
MAHARASHTRA STATE BOARAD OF TECHNICAL EDUCATIOD
(Autonomous)
(ISO/IEC-27001-2005 Certified)
Step No. 5:- Determined the size length & dimensions of ICTP earth wire at input cable:-
The rating of main switch is 450 V, 40 Amp ICTP ISI mark
Size of earth wire 8 SWG copper or 6 SWG GI ---------------------- (1/2 Mark)
Length of earth wire = 2 times length of cable
Length of input cable for I .M at actual
Step No.6: Draw the circuit Diagram. -------------------------------------------------- (1/2 Mark)
or equivalent figure
Step No. 7:- Find out the estimation chart with material cost & labour cost: ----- (1 Mark)
Length of cable - it should be calculated as per their assumed distances
Common Material: (Any eight points expected)
1. 4 core Armored cable: (Size of cable is depends on load. & length of cable is
depends on service connection premises)
2. Brick, soft sand for protection of cable.
3. If cable is laid across the public road then Cement pipe, DWC pipe or GI pipe is
required for better protection of cable
4. Cable lug as required size.
5. Cable Gland as required size
6. Feeder piller or cable box or bus bar and cable end box.
7. GI pipe as required size.
8. Cable bushing.
9. 8 SWG Wire
10. Clamps, saddles etc
11. As such all service connection material like main switch, MCB, Energy meter,
MAHARASHTRA STATE BOARAD OF TECHNICAL EDUCATIOD
(Autonomous)
(ISO/IEC-27001-2005 Certified)
Neutral link, IC cut out, earthing nut, screws, and wooden board. etc
12. 16 mm2, 4 core cable having the length of 23 meter and 6 core 2 Mtr for starter.
13. RYB mains indication lamps.
14. 1m x 1m wooden board as main board.
15. Earthing plate 60cm x 60 cm x 3.18 mm – 1 Nos.
16. Earthing sundry char coal and salt.
17. 10 HP Star-delta starters.
18. 8 SWG copper or 6 SWG GI earthing wire, having the length of 50 Mtr.
d) Prepare a schedule of material for electrical wiring of industrial load as shown in figure
No.1 of Q.5 (c)
Ans: (Costing of material is not required marks are only allotted for Material list: 8 Point
Expected Each Point: 1/2 Marks –Total 4 Marks)
Schedule of Material: -
S.No. Name of Material Qty
1 63 A Busbar with Neutral link 01
2 3-ph,4 wire 415V, 60-80A, A.C. supply Energy 01
Meter
3 ICTP 450V,100A 01
4 ICTP 450V,63A 01
5 ICTP 450V,32A 01
6 ICTP 450V,16A 01
7 Star-Delta Starter 03
8 DOL Starter 01
9 8 SWG Earthing Wire 50 Mtr
10 60 cm x 60 cm x 6.36 mm Copper Earthing Plate 01
11 Earthing Nut-bolt 04
12 Earthing Sundry lumsump
13 36 x 36Wooden Board for SDB 03
14 24 x 24 Wooden Board for SDB 03
15 Screw 3 inch length 30 No
16 Screw 1 inch length 50 No
17 R,Y,B Indication Lamp 03
18 PVC Tape 04
19 Saddles 1 box
20 32mm PVC conduit (3 Mtr pipe) 1.5mm thickness 20 pipe
21 3.5 core x 6 Sqmm Al. armoured cable 40 Mtr
22 3.5 core x 4 Sqmm Al. armoured cable 20 Mtr
23 3.5 core x 2.5 Sqmm Al. armoured cable 60 Mtr
MAHARASHTRA STATE BOARAD OF TECHNICAL EDUCATIOD
(Autonomous)
(ISO/IEC-27001-2005 Certified)
OR
HP 735.5
1. For 20HP machine current I L ----------------------(1/2 Marks)
3 VL Cos
20 735.5 14710
Rated input current I L
3 440 0.8 0.8 443.392
Rated /Full load Current in Motor:- = 33.17 Amp ---------------(1/2 Marks)
It is assumed that starting current is two times rated input current.
Starting current = 2 x 33.17 = 66.34 Amp ------------------- (1/2 Marks)
HP 735.5
2. For 10HP machine current I L
3 VL Cos
10 735.5 7355
Rated input current I L
3 440 0.8 0.8 443.392
Rated /Full load Current in Motor:- = 16.585 Amp ---------------(1/2 Marks)
HP 735.5
3. For 5 HP machine current I L
3 VL Cos
5 735.5 73553677.5
Rated input current I L
3 440 0.8 0.8 443.392
1 735.5 735.5
Rated input current I L
230 0.8 0.8 147.2
HP 735.5
5. For 1HP 400V machine current I L
3 VL Cos
1 735.5 735.5
Rated input current I L
3 400 0.8 0.8 256
Main Switch fir Four Motor = Starting Current of highest rated m/c = full load current of
remaining all m/c
= 66.34 +16.585 + 8.29 + 5
= 96.215 Amp
Rating of Main switch for all Motors = 100 Amps, 415 Volt------------------------- (1/2 Mark)
e) State the rating of lamps, Fan and socket outlet points used in residential installation.
Ans:
Rating of lamps, fan and socket outlet points used in residential installation: (4 Mark)
S.No Points used in residential installation Rating of Lamp
1 Lamps 40 watt or 60 watt
2 CFL 20 watt
3 LED 12 watt or 25 watt
4 Fan 60 watt or 100 watt
5 Socket outlet Lighting socket: 100 watt
Power socket : 1000 watt
1. To provide an alternative path for the leakage current to flow towards earth.
2. To save human life from danger of electrical shock due to leakage current.
3. To protect high rise buildings structure against lightening stroke.
4. To provide safe path to dissipate lightning and short circuit currents.
5. To provide stable platform for operation of sensitive electronic equipment.
Diagram for plate earthing : ( 2 Marks)
or equivalent figure
------------------------------------------------------END-------------------------------------------------------