Basic Design of Primary Reforming of Methane Final Report Submitted
Basic Design of Primary Reforming of Methane Final Report Submitted
net/publication/360255849
CITATIONS READS
0 530
1 author:
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
Plant Design on Coversion of Waste Plastic into Fuel Gas and Fuel Oil View project
All content following this page was uploaded by Saroj Raj Kafle on 29 April 2022.
January 2019
Contents
i
List of Tables
ii
Abstract
iii
1 Introduction
Urea is the most widely used fertilizer in Nepal, and so the Nepalese Ministry of Supplies
decided to build a urea factory in Bardaghat, Nawalparasi. The proposed plant is expected
to cost Rs. 72 billion and its annual capacity is estimated to be 700,000 tons. Urea is
normally synthesized from ammonia and carbon dioxide. The ammonia that is used to
make urea is produced by combining hydrogen from natural gas with nitrogen from the
air.[1]
It is known that it is possible to produce urea from natural gas in a two-step method. In a
first step, nitrogen is bound as ammonia, and at the same time carbon dioxide is produced
from the natural gas, while in a second method step the ammonia and the carbon dioxide
are converted to urea. Normally, in the first method step, that is the ammonia synthesis, a
synthesis gas is produced from natural gas, and an oxygen-containing gas, e.g. air, in a
steam reformer, and then in a further method step (“secondary reformer”) the oxidation of
the carbohydrates contained in the natural gas is largely concluded. [2]
The reforming of the hydrocarbon feed takes place in two stages – first, in a direct fired primary
reformer and later in an auto-thermal catalytic secondary reformer. [3] In this report, we will be
dealing with the design of Primary Steam Reformer where, the Natural gas is converted to synthesis
gas.
1
1.1 Primary Reformer [4]
In the primary reformer, synthesis gas is produced by the reaction of natural gas with steam.
Primary reformers are basically fired heater, in which the reforming reaction occurs.
Primary reformers are of different types based on their burner position:
i. Bottom Fired
ii. Top Fired
iii. Terrace Wall
iv. Side Fired
In our design of primary reformer, we have used bottom fired primary reformer with the
tubes lined at the walls of the reformer.
2
2 Design Basis
The primary reformer design has been based on the following data:
Capacity: 2000 kg-mole/hr (Inlet)
Feed and Product Specification: The feed and product specifications were
calculated based on the data provided, using Appendix II.
H2 55.215 3563.178
N2 106.964 106.964
C3H8 18.408 0
CO 0 519.8448
Utilities Requirement:[5]
3
Maximum Allowable NO2 concentration = 100 ppb
Maximum Allowable Particulate Matter = 36.4 micron
For Noise:
Noise levels: Maximum 75db at day, 70db at night
Occupational Health and Safety Guidelines
National Occupational Safety and Health Policy
Design Code: ASME BPVC Section I - Rules for Construction of Power Boilers
Climate Data[8]:
For the location of Bardaghat, the nearest climatic data was found for Bhairahawa for
the years 2012/13.
Approx. Maximum Temperature: 43.8oC
Approx. Minimum Temperature: 3.5oC
Maximum Rainfall: 233.6 mm
Average Rainfall: 22.4 mm
4
3 Process Description [9]
First the hydrocarbon mixture and steam are mixed in the reformer. The conversion of
hydrocarbons to a mixture of CO, CO2 and H2 takes place by two reactions:
1. Steam Reforming
At high temperature (700 – 1100 °C) and high pressure in the presence of a metal
based catalyst (nickel), steam reacts with methane to yield carbon monoxide and
hydrogen. This reaction is strongly endothermic.
CH4 +H2O↔ CO + 3H2
Here the Rate of shift is fast compared to reforming and Methane conversion favored by:
– High pressure
– high temperature
– high steam to carbon ratio
5
4 Process Flow Diagram
6
5 Piping and Instrumentation Diagram
7
5.1 Piping and Insulation Specification [10][11]
Cellular
Steam 7.841 8 40 7.981 8.625 3.15
glass
Natural Cellular
6.787 8 40 7.981 8.625 3.15
Gas glass
Mineral
Syn
25.512 30 80 29 30 Wool 10.98”
Gas
(Rock)
Fuel 33.94 36 40 35.25 36 - -
8
6 List of Equipment and Instrumentation
6.1 List of Equipment
Table 6.1 List of Equipment[12]
EQUIPMENT LIST
SPEC OPERATION DESIGN
ITEM EQUIPMENT INSUL. DRIVING
NO. QTY AND PART MATERIAL TEMP PRESS REMARKS
NO. NAME TEMP(oC) PRESS(Bar) mm SYSTEM
SIZE (oC) (Bar)
H- FIRED Carbon
1 1 - SHELL 65 1 75 1.1 - -
224 HEATER Steel
H- FIRED INCONEL
2 340 - TUBES 1000 38 1100 42 - -
224 HEATER 601
9 FT-211 H-224 STEAM (S) 45.5 50 260 300 5321.06 5400 5200
11 FY-215 H-224 - - - - - - - -
FIC-
12 H-224 STEAM (S) - - - - - - -
212
FIC-
13 H-224 NG (G) - - - - - - -
217
FIC-
14 H-224 FUEL (G) - - - - - - -
221
15 CV-101 H-224 STEAM (S) 45.5 50 260 300 5321.06 5400 5200
STEAM
19 SV-104 H-224 40 45 - - - - -
AND NG
NOR- NORMAL FLOW RATE
MAX-MAXIMUM DESIGN FLOW RATE
MIN- MINIMUM DESIGN FLOW RATE
(1) FLUID STATE (2) LOCATION (3) SIGNAL
L: LIQUID L: LOCAL E: ELECTRIC
G: GAS OR VAPOR AO: ANALOG OUTPUT
S: STEAM
9
Table 6.3List of Instrumentation (Part 2/2)[13]
REFE
LINE RENC
TAG NO. SPECIFICATIONS P&ID
NO. ES
(4)
RFQ
LO RANGE CONN. MATERIAL CONT.
NO./ SIG.
INSTRUMENT C. OF SET SIZE BODY/ELEM ACTIO
MAKE (3)
(2) POINT (INCH) ENT N
R
Nickel-
Temperature Indicator 12-16 0-450 PID-
1 TI-214 L - Chromium/Nic -
(Thermocouple) mV (oC) 0010
kel-Alumel
Nickel-
Temperature Indicator 12-16 0-450 PID-
2 TI-218 L - Chromium/Nic -
(Thermocouple) mV (oC) 0010
kel-Alumel
Nickel- Tempe-
TC- Temperature Controller 12-16 0-850 PID-
3 L - Chromium/Nic rature
222 (Eurotherm T.S.) mV (oC) 0010
kel-Alumel Control
Nickel-
TT- Temperature Transmitter 4-10 0- PID-
4 L - Chromium/Nic -
223 (Thermocouple) mA 850(0C) 0010
kel-Alumel
Pressure Indicator 4- 0-50 Copper-Nickel PID-
5 PI-213 L - -
(Strain Gauge) 20mA (bar) Alloy 0010
Pressure Indicator 4-10 0-50 Copper-Nickel PID-
6 PI-219 L - -
(Strain Gauge) mA (bar) Alloy 0010
Pressure Indicator 4-10 0-50 Copper-Nickel PID-
7 PI-210 L - -
(Strain Gauge) mA (bar) Alloy 0010
Flow Transmitter 0-100 PID-
8 FT-216 L 1-5 v - SUS-316 -
(Differential pressure) (Ft/s) 0010
Flow Transmitter 0-200 PID-
9 FT-211 L 1-5 v - SUS-316 -
(Differential Pressure) (Ft/s) 0010
Flow Transmitter 0-100 PID-
10 FT-220 L 1-5 v - SUS-316 -
(Differential Pressure) (Ft/s) 0010
3:1
FY- 4- PID-
11 Flow Transducer L (steam: - - -
215 20mA 0010
carbon)
FIC- 4-10 0-200 Flow PID-
12 Flow Indicator Controller L - -
212 mA (Ft/s) control 0010
FIC- 4-10 0-100 Flow PID-
13 Flow Indicator Controller L - -
217 mA (Ft/s) control 0010
FIC- 4-10 0-100 Flow PID-
14 Flow Indicator Controller L - -
221 mA (Ft/s) control 0010
ASTM A182
CV- Control valve PID-
15 L - 8 F316
101 (Globe valve) 0010
SS
ASTM A182
CV- Control valve PID-
16 L - 8 F316
102 (Globe valve) 0010
SS
CV- Control valve ASTM A182 PID-
17 L - 8
103 (Globe valve) F316 SS 0010
GV- ASTM A182 PID-
18 Glove valve L - 8
105 F316 SS 0010
SV- ASTM A182 PID-
19 Safety Relief Valve L - 8
104 F316 SS 0010
NOR- NORMAL FLOW RATE
MAX-MAXIMUM DESIGN FLOW RATE
MIN- MINIMUM DESIGN FLOW RATE
(1) FLUID STATE (2) LOCATION (3) SIGNAL
L: LIQUID L: LOCAL E: ELECTRIC
G: GAS OR VAPOR AO: ANALOG OUTPUT
S: STEAM
10
7 Equipment Specification Sheet
Table 7.1 Equipment Specification Sheet
PURCHASER / OWNER : ITEM NO. :
SERVICE : LOCATION :
1 UNIT: PRIMARY REFORMER *NUMBER REQUIRED:
2 MANUFACTURER: REFERENCE:
3 TYPE OF HEATER:TUBULAR REFORMER
4 TOTAL HEATER ABSORBED DUTY, MW. :
5 PROCESS DESIGN CONDITIONS
6 CALCULATED DESIGN
7 PROCESS DUTY MM BTU/HR. 357.1692 392.88
1000.4664 1100.51
` C
8 FIRING DUTY, MM BTU/HR
9 WALL HEAT LOSS, MM BTU/HR 20.0093 22.01 VB
10 PCT FIRING DUTY LOST THRU 2.0000 0.022
WALL, %
11 ADIABATIC FLAME TEMP. FROM 1863.2488 2049.57
LHV, OC
12 RADIATING GAS TEMPERATURE, 1224.5765 1347.03
A
OC
11
52 TUBE DESIGN :
53 DESIGN BASIS: TUBE INCONEL 601[14]
SPECIFICATION
54 DESIGN PRESSURE, BAR 44 (Ministry of Environment, NOTE: TUBES MUST BE REMOVABLE FOR CATALYST
Government of India, 1986) LOADING
O
55 DESIGN FLUID TEMPERATURE, C 407
DESIGN TUBE METAL 1100 Type
56
TEMPERATURE, OC
57 TUBE ARRANGEMENT : A Raschig Ring Nickel
58 TUBE ORIENTATION VERTICAL Catalysts Packing
59 SERVICE TEMPERATURE OF 1100 B Insulating Firebricks
TUBE,0C
60 TUBE OUTSIDE DIAMETER, mm 127 C Carbon Steel Vessel
61 MELTING POINT OF TUBE,0C 1370 Shell
62 TUBE WALL THICKNESS, mm 3.4056
D Burner
63 NUMBER OF TUBES 340
64 OVERALL TUBE LENGTH, m 13
65 TUBE PITCH, mm 191
66 TUBE SUPPROT 25Cr-20Ni
67 AVERAGE TUBESKIN 1100
TEMPERATURE, OC
68 CATALYST: Remarks:
69 CATALYST MATERIAL NICKEL[15]
70 BULK DENSITY, KG/m3 849.74
71 VOLUME OF CATALYST, m3 52.52
72 MASS OF CATALYST, KG 44620.8
73 STACK:
74 TYPE NATURAL
75 AMBIENT TEMPERATURE, K 298.15
76 FLUE GAS TEMPERATURE, K 1333.64
77 ATMOSPHERIC PRESSURE, millibar 1013.24
78 STACK MATERIAL(ASTM AND 316 SS
SPECIFICATION)
79 DRAFT, mm H2O 12.7
80 STACK HEIGHT, m 14
81 REFORMER SPECIFICATION
82 VESSEL SHELL: Carbon Steel SA516-70 [12]
83 REFRACTORY:TYPE INSULATING
FIREBRICKS (C-26) [16]
84 REFRACTORY(ASTM C182-88
SPECIFICATION)
85 THERMAL CONDUCTIVITY, 0.35
W/m.K
86 SOFTENING TEMPERATURE, OC 1200
87 MELTING TEMPERATURE, OC 1650-1700
88 THICKNESS OF FIREBRICKS, mm 63.5
12
8 Conclusion
The inlet temperature and pressure of the feeds were taken at 370oC and 40 bar while the outlet
conditions are at 800oC and 38 bar. The total molar flow rate of inlet being 7220.116 kg-mol/hr,
the outlet total molar flow rate, calculated on the basis of mass balance, was 9252.422 kg-mol/hr.
Also, the calculated heat load was 1.04E+08 watt with 15% excess air.
Raschig Ring Nickel catalysts were used with removable tubes for catalyst loading. The bulk
density and volume of catalyst were taken as 849.74 kg/m3 and 52.52m3 respectively, and mass
of catalyst was calculated to be 44620.8 Kg.
The tubes inside the fire heater being specified as Inconel 601 material was designed with
pressure at 44 bar. Fluid and tube metal temperature were designed as 4070C and 11000C
respectively. Tube arrangement was done vertically with tubes of outside diameter of 127mm
and wall thickness 3.4056mm. Calculated number of tubes was 340 and length was assumed to
be 13m with tube pitch 191mm. The dimension of fired heater was estimated as 120ft * 12ft *
50ft.
Natural type stack of material stainless steel was designed at 1013.24 millibar whose ambient
and flue gas temperatures were 298.15 k and 1333.64 k respectively with height 14m and draft
12.7 mm H2O.
Reformer was specified by vessel shell of carbon steel SA516-70, with the walls lined by
insulating firebricks of thickness 63.5mm with specification of C182-88 whose thermal
conductivity is 0.35 W/m.k and melting temperature is around 17000C.
13
Appendix I: Symbol List
14
Appendix II Reformer Calculations
1. Material Balance in the Reformer[17]
Steam to carbon ratio 3:1
H20 (Steam) = (3*1773.686) =5321.058
Inlet (Ii) Outlet (Oi) 𝑦𝑖
Element (E)
55.215 6787.717-4x-y 𝑂1
H2 z
106.964 106.964 𝑂2
N2 z
1637.112 x 𝑂3
CH4 z
81.358 1773.686-x-y 𝑂4
CO2 z
18.405 0 𝑂5
C3 H8 z
5321.058 1936.402+2x+y 𝑂6
H20 z
0 y 𝑂7
C0 z
I z 1
Total
Total C
1637.112+(3*18.405)+81.35 = x + y + CO2out
CO2out = 1773.686 - x - y
O balance
(2*81.358)+5321.058 = y +(2* CO2out) + (H20out)
H20out = 1936.402+ (2*x) + y
H2 balance
55.215 +(2*1637.113)+(4*18.405)+5321.058 = (H2 )out +(2*x)+ H20
(H2 )out = 6787.717- (4*x) – y
3
𝑃 ∗𝑃 26830
𝐾𝑟𝑒𝑓𝑜𝑟𝑚 = 𝑃 𝐶𝑜 ∗ 𝑃H2 = exp (30.114 − ( ))
CH4 H20 𝑡
1
𝑃CO2 ∗𝑃H2 4400
𝐾𝑠ℎ𝑖𝑓𝑡 = = exp (( ) − 4.036)
𝑃Co ∗ 𝑃H20 𝑡
𝑃𝑖 = 𝑦𝑖 *𝑃𝑡𝑜𝑡
15
2. Polymath results
Variable Value
1 kref 166.1407
2 kshi 1.066177
3 P 38.
4 t 1073.15
5 ych4 0.0730807
6 yco 0.0561847
7 yco2 0.0624342
8 yh2 0.3949428
9 yh2o 0.4116321
10 z 9252.422
Nonlinear equations
1 f(x) = ((yco*P*((yh2*P)^3))/(ych4*P*yh2o*P))-kref = 0
2 f(y) = ((yco2*P*yh2*P)/(yco*P*yh2o*P))-kshi = 0
Explicit equations
1 z = 10604.769-(2*x)
2 yco = y/z
3 yh2 = (6878.717-(4*x)-y)/z
4 ych4 = x/z
5 yh2o = (1936.402+(2*x)+y)/z
6 yco2 = (1773.686-x-y)/z
7 t = 800+273.15
8 kref = exp(30.114-(26830/t))
9 kshi = exp((4400/t)-4.036)
10 P = 38
16
Appendix III Other Calculations
1. Pipe diameter calculation[18]
Rules of Thumb:
- Velocity for gases: 100 ft/s (dry), 60 ft/s (wet)
- Velocity for steam: 100 ft/s (< 8 bar), 150 ft/s (> 8bar)
𝑣 = velocity of fluid
𝑉
Area (a) = 𝑣
4∗𝑎
Diameter (d) = √ 𝜋
Heat load = ∑𝑛𝑗=1 𝐹𝑗𝑜 (𝐻𝑓𝑗 𝑜 +𝐻𝑗 - 𝐻𝑗 𝑜 ) - ∑𝑛𝑗=1 𝐹𝑗𝑜 (𝐻𝑓𝑗 𝑜 +𝐻𝑗 - 𝐻𝑗 𝑜 )o
𝑇
𝐻𝑗 - 𝐻𝑗 𝑜 = ∫𝑇 𝑜 𝐶𝑝𝑖 ∆𝑇
𝑓
𝑜 𝑇
𝐻𝑗 - 𝐻𝑗 = ∫𝑇 𝑖 𝐶𝑝𝑖 ∆𝑇
𝑓
• 𝐶𝑝𝑖 =( A+ BT + C𝑇 2 + 𝐷𝑇 −2 )*R
ℎ𝑒𝑎𝑡 𝑙𝑜𝑎𝑑(𝑄)
• Number of tube(n) = ℎ𝑒𝑎𝑡 𝑓𝑙𝑢𝑥 ∗3.142∗𝐷∗𝑍 ; heat flux = 20,000 Btu/ hr.ft2
• Reactor volume(𝑉1) = 𝑛*𝜋 *𝐷2 *Z/4
17
Component A [19] B [19] C [19] D [19] Hfjo [19]
𝜌 = 849.74 kg/m3
18
9 References
[1] Khanal, R. (2017, April 6). The Kathmandu Post. Retrieved from ekantipur:
http://kathmandupost.ekantipur.com/news/2017-04-06/rs72b-urea-plant-to-be-set-up-in-
nawalparasi.html
[2] Davey, W., & Wurzei, T. (2006). USA Patent No. US7674932B2.
[3] Baboo, P. (2015). Brief Description of Ammonia & Urea Plant with implementation of
Energy Saving Scheme. Research Gate.
[4] C.M., K. (2017). Primary Reformer Design: Production of Ammonia from Naptha.
Department of Chemical & Process Engineering, University of Moratuwa.
[5] Park, K. Y. (2018, November 11). Instructions and Guidelines on Chemical Plant Design
Project. Nepal.
[6] Environmental Protection Agency. (2016, August 31). AirNow. Retrieved from Air
Quality Index (AQI) Basics: https://www.airnow.gov/index.cfm?action=aqibasics.aqi
[7] Ministry of Environment, Government of India. (1986). Industry Effluent Standards. The
Environment (Protection) Rules. India: Central Pollution Control Board.
[8] Open Nepal. (2012-13). Annual Rainfall by Station. Retrieved from Open Data Nepal:
http://data.opennepal.net/keywords/rainfall
[9] IbDybkjaer. (1995). Tubular reforming and autothermal reforming of natural gas — an
overview of available processes. ScienceDirect.
[10] USA Industries. (2019). Piping Schedule Chart. Retrieved from USA Industries:
https://www.usaindustries.com/charts-and-tables/pipe-size-od-id-schedules-chart.php
[11] The Economic thickness of Insulation for Hot Pipes. (Dec 2018). Fuel Efficiency Booklet.
UK.
[12] American Petroleum Institute. (2001). Fired Heaters for General Refinery Service.
Washington DC: API Publishing Services.
[13] Define Instruments. (Jan 2019). Temperature Transmitters. Retrieved from Define
Instruments: http://www.defineinstruments.com/pages/temperature-
transmitters?fbclid=IwAR0hHv5fnM-
n2UNLXTLscUZ8wqhFuWTauAiXVevZVHzG1aFKuG4ZcG23Ti8
[14] Mega Mex. (Jan 2019). Inconel 601. Retrieved from Mega Mex:
http://megamex.com/inconel_601.html?fbclid=IwAR1j6YBcm_sq1REYChLKu9-
KIsxs0HVgC8OmPMTmquOT5Rd8R1-PMWsn9xM
[15] Steam Reforming, Case Study 111.
19
[16] Christy Refractories. (2004, June). Insulating Firebrick. St. Louis, USA: Christy
Refractories.
[17] Himmelblau, D. M., & Riggs, J. B. (2012). Basic Principles and Calculations in
Chemical Engineering. Prentice Hall.
[18] Park, K. Y. (2018). Teaching Material #5. Nepal.
[19] Smith, J. M., Van Ness, H. C., & Abott, M. M. (2016). Introduction to Chemical
Engineering Thermodynamics. McGraw Hill Education.
[20] Sinnot, R., & Towler, G. (2015). Chemical Engineering Design. Elsevier.
20