CH2-2-Solving Project Using AON
CH2-2-Solving Project Using AON
Example1: The following table lists the jobs of a network with their time estimate.
Activity A B C D E F G H
Predecessors ------ ----- A A,B C C E,D F,G
Duration(day) 2 3 2 4 4 3 5 2
a) Draw the project network using Activity on Arrow (AOA).
b) Calculate the time for completing of the project and find the critical path.
1
Mohammad Hameed DUC
Solution: a)
Example2: The following table lists the jobs of a network with their time estimate.
Activity A B C D E F G H
Predecessors ------ ----- A A,B C C E,D F,G
Duration(day) 2 3 2 4 4 3 5 2
a) Draw the project network Activity on Node (AON)
b) Calculate the time for completing of the project and find the critical path.
Solution: a)
c)
2
Mohammad Hameed DUC
d) Critical path (slack= LS-ES=0) (i.e. when LS=ES)
3
Mohammad Hameed DUC
(Note: Slack is the length of time an activity can be delayed without delaying the
entire project).
Example3: The following table lists the jobs of a network with their time estimate.
Activity to tm tp
1--2 3 6 15
1--6 2 5 14
2--3 6 12 30
2--4 2 5 8
3--5 5 11 17
4--5 3 6 15
6--7 3 9 27
5--8 1 4 7
7--8 4 19 28
a) Draw the project network using (AON).
b) Calculate the length and variance of the critical path.
c) What is approximate probability that the jobs on the critical path will be
completed by the due date of 40 day?
d) What due date has about 95% chance of being met?
Solution: a)
Activit Activity predecessor to tm tp Mean duration Variance standard
y
1--2 A ----- 3 6 15 7 4 deviation
2
1--6 B ----- 2 5 14 6 4 2
2--3 C A 6 1 30 14 16 4
2--4 D A 2 25 8 5 1 1
3--5 E C 5 1 17 11 4 2
4--5 F D 3 61 15 7 4 2
6--7 G B 3 9 27 11 16 4
5--8 H E,F 1 4 7 4 1 1
7--8 I G 4 1 28 18 16 4
9
4
Mohammad Hameed DUC
b) The critical path calculations are shown in Figure, the critical path is:
A—C—E—H
c)
(
P ( x ≤ 40 ) =P Z ≤
x−μ
δ ) (
=P Z ≤
40−36
5 )
P ( Z ≤0.8 )=0.7881=78.81 %
P ( 0.95 ) ⇒ Z=1.64∨1.65
x −μ x−36
Z= ⇒1.64= ⇒ x =44.2=44 Week
δ 5
Gant Chart
Solution:
5
Mohammad Hameed DUC
6
Mohammad Hameed DUC
Example4: H.W: Solve all previous examples (AOA) in CH2 using (AON).
7
Mohammad Hameed DUC