NTDC - Program Management May 15V2
NTDC - Program Management May 15V2
NTDC - Program Management May 15V2
A. Background
1. The Government of the Islamic Republic of Pakistan (the Government) and Asian
Development Bank (ADB) has entered into an agreement for the implementation of the Second
Power Transmission Enhancement Investment Program – Tranche 4 on the terms and
conditions set forth in the ADB Loan Agreement. In parallel, the Government has requested
funding from ADB to finance the Power Transmission Strengthening Project subject to the ADB
Board of Directors’ consideration in Q32023.
B. Introduction
1. The monitoring and management of the overall program (initially for only SPA).
2. The monitoring and management of SPA ADB funded contracts (Goods & Plant)
INTERNAL. This information is accessible to ADB Management and staff. It may be shared outside ADB with appropriate permission.
3. The monitoring of NTDC funded SPA civil works contracts.
4. Providing bespoke assistance to NTDC’s project management unit
ADB-401D- 220kV double circuit Plant - design, supply, 1 lot only 16,000,000.00
2022 transmission line for looping installation, testing and
in/out one circuit of the existing commissioning
Jamshoro T.M. Khan 220kV D/C
T/L at Hala Road 220kV
Substation
ADB-401E- Addition and augmentation of six Goods Procurement Lot 1: 750 MVA 500/220kV ATB 7,385,340.00
01-2022 existing grid stations for removal for 500kV Faisalabad West
of NTDC system constraints
Goods Procurement Lot 2: 600 MVA 500/220kV ATB 6,584,224.00
for 500kV Sheikhpura
Goods Procurement Lot 3: 450 MVA 500/220kV ATB 15,210,026.00
for 500kV Dadu, 500kV New
Multan 500kV Rawat
Goods Procurement Lot 4: I.250 MVA 220/132kV ATF 9,051,210.00
for 500kV Guddu and 500kV RYK
(3 Nos.) II.250 MVA 220/132kV
ATF for 220kV Jamrud G/S (2
Nos.)
1
Asian Development Bank
INTERNAL. This information is accessible to ADB Management and staff. It may be shared outside ADB with appropriate permission.
Post Insulators
ADB-401E- 500 kV, 220 kV, 132 kV Control, Plant - design, supply, 1 Lot only 3,700,000.00
02-2022 Relay, AC/DC Panels installation, testing and
commissioning
ADB-401E- Connectors, String Assemblies, Goods Procurement Lot 1: Connectors, String 1,750,000.00
03-2022 Power and Control Cables, and Assemblies, Aluminium Tubes
Conductors and associated Hardware
INTERNAL. This information is accessible to ADB Management and staff. It may be shared outside ADB with appropriate permission.
NTDC- ???? Dadu, 500kV New Multan Grid Civil Works, Erection,
Station Stringing, Testing &
Commissioning
NTDC- ???? Rawat 500kV Grid Station Civil Works, Erection,
Stringing, Testing &
Commissioning
NTDC2- ??? 500kV Guddu Grid Station Civil Works, Erection,
? Stringing, Testing &
Commissioning
NTDC- ???? 220kV Jamrud Grid Station Civil Works, Erection,
Stringing, Testing &
Commissioning
NTDC- ???? 220kV Dharki to Rahim Yar Civil Works, Erection,
Khan Transmission Line Stringing, Testing &
Commissioning
NTDC- ???? 220kV Rahim Khar to Civil Works, Erection,
Bahawalpur Transmission Line Stringing, Testing &
Commissioning
NTDC- ???? 220kV Sheikh Muhammadi to Civil Works, Erection,
Jamrud Transmission Line Stringing, Testing &
Commissioning
2
National Transmission and Despatch Company Limited
INTERNAL. This information is accessible to ADB Management and staff. It may be shared outside ADB with appropriate permission.
Stand Alone 4 (SPB) – Contract List
Funder / Contracts
Estimated
Package General Description
Value (in US$)
Number
INTERNAL. This information is accessible to ADB Management and staff. It may be shared outside ADB with appropriate permission.
6. In essence, the consultant will play an overarching program management role & be
responsible for the monitoring & reporting of the overall program (both ADB &NTDC funded
elements). The construction supervision of the NTDC funded contracts is not part of this
scope.
8. The Consultant shall act as a Program / Project Management Consultant (PMC) for the
project as specified in the SPA project list and provide all services as may be appropriate for a
person or firm acting in the role of a PMC (the “Services”) including but not limited to:
1.1. Consult with the Employer and establish an organization chart for the program
(ADB funded good packages, NTDC funded civil works, NTDC warehouse {where
equipment may be stored}, NTDC Project Management Unit, etc.) establishing the
identity of all key people involved in the project and their respective responsibilities, the
lines of reporting and communication and contractual relationships.
1.2. Prepare a strategic master programme for the projects detailing milestones for
equipment packages and civil works projects. The program is to be prepared taking
into consideration project procurement cycle. Monitor and update such strategic master
programmes as necessary throughout all stages of the project. The strategic master
programme should illustrate all significant milestone deliverables (with dates) for the
entire project. This may entail grouping data from different contracts into one
programme.
1.3. Prepare Programme Execution Plan (PEP, which inter alia, is to include how the
following is to be addressed throughout all stages of the project:
INTERNAL. This information is accessible to ADB Management and staff. It may be shared outside ADB with appropriate permission.
1.4 Monitor and manage the overall program as per the approved PEP.
1.5 Organize the joint kick-off meeting with the Client (NTDC) and ADB in Lahore,
Pakistan with the objective to present the full Consultant’s team for the projects,
confirming the project schedules and roles and responsibilities, including
communication channels & reporting formats / frequency.
1.6 In the event of contractual disputes, assist the Client in collating and preparing
factual documentation and recommend a line of actions. If required by the employer,
the Consultants will attend hearings.
1.7 Provide the Employer with the anticipated cash flow to facilitate stage payments
under the Contracts and the consultant appointments.
1.8 Monitor the disbursement procedures that are agreed between the Client and the
Donor
2. The monitoring and management of SPA ADB funded Goods & Plant contracts.
2.1.2. Review bidding documents and produce a report 60 days after contract
signing with respect to:
Quality of the documents, standard and in partial refer to the national and
international code and standard Performance of chosen goods, materials and
equipment with particular attention to avoid branding and single sourcing.
Early identification of items with long delivery periods
Compliance with relevant statutory requirements
2.1.3. Represent the Employer in all interactions with the supplier and any other
consultants.
2.1.4. Create a program detailing the delivery of all goods to either the NTDC
warehouse or individual sites.
2.1.5. Receive and check all supplier and other consultants’ requests for
payment and recommend payment to the Employer as appropriate.
INTERNAL. This information is accessible to ADB Management and staff. It may be shared outside ADB with appropriate permission.
2.1.7. Assist the Employer in the consultation with any local or other Authority
as and when required on any matter relating to the program and scope of services.
2.1.8. Assist and report finding in settling any dispute or difference relating to
the projects which may arise between the Employer and the suppliers, consultants,
contractors and/or any of the subconsultants / subcontractors.
2.1.9. Where at any time, during projects lifecycles, there is a reported increase
in the project budget or cost to completion, provide all parties with detailed
particulars of such overspend and potential mitigation measures.
2.1.11. Monitor compliance by the suppliers with all schedules and timetables.
2.1.12. Monitor the supplier’s obligation with respect to their obligations linked to
the delivery and installation of equipment on NTDC civil works sites.
2.1.13. Monitor and report on the performance of all suppliers in performing their
duties under their agreements with the Employer. If required advise on remedial and
other measures necessary to improve performance.
2.1.14. Receive instructions from the Employer and communicate these to the
relevant entities for action.
2.1.15. Report to the Employer on the cost and programme implications of any
variations and any delays in progress and advise the Employer on appropriate action
to overcome delays and mitigate costs.
2.2.2. Organize a joint kick-off meeting with the Client (NTDC) and ADB in
Lahore, Pakistan with the objective to present the full Consultant’s Team for the
INTERNAL. This information is accessible to ADB Management and staff. It may be shared outside ADB with appropriate permission.
projects, confirming the project schedules and roles and responsibilities, including
communication channels & reporting formats / frequency.
2.2.3. Review bidding documents and produce a report 60 days after contract
signing with respect to:
Quality of the documents, standard and in partial refer to the national and
international code and standard Performance of chosen goods, materials
and equipment with particular attention to avoid branding and single
sourcing.
Early identification of items with long delivery periods
Compliance with relevant statutory requirements
Compliance with relevant environmental requirements
Compliance with relevant safeguards requirements
Compliance with relevant security requirements
2.2.4. Review all project documents and within 14 days and submit a risk
register to the employer.
2.2.5. Within 14 days of mobilization visit all project sites (if applicable), report
on any LARP issues (if applicable) and propose mitigation measures to the
employer.
2.2.6. Within 28 days of contract award review the proposed transmission Line
routing details and substations layout and report any risks to the employer
2.2.8. Verify project titles, location and status. Assist the Client with formal
handover of sites.
2.2.9. Review and approve all Contractor schedule submittals and comment on
implementation periods.
2.2.11. Monitor the contract and compliance by the contractors and the
consultants in relation their contract obligations.
2.2.13. Attend all meetings as necessary in connection with the works including
site progress meetings, project design meetings and Employer’s meetings at the
request and presence of the Employer.
INTERNAL. This information is accessible to ADB Management and staff. It may be shared outside ADB with appropriate permission.
2.2.14. Monitor the progress of all Works against the overall master programme
or other agreed programmes and timetables. Formally report to the Employer on
progress at monthly intervals and monitor that all programmes and timetables are
adhered to.
2.2.16. Receive instructions from the Employer and communicate these to the
relevant entities for action.
2.2.17. Manage the change management process and monitor the actual costs
incurred against the contract sum (including any provisional sums and Prime cost)
and advise the Employer at regular intervals thereon of any variance against
approved budget.
2.2.18. Report to the Employer on the cost and programme implications of any
variations and any delays in progress and advise the Employer on appropriate action
to overcome delays and mitigate costs.
2.2.19. Monitor and report the contractor’s activities in the coordination of the
work of statutory authorities and service providers with the project and use all
reasonable endeavors to assist the contractor to ensure that all equipment provided
by statutory authorities and service providers are installed on time.
2.2.20. Monitor and report that the testing and commissioning of all plant and
equipment is executed in accordance with the contract programme.
2.2.21. Receive, examine, and certify to the Employer all applications for
payments submitted by the consultants and contractors.
2.2.22. Verify any claims for extensions of time or additional payment made by
contractors under the terms of the construction contract and recommend to the
Employer thereon.
INTERNAL. This information is accessible to ADB Management and staff. It may be shared outside ADB with appropriate permission.
2.2.25. Manage the preparation of the contractors‟ final accounts” including
finalization of the Projects Preliminary Acceptance Certificate
2.2.29. Review and approve the contractor’s design drawings, calculations or any
other design related documentation submitted by the contractor
2.2.31. Liaise with the employer on necessary power outages and shutdown
requirements as required by the Contractors.
2.2.32. Investigate with the consultants and the Employer any site restrictions
arising from rights of way or other easements and arrangements for diversion of
paths, highways and services.
2.2.36. Review and approve Contractor / sub-Contractor’s quality plan and quality
system and provision of recommendations on all quality issues.
2.2.38. Review and approve, the Contractor’s supply and installation schedules
or revisions.
INTERNAL. This information is accessible to ADB Management and staff. It may be shared outside ADB with appropriate permission.
2.2.40. Oversee the contractor’s design of the interface between the supplied
systems and Utilities’ (NTDC) systems as applicable.
2.2.41. After employer approval, issue the completion and take-over certificates.
2.2.43. Review for adequacy and completeness the as-built drawings, operation
and maintenance manuals provided by contractors.
2.2.44. Ensure that the Contractors have submitted final as-built drawings,
operation, and maintenance manuals as per the requirement and quantity specified
in the contracts.
2.2.46. Inspect regularly the records of the contractor’s site activities (site diaries)
and ensure that they adequately document the progress and performance of the
work. Recommend corrections/changes to the records as required.
2.2.49. Examining and approve the program for factory testing and acceptance
proposed by the contractor.
2.2.50. Coordinating with contractors and the employer prior to and during
Factory Tests (FAT) and Type Testing of major equipment or plant (i.e., power
transformer, circuit breakers, measuring transformers, protection and control panels,
SCADA, telecom equipment, underground cables, overhead power conductors, steel
towers, insulators, and other relevant equipment) to be supplied by Contractors.
2.2.52. Monitor that equipment and materials conform with contract specifications
and standards.
INTERNAL. This information is accessible to ADB Management and staff. It may be shared outside ADB with appropriate permission.
2.2.53. Monitor that the equipment and materials do not contain any
internationally banned chemicals or substances.
2.2.54. Review and approve the program for factory testing and acceptance
proposed by the contractor, participate in works acceptance procedures and draw up
the reports for each works inspection.
2.2.55. Ensure that all equipment and materials have been subjected to type
tests already and certified and any additional test described in the Bid documents
have been undertaken.
2.2.58. Conduct factory inspections and performance tests within the framework
of the supply contracts.
2.2.60. Ensure that equipment and materials delivered on site are in conformity
with stipulated specifications and work schedules.
2.2.63. Monitor that contractor has undertaken correct storage of materials and
equipment as per the manufacturer’s storage procedure and recommendation.
2.2.65. Witness and approve the contractor on site tests and commissioning for
each equipment, accessories and materials covered by the Project.
INTERNAL. This information is accessible to ADB Management and staff. It may be shared outside ADB with appropriate permission.
2.2.66. Carry out final inspection of the installation works, including deficiency
lists, witness commissioning tests, perform acceptance procedures for all equipment,
and issue the corresponding completion certificates in accordance with the relevant
conditions of contract with prior consent of the Client.
2.2.67. Review and finalize shop and site performance test procedure for all
major equipment and systems, as well as the review and approval of the
manufacturer’s inspection / test report and test certificates.
2.2.68. Review and approve contractor’s commissioning plan and make comment
to the employer.
2.2.69. Monitor and report upon the progress in relation to the consultant’s /
contractor’s close outs.
2.2.70. At the completion of supply and installation works by the contractors of
the different project packages, the Consultant shall assist the employer with all
activities related to inspection, testing and commissioning of all equipment and
installations and ensure that such installations and equipment are properly handed
over to the employer in acceptable and satisfactory conditions to the requirements
of the respective contracts.
2.2.73. Ensure that all the sites (if any) and support
facilities (storage yards, etc.) are restored and
decommissioned in line with the Contractors
decommissioning plans.
INTERNAL. This information is accessible to ADB Management and staff. It may be shared outside ADB with appropriate permission.
2.2.75. Following practical completion of the works, provide
assistance to the Employer during the initial occupancy
of the building liaising as necessary with the consultants,
facilities manager and others to provide a seamless
transfer of the Employer’s operations.
INTERNAL. This information is accessible to ADB Management and staff. It may be shared outside ADB with appropriate permission.
3. The monitoring of NTDC funded civil works contracts.
These contracts will have NTDC funded construction supervision consultants in place.
Interaction and coordination with these consultants will be fundamental.
3.1 Review bidding documents, bid evaluation reports and other procurement
documents to determine alignment to ADB’s overarching procurement
principles. Propose any changes to ensure alignment.
3.3 Utilizing the employer’s project monitoring dashboard (PMD) system, provide
monthly reports for each contract.
3.5 Laisse with and monitor any third-party safeguards monitoring consultants.
3.7 Ensure that all relevant Environmental, Social, Health and Safety measures
are implemented by providing semi-annual reports and/or any other reports
as per relevant ADB Guidelines.
3.8 Monitor Environmental, Social, Health and Safety related issues closely to
ensure there is no impact on the program
INTERNAL. This information is accessible to ADB Management and staff. It may be shared outside ADB with appropriate permission.
3.10 Review and approve the Contractor’s proposal for remedial actions and
their timeframe for implementation. Monitor any remedial actions.
Gender Monitoring
4.1. Review the gender features and Gender Action Plan (GAP) implementation
practices, institutional policies and strategies of Executing Agency (EA) and
Implementing Agencies (IAs) and identify gaps to address areas of improvement.
4.2. Prepare poverty, social and gender assessment (PSGA) report and collate baseline
data (sex-disaggregated) relevant to the scope and design of the proposed MFFII
Tranche 4 and PTSP projects, Design and Monitoring Framework (DMF) and GAP.
4.3. Identify key gender entry points relevant to project’s overall scope and design and
prepare the GAP for the ensuing project in close coordination with the consultants’
team and NTDC.
4.4. Support NTDC in conducting separate consultations with women staff and
communities and recommend the gender entry points to be incorporated in the GAP
of the proposed projects in the program.
4.6. Assess the NTD’s existing HR policies, internship programs, training programs (from
a gender lens) and gender-specific initiatives
4.7. Based on the assessment, identify the areas for improvement in relation to NTDC’s
HR policies, internship programs, training programs as part of the gender actions
under the GAP.
4.8. Work closely with NTDC to ensure that the communication/social safeguard plan of
the proposed project has special initiatives to reach out women, people with
disabilities, and other vulnerable segments of the population
INTERNAL. This information is accessible to ADB Management and staff. It may be shared outside ADB with appropriate permission.
3.12
5.1. Ensure that all contractors and suppliers (both ADB funded and NTDC funded
contracts) are using the approved contract management plan (CMP). Ensure that
the CMP is submitted and approved within 14 days of contract signing. Sample
CMP template is attached for reference.
7. Risk Management
7.1. Identify, manage, and document, in consultation with the contractor and consultants,
risks to the Project in the form of a risk register (including risk weightings and
potential financial impacts) and recommend mitigation measures in respect of
Project risks. Lead monthly risk management meetings under the direction of the
Employer and attended by the consultants (including the contractor in the
construction phase) throughout the duration of the projects as necessary at intervals
not exceeding one month. The risk registry will be imputed & maintained by utilizing
the employer’s web-based dashboard monitoring (PMD) system.
8. HSE
8.1. Review the contractor’s comprehensive site-specific Health and Safety plan for the
Projects and in consultation with the employer approve the plan. Communicate the
approved plan to all consultants and contractors throughout all project stages.
Request the contractor to update the Health and Safety Plan if unforeseen events
occur and obtain approval from the employer for updated plan. Undertake formal
monthly health & safety audits throughout all stages of the Project to provide the
consultant and contractor (s) with advice and observations for the improvement of
health, safety, and tidiness on site.
INTERNAL. This information is accessible to ADB Management and staff. It may be shared outside ADB with appropriate permission.
8.2. Input monthly HSE statistics for all projects by utilizing the employer’s web-
based dashboard monitoring (PMD) system.
9. Reports
The consultant shall provide (but not limited to) the following reports:
9.1. Provide the Employer with detailed monthly progress reports, including (without
limitation) details concerning the progress of the design and construction, forecast
completion date, a project cost report identifying forecast cost to completion and
variation trends, risk register and mitigation action, health and safety issues, and
recommendations for mitigation measures if required. Monthly project report
template is attached as Appendix A. The consultant must utilize the employer’s
web-based dashboard monitoring (PMD) tool for the creation and submission
of the monthly progress reports. This tool will be provided free of charge and
is to be used to report on (monthly) all of the projects in the program (ADB &
NTDC funded).
1.21 Under the directions and the presence of the Employer, organize, chair, minute
and participate in periodic meetings, throughout all project stages, which are
required to perform these services, providing up to date management reports and
advice on progress and any required risk mitigation measures. The meetings shall
include, but not be limited to, the following:
9.2. Monthly Project Monitoring Report should be as per the approved Contract
Management Plan
9.4. Contract Familiarization Report and Presentation (Due 14 Days after contract
award)
INTERNAL. This information is accessible to ADB Management and staff. It may be shared outside ADB with appropriate permission.
9.4.1. Submit a report to the employer that will include but not be limited
to the adequacy of the contract and project documents.
9.5. Personnel and Mobilization Report (Due 28 Days after contract award)
The approval of the project completion reports by emplyer and the Donor
shall be a payment event of the consultant’s invoice.
INTERNAL. This information is accessible to ADB Management and staff. It may be shared outside ADB with appropriate permission.
11.7 Monthly report as per agreed in the Contract Management Plan
INTERNAL. This information is accessible to ADB Management and staff. It may be shared outside ADB with appropriate permission.
D. Role of Parties
1. Consultant
2. NTDC
b) NTDC shall use its best efforts to ensure that the Government of the Islamic
Republic of Pakistan will grant the Consultants whose names shall be
communicated in advance, the following facilities and exemptions:
Duration of the consulting services is approximately 36 months. The team composition of the
International and National consultants along with their estimated person-months (PM) is
provided in the Table below. Consultant may propose changes in person-month input of
consultants to effectively deliver the optimized outputs. However, the total input from the
international and national consultants should remain as ??? PM and ???? PM respectively.
The Client will provide the Consultant, free of charge, with relevant data, information and
documents which the Consultant may reasonably request e.g., power system data,
transmission/sub-station design specifications, sector data, details of any business planning and
future growth, financial records to NTDC, and any other planning information like land
ownership and acquisition, legal requirements, permits needed and granted, public information,
among others. The Client will arrange and facilitate meetings with relevant institutions and
authorities as required and will provide in such context where possible and requested by the
Consultant translation services which will be at Consultants expense.
It is required that the Consultant has experience in design and supervision of outage
management strategies, construction of new High, Medium and low Voltage Transmission,
Substation Systems and distribution systems (20 kV), for voltage level of 220kV and above,
including experience in training of power utility personnel. The Consultant will deploy a team of
well qualified personnel/experts to undertake field activities who will be supported by a
competent team at the consultant’s home office.
There is a total of ?? projects under this assignment. The team of the Consultants is led by a
Project Director, supported by Project Managers and other technical experts.
INTERNAL. This information is accessible to ADB Management and staff. It may be shared outside ADB with appropriate permission.
All National Consultant roles will be based inside Pakistan, either in Lahore at NTDC’s Head
Quarters or on site. A high percentage of International staff will also be required to be present
in Pakistan on a full-time basis. Where appropriate, a percentage of the International
Consultant’s time may be spent in their home country, but this will require preapproval from
NTDC.
During annual leaves, the Project Director and the Project Managers shall be deputized by
short-term replacement experts duly approved by the client.
The total national and international experts required under this assignment are stated in table
below:
INTERNAL. This information is accessible to ADB Management and staff. It may be shared outside ADB with appropriate permission.
Table 2
International Consultants National Consultants
5 Electrical Engineer
6 Structural Engineer
12 Commercial Manager
Contracts Management
13 Specialist
14 HSE Specialist
Power Control System
and Protection
15 Engineer
Power Distribution
16 Systems Engineer
17 Gender Expert
Subtotal
For the purpose of evaluation of the quality of the proposed staff, it should be underlined that
apart from other important details, the CVs shall clearly indicate the experiences of the staff
including types of activities performed and respective client references including financiers.
INTERNAL. This information is accessible to ADB Management and staff. It may be shared outside ADB with appropriate permission.
The total staffing requirements are estimated to be in the range of:
1. ??? person-months for international staff
2. ??? person-months for national staff
The Client’s expectations of the Consultant’s key staff and requirements for carrying out the
assignment are as follows:
The national and international experts to be hired under this assignment shall have the
expertise and will be responsible for the duties as described below in their relevant position:
Project Director
Major Responsibilities
a) Solely responsible for managing the overall program consisting of the projects
outlined in table 1.
Project Manager
INTERNAL. This information is accessible to ADB Management and staff. It may be shared outside ADB with appropriate permission.
3. Must have at least 3 years’ experience in construction supervision (client side) and
management of high voltage transmission lines, substations or distribution network
projects.
Major Responsibilities
1. Responsible for ensuring that the scope of services as outlined above is undertaken in
a professional and timely manner for the project site they are allocated.
3. Must have experience in the role of a Transmission Lines engineer as part of a client-
side project management / site supervision team.
INTERNAL. This information is accessible to ADB Management and staff. It may be shared outside ADB with appropriate permission.
g. working knowledge of electrical substation facilities and preparation of design for
an assigned system including analysis, calculations, research, selection, layout,
etc., necessary to develop required design documents.
Major Responsibilities
3. Must have experience in the role of a Power Control Systems and Protection Expert
as part of a client- side project management / site supervision team.
Major Responsibilities
INTERNAL. This information is accessible to ADB Management and staff. It may be shared outside ADB with appropriate permission.
2. Preferably have 10 years of relevant experience in development/rehabilitation of
transmission lines, substations, and grid systems.
3. Must have experience in the role of a Power Systems Expert (Power Control in
Substations) as part of a client- side project management / site supervision team.
Major Responsibilities
3. Must have experience in the role of a Power Distribution System Expert as part of a
client- side project management / site supervision team.
Major Responsibilities
Structural Engineer
INTERNAL. This information is accessible to ADB Management and staff. It may be shared outside ADB with appropriate permission.
3. Must have experience in the role of a Civil /Structural Engineer as part of a client-
side project management / site supervision team.
Major Responsibilities
3. Must have experience in the role of an Electrical Engineer as part of a client- side
project management / site supervision team.
Major Responsibilities
INTERNAL. This information is accessible to ADB Management and staff. It may be shared outside ADB with appropriate permission.
3. Must have experience in the role of an Electrical Engineer as part of a client- side
project management / site supervision team.
Major Responsibilities
3. Preferably be well versed with all relevant polices, handbooks, and guidelines of
ADB and in particular Safeguard Policy Statement (SPS) of 2009 that governs the
environmental safeguards of ADB's operations to avoid, or when avoidance is not
possible, to minimize and mitigate adverse project impacts on the environment and
affected people, and to help borrowers strengthen their safeguard systems and
develop the capacity to manage environmental and social risks.
Major Responsibilities
1. Monitor Environmental and Social related issues closely to ensure there is no impact
on the program.
3. Review and approve the Contractor’s proposal for remedial actions and their
timeframe for implementation. Monitor any remedial actions.
4. When necessary, Update the Environment Management Plan (EMP) detailing the
environmental mitigation measures to address each identified impact, and
recommend appropriate environmental mitigation measures.
INTERNAL. This information is accessible to ADB Management and staff. It may be shared outside ADB with appropriate permission.
5. When necessary, Update Initial Environment Examination (IEE),) and all related
documentations.
Major Responsibilities
1. Review the result of contractor’s site/route surveys for the projects to advise on the
most cost-effective design, wherever possible, seeking to avoid involuntary
resettlement and land acquisition.
Gender Expert
Major Responsibilities
HSE Specialist
1. Must have a degree in Environment, Occupational Safety & Health. Engineering or relevant
degree
INTERNAL. This information is accessible to ADB Management and staff. It may be shared outside ADB with appropriate permission.
2. Must have a current relevant health and safety qualification (e.g., NEBOSH
Diploma/IOSH/CSP Certificate or equivalent)
Major Responsibilities
2. Undertake site safety and security patrols to identify any inappropriate practice.
Inform assigned individuals to undertake necessary measure to correct
discrepancies, and assure that corrective actions are followed up.
Note - Any project team members deploying to Pakistan will also be required to obtain security
clearance. This can be arranged but will require the completion of several forms by the
individual. This process can take up to 3 months and so time should be factored in for this.
2. Must have a minimum of 10 years in the execution and administration of large and
complex construction contracts.
Major Responsibilities
The Client shall provide Office Space at their office when required, however, the Consultant
shall make its own arrangement for furnishing, equipment facilities (phone, e-mail, internet,
computers, copying, editing, etc.) Residential accommodation is not provided by the client.
Office space on site shall be provided by the Contractor.
INTERNAL. This information is accessible to ADB Management and staff. It may be shared outside ADB with appropriate permission.
The Consultant shall make his own transport arrangements at all times and for all phases of the
project.
Table 4
Report NTDC ADB
Project Execution Plan 3 hard copies and 1 digital -
copy
Manning/Mobilization 3 hard copies and 1 digital -
Schedule copy
Monthly Reports Utilizing PMD software
Quarterly / Other Reports Three (3) hard copies as well One (1) hard copies as well
as one digital copy as one (1) digital copy
Final Project Completion Nine (9) hard copies as well One (1) hard copies as well
Report as one (1) digital copy as one (1) digital copy
J. Admin Staff
Consultant shall hire admin staff as required by the project for providing document management
system services as well as for other admin services.
Consultant shall hire one Logistics, Admin and Office Manager during the entire period of the
project in order to manage the day-to-day office activities pertaining to logistics, admin and
office management.
NTDC would only provide office space at the NTDC Headquarters (if required). Consultant is
responsible for furnishing and equipment.
The recruitment of consultant will be in accordance with ADB’s Guidelines on the Use of
Consultants (2017), as amended from time to time, using the quality- and cost-based selection
(QCBS) method (80:20). The proposal will be a full technical proposal.
INTERNAL. This information is accessible to ADB Management and staff. It may be shared outside ADB with appropriate permission.