CED GEVGELIJA 20 MW Izvestuvanje-za-namera-Veteren-park-Petrovo 20MW EN
CED GEVGELIJA 20 MW Izvestuvanje-za-namera-Veteren-park-Petrovo 20MW EN
CED GEVGELIJA 20 MW Izvestuvanje-za-namera-Veteren-park-Petrovo 20MW EN
May, 2020
Notice of intention to carry out a project: "Petrovo" Wind Park (40 MW), Municipality of Gevgelija
Content
2
Machine Translated by Google
Notice of intention to carry out a project: "Petrovo" Wind Park (40 MW), Municipality of Gevgelija
1 Investor information
Postal address of headquarters st. "Mark and Engels" no. 1 - 5/2 Skopje, R.
S. Macedonia
e-mail: [email protected]
The construction of the wind park "Petrovo" in the Municipality of Gevgelija aims to use the potential
of renewable energy sources, more specifically wind energy, and thereby contribute to the total
production of electricity in the Republic of North Macedonia. The project envisages the installation
of 11 wind turbines, with a total installed power of 40 MW, at a location in the vicinity of the village
of Petrovo, Gevgelija Municipality.
With the implementation of the project, the Investor will contribute to the production of electricity
from the so-called "clean sources", and thus it will have a positive impact on the environment. By
starting with the implementation of the project activities, the project approaches and contributes to
the realization of the main goals of the Strategy for the use of renewable energy sources until 2020,
the National Strategy for Sustainable Development (2009-2030), the Strategy for the Development
of the Energy of the Republic Macedonia until 2030, the Third National Plan for Climate Change,
December 2013, as well as the Law on Energy ("Official Gazette of the Republic of Macedonia
16/11, 136/11, 79/13, 164/13, 41/14, 151/14 , 33/15, 192/15 and 06/16).
• Construction of a connection to the electric power system through the existing planned and
projected 110 kV transmission line and substation TS 33/110kV of the wind park "Dren"
which is under construction and construction of TS Petrovo 35/110kV.
3
Machine Translated by Google
Notice of intention to carry out a project: "Petrovo" Wind Park (40 MW), Municipality of Gevgelija
In accordance with the Decree on the determination of projects and on the criteria on the basis of
which the need to implement the procedure for the assessment of environmental impacts is
determined ("Official Gazette of the Republic of Moldova" no. 74/05, 109/09, 164/12 and 202/16),
this Project is categorized in the group of generally defined projects for which the need to
implement an environmental impact assessment procedure is determined - Annex II1 ,
Point 3-Energy, (i) Installations for the use of wind power, for the purpose of energy
production (so-called wind farms).
Based on this, the Developer has prepared this Notice of Intent to Carry Out a Project, along with
a checklist to determine the need for environmental impact assessment and a checklist for
determining the extent of environmental impact assessment.
The increasing need for electricity in recent years emphasizes the importance of building and
using energy systems from renewable sources. The implementation of the "Petrovo" Wind Park
project will contribute to increasing the share of renewable energy sources in the total production
of electricity in R. S. Macedonia.
Wind energy, as a renewable energy source, has the highest growth rate in the last two decades
and is considered a very important source of electricity for the future. The use of wind energy in
global world electricity production in 2020 is estimated to account for 12%.
In the past period, several studies have been done to determine the potential of wind energy in
Macedonia and to select the most suitable locations for the construction of wind power plants.
According to the geographical location and relief configuration, suitable
locations in Macedonia for the construction of wind power plants are the valley of the river Vardar, that is
Povardarieto, Ovche Pole around Sveti Nikole, as well as the higher mountain parts where there
are high wind speeds. One of the several projects and studies is the produced wind energy atlas.
In accordance with the prepared atlas of wind energy2 and in accordance with the Strategy for
the use of renewable energy sources (RES) in RS. Macedonia, the location in question belongs
to the second group of most favorable locations for the construction of wind power plants. The
following table presents data on the 15 most favorable locations for the construction of wind farms,
including our subject location.
1
Projects for which the need to implement a procedure for assessing the impact on animals is determined
environment (Generally defined projects)
2
Wind Energy Resource Atlas and Site Screening of the Republic of Macedonia, AWSTruewind, June 2005
4
Machine Translated by Google
Notice of intention to carry out a project: "Petrovo" Wind Park (40 MW), Municipality of Gevgelija
Table 1 Data on the most favorable locations for the construction of wind power plants3
Speed of Lowest wind CF*estimate at
P (MW)
80 connection costs in m (m/s)
Elevation (m.a.s.l.)
EEC (million €)
1. 1896 8.41 2.02 0.389 25
2. 2079 7.97 2.10 0.338 25
3. 566 7.35 1.50 0.338 24.9
4. 1994 7.63 2.00 0.325 25
5. 2088 7.85 2.38 0.329 25
6. 1159 7.53 3.76 0.347 25
7. 1453 7.45 2.14 0.324 25.4
8. 641 6.96 1.39 0.313 26.4
9. 2511 8.06 2.55 0.325 25.4
10. 408 7.04 1.39 0.305 25
11. 2003 7.30 2.13 0.306 25
12. 1998 7.43 3.05 0.314 25.9
13. 2134 7.13 1.99 0.288 25
14. 2319 7.29 2.92 0.297 27.4
15. 1577 6.68 1.79 0.272 25.9
*CF = W/(8760-P) where W is the annual electricity production and P is the installed power of the wind farm; CF is a factor of annual
engagement of electricity with the installed power
The following picture shows all the most favorable locations for the construction of windmills in RS.
Macedonia together with the location in question (point 8 and point 3 in Figure 1).
Subject
location
Figure 1 Map of the most favorable locations for the construction of wind farms in R. Macedonia4
3
Strategy for the use of renewable energy sources in the Republic of Macedonia, June 2010
4
According to a study based on satellite images from AWSTruewind - Wind Energy Resource Atlas and Site
Screening of the R. of Macedonia, AWSTruewind, June 2005
5
Machine Translated by Google
Notice of intention to carry out a project: "Petrovo" Wind Park (40 MW), Municipality of Gevgelija
The subject location in Petrovo is included in the second group of potential locations for the construction
of wind power plants. For this group of locations there are no measured values, for which measuring
stations should be installed, and expected production obtained. However, the locations are similar in
configuration to the locations where there are measured values
or they are located near them, so it is to be expected that theirs is too
production would be within the same limits as for the measured locations of the first group.
The total installed capacity of wind farms by 2030, in Rs. S. Macedonia
it is planned to be around 360 MW, with an expected annual production of around 720 GWh.5
At the site in question, for the construction of the wind park "Petrovo", Municipality of Gevgelija, it is
planned to install 11 columns for wind turbines of the Goldwind brand with a power of 4.2 MW each or
with a total operating power of 40 MW.
- Minimum operating wind speed Vmin = 2.5 m/s - that is, it is the speed at
which starts with the production of electricity;
- Maximum operating speed Vmax= 25 m/s - is actually the speed at which the turbine
it stops working.
• rotor - 3 blades that convert wind power into low-speed mechanical power;
The appearance of the wind turbines and their components are shown in the following figure.
5
Strategy for the use of renewable energy sources in R. Macedonia until 2020, MANU June 2010 http://manu.edu.mk/wp-content/uploads/
2017/10/%D0%A1%D0%A2%D0%A0%D0%90%D0%A2% D0%95%D0%93%D0%98%D0%88%D0%90-
%D0%97%D0%90-%D0%98%D0%A1%D0%9A%D0%9E%D0%A0%D0%98%D0%A1%D0%A2%D0%A3%D0%92% D0%90%D0%8A%D0%95-
%D0%9D%D0%90-%D0%9E%D0%91%D0%9D%D0%9E%D0%92%D0%9B%D0%98%D0%92%D0%98%D0%A2% D0%95-
%D0%98%D0%97%D0%92%D0%9E%D0%A0%D0%98-%D0%9D%D0%90-%D0%95%D0%9D%D0%95%D0%A0 %D0%93%D0%98%D0%88%D0%90-
%D0%92%D0%9E-%D0%A0%D0%95%D0%9F%D0%A3%D0%91%D0%9B%D0%98%D0%9A%D0%90-
%D0%9C%D0%90%D0%9A%D0%95%D0%94%D0%9E%D0%9D%D0%98%D0%88%D0%90-%D0%94%D0%9E- 2020-
%D0%93%D0%9E%D0%94%D0%98%D0%9D%D0%90.pdf
6
Machine Translated by Google
Notice of intention to carry out a project: "Petrovo" Wind Park (40 MW), Municipality of Gevgelija
The turbine rotor is a free-standing construction with three blades (propellers) mounted on a
support pole. The diameter of the turbine is 155 m.
The aerodynamic profile of the propeller is the main factor that determines the way the kinetic
energy of the wind is converted. Due to the difference in the flow of wind speeds from the back
and the front, a difference in pressure occurs, which results in a driving force, i.e. causes a
torque. In addition to this force, the force of direct wind pressure also acts on the propellers, but
this influence is very small.
Turbine power is regulated by pitch control and rotor speed is variable to maximize aerodynamic
efficiency and reduce load on the gearing system during power control.
7
Machine Translated by Google
Notice of intention to carry out a project: "Petrovo" Wind Park (40 MW), Municipality of Gevgelija
Generator
The generator is double fed, flat rotor and slip rings. It is cooled by an air exchanger. The control
system allows variable speed operation using frequency control of the rotor intensity. The features
and functions of this generator are:
ÿ Optimal operation, maximizing production and minimizing load and noise, thanks to variable
speed operation.
The pole on which the wind turbine will be mounted is steel, conical and tubular. The height of the
pillar is 110 m.
Foundation
Standard foundations have a combined truncated cone and cylindrical shape. They will be designed
using calculations based on the load capacity of the wind turbine and
geological surveys of the soil.
During the construction phase of the wind turbines, control of the embedded concrete masses
should be carried out in accordance with the applicable regulation and building regulations in the
Republic of Moldova. S. Macedonia. To dimension the foundations of each wind turbine,
geomechanical testing is currently being carried out at the site. Based on the field and laboratory
tests, a report will be prepared for geological, engineering-geological, hydrogeological,
geomechanical and geophysical research for the locations planned for the installation of each wind
turbine. The results of the Report, as well as the assessment of possible impacts, will be part of
the environmental impact assessment study.
Regarding the technical characteristics, the access roads will be dimensioned according to the
needs for installing the wind turbines. They will be made of natural material (macadam), with a
width of about 5 m, a gradient of less than 8% and a radius of curves over 35 m.
8
Machine Translated by Google
Notice of intention to carry out a project: "Petrovo" Wind Park (40 MW), Municipality of Gevgelija
During the construction phase, the access roads should enable the transport of the machinery
for the execution of the works, the transport of the necessary material for the construction of the
wind turbines and the equipment that will be installed.
The following tabular overview provides coordinates of 11 proposed locations for the installation
of wind turbines.
Satellite image of the project site on which the location of the wind turbines is marked
turbines is given in the following figure.
9
Machine Translated by Google
Notice of intention to carry out a project: "Petrovo" Wind Park (40 MW), Municipality of Gevgelija
The nearest settlements around the project area are the following: in the southeast n.m. Gabrovo,
to the east via the highway "Prijatelsto" n.m. Miravci, to the west the Municipality of Kavadarci,
and to the northwest the Municipality of Demir Kapija.
The following pictures show topographical maps of the project area in a scale of 1:25000 with the
location of the wind turbines from the wind park "Petrovo".
10
Machine Translated by Google
Notice of intention to carry out a project: "Petrovo" Wind Park (40 MW), Municipality of Gevgelija
T 11
T1
T 10
T2
T4
T8
11
Machine Translated by Google
Notice of intention to carry out a project: "Petrovo" Wind Park (40 MW), Municipality of Gevgelija
T7
T3
T9
T6
T5
Figure 5 Topographic map of the area with marked locations of 11 wind turbines (1:25000)
12
Machine Translated by Google
Notice of intention to carry out a project: "Petrovo" Wind Park (40 MW), Municipality of Gevgelija
The following picture shows the location of the new wind turbines and the proximity of the existing wind farm "Dren",
as well as the locations of the planned future projects for the wind farm "Koprišnica", "Petrovo" and the expansion of
the wind farm "Dren 2".
T9
A location for the future
expansion of
T2
Location of T8 Dren Wind Park
wind turbines for
T5
wind farm
"
"Peter T4
T3
T7 T6
T11
T10
T8
T4
T1
T2
T3
T5
T7
T6
T9
13
Machine Translated by Google
Notice of intention to carry out a project: "Petrovo" Wind Park (40 MW), Municipality of Gevgelija
Municipality of Gevgelija
The openness of the municipality of Gevgelija to the Thessaloniki valley through the Vardar valley
conditions the strong influence of the Mediterranean climate in this region, especially expressed in
the valley part up to 300 m above sea level, and less changed in the hilly area up to
600 m above sea level. Mountain climate prevails only in the highest parts of Kozhuf mountain. The
average annual temperature in Gevgelija is 14.3°C. The average annual amount of precipitation is
745.2 mm3 . The distribution of precipitation is not uniform, it is most abundant in autumn and least
abundant in summer. The most prominent are the Vardarec and Jug winds. Vardarets comes from
the north, and the south from the southeast direction.
The territory of the municipality covers part of the basin of the lower reaches of the Vardar River,
which is the most important watercourse that drains surface and underground waters. Larger
watercourses that flow into the Vardar River are the Suva, Konjska, Mrzenska, Kovanska, Zuica,
Petrushka and Javorica rivers. The tributaries of Vardar are relatively shallow, which is why some of
them dry up during the summer. The hydrographic structure also includes the reservoirs in
Bogorodica, Toplec, Dos, Kalica and others. The municipality has rich sources of mineral and thermo-
mineral water. One of the most famous sources of mineral water is located at the Smrdliva voda
tourist site. While there are rich springs of thermo-mineral water near the Negorski spas and near
the village of Smokvica.
The rivers Petrushka and Stara reka pass in the surroundings of the project area.
14
Machine Translated by Google
Notice of intention to carry out a project: "Petrovo" Wind Park (40 MW), Municipality of Gevgelija
Project area
The municipality of Gevgelija covers the Lower Povardarie, that is, the Gevgelija valley, which
stretches from the northern and southern sides of the Macedonian-Greek border.
15
Machine Translated by Google
Notice of intention to carry out a project: "Petrovo" Wind Park (40 MW), Municipality of Gevgelija
The area is distinguished by areas of hilly plain terrains, which rise up to about 600 m.a.s.l., on
which semi-vial - deluvial and cement brown soils develop, and mountainous area, from 600 -
2000 m.a.s.l., dominated by sour -
brown soils. From a geological point of view, the terrains are built mostly of gabbro and diabase,
and partly of granites and carbonates.
The relief is varied and consists of numerous hills, hills and mounds between which are wide and
shallow valleys that gravitate towards the south. Very interesting is the appearance of three lonely
hills (Dinqut, Mrzenski and Vardarski Rid) whose origin is probably erosive, but possible tectonic
influences are not excluded. These hills give the city of Gevgelija special landscape values and
mark its identity.
The location of the project area is in a region that also belongs to the Vardar region
seismic zone (Serbian-Macedonian massif subzone), which are some of the seismic ones
the most active zones in Macedonia and the Balkans.
According to the seismic scale, the project area belongs to the VIIIº MCS of increased
seismic activity.
16
Machine Translated by Google
Notice of intention to carry out a project: "Petrovo" Wind Park (40 MW), Municipality of Gevgelija
Project area
Under the influence of the Mediterranean climate in the Municipality of Gevgelija there is a
xerothermal community of the prnar, in which numerous Mediterranean species take part. In
a vertical view, the oak blagun appears above the prnar, and above it the forest is represented
by three belts of beech forests, known as sub-mountain, mountain and sub-alpine, and fir is
also present in them.
In terms of fauna, in the forest areas of Gevgelija you can meet partridge, wild goose and
harrier, pike, quail, black and bearded vulture, griffon vulture, ringed mouse, common kestrel,
imperial eagle, wild boar, rabbit, bear, wolf, fox, chamois, snakes, wild cat, badger and squirrel
The Vardar River has a fish stock of the following types of fish: catfish, carp, barbel, chub and
whiting.
In the Municipality of Gevgelija, more specifically, the Municipality of Petrovo, the church "St.
Spas" - or "Ascension of Christ". The church was built before 1860. But around 1860-1861 it
was burned down, and then -
in 1867, it was restored by the local population. According to his
17
Machine Translated by Google
Notice of intention to carry out a project: "Petrovo" Wind Park (40 MW), Municipality of Gevgelija
architectural form, the church is three-nave with wooden ceilings, with a semi-circular apse
on the eastern wall and a female section on the western wall. The interior of the temple is
decorated with very beautiful frescoes, painted on the northern and southern walls. The
iconostasis is carved. All icons, which fill the iconostasis, date from the 19th century, with
the names of the donors.
The following pictures show maps of protected areas and cultural heritage in R. S. Macedonia,
in accordance with the data from the National Spatial Plan of R. Macedonia (2002 - 2020)6 .
6
http://app.gov.mk/wp-content/uploads/2015/04/%D0%9030104-PP-na-RM-2002-2020.pdf
18
Machine Translated by Google
Notice of intention to carry out a project: "Petrovo" Wind Park (40 MW), Municipality of Gevgelija
Project area
19
Machine Translated by Google
Notice of intention to carry out a project: "Petrovo" Wind Park (40 MW), Municipality of Gevgelija
Project area
20
Machine Translated by Google
Notice of intention to carry out a project: "Petrovo" Wind Park (40 MW), Municipality of Gevgelija
Within the planning scope, no characteristic species of flora and fauna have been recorded.
In the area where the realization of the project is planned, there are no cultural-historical
monuments and/or localities.
21
Machine Translated by Google
Notice of intention to carry out a project: "Petrovo" Wind Park (40 MW), Municipality of Gevgelija
The impacts that will result from the realization of the "Petrovo Wind Park" project will be
considered in the construction and operational phase. They will be the same
assessed against receptors.
In order to evaluate the possible impacts from the implementation of the Project, below is an
overview of the planned activities that will be carried out in the construction and operational
phases.
a) Construction phase
The construction phase includes the preparation of the construction site, i.e. marking and
clearing the terrain, transportation of materials, raw materials, waste and workers, excavation
of foundations and foundation of the pillars, excavation of channels for installation of energy
infrastructure, concreting, transportation and installation of the equipment, final construction
works and clearing of the construction site.
During the construction activities, the following will be generated: fugitive emissions of dust
and exhaust gases in the ambient air from the construction machinery, municipal waste water
from the workers, different fractions of waste, noise and vibrations from the machinery, etc.
Based on the above in the construction phase, negative impacts on air quality, groundwater,
soil, noise, landscape and biological are possible.
variety.
b) Operational phase
The operational phase involves the operation of the wind farms and the production of
electricity. The equipment will be able to work continuously (depending on the dynamics and
parameters of the wind energy), without the continuous presence of employees. Regular and
extraordinary servicing of the wind turbine equipment will be carried out. The competent
companies will regularly maintain the equipment and devices for the transmission of electricity.
Negative impacts in the operational phase can occur in the event of a breakdown/
breakdown of a wind turbine, during which certain fractions of waste may be generated due
to repair of a defect, and the activities may affect the soil and
biological diversity.
c) Post-operative phase
The activities in the post-operational phase are similar to the activities that will be performed
in the construction phase. The post-operational phase covers the period after the end of the
operational life of the wind turbines. This phase includes removing the infrastructure and
rehabilitation/remediation of the site and returning it to its original condition or replacing the
wind turbines with new ones.
22
Machine Translated by Google
Notice of intention to carry out a project: "Petrovo" Wind Park (40 MW), Municipality of Gevgelija
Based on the above, it cannot be predicted whether actions will be taken to remove the wind
turbines or whether they will be replaced. Impacts will depend on future decommissioning
techniques available at the time of decommissioning, which cannot be predicted as they are
not subject to
consideration.
Making noise ÿ ÿ
Dust ÿ x
Effluents ÿ x
Overnight operation x ÿ
Intensification of traffic ÿ ÿ
Transboundary impacts ÿ x x
Below is a more detailed description of the possible impacts on the environment from the
implementation of the project in the construction and operational phases and measures to
mitigate them.
Ambient air
23
Machine Translated by Google
Notice of intention to carry out a project: "Petrovo" Wind Park (40 MW), Municipality of Gevgelija
The amount of generated dust emissions will depend on the way the activities are performed,
the applied measures of good construction practice, the characteristics of the mechanization,
the duration of the construction activities, meteorological conditions, etc. The emission of
exhaust gases will depend on the composition of the fuel that will be used (gasoline, diesel,
gas), the frequency of movement of machinery and the duration of construction activities.
When diesel fuels are burned, vehicles and other equipment generate gases, known as
greenhouse gases. The sources of greenhouse gas emissions are: vegetation cleaning
equipment, transportation of materials
and improperly disposed organic waste. Sensitive receptors are the biological diversity in the
area and the performers of the activities.
The impacts on ambient air quality, which originate from the listed emissions, at this stage,
are evaluated as negative, direct, of low intensity, short-term, reversible, with a certain
probability of occurrence, and of a local character.
Measures to reduce impacts: application of good construction practice, water spraying with
the help of tankers on access roads and in locations where they will be carried out
excavations, use of high-quality fuels, regular control of construction machinery, turning off
the engines of machinery and vehicles when they are not in use
movement or do not perform any activity.
Operational phase: In this phase, the generation of emissions in the ambient air is not
expected, with the exception of the occurrence of defects and breakdowns in which there is a
need to use machinery.
Impact reduction measures: In the event of a breakdown or breakdown, it is recommended
to apply the impact reduction measures specified for the construction phase.
24
Machine Translated by Google
Notice of intention to carry out a project: "Petrovo" Wind Park (40 MW), Municipality of Gevgelija
of machinery and vehicles when they are in the so-called "empty of" i.e. not in
operability.
Operational phase: In this phase, the generation of noise emissions from the operation of the
wind turbines is expected, as well as in cases of regular service and/or occurrence of defects
and breakdowns in which there is a need to use mechanization. The expected increased noise
level is due to the fact that the wind turbines themselves generate
noise of about 100 dB, which decreases with increasing distance. Since there are no
settlements in the immediate vicinity of the project area, sensitive receptors are the biological
diversity in the immediate surroundings of the area.
Measures to reduce impacts: Application and installation of turbines that produce low levels
of noise or the so-called "quiet turbines". In the event of a breakdown or breakdown, it is
recommended to apply the measures to reduce the impacts specified for the construction
phase.
Lead
Impacts on surface and underground water are not expected either in the construction or in
the operational phase, if one takes into account the location of the locations where the wind
turbines will be installed and the depth of the excavations for laying the foundations and
channels for laying the energy infrastructure, as well as the fact that there is no surface flow in
the immediate vicinity of the location, it can be considered that minimal indirect impacts are
possible only on groundwater, which would eventually appear as a result of incident situations.
The generation of sanitary waste water during the construction phase by the hired workers is
also expected. Adequate measures are foreseen for these impacts.
The impacts on surface and underground waters in the construction and operational phase
are evaluated as negative, indirect, of low intensity, short-term, reversible, with a possible
probability of occurrence, of a local character.
Soils
Construction phase: Impacts on the quality of the soil are expected during the performance
of geotechnical investigations of the stability of the substrate, excavations and leveling of the
terrain, the construction of internal access roads, manipulation of the mechanization. As a
result of the above activities, there is a possibility of erosion, compaction of the soil, reduction
of its fertility,
25
Machine Translated by Google
Notice of intention to carry out a project: "Petrovo" Wind Park (40 MW), Municipality of Gevgelija
pollution etc. Soil pollution can also occur as a result of inadequate management of waste
fractions, accidental leakage of oils and fuel from machinery, etc.
The impacts on the soil during the construction phase are assessed as reliable, negative,
direct, with low to moderate intensity, short-term, reversible and irreversible, of a local
character.
Biological diversity
Construction phase:
In order to determine the impacts of the project on biological diversity, an extensive research
and monitoring of the existing condition of the flora and fauna of the site in question will be
carried out and mitigation measures will be proposed for all phases of the project. The project
area and the wider surroundings are not characterized by vegetation that is of particular
importance and therefore there is no need for a special value for protection. The removal of
vegetation can cause erosion in places where construction activities will be carried out. The
use of construction machinery will generate a high level of noise, the generated hazardous
waste and the incidental spills of hazardous materials and substances may cause negative
impacts on animal species in the project area.
The impacts on biological diversity in the construction and operational phase are assessed as
possible, local, negative, of medium intensity and duration determined by the duration
of the construction works and the operation of the wind turbines.
The current operation of the Petrovo wind farm will have an impact on the birds present on
the site and possibly bats if identified during the monitoring phase. At this stage, it is not
possible to precisely determine the size and degree of impact, but based on several studies
done on this type of construction, the impact on birds is assessed as minor. No impacts on
the flora and other fauna are expected during the operational phase.
26
Machine Translated by Google
Notice of intention to carry out a project: "Petrovo" Wind Park (40 MW), Municipality of Gevgelija
Measures to reduce impacts: after monitoring and impact assessment, a set of measures
will be proposed in the environmental impact assessment study in order to mitigate and/or
avoid negative impacts.
Area
Landscape and visual impacts during construction work are mainly related to
construction activities, the presence of vehicles, waste storage, etc., while in the operational
phase the visual impacts are mainly due to the installed wind turbines. The implementation of
the project will have an impact on the landscape and the visual environment because the
wind turbines are high construction buildings (110 m), placed at a higher altitude (500 – 650
m above sea level), and they will be visible from great distances.
The impacts on the landscape in the construction and operational phase are evaluated as
negative, direct, irreversible, with high intensity, with a certain probability of occurrence,
of a local character.
Measures to reduce impacts: Restoration of the area after the completion of construction
activities and application of good construction practice. Restoration of the landscape and its
remediation after the end of the use of the wind turbines
Waste
During the construction phase, different fractions of waste will be generated, which will mainly
represents construction waste, packaging waste, municipal waste, waste from removed
vegetation, hazardous waste, etc.
In the operational phase, waste will be generated in the event of the repair of a breakdown of
the wind turbines, whereby waste from electrical and electronic equipment (WEEE), packaging
waste, etc. will be generated.
The contractor is obliged to act according to the legal regulations for this type of waste.
Improper waste management can cause negative impacts on media quality and environmental
areas.
The impacts of the waste in the construction and operational phase are evaluated as
negative, direct, of low intensity, will appear immediately, reversible, with a certain
probability of occurrence, and of a local character.
27
Machine Translated by Google
Notice of intention to carry out a project: "Petrovo" Wind Park (40 MW), Municipality of Gevgelija
Cultural heritage
The impacts on possible undiscovered cultural heritage sites in the construction phase are evaluated as negative,
direct, irreversible, with a possible probability of occurrence, of national importance.
Measures to reduce impacts: To establish communication with the Ministry of Culture, to undertake activities of
education of workers and
fig.
Construction and operational phase: The potential risks and dangers associated with the project in the
construction phase are: risk of natural disasters, risk of leakage of dangerous substances (in the construction phase
and during the repair of a defect in the operational phase), risk of fire, risk of breakdown of wind turbines and energy
supply that may cause negative impacts on
Impacts are evaluated as possible, negative, reversible, of low intensity and from
local character
Mitigation measures: Preparing emergency management procedures for a wide range of situations. An emergency
management plan should also be drawn up to identify emergency conditions that could lead to the breakdown of the
wind farm and provide for emergency measures to prevent
Construction and operational phase: Based on the fact that the nearest settlements are located at an aerial
distance of 800 m to 2,300 m, the impacts on the population and the health of the population in the construction and
operational phase are assessed as negative, no impact.
28
Machine Translated by Google
Notice of intention to carry out a project: "Petrovo" Wind Park (40 MW), Municipality of Gevgelija
5. Additional information
The competent authority for issuing the Decision for the implementation of the project is the
Ministry of Environment and Spatial Planning, i.e. the Administration for
environment.
The checklist for determining the need for an environmental impact assessment and the list for
determining the scope are given in APPENDIX 1 and APPENDIX 2, in continuation of this
notification.
With respect,
FBC LLC
29
Machine Translated by Google
Notice of intention to carry out a project: "Petrovo" Wind Park (40 MW), Municipality of Gevgelija
Briefly describe.
3. Whether the project will involve the use, Yes, construction materials No
storage, transport, handling or production and inert waste will be With the application of
of substances or materials that could be used and temporarily good construction
harmful to human health or the environment, stored during the practice and additional
or that would raise concerns regarding real construction phase.
measures, in accordance
or perceived risks to the health of the During the operational with the Law, no significant
people? phase, there will be no impacts are expected
storage of materials on
site
30
Machine Translated by Google
Notice of intention to carry out a project: "Petrovo" Wind Park (40 MW), Municipality of Gevgelija
Briefly describe.
Yes.
4. Will the project produce solid waste during Yes, during the construction
construction, operation, or facility closure? phase of the project, waste will
The implementation of the
be generated, which will have
planned project activities
the characteristics of non-
implies the need to undertake
hazardous waste.
appropriate measures and
In the operational phase, the procedures for sustainable
generation of packaging waste, waste management, in
municipal waste, WEEE, etc. is accordance with the obligations
expected. incorporated in the national
waste management regulation
5. Will the project release pollutants or any hazardous, Yes, in the construction phase No
toxic or harmful substances into the air? emissions of dust and exhaust
By applying good
gases will be generated, as a
construction practice, using
result of the performance of
regularly serviced machinery
construction works and the use
and applying the measures
of equipment and machinery.
prescribed in the Environmental
Uncontrolled generation of
Program, the impacts on air
emissions can cause disruption quality will be reduced to a
minimum.
the quality of
31
Machine Translated by Google
Notice of intention to carry out a project: "Petrovo" Wind Park (40 MW), Municipality of Gevgelija
Briefly describe.
32
Machine Translated by Google
Notice of intention to carry out a project: "Petrovo" Wind Park (40 MW), Municipality of Gevgelija
Briefly describe.
possible degree.
An increase is expected
of income from local
businesses during
construction (accommodation,
food and other needs for
construction company
employees).
10. Are there other factors that should be taken into Yes No
account such as subsequent development that could
Adjacent to the site where 11 The impacts will be reduced
lead to environmental impacts or the possibility of and
wind turbines will be located,
cumulative impacts with other existing or planned
the wind farm is under controlled given the fact that
activities on the site?
construction existing access roads and
transmission power systems
"Dren" will be used
33
Machine Translated by Google
Notice of intention to carry out a project: "Petrovo" Wind Park (40 MW), Municipality of Gevgelija
Briefly describe.
12. Are there any other areas on or around The project area has not It will be performed extensively
the site that are important or sensitive from been explored. According research and
an ecological point of view, such as aquatic to the available literature, monitoring of
habitats, watercourses or other water bodies, there are no ecologically the existing state of the
coastal zone, mountains, forests, which could important or sensitive areas biological
be affected by the project? recorded on the site. diversity of the
site in question and
In the preparatory phase of appropriate measures will
the preparation of the be proposed
environmental impact
assessment, it will be
carried out extensively
research and
monitoring of the existing
state of the biological
diversity of the
site in question and
mitigation and/or avoidance
measures will be proposed.
13. Are there any other areas on or around The project area has not No
the site used by protected, important or been explored. According It will be performed extensively
sensitive species of fauna and flora, for to the available literature, research and
example for breeding, nesting, foraging, there are no ecologically monitoring of
resting, wintering or migration, which could important or sensitive areas
the existing state of the
be affected by the project ? recorded on the site. biological
diversity of the
Extensive research and site in question and
monitoring of the current appropriate measures will
state of biodiversity at the be proposed
site in question will be
carried out and mitigation
measures will be proposed.
34
Machine Translated by Google
Notice of intention to carry out a project: "Petrovo" Wind Park (40 MW), Municipality of Gevgelija
Briefly describe.
35
Machine Translated by Google
Notice of intention to carry out a project: "Petrovo" Wind Park (40 MW), Municipality of Gevgelija
Briefly describe.
36
Machine Translated by Google
Notice of intention to carry out a project: "Petrovo" Wind Park (40 MW), Municipality of Gevgelija
1. Will the construction, operation or closure of the project involve activities that will
cause physical changes to the site (topography, land use, changes in water bodies,
etc.)?
1.2 Clearing existing land, vegetation It will come to NO, because it is about the
and buildings? removal of forest construction and installation
YES
mass, removal of of 11
vegetation from wind farms and the Study
will propose compensatory
the pastures as well measures for the removed
earth excavation vegetation and forests
1.3 Creation of new land uses? YES Pasture and forest land NO, because the Study will
propose compensatory
measures for the removed
vegetation and forests
geomechanical
with
37
Machine Translated by Google
Notice of intention to carry out a project: "Petrovo" Wind Park (40 MW), Municipality of Gevgelija
1.5 Construction work? The land in the project YES, in locations where
area, i.e. forests and excavation for foundations
YES
pastures, will be and construction of access
affected roads will be carried out
1.7 Temporary sites used for construction By placing No, because with a construction
work or to house construction NO camp, the completion of thetheoccupation
construction of
workers? activities, the surface where
bethe
placed
camp willwill
return to its
pastures original state
temporarily in the
construction phase
NO / /
1.10 Works on Cultivation of
barren land?
1.11 Digging with an excavator? The project NO, because these
land and the activities are
surrounding area intended to be only in the
YES
vegetation and construction phase
forests during current
operation and
excavations with an
excavator /
1.12 Coastal constructions, e.g. /
walls by the sea, NO
ports?
1.13 Coastal facilities? NO / /
38
Machine Translated by Google
Notice of intention to carry out a project: "Petrovo" Wind Park (40 MW), Municipality of Gevgelija
the operation?
1.19 New land, rail, air, water or / /
other transport
infrastructure
NO
including new or modified
roads and
stations, ports,
airports etc.?
1.20 Closure or Redirection / /
of
existing transport routes or NO
transmission lines
1.22 Capture of waters, construction / /
of dam, underwater channel,
the aquifers?
1.23 Crossing watercourses? NO / /
while in
the operational
phase transport of
workers and
materials for
maintenance
39
Machine Translated by Google
Notice of intention to carry out a project: "Petrovo" Wind Park (40 MW), Municipality of Gevgelija
wind farms
1.27 Long-term activities for dismantling, YES The project area No, because the
closing or rebuilding (reconstruction) and same access roads
of the access roads already under
objects during the construction will be
transportation of designed so that the
the wind turbines transportation of the wind
turbines can take place
smoothly
1.28 Current activity during the closing NO / /
that could have an impact
on the environment?
1.29 Inflow of people into NO / /
a certain area either
temporary or permanent?
1.30 Entry of others NO / /
(external) species?
1.31 Loss of natives NO / /
species or genetic
diversity?
1.32 Any other activities? NO / /
2. Whether the construction or operation of the project will use natural resources such
as land, water, materials or energy, and especially
non-renewable or scarce resources?
No. Issues to consider What characteristics of the Is the exists
in Yes project environment could be effect likely
No/? to be significant? Why?
the determination of affected and how?
the scope of the EIA
2.1 Land, especially Green areas will be occupied Yes, there will be a permanent i.e.
undeveloped or YES pastures and forests for the conversion activities
of construction land
agricultural
land?
2.2 Water? YES In the construction phase when spraying No, as it will only
with water in order to suppress the appear during the build
dust generated during excavations phase
and transport
2.3 Minerals? 2.4 NO / /
Aggregates (sand, During the NO
gravel, crushed stone)? construction of the foundations and Because these
YES
the access road, gravel will be materials will
used for buffering. be brought by the
contractor from outside
suppliers
2.5 Forests and trees? NO / /
2.6 Energies, including
electricity and Fuel will be used for NO
fuels? construction machinery and The shows are not with
transport vehicles. The quality high intensity, they
Yes
will be affected are short-lived only
the ambient air in during construction
the immediate environment of
exhaust gas emissions.
40
Machine Translated by Google
Notice of intention to carry out a project: "Petrovo" Wind Park (40 MW), Municipality of Gevgelija
3. Whether the project will involve the use, storage, transport, handling or production of
substances or materials that could be harmful to human health or the environment, or
that would raise concerns regarding real or perceived risks to the health of the people?
insects or water)?
3.3 Will the project have an impact / /
on people's well-being, for
example through NO
patients, elderly?
3.5 Any other reasons? NO / /
4. Will the project produce solid waste during construction, operation, or facility closure?
41
Machine Translated by Google
Notice of intention to carry out a project: "Petrovo" Wind Park (40 MW), Municipality of Gevgelija
4.2 Municipal waste (household waste In the construction phase and in No.
or commercial waste)? the closure phase of the wind The quantities will not be significant,
farm, municipal waste generated they will be regularly handed over
YES by the hired workers during the to a person (legal or physical) who
construction and dismantling of the holds a license for collecting and
wind farms is expected transporting municipal waste.
4.3 Hazardous or toxic waste YES Yes, possible occurrence of hazardous No, because appropriate
(including radioactive waste during the construction phase measures to reduce the impacts are
waste)? in the event of fuel, oil or petroleum provided for them
leakage on the ground. If it is not
handled according to the regulations,
it can be
4.7 Construction debris or During the construction No, considering the relatively
waste from demolition activities? phase of the wind park, small amount of waste generated
construction debris, inert and the inert nature of this type of
YES waste, excess excavated material waste.
will be generated. If it is not handled
according to the regulations, the soil
and groundwater may be affected
underground water
4.10 Waste from agricultural NO / /
activities?
4.11 Other waste from NO / /
industrial processes?
42
Machine Translated by Google
Notice of intention to carry out a project: "Petrovo" Wind Park (40 MW), Municipality of Gevgelija
5.1 Emissions combustion of During the construction phase, No, because the shows aren't
fossil fuels from stationary gas emissions will be generated with great intensity,
or from mobile sources that are short-lived (for the time (mechanization).
mobile sources? YES of construction) and local.
Ambient air quality will be affected
6. Will the project cause noise and vibration or the release of light,
thermal energy or electromagnetic radiations?
No. Questions to Yes/ What features of Is the effect likely to be
Consider No/? project environment could be significant? Why?
in determining the scope of affected and how?
the EIA
6.1 From the operation of In the construction phase, the appearance of the Effect can be
the equipment, eg an increased level of noise significant
thatif will
withbeextensive research
as a result of the
engines, ventilation plant, YES implement the project In the operational
engagedphase,mechanization.
the occurrence of the
crushers? area is proven that the noise from the workand
of rare of there
wind is the presence
turbines
43
Machine Translated by Google
Notice of intention to carry out a project: "Petrovo" Wind Park (40 MW), Municipality of Gevgelija
the activity.
6.7 From sources of During the operational phase It has not been investigated
7. Will the project lead to risks of land or water contamination from discharges of pollutants
onto land or into surface waters, coastal waters or the sea?
fuels
7.2 From the discharge of
wastewater or other effluents
(treated NO / /
or untreated) in water
or soil?
7.3 Through the deposition of The soil would be affected, No, because of the dynamics of the
pollutants emitted into YES air and the surrounding flora and activities
time (only
andinthe
fauna
shortasperiod
a result
of
the air on land or in water? of the construction phase)
use of construction
machinery
7.4 From some other sources?
/ /
NO
44
Machine Translated by Google
Notice of intention to carry out a project: "Petrovo" Wind Park (40 MW), Municipality of Gevgelija
accumulation of NO
/ /
pollutants in the environment
from
these sources?
8. Is there a risk of accidents during the construction or operation of the project that could
affect human health or the environment?
No. Issues to be considered What features of Is the effect likely to be
in determining the Yes/ project environment could significant? Why?
scope of the EIA No/? be affected and how?
8.1 From explosions, In the construction phase and Yes, if the post-operational phase
spills, fires, etc.; from keeping is not used PPE and legal regulations
and measures are not respected, possible injuries at work
handling, use or for the sake of the workers
YES
the specificity of
production of dangerous construction and assembly
or toxic works
substances?
8.2 From events outside of
the limits of
the usual protection
the environment, e.g. NO / /
failure of pollution control
systems?
earthquakes, landslides,
etc.)?
9.1 Changes to
size, age, population
structure, social groups / /
NO
etc?
45
Machine Translated by Google
Notice of intention to carry out a project: "Petrovo" Wind Park (40 MW), Municipality of Gevgelija
the economy?
9.6 Any other reasons? NO / /
10. Are there other factors that should be taken into account such as subsequent
development that could lead to environmental impacts or the possibility of cumulative
impacts with other existing or planned activities on the site?
No. Questions you should What features of Is the effect likely to be significant?
are taken into account in Yes/ the project environment could also be Why?
the determination of No/? affected
the scope of the EIA how?
10.1 Will the project lead
to pressure for
subsequent development that
could have a significant impact on NO
the environment, such as a larger
number / /
residences, new
roads, new ancillary industries or
establishments etc.?
ÿ auxiliary
46
Machine Translated by Google
Notice of intention to carry out a project: "Petrovo" Wind Park (40 MW), Municipality of Gevgelija
infrastructure
(roads, electricity
supply
NO
energy, waste or
wastewater treatment,
etc.)
ÿ construction of
residences
ÿ extractive industrial
activities
ÿ activities of
supply
ÿ • others?
10.3 Will the project lead to
concern for the site
after the termination
of installation work NO / /
that could have an impact
on the animal
environment?
10.4 Will the project
set a precedent for NO
future developments?
10.5 Will the project have Near the project Yes, it is expected to be a location is predicted
cumulative effects due to to be significant only in the construction
windconstruction
phase on allofmedia
the and
proximity to other existing YES power plants. If the projects are in the operational areas
or
planned projects with be realized in the same period will come
stagetowill
thehave
cumulative
an impact on
similar impacts? surrounding fauna.
impacts on all media and
environmental areas
47