Specification Building Tech IV
Specification Building Tech IV
and
Technical Specifications
2
Part I. General Conditions
a. The term “owner” as used in this specification refers to the management of Lungsod ng
Quezon
b. The term “Construction Architect/ Engineer” shall mean the person executing the
contract on behalf of the Owner for the construction of the project and said Construction
Architect’s/ Engineer’s duly authorized assistants or representatives.
c. The term “Contractor” means the entity that will provide all labor, materials, equipment,
and who shall perform all the work necessary for the completion of the project in
accordance with the plans and specifications.
d. The term “Architect” refers to the designer, planner and consultant of the owner.
e. The term “Completion of Contract” shall mean full performance by the contractor of his
obligations under the contract, and all amendments and revisions thereof except his
obligation concerning (1) release of liens and certificate of Contractor, (2) other final
documents. The term “completion of the project” shall mean the contract and all
amendments and revisions thereof. The certificate of Completion, signed by the
Construction Architect/ Engineer and approved writing of the Owner shall be the sole and
conclusive evidence as to the date of completion.
f. The term “default” used herein shall include any such failure by the Contractor to make
progress in the prosecution of work so as to endanger the completion of the project within
the calendar days allotted.
g. Whenever in the specifications or upon the drawings the words “directed”, “required”,
“ordered”, “designated”, “prescribed”, or other words like import are used, it shall be
understood that the direction, requirement, designation or representation of the
Construction Architect/ Engineer is intended. Similarly, the words “approved”,
“acceptable to”, or “satisfactory to” refers to the Architect/ Designer unless otherwise
expressly stated.
h. Where “as shown”, “as indicated”, “as detailed”, or words of similar import are used, it
shall be understood that the reference is made to the drawings accompanying these
specifications, unless stated otherwise. The word “provided” as used herein shall be
understood to mean “provided complete in place”, that is, furnished and installed.
3
DIVISION OF THE SPECIFICATION.
These specifications are divided, for convenience, into sections as set forth in the Table of
Contents preceding these General Conditions. Any mention in these sections or indication on the
drawings of the articles, materials, operations, or methods, requires that the Contractor shall
furnish each item so mentioned or indicated, of the kind, type or design and quality specified or
shown on the drawings. Likewise, the contractor shall furnish all labor, equipment, incidentals,
superintendence necessary to complete the work in accordance with the true meaning and the
intent of these specifications although such articles, materials, operations, methods, quality,
qualifications, or condition is not expressed in complete complete sentences. Where devices,
items, or parts thereof are referred to in the singular, it is intended that such reference shall apply
to as many such devices, items or parts as are required to properly complete the work. The
Contractor shall coordinate the work covered in each section with the work of other sections. The
necessary information - items, accessories, anchors, connections, patterns, templates, etc.- shall
be delivered when required in order to prevent any delay in the progress and completion of work.
4
but shall be performed as if fully and correctly set forth and described in the drawings
and specifications.
c. Deviations from the drawings and dimensions therein given, whether or not error is
believed to exist, shall be made only after written authority is obtained from the
Architect.
a. The progress schedule shall be submitted within two weeks after the date of award of
contract and shall be subject to the approval of and/or modification by the Architect.
b. The process schedule shall be in Chart Form or Critical Path Method (CPM) and shall
show the order in which the Contractor proposes to carry on the work, the dates on which
he will start the several salient features (including procurement of materials, plant and
equipment), and the contemplated dates for completing the same.
5
a. Workmen’s Compensation Insurance covering all employees in statutory limits who
perform any of the obligations assumed by the Contractor under the contract, except as
specified herein.
b. Public Liability and Property Damage Liability Insurance covering all operations under
the contract: limits for bodily injury or death not less than P25,000.00 for one person and
P75,000.00 for each accident; for property damage, not less than P25,000.00 for each
accident and P45,000.00 aggregate for accidents during the policy period.
c. Automobile Liability Insurance on all self-propelled vehicles used in connection with the
contract, whether owned or hired, public liability limits of not less than P25,000.00 for
one person and P75,000.00 for each accident; property damage limit of P20,000.00 for
each accident.
6
b. The Owner reserves the right to require the removal from the project of any employee of
the Contractor if in the judgment of the Owner such removal shall be necessary in order
to protect the interest of the Owner. The owner shall have the right to require the
Contractor to increase the number of his employees and to increase or change the amount
or kind of tools and equipment of at any time the progress of the work shall be
unsatisfactory to the Owner. But the failure of the Owner to give such directions shall not
relieve the Contractor of his obligations to complete the work within the time and in the
manner specified.
c. The manner of performance of the work and all equipment used therein shall be subject
to the inspection, tests, and approval of the Owner. He shall have the right to inspect all
payrolls and other data and records of the contractor relevant to the work. The Contractor
will provide all reasonable documents for such inspection and tests. The Contractor shall
have an authorized agent to accompany the inspector when the final inspection is made
and if requested by the Owner when any other inspection is made.
d. The Construction Architect/ Engineer may recommend to the Owner that the Contractor
suspend the work wholly or in part, for such period or periods if he deems it necessary
due to unsuitable weather or such other condition which are considered unfavorable, for
the satisfactory prosecution of the work, if there is a failure on the part of the Contractor
to comply with any of the provisions of the contract, the Contractor shall not suspend
work pursuant to this provision without written authority from the Owner to do so. The
time of completion herein above set forth shall be increased by the number of days of any
such suspension, except when such suspension is due to the failure of the Contractor to
comply with any of the provisions of this contract. In the event that work is suspended by
the Contractor with the consent of the Owner, the Contractor, before resuming work shall
give the Owner a written notice at least twenty-four (24) hours notice thereof in writing.
7
any payment hereunder so long as any defective workmanship, in respect to the project of
which the contractor shall have had notice, shall not have been remedied.
b. Should any workmanship be found both to have complied with the requirements within
the one-year period after issuance of certificate of completion by the Owner or
Construction Architect/Engineer, the Contractor shall remedy such defect within thirty
days (30) upon written notification by the Owner. In the event the Contractor fails to
make such remedy, the Owner may execute the corrective measures but the Contractor
shall pay the cost involved thereof.
General Condition-11 PAYMENTS TO CONTRACTOR. Within the first seven (7) days of
each calendar month, the Contractor shall request partial payment from the Owner for the
construction accomplished during the preceding calendar month. This shall be furnished in
quadruplicate and certified by the Contractor, recommended by the Construction
Architect/Engineer, and approved by the Owner solely for the purpose of payment. Such
approval however, shall not be deemed approval of the workmanship. Only ninety (90%) percent
of each estimate approved for each month during the construction of the project, shall be paid by
the Owner to the Contractor prior to completion of the project. The Contractor shall submit a
detailed breakdown of the major items as outlined in the accomplished cost breakdown in the
Proposal Form. The approved breakdown will be the basis for payment when each item is in
place or accomplished. Total cost of the detailed breakdown shall be equal to the contract price.
Each billing must be furnished with a copy of the record/ compliance of the construction material
quality control.
8
General Condition-12 PROGRESS PHOTOGRAPHS
a. The Contractor, shall at his expense, furnish to the Construction Architect/Engineer
progress photographs that shall be taken monthly starting when the work begins and
continuing so long as the work is in progress on the exterior or interior of the building,
from station points designated by the Construction Architect/Engineer.
9
10
Part II. Technical Specifications
4. A logbook shall be available at the site. It shall contain the daily activities in the
site, including but not limited to weather condition, delivery, manpower and
other matters pertaining to the condition of the project. It will also serve as the
data for the contractor and the Project Inspector and shall be surrendered to the
CPDMO at the end of the project.
5. Identification Cards of construction workers and engineer/representative shall be
supplied by CPDMO with corresponding fees; it should be worn at all times
while inside the building/campus premises. Those without IDs shall not be
allowed to enter the premises for security purposes.
11
6. No alteration or additional work that will result in an additive or deductive cost
change from the Contract shall be allowed without the approval of the
chancellor.
7. The contractor shall submit at least three (3) options per item for approval.
Complete specifications with product samples shall be submitted by the
contractor to CPDMO and end-user for evaluation. Inspection of the Project
Architect/Engineer in-charge shall be required prior to installation of any
item/material on the construction.
8. Regular coordination meetings shall be conducted with CPDMO, contractor and
End-user for proper project monitoring.
9. Existing conditions of the work site shall be documented by the contractor and
photos shall be taken before commencement of work to ensure such status. Any
damage to the areas due to the contractor's on-going work shall be restored at his
expense.
10. The contractor shall provide a complete copy of "As built plans" of the
project/unit concerned which shall include all the civil, architectural, plumbing,
electrical and other related layouts in 20" x 30" original sheets. It should be
properly drawn indicating all the specifications, layouts, tables and necessary
data. An initial layout should be submitted in a A3 sheet for checking and
approval of Project Architect/Engineer. Final "As built plans" shall be submitted
in 20"x 30" tracing sheets, 3 blueprints with signature of project engineer, and an
electronic Autocad drawing file. A copy of the technical documents and
warranties of the items shall also be submitted in soft and hardcopies.
11. The contractor shall promptly remove from the premises all rubbish, trash,
debris, and all superfluous building materials weekly. After the completion of all
works, restore all areas that were damaged as affected by the construction works
and leave the site clean to the satisfaction of the Project Inspector or his
representative and End-user.
12
12. All materials removed from the unit shall be properly documented prior to
turn-over to the End-user for proper safe keeping. The turn-over document shall
be attached to the contractor's final billing.
1.2 Submittals
13
DIVISION 2. SITE WORK
2.1 SCOPE
The work covered by this section of the specification consist in furnishing all items,
articles, methods, plants, labor equipment appliances and materials and performing all operations
that may be necessary proper or incidental, to complete excavation, filing backfilling and
grading in accordance with this section of specification all applicable plans and drawing, and
subject to the term and condition of the contract.
2.2 EXCAVATION
A. The contractor shall make all necessary excavations for foundations to grades
indicated without extra compensation including all other excavations, required and necessary for
the proper persecution of the work. Incidental excavation to the level the bottom of footings,
compacting and tamping are included in the building contract.
C. In spaces where slab rest on ground, (or on fill) this shall be leveled and accurately
graded with 0.10 mts (4") of gravel and sand, and tampered thoroughly before concrete pouring
is done.
14
Clear the area from all obstructions or as affected by the construction works, except
those structures indicated on the drawings or designated by the Project Architect/Engineer to be
left standing. It shall be properly protected from accidental damage due to construction works
by the erection of suitable barriers upon approval of the Project Architect/Engineer.
Site monitoring shall be a must to the contractor for the effective implementation of the project.
Any discrepancies on plans and actual site conditions shall be properly coordinated with the
Project Architect/Engineer concerned for verification. Regular coordination meetings shall be
done between the contractor or its representative and the Project Architect/Engineer concerned
at CPDMO.
Utility Service/Consumption
Provision of electric and water meter shall be included in the quotation to be
charged to the contractor's overhead. All utility consumption shall be provided with
meters to limit the usage of such during the working period. Payments of bills shall be
made thru the Cashiers Office after the renovation period presenting the statement of
account issued by Accounting upon recommendation of the Chief of CPDMO.
DIVISION 3. CONCRETE
3.1 GENERAL
All concrete work shall be done in accordance with standard "specification for government
reinforced concrete" as adopted by the government in so far as it does not conflict with the
specific provisions specified herein for "concrete masonry works" and the revised proportioning
of concrete as specified hereinafter.
15
3.2 USE CLASS "A" (3000-PSI CONCRETE) FOR FOOTINGS, COLUMNS, BEAMS,
AND ALL CONCRETE SLABS. (2500PSI) FOR SLAB ON FILL.
DIVISION 4. MASONRY
4.1 General
Concrete masonry construction shall include the furnishing of all labor, material, and
equipment, and
4.1.1 Scope
16
performing all operations necessary to execute all concrete masonry construction, as
specified.
Contractor shall make all preparations and do all work necessary to receive and adjoin
other work.
Contractor shall give the work his personal supervision and shall keep a competent
foreman on the job at all times when he is not there himself.
Contractor shall specify the position of all dowels required for masonry on other
construction, including foundations.
Contractor shall arrange for the necessary storage space for construction materials at the
job site.
4.1.2 Submittals
Prior to beginning work, the Contractor shall furnish to the Owner the following:
a. Color sample of Concrete Masonry Units. Unless specified otherwise, color of the Concrete
Masonry Units shall be Desert Sand
4.2 Materials
All materials shall conform to the following standards:
4.2.1 Concrete Masonry Units Masonry units shall conform to Section 202-2.1.1 of the
Standard Specifications. [4/08] 7-2
4.2.2 Mortar
Mortar shall conform to Section 202-2.1.2 of the Standard Specifications, unless specified
otherwise. Mortar shall be Class E with ¼-part lime putty.
4.2.3 Grout
Grout shall conform to Section 202-2.1.2 of the Standard Specifications.
4.2.4 Lime Putty
Lime putty shall be made from approved quicklime or hydrated lime and shall weigh not less
than 83 pounds per cubic foot. Hydrated lime shall conform to ASTM C207, latest. Quicklime
shall conform to ASTM C51, latest. Quicklime shall be slaked and then screened through a
17
16-mesh sieve. After slaking, screening, and before using, it shall be stored and protected for not
less than 10 days.
4.2.5 Reinforcing Steel
Reinforcing steel shall conform to Section 201-2 of the Standard Specifications. Unless specified
otherwise reinforcing steel shall be Grade 60
4.2.6 Mixing
Concrete shall be mixed well using the proportion specified by the Engineer. Hand mixing shall
be done, using shovels, on a level concrete slab or steel plate. Mix aggregate and cement until the
color is uniform. Spread the mixture out, sprinkle water over the surface and ~ix. Continue with
this process until the right amount of water has been mixed in. Mixture shall be free from
impurities such as dirt and grass. If a batch mixer is used, accurate timing and measuring devices
shall be observed as per manufacturer's recommendation.
4.2.7 Moulding
Hand operated machines shall be used as manufacturer's recommendation. The mould of a
powered machine should be filled until six (6) to eight (8) cycles of compaction are required to
bring the compacting head to its stops. Demoulding or removal of the mould shall be done
carefully so that the fresh blocks are not damaged. Fresh blocks shall be protected from rain with
plastic sheets or any suitable covering during the first day and from the drying effects of the sun
and wind until curing starts.
4.2.8 Curing
After being removed from the mold, the Concrete Hollow Blocks (CHB) and Louver Blocks
shall be covered with a plastic sheet or tarpaulin and kept damp and shaded for at least seven (7)
days in order to effectively cure. This can be achieved by continually spraying them with water
or keeping them under water in tanks.
4.2.9 Installation
1. All masonry work shall be laid true to line, level, plumb and neat in accordance with the Plans.
18
2. Units shall be cut accurately to fit all plumbing ducts, opening for electrical works, and all
holes shall be neatly patched.
3. No construction support shall be attached to the wall except where specifically permitted by
the Engineer.
4. Masonry unit shall be sound, dry, clean and free from cracks when placed in the structure.
5. Proper masonry units shall be used to provide for all window, doors, bond beams, lintels,
plasters etc., with a minimum of unit cutting.
6. Where masonry units cutting is necessary, all cuts shall be neat and true to line.
DIVISION 5.METALS
5.00 GENERAL
5.01 SCOPE
A. Furnish all materials, labor, equipment, plant, tools, required to complete fabrication and
erection of all structural steel and miscellaneous steel items complete, as shown and/or as
specified including: Furnishing of anchor bolts for structural steel columns and responsibility for
their correct locations; provide templates; Brackets and miscellaneous iron connections,
shop-connected to structural members; Beam Penetrations as indicated in the drawings;
Installing and removing temporary guys, shores, scaffolding and bracing required for steel
erection.
B. Where so indicated on the plans, structural members shall be joined by welding. The welds
shall be of size and type indicated and shall be made by competent operators.
5.02 RESPONSIBILITY
A. Contractor shall be responsible for the accurate location of all steel work including all items
used to attach materials to other parts of the work.
19
B. Contractor shall see to it that any and all items of work which are to be built into the works of
other trades are installed at the proper time.
C. Contractor shall notify the Architect / Engineer if the steel work shall be fabricated in a shop
other than the site, so that arrangements can be made together with the Project Representative in
the inspection of the delivered materials and in the fabrication of the steel work.
D. Where specified steel sizes and thicknesses are found unavailable in the market, all affected
items shall be upgraded to the next higher level of size and thickness.
5.03 SUBMITTALS
A. Shop Drawings
1. In accordance with the requirements of the General Conditions, furnish complete detailed
fabrication and erection shop drawings including details of all connections for review and
approval of the Engineer.
2. The Engineer will review and approve all shop drawings. Re-submit if any corrections are
required.
B. Proof of Compliance: Submit the following in three (3) copies for review by Testing
Laboratory and Architect.
1. Certified reports of tensile properties and bend tests for steel shapes, bar, and plates.
2. Certificates of conformance for structural steel tubing.
3. Affidavit (in duplicate) that structural steel having a yield strength greater than 36 ksi
conforms to requirements of Drawings and Specifications.
A. Shipping statements shall be delivered in the jobsite. The Project Representative and the
Engineer shall inspect the materials per delivery and may request additional tests on the materials
delivered, if in their opinion, there is reasonable doubt as to the materials specification. The
20
fabrication and delivery of the fabricated structural steel should conform with the approved
schedule of erection and items such as anchor bolts, anchorage and others that have to be placed
in concrete which shall be in jobsite before such concrete structural member will be poured.
Erection marks shall be painted on structural steel members and fabricated sections. Small
structural members such as rivets, bolts, nuts, washers, etc, should be shipped and kept in
properly marked suitable containers.
B. Structural steel members which are stored at the site or a staging area shall be above ground
on platforms, skids, or other supports. Store fasteners and welding electrodes in a weather tight
and dry place until ready for use. Store packaged materials in their original containers.
5.05 EXECUTION
5.07 ERECTION
A. General - The Contractor shall use special care in unloading, handling and erecting the steel to
avoid bending, twisting or otherwise distorting the steel members. The erector shall handle the
materials in such a way as to minimize the damage to the shop coat of paint. The Contractor shall
plan and execute the erection in such a way so that the close fit and neat appearance of the joints
and the structure, as a whole will not be impaired. If temporary braces or erection slips are
employed, care shall be taken to avoid any unsightliness upon removal. Tack welds shall be
ground smooth and holes shall be filled with weld metal or body solder and smoothed by
grinding or filing. The Contractor shall submit to the Architect or Engineer the sequence of
erection for approval.
21
B. Erect items of structural steel in accord with applicable provisions of Reference Standard
1.03.
C. Erection Tolerances: 1. Structural Steel work erection tolerances shall be in accord with
“AISC Specification for the Design, Fabrication and Erection of Structural Steel for Buildings”
and “AISC Code of Standard Practice for Steel Buildings and Bridges”
2. Let all structural members of single rolled shape and built-up members fabricated by riveting
or welding, unless otherwise specified, be straight within the tolerances allowed by ASTM
Specification.
3. Never let compression members deviate from straightness by more than 1/100 of the axial
length between points which are to be laterally supported.
4. Let completed members be free from twists, bends and open joints. Sharp kinks or bends shall
be the cause of rejection of materials.
F. Alignment: No riveting, permanent bolting or permanent welding shall be done until the
structure has stiffened with the resulting stresses and properly aligned.
22
DIVISION 6. WOOD AND PLASTICS
7.1 Materials
· Use flexible cementitious waterproofing on concrete ledges, decks, and related
areas of the building and other concrete surfaces as necessary.
7.2 Application
· Follow manufacturer's specifications and allow only the skilled manpower to apply
the necessary materials.
23
· All works to be done should be inspected and approved by the Project Architect/
Engineer and End-users.
Technical Data
Tested at:
-40.0 8 hrs
-20.0 16 hrs
20.0 16 hrs
120.0 8 hrs
PH 5-6
Proportion 1.2
24
M.F.T. Odeg C
*Durability Excellent
8.3 MATERIALS
All members shall be hot-rolled new billet steel frame and ventilators sections
not less than 1” deep from front to back. Frame members to be equal leg design only at
points where called for by detailed drawings. Zoo-type section of special design, with
offset permitting down-turned leg of the bent member to seat flush when bent is in a
fully closed position shall be used for frame. Ventilator have integral weathering battles
provided double flat parallel weathering contracts of not less than 1⁄4” width on all four
sides of the vent. Muntis shall be 1/8” x 1”.
8.4 CONSTRUCTIONS
25
Corner events shall be electrically butt welded and ground smooth. Corners of
the frames all the window joints and interjections of Muntis with frames and all vent
members shall be coped and electrically yielded, Muntis bars, except where ventilators
accord, are to be continues from jamb to jamb. Muntis cross joints; shall be rigidly and
neatly interlocked with faces flushed. Frame sections at vent sills have weep holes
provide for drainage. Continues whether drips shall be provided where required at the
heads for side hinged ventilator or doors. Windows and doors shall be designed for
glassing from the outside with wire glazing cups and steel casement putty.
26
8.8 ERECTION
B. Standard Anchors;
C. Grouting;
Windows and doors shall be grouted with a non-shrink aggregate as follows;
D. 1. Where tree passage of grout is not hindered by pea gravel, grouting mix
shall be:
1 part embeco non-shrink aggregate
1 part Portland cement
1 part sand
1.5 parts pea gravel (size 1⁄4”-3/4”)
DIVISION 9. FINISHES
9A. Ceiling
· The work covered by this item shall consists of furnishing all ceiling finishes,
equipped with fixing accessories in accordance with Plan and/or shop drawings
and as herein specified.
27
9A.2 Material Requirement
· Use 0.60M x 0.60M x 4.5mm thick Fiber Cement boards with 1/8" groove on
T-Runner
with fixed hanger support; puttied, sanded and ready to receive paint primer
coating.
· Gauge # 12 fixed hanger rod, power load, drive pin, 1-1/2" x 1/8" steel angle and
accessories. Provide support at a maximum of 1.20 m x 1.20 m spacing both ways.
· Fixed hanger rod shall be at 1.20 m maximum interval both ways but provide
additional hanger and support on critical areas.
· Provide all the necessary accessories and framing for proper installation.
· Ensure adequate hanger and support to all the utilities on the area.
· This Item shall consist of furnishing all paints, enamels, varnishes and other
products to be used including labor, tools and equipment required as shown on the
Plans and in accordance with this Specification.
28
· Specified materials shall be delivered to the job site bearing manufacturers' name,
brand name, type of paint, analysis showing all important constituents of the paint,
color of paint and instructions for thinning.
· Store materials in a well-ventilated space designated for the storage and mixing of
paint. Materials delivered to the site shall be properly stored to minimize exposure
to extremes of temperature.
The University reserves the right to subject material samples to test at his expenses.
If such material tests do not meet the specified standards, the cost will be charged to
the Contractor.
9B.4 Submittals
· Submit 2 samples of each and every color or finish (including all coats). Where
the same color or finish Is to be applied over different materials, samples of each
shall be submitted on different materials, where practical.
9B.5 Protection
· Paint materials shall be properly protected from damage, providing for adequate
storage space. Take all necessary precautions to prevent fire, such as keeping oily
29
rags in U. L. approved metal containers or removing from building at the end of
each day's work.
· All work fittings, furniture, etc., are to be suitably protected during execution of
the work. Splashes on floors, walls, etc. are to be removed during progress of
work and on the whole, left clean and perfect upon completion.
· No exterior or exposed painting shall be carried out under adverse weather
conditions, such as extremes of temperature, during rain, fog, etc., or if there is
excessive dust in the air.
· All voids, cracks, nicks, etc., will be repaired with proper patching material and
finished flush with surrounding surfaces.
· Marred or damaged shop coats on metal shall be spot-primed with appropriate
metal primer.
· Defective or damaged items and/or components, which cannot be repaired or
restored to initial conditions, shall be removed and replaced to the satisfaction of
the Architect at no additional cost to the end-user.
9B.8 Cleaning
· Upon completion of the building, the Painting Contractor shall remove all paint
spots from all finished work, remove all empty cans and leave the entire premises
free from rubbish or other debris caused by his work. He shall remove his
30
equipment from the premises. He shall clean off all glass free from paint spots
and smears and shall present the work clean and free from all types of blemishes.
C. Products
9C.1 General:
· Materials are specified to establish the standards of grade and quality desired for
the work, principal pigments and vehicle types and minimum percentage of solids
content by volume.
· The products of Manufacturers not named may be submitted for use provided they
are equal in quality and grade to the primers and finishes specified as approved by
the Architect. If substitute paint products are desired, a statement shall be
submitted to the Architect giving the Manufacturers name, proposed primer and
finish for each paint system, analysis for each type of paint, and the use or uses
intended. Failure to submit such statements will be cause for rejection.
· Refer to the Finish Schedule. All work Is to be completed without deviation from
these unless written approval Is received from the Architect. No extra cost shall
be allowed because of the color variety scheduled.
D. Execution
9D.1 General:
31
· Work-in-place, on which specified work is to be applied, shall be examined to
ensure that conditions are satisfactory for application of specified materials. Any
defect, which may influence satisfactory completion of specified work, shall be
reported, in writing, to the Architect. Absence of such notification will be
construed as acceptance of work-in-place.
· Do not apply exterior paint in damp or rainy weather or until surfaces have
thoroughly dried from the effects of such weather.
· Before the start of painting, remove finish hardware, accessories, plates, lighting
fixtures, and similar Items, as approved by the Architect, except UL. Labels on
Fire Door and Frames, which must not be removed. Use only workmen skilled in
the applicable building trade for removal and reinstallation of finished item
in-place .
(a) Wood
New Surface:
· Surface to be painted should be clean and dry, free from oil, grease, dust,
dirt, contaminants and all loose girt or mortar; sand rough edges remaining,
countersink nail heads for putty applications.
32
· Dust off surfaces completely then wipe with a clean rag.
Repainting:
· Remove scaling, flaking, blistering, and peeling off paint, wire brushing,
scraping, or water blasting. Let dry.
(b) Metal
Nezv Surface:
· Surface to be painted should be clean and dry, free from oil, grease, dust,
dirt, wax, solder flux, and other contaminants by wiping with mineral spirits
or paint thinner.
Repainting:
· Sand wire brush or scrape rusted metals and apply METAL ETCHING
SOLUTION to remove rust. Let it stay for 10 to 15 minutes. Be sure to
wash off surface thoroughly with mineral spirits, letting it dry before
applying paint. Primer should be applied a few hours after application of
metal etching solution before rust sets in.
(c) Concrete
Repainting:
33
· Remove all loose, scaling, flaking and peeling off paint using PAINT AND
VARNISH REMOVER by wire brushing, scraping, or water blasting. Let
dry.
Paint Application
34
15 cm In width. Rollers for applying enamel shall have a short nap. Spray
equipment shall be as recommended by the manufacturer of the paint used. Areas
inaccessible to spray painting shall be coated by brushing or suitable method.
● · Coating: Consecutive coats of paints are to be slightly differing tints
except in the case white. Each coat shall be allowed to harden before the next Is
applied. Rubbing down between coats is to be done with fine abrasive paper.
● · Wood Finishing: Wood to have natural satin varnish finish shall be
stained as required and sealed as soon as such Items are delivered to the job site.
Seal all ends to exclude moisture. Knotting shall be carried out by using shellac
dissolved in spirit or approved ready mixed compound.
● · Defects in Masonry, Concrete, Plaster and Fiber Cement Board: Small
cracks, holes, and other similar imperfections in masonry, concrete and plaster
surfaces,
which show up after the prime-sealer has been applied to the surface, shall be filled
with an approved sparkling compound before application of succeeding coats.
· Final Touch-Up: Upon completion, finish work shall be touched-up and restored
where damaged and left in good condition.
Painting Schedule
General:
35
· Film Thickness: As recommended by paint manufacturer for the paint
specified, includes thickness in mils and number of coats.
Exterior Specialties
Scope of Work
· This item shall consist of Construction of additional weep hole (confer to
CPDMO) including labor, tools, equipment, and the satisfactory performance in
undertaking the proper installation of the system as shown on the Plans and in
accordance with this Specifications
1. Base Units - End panels and back reinforced with internal reinforcing front and rear posts.
36
2. 49 Inch and 84 Inch High Cases - Formed end panels with front and rear reinforcing post channels;
back shall be formed steel panel, recessed 3/4 inch for mounting purposes.
3. Posts - Front post fully closed with full height reinforcing upright. Shelf adjustment holes in front and
rear posts shall be perfectly aligned for level setting, adjustable to 1/2 inch o.c.
4. Secure Intersection of Case Members With Spot and Arc Welds - Provide gusset reinforcement at front
corners.
5. Base Unit Backs - Where utility chases are located behind base units, provide drawer units without
backs and cupboard units with removable backs for access to services. At all other locations, provide
fixed backs at drawer and cupboard units.
6. Bottoms - Base units shall have one piece bottom with front edge formed into front rail, rabbeted as
required for swinging doors and drawers and flush design for sliding doors.
B. Drawers
1. Drawer Fronts - 3/4 inch thick, double wall construction, pre-painted prior to assembly and sound
deadened.
2. Drawer Bodies - Bottom and sides formed into a one-piece center section with bottom and sides coved
and top edges formed. Front and back panels are spot welded to the center section.
3. Drawer Suspension - Heavy duty coved raceways for both case and drawer with nylon tired, ball
bearing rollers; self-centering and self-closing when open to within 3 inches of the closed position.
4. Provide Drawer With Rubber Bumpers - Friction centering devices are not approved.
5. Security Panels For Drawers - Provide security panels for drawers with keyed different locks.
6. File Drawers - Provide with 150# full extension slides for full access and operation. C. Doors 1. Solid
Panel Doors 3/4 inches thick, double wall, telescoping box steel construction with interior pre painted and
sound deadened, top corners welded and ground smooth. Reinforce interior of front panel with welded
steel hat channels. Hinges with screws to internal reinforcing in case and door. Hinges shall be removable;
welding of hinges not approved. Doors shall close against rubber bumpers.
D. Shelves
1. Form front and back edges down and back 3/4 inch. Form ends down 3/4 inch.
2. Reinforce shelves over 36 inches long with welded hat channel reinforcement the full width of shelf.
3. Pull out shelves: Same suspension as specified for drawers.
4. Depth and Weight Capacity: 305 mm , 180 pounds.
E. Corner Base Guards - 102 mm high No. 304 stainless steel corner guards.
37
F. Hardware
1. Drawer and Hinged Door Pulls – Brushed Aluminum rectangular style finger pull.
2. Sliding Door Pulls - Recessed stainless steel, styled and sized to harmonize with drawer pulls.
3. Hinges - Institutional type, five knuckle projecting barrel hinges, minimum 2-1/2 inches long, Type 302
or 304 stainless steel. Provide two hinges for doors up to 36 inches high; three hinges for doors over 36
inches high. Drill each leaf for three screw attachments to door and frame.
4. Door Catches - Adjustable type, spring actuated nylon roller catches.
5. Elbow Catches - Spring type of cadmium plated steel, with a strike of suitable design.
6. Locks - National Lock "Snap-In" Cam Pin Tumbler, heavy duty cylinder type. Exposed lock noses shall
be dull nickel (satin) plated and stamped with identifying numbers.
7. Keying - Locks shall have capacity for 225 primary key changes. Master key one level with the
potential of 40 different, non interchangeable master key groups.
8. Keys - Stamped brass available from manufacturer or local locksmith, and supplied in the following
quantities unless otherwise specified: A. 2 - for each keyed different lock.
INSTALLATION
38
DIVISION 13. SPECIAL CONSTRUCTION
39
A. The contractor shall furnish all labor, tools and materials necessary for the complete
installation of the plumbing system, including all fixtures and connections of the building to the
sewer, or to and from septic vault as the case may be.
B. The plumbing shall also include the water service to all fixtures and equipment within the
building, the water supply pipes to the water main. It also includes the waste, soil and bent pipes.
C. The contractor shall pay all fees and permits incidental to the completion of the work, ready
for service.
D. All works shall comply with the pertinent provisions of the national plumbing code of the
Philippines.
15.3 PIPING
C. Exposed bent pipes in rooms or on the exterior of the building 2 inches diameter shall be of
steel, galvanized pipe. Waste pipes shall be of cast iron, except those exposed in rooms which
shall be nickel plated like traps.
40
15.6 MAKE
Locally manufactured plumbing fixtures shall be provided with U.S. manufacture fittings and
accessories.
15.7 LAVATORIES
The contractor shall provide and set complete ready for service the following
Lavatories:
A. For all toilet rooms, use “Philippine Standard” vitreous China lavatory “New Lucerne”
Modern PF 361, colored, size 16” x 20”, with splash back-front overflow, anti-splash rim
cast-in-soap dish, basin off-center. To right hand side, pocket hanger and integral China brackets,
(or approved equivalents)
B. Elsewhere, “Northern Hill” Grecian acid resisting enameled cast iron built-in lavatory
with stainless steel frame (MF-1824) integral front overflow, anti-splash rim and two
cast-in-soap depression, colored, size 20” x 18” (or approved equivalents)
16.1 GENERAL
16.1. APPLICATION This section applies to all sections of Division 16, "Electrical," of this
project except as specified otherwise in each individual section.
41
16.2. SUBMITTALS
Obtain approval before procurement, fabrication, or delivery of items to the job
site. Partial submittals will not be acceptable and will be returned without review.
Submittals shall include the manufacturer's name, trade name, place of manufacture,
catalog model or number, nameplate data, size, layout dimensions, capacity, project
specification and paragraph reference and technical society publication references, and
other information necessary to establish contract compliance of each item to be furnished.
42
the item does not meet requirements specified, such as "as good as''; "achieve the same
end use and results as materials formulated in accordance with the referenced
publications"; or "equal or exceed the service and performance of the specified material”.
Certifications shall simply state that the item conforms to the requirements specified.
Certificates shall be printed on the manufacturer's letterhead and shall be signed by the
manufacturer's official authorized to sign certificates of compliance.
43
received. Failure to furnish recommendations shall be cause for rejection of the
equipment or material.
A. When the installation is reported in writing by the electrical contractor to be complete and
ready for acceptance, a test as directed shall be made by the electrical contractor in the presence
of the engineer-in-charge.
B. All apparatus, materials and labor required for making test of all work shall be supplied by the
contractor at his own expense.
A. Conduit dust to be installed for this project shall be PVC electrical conduits smooth inside and
free from flaws and imperfections.
B. No conduit of less than 1⁄2 inch nominal diameter will be permitted on any-part of the
installation and shall be larger where so required by the number and size of wires to be installed
therein.
44
All conductors used for this project shall be rubber-covered, double braided,single copper
conductor of the approved type of building wires. They shall be rubber-covered, double braided,
single copper conductors. If run in underground conduits or conduits installed at wet locations,
conductors shall be thermoplastic type “TW” or rubber covered type “RW” use “Phelps Dodge”
electrical wire and cables.
45
PART III. TECHNICAL DRAWINGS
46