Testing Procedure Part-I
Testing Procedure Part-I
00
2.0 Definition:
Mega ohm Meter: (popular trade name "megger"). Megger consists of a DC power source and a
measuring system. The power source is a hand operated or electrically driven built in DC
generator in the instrument.
7.0 Precautions:
i) Clean the bushing porcelains by wiping with a piece of dry cloth.
ii) When using a megger, observe the usual accident preventive rules.
iii) Transformer windings possess a substantial capacitance and therefore, the current carrying
parts can only be touched after electric charge has been removed from them.
iv) If moisture condensation is suspected on porcelain surface, provide aluminium foil taping
below the lower most porcelain shed. (Especially for small bushings like Neutral Bushing)
Document No: RPS/Testing/001. Rev. 00
LV to E HV + IV +LV to E
Where HV- High voltage, IV-Intermediate voltage, LV-Low voltage/Tertiary voltage windings, E-Earth
Record date and time of measurement, sl. no., make of megger; oil temperature and IR values at
intervals of 15 seconds, 1 minute and 10 minutes.
The "LIVE" terminal of the instrument shall be connected to the winding under test.
IR values may be checked with the values in manufacturer's test certificate and these values
may be used as bench marks for future IR monitoring in service. It shall be noted that IR values
vary with type of insulation (transformer oil or air), temperature, duration of application of
voltage and to some extent applied voltage.
Insulation resistance varies inversely with temperature and is generally corrected to a standard
temperature (usually 20 °C). Suppose IR value of 300 MΩ at 70°C to be converted at 40°C, the
curve will give a factor k for difference in temperature (i.e. 70°C - 40°C) = 30°C . K for 30°C
temperature difference is 4.2 , So the IR value at 40°C will be 4.2*300=1260 MΩ.
Document No: RPS/Testing/001. Rev. 00
10 1.65
20 2.6
30 4.2
40 6.6
50 10.5
Please Note: These converted IR values fairly tally with the actual IR values obtained by
BHEL while cooling the transformer
An indicative M in insulation Values for one minute resistance measurements for transformers
may be obtained by using the following empirical formula:
R = CE / VKVA Where
R = Insulation resistance, in MΩ
C = 1.5 for oil-filled transformers at 20°C, assuming that the transformer’s insulating oil is dry,
acid free, and sludge free
= 30.0 for un tanked oil-impregnated transformers
E = Voltage rating, in V, of one of the single-phase windings (ph-to-ph for delta connected and
ph-to-neutral for wye connected transformers)
KVA = Rated capacity of the winding under test (If the winding under test is three-phase and
the three individual windings are being tested as one, the rated capacity of three-phase winding
is used.)
IR test results below this minimum value may indicate probable insulation breakdown. A mega
ohm meter test that indicated zero or a very low value of ohms would indicate a grounded
winding, a winding-to-winding short, or heavy carbon tracking.
Unless otherwise recommended by the manufacturer the following IR values as a thumb rule
may be considered as the minimum satisfactory values at 30°C (one minute measurements) at
the time of commissioning.
Even if the insulation is dry, IR values will be low if the resistivity of oil is poor.
With the duration of application of voltage, IR value increases. The increase in insulation
resistance is an indication of dryness of insulation. The ratio of 60 second insulation resistance
to 15 second insulation resistance value is called dielectric absorption coefficient or Index
(DAI). For oil filled transformers with class A insulation, in reasonably dried condition the
absorption coefficient at 30°C will be more than 1.3.
Polarization Index Test is ratiometric test, insensitive to temperature variation and may be
used to predict insulation system performance even if charging currents (i.e. capacitive,
absorption or leakage currents) have not diminished to zero. Since leakage current increases at a
faster rate with moisture present than does absorption current, the megohm readings will not
increase with time as fast with insulation in poor condition as with insulation in good condition.
This results in a lower polarization index. An advantage of the index ratio is that all of the
variables that can affect a single mega ohm reading, such as temp and humidity, are essentially
the same for both the 1 min and 10 min readings. The polarization index test is performed
generally by taking mega ohm readings at the following intervals at a constant dc voltage: 1
min and then every minute up to 10 min. The polarization index is the ratio of the 10 min to
the 1 min mega ohm readings.
The following are guidelines for evaluating transformer insulation using polarization index
values:
A PI of more than 1.25 and DAI of more than 1.3 are generally considered satisfactory for a
transformer when the results of other low voltage tests are found in order. PI less than 1 calls
for immediate corrective action. For bushings, an IR value of above 10,000 MΩ is considered
satisfactory.
Document No: RPS/Testing/001. Rev. 00
7.0 PRECAUTIONS
* Test voltage to be applied shall not exceed half of the power frequency test voltage or 10 kV,
whichever is lower. It is desirable to have the test set or bridge frequency different but close
to operating power frequency; so that stray power frequency currents do not interfere with
Document No: RPS/Testing/001. Rev. 00
the operation of the instrument.
* Porcelain of the bushings shall be clean and dry before test. Remove any dirt or oil with
clean dry cloth.
* Test shall not be carried out when there is condensation on the porcelain. Preferably, tests
shall not be carried out when the relative humidity is in excess of 75%.
* Terminals of the bushings of each winding shall be shorted together using bare braided
copper jumper. These jumpers shall not be allowed to sag. Transformer windings not being
tested shall be grounded.
* Measure and record the ambient temperature and relative humidity for reference. Record
OTI and WTI during the measurement.
Do not test a bushing (new or spare) while it is in its wood shipping crate, or while it is lying on
wood. Wood is not as good an insulator as porcelain and will cause the readings to be inaccurate.
Keep the test results as a baseline record to compare with future tests.
Please refer manufacturer’s Operating Instructions for the C and Tan δ kit available at site.
Care shall be taken to control the above factors during measurements. Testing during periods
of high humidity or precipitation should be avoided; otherwise proper evaluation of test
results becomes very difficult. A very small amount of water vapour on the surface of
external insulation could increase the amount of leakage current and will appear as increased
loss in the test result.
The acceptance criterion to assess the probable condition of the insulation of the transformer
is no substantial variation in the measured values of tan delta (dissipation factor) at
periodic interval when compared with previous references. For bushings, the tan delta value
shall not exceed 0.7%.
The main capacitance (C1) of the bushing i.e., the capacitance between high voltage
terminal and test tap is not affected by the surrounding conditions and the accepted deviation
from the values measured at factory tests should be less than 10%. The capacitance between
bushing test tap and ground is largely influence by the stray capacitances to ground parts in
the transformer and hence large deviation in the measured value shall be accepted when
compared with the factory test value.
Rate of change of tan Delta and capacitance is very important. Rate of rise of tan delta
should not be more than 0.001 per year. Capacitance value can be within +10%, -5% in
capacitance value.
7.0 PRECAUTIONS
The test set is a source of high voltage electrical energy and operator must use all practical
safety precautions to prevent contact with energised parts of the test equipment and related
circuits. Following precautions need to be taken:
Never connect the test set to energised equipment.
The ground cable must be connected first and removed last.
Heart patients should avoid using this H.V. equipment.
The ground terminal of the input supply card (green lead) must be connected to the
protective ground (earth) terminal of the line power source.
Keep the high voltage plugs free from moisture, dust during installation and operation.
Adequate clearances (Min 1 foot i.e. 30 cm) are maintained between energised conductor
and ground to prevent any arc over.
It should be ensured that test specimen is de-energised and grounded before making any
further connection and no person may come in contact with HV output terminal or any materiel
energised by the output.
iii) For a three winding transformer, measurement should be made between each winding
and ground with one remaining winding guarded and the second remaining winding grounded
(GST L GUARD test mode)
iv) Finally measurement should be made between all windings connected together and the
grounded tank.
The combination for C & tan measurement of winding is same as that of measurement of
IR value. The summery of probable combination is given below:
Ensure that test specimen is isolated from other equipments. Removal of Jumpers from
Bushings is Pre-Requisite for C & Tan _ Measurement of Windings.
Position the test set at least 6 feet (180 cm) away from the test specimen to be tested.
To prevent damage to the test set always set the capacitance multiplier dial to the
SHORT position, the capacitance measuring dials to their respective ‘O’ position.
Keep UST-GST switch to UST position.
Keep interference suppressor switches in OFF position.
Connect the ground terminal of the test set to a low impedance earth ground (to Earth
mat of the substation).
• Connect control unit to the high voltage unit using two 5 feet long shielded cables. Screw
the plugs down fully on the receptacles.
• Connect the low voltage cable with red boot/sheath to the ‘CxL red terminal’ of the test set.
Make sure the connector locks to the receptacle.
• Connect the external interlock cable to the ‘Interlock terminal of the test set.
• Connect the high voltage cable with Black boot/sheath to the high voltage terminal of the
high voltage unit. Connect the pig -tail for the outer shield to the black binding post (ground)
on the high voltage unit. Screw down the plug shell fully on the receptacle.
• With the main breaker switched OFF, plug the input power card into the test set power
receptacle and into a 3 wire grounded power receptacle having the appropriate voltage rating
and current capacity.
• Each capacitor (insulation section) in a complex insulation system should be tested
separately. The determination of the characteristics of the individual components of a
complex system is valuable in detecting and locating defective insulation in the system.
Direct measurement of each component is recommended for greatest accuracy rather than
using a combination of measurements and calculations.
Document No: RPS/Testing/001. Rev. 00
DETAILED PROCEDURE:
• For ICTs (Auto-Transformers): Shorting of all three phase Bushings (400kV&220kV)
and neutral to be done. In case of single phase, 400kV, 220kV and neutral Bushings to be
shorted Capacitance and Tan δ measurement of windings should be done in following
combinations:
TEST VOLTAGE
C and Tanδ measurement can be performed at any voltage within normal operating range of
the equipment under test. Test voltages for typical field test sets range from below 100 V to
as high as 12 kV, however field tests on most electrical equipment are usually performed at
rated voltage or a max. of 10 kV.
A large percentage of electrical apparatus failures are due to a deteriorated condition of the
insulation. A large number of these failures can be anticipated in advance by regular
application of this test. An insulation system or apparatus should not be condemned unless
until it has been completely isolated, cleaned or serviced and measurements compensated for
temperature. Changes in the normal capacitance of an insulator indicate abnormal conditions
such as the presence of moisture, layer short circuits or open circuits in the capacitance
network.
Dissipation factor measurements can indicate the following conditions:
• Chemical deterioration due to time and temperature, including certain cases of acute
deterioration caused by localized overheating.
• Contamination by water, carbon deposits, bad oil, dirt and other chemicals.
• Severe leakage through cracks and over surfaces.
• Ionization
Maximum values of Dissipation Factor (Tan Delta) of class A insulation e.g. paper insulation,
oil impregnated is 0.007. Rate of change of tan Delta and capacitance is very important. The rate of
change of tan 5 more than 0.001 per year needs further investigation. Capacitance value can be
within +10%, -5% in capacitance value. Comparison of test results to those for similar piece of
equipment especially those tested under the same conditions shall be done.
These tests provide a valuable index of dryness and are helpful in detecting undesirable
operating conditions and failure hazards resulting from moisture, carbonisation of insulation,
defective bushings, contamination of oil by dissolved material or conducting particles improperly
grounded or ungrounded core etc.
Document No: RPS/Testing/001. Rev. 00
Transformer winding resistance are measured in the field in order to check for any
abnormalities due to loose connections, broken strands and high contact resistance in tap
changers as a pre-commissioning checks and compare the measured values with factory test
values
2.0 Definitions
Ensure the isolation of Transformer from High Voltage & Low voltage side with physical
inspection of open condition of the concerned isolators/disconnectors. In case tertiary is also
connected, ensure the isolation of the same prior to commencement of testing.
6.0 Precautions
6.1 As the transformer resistance is Low resistance, the measurement has to be carried out with
the help of Kelvin Double Bridge / Transformer ohm meter. Normally winding resistance
values 1 ohm or above is measured using Wheatstone Bridge and winding resistance values
less than 1 ohm is measured using micro-ohm meter or Kelvin Bridge.
Document No: RPS/Testing/001. Rev. 00
6.2 To reduce the high inductive effect it is advisable to use a sufficiently high current to
saturate the core. This will reduce the time required to get a stabilized reading.
6.4 Care shall be taken that self inductive effects are minimized.
6.5 Care also must be taken to ensure that direct current circulating in the windings has settled
down before the measurement is done. In some cases this may take several minutes
depending upon the winding inductance.
6.6 The winding resistance shall be preferably done when the difference in the top and bottom
temperature of the winding (temperature of oil in steady-state condition) is equal to or less
than 5°C.
6.7 The winding resistance should preferable be carried out last after completion of all other LV
tests, as after this test core gets saturated and tests like magnetizing current, magnetic
balance etc. carried out after winding test may be affected and indicate a misleading results,
if the core is not de-magnetized before carrying out these tests.
7.2 For star connected winding with neutral brought out, the resistance shall be measured
between the line and neutral terminal and average of three sets of reading shall be the tested
value. If neutral bushing is not available on Star connected windings, take measurement
between each phase and ground (if the neutral is grounded), or take readings between pairs
of bushings as if it were a Delta connected winding. Repeat in same fashion so that proper
comparison can be made.
7.3 For star connected auto-transformers the resistance of the HV side is measured between
HV terminal and IV terminal, then between IV terminal and the neutral AT ALL TAPS. The
tap changer should be changed from contact to contact so that contact resistance can also be
checked.
7.4 For delta connected windings, such as tertiary winding of auto-transformers, measurement
shall be done between pairs of line terminals and resistance per winding shall be calculated
as per the following formula:
7.5 Take the winding temperature reading while doing the resistance measurement.
Please refer manufacturer’s operating instructions for the instrument available at site
Document No: RPS/Testing/001. Rev. 00
The resistance value obtained as per 8.1 - 8.6 should be compared with the factory test value
in case of pre-commissioning and with pre-commissioning test value in case the test is being
carried out during routine maintenance.
Excitation/ Magnetising current test is performed to locate defect in magnetic core structure,
shifting of windings, failures in turn to turn insulation or problems in tap changers. These
conditions change the effective reluctance of the magnetic circuit thus affecting the current
required to establish flux in the core.
2.0 Definitions
Exciting/ Magnetising current: is the current required to force a given flux through the
core.
Ensure the isolation of Transformer from High Voltage & Low voltage side with physical
inspection of open condition of the concerned isolators/Disconnector. In case tertiary is also
connected, ensure the isolation of the same prior to commencement of testing.
6.0 Precautions
6.1 This test should be done before DC measurements of winding resistance to reduce the effect
of residual magnetism.
Document No: RPS/Testing/001. Rev. 00
6.2 Magnetizing current readings may be effected by residual magnetism in the core Therefore,
transformer under test may be demagnetized before commencement of magnetizing current
test.
7.1 The test comprises a simple measurement of single-phase current on one side of the
transformer, usually the high-voltage side, with the other side left floating (with the
exception of a grounded neutral)
7.2 Three -phase transformers are tested by applying Single- phase 10 kV voltage to one
phase (HV terminals) at a time. Keep the tap position in the lowest position and IV and LV
terminals open.
7.3 Measure the voltages applied on each phase (Phase wise) on HV terminals and current in
each phase of HV terminal.
7.4 After completion of the above steps keep the tap position in Normal position and repeat the
steps 7.2 to 7.3
7.5 After completion of the above steps keep the tap position in Highest position and repeat the
steps 7.2 to 7.3
7.6 Keep the tap position in normal position and keep HV and LV terminals open.
7.8 Measure phase to phase voltage between the IV terminals and current on each of the IV
terminals.
Please refer manufacturer’s Operating Instructions for the C and Tan δ kit available at site. The
instrumentation should, whenever possible, exclude from the measurement the capacitive currents
between the excited winding and other windings, the core, or the tank.
9.1 The set of reading for current measurement in each of the tap position should be equal.
Unequal currents shall indicate possible short circuits in winding.
9.2 Results between similar single-phase units should not vary more than 10 % .The test values
on the outside legs should be within 15 % of each other, and values for the centre leg should
not be more than either outside for a three-phase transformers. Results compared to previous
tests made under the same conditions should not vary more than 25%. If the measured
exciting current value is 50 times higher than the value measured during pre-commissioning
checks, then there is likelihood of a fault in the winding which needs further analysis. The
Document No: RPS/Testing/001. Rev. 00
comparison of the test values of healthy condition with the faulty condition shall help in
pinpointing the trouble spots.
9.3 If an out-of-tolerance reading is experienced while turns ratio, winding resistance, and
impedance tests are normal, residual magnetism should be suspected Residual magnetism
may be eliminated or reduced by applying a dc voltage to the windings through a voltage
divider. The voltage should be raised from zero to a max. value that will yield a current of
no more than 10 A through the winding and then returned to zero. Care must be taken not to
break the circuit while dc current is flowing in the winding. The polarity should then be
reversed and the procedure repeated. Repeat the process several times, each time reducing
the magnitude of current and each time reversing the polarity. The excitation current test
should then be repeated.
Document No: RPS/Testing/001. Rev. 00
Frequency Response Analysis (FRA) is made to assess the mechanical integrity of the
transformer. Transformers while experiencing severity of short circuit current looses its
mechanical property by way of deformation of the winding or core. These changes cannot be
detected through conventional condition monitoring techniques such as Dissolved Gas Analysis,
Winding Resistance Measurement, Capacitance and Tan delta measurement etc. Sometimes
even transportation without proper precaution may cause some internal mechanical damages.
FRA measurement, which is signature analysis, provides vital information of the internal
condition of the equipment so that early corrective action could be initiated.
It is ensured that winding which is not under test is terminated in open condition in order to
avoid response difference among the three phases. The same procedure is followed on
subsequent tests on the same or similar transformer, to ensure that measurements are entirely
repeatable.
The voltage transfer function T1/R1 is measured for each winding for four standard frequency
scans from 5 Hz to 2 MHZ and amplitude & phase shift results are recorded for subsequent
Document No: RPS/Testing/001. Rev. 00
analysis
Document No: RPS/Testing/001. Rev. 00
As per EuroDoble Client Committee, the traces in general will change shape and be distorted
in the low frequency range (below 5 KHz) if there is a core problem. The traces will be distorted
and change shape in higher frequencies (above 10 KHz), if there is winding problem. Changes
of less than 3 decibels (dB) compared to baseline traces are normal and within tolerances. In
general, changes of +/- 3 dB (or more) in following frequency range may indicate following
faults:
Isolation required:
Ensure the isolation of Transformer from High Voltage & Low voltage side with physical inspection of
open condition of the concerned isolators/Disconnector. In case tertiary is also connected, ensure the
isolation of the same prior to commencement of testing. The secondary circuits of the CTs may be
disconnected in the Relay panels in control room.
SAFETY REFERENCE:
This testing shall be carried out during Shut down period and all testing shall be done under PTW
(Permit To Work).
Testing Instruments:
Transformer turns ratio meter High resistance measuring Ohm meter with required accessories &
Cables 5 kV motorized Mega ohm meter (megger) with associated accessories & cables.
TESTING PROCEDURE:
1. POLARITY CHECK
The lead polarity of any transformer CT/PT) is a designation of the relative instantaneous direction of
currents in its leads. Primary and secondary leads are said to have the same polarity when at a given
instant the current enters the primary lead in question and leaves the secondary lead in question in the
same direction as though two leads formed a continuous circuit.
The polarity check can be done by inductive kick with direct current method. In this test, a 6-10 V
battery pack is connected momentarily to the primary P1-P2 of bushing CT under test and the
momentarily deflection of pointer of voltmeter (Zero centre) or analog multimeter in dc m.Amp
selection is connected to secondary is noted. If the connections are made as shown in the diagram then
the deflection will be upscale when the battery is connected and downscale when the battery is
disconnected, if the polarity is in accordance with the terminal marking. This test is also valid with the
battery applied to secondary and the meter connected to primary. Use of mA or mV meter may be
made.
Document No: RPS/Testing/001. Rev. 00
Precautions:
i. If a bushing CT installed in a power transformer is being tested by connecting the battery
to the power transformer terminals, the other windings on the same phase of the power
transformer may have to sort0 circuited in order to obtain a stable reading.
ii. It is advisable to demagnetise any CT that is tested by impressing DC voltage across a
winding.
iii. A dangerous voltage may be generated while disconnecting the battery from the
transformer winding. Therefore, a knife switch is not used, a hot stick or rubber gloves
must be used for connecting and disconnecting the battery.
2. RATIO TEST:
A suitable voltage, below saturation, is applied to the secondary (full winding) and the primary voltage
is read with a high impedance (20 000 Ρ/V or greater) low range voltmeter as shown in the diagram
below:
The turns ratio is approx. equal to the voltage ratio. Saturation level is usually about 1 V per turn in
most low- and medium- ratio bushing CTs. At the same time, the overall ratio is being determined, the
tap section ratio may be checked with a voltmeter by comparing tap section voltage with the impressed
voltage across the full winding. An ammeter is included in the recommended test method as a means of
detecting excessive excitation current.
3. EXCITATION TESTS:
These tests are carried out during pre-commissioning stage to check if any turns of CT are short-
circuited and to establish CT characteristics as well as capability of CT. Excitation tests is made on CTs
for comparison with factory test results or previously measured data to determine if deviations are
present.
To perform the test, an AC test voltage is applied to the secondary winding with the primary open
circuited as shown in the diagram:
The test voltage applied to the secondary of the current transformer is varied, and the current drawn by
the winding at each selected value of voltage is recorded. Readings near the knee of the excitation curve
Document No: RPS/Testing/001. Rev. 00
are especially important in plotting a comparison curve. For current transformers with taps, the
secondary tap should be selected to assure that the current transformer can be saturated with the test
equipment available. The highest tap which can accommodate that requirement should be used.
The selection of instruments is especially important for this test. The ammeter should be an rms
instrument. The voltmeter should be an average reading voltmeter. It should be calibrated to give the
same numerical indication as an rms voltmeter on sine wave voltage.
Any substantial deviation of the excitation curve for the current transformer under test from curves of
similar transformers or manufacturer’s data should be investigated. Deviation from expected results
may indicate a turn-to-turn short circuit, distortion of test supply voltage waveform, or the presence of a
completed conducting path around the current transformer core.
Insulation resistance between CT secondary and ground is usually checked by the use of conventional
test instruments. The neutral ground must be removed and the CT preferably isolated from its burden
for this test. Actually, the neutral can be used to test all three phases simultaneously.
Meggering core by core (to ground) keeping other cores temporarily grounded. It should be done by
500 V megger for 1 min.
The IR value should be compared with those of similar devices or circuits. Readings lower than those
known to be good should be carefully investigated. The generally accepted min. IR value is 1 MQ. One
of the most common reasons for low readings is the presence of moisture. Drying out the equipment
and retesting should be considered before it is dismantled.
Precaution:
If relays are left connected to the CT during test, the relay manufacturer should be consulted before test
values above 500 V are used. Many solid-state relay designs have surge-suppression capacitors
connected from input terminals to ground which may be damaged by use of a higher voltage.
Document No: RPS/Testing/001. Rev. 00
To determine the phase relationship and polarity of transformers. Transformer winding ratio,
vector group and polarity should be checked before energizing the transformer for the first time
on site.
Polarity of a transformer is determined by the internal connections and is indicated by the name
plate markings. Polarity is of interest if the transformer is to be connected in parallel with one or
more other similar transformers
3.0 Definitions
Nil
Pre-commissioning activity.
Ensure the isolation of Transformer from High Voltage & Low voltage side with physical
inspection of open condition of the concerned isolators/disconnectors. In case tertiary is also
connected, ensure the isolation of the same prior to commencement of testing.
7.0 Precautions:
This testing shall be carried out during Shut down period and all testing shall be done under
PTW (Permit To Work). Ensure the isolation of Transformer for High Voltage & Low voltage
side with physical inspection of open condition of the concerned isolators/ disconnectors. In
case tertiary is also connected, ensure the isolation of the same prior to commencement of
testing
8.1 The test shall be conducted with three phase supply (415V, 3 phase supply) and
voltmeters.
8.2 By the measured voltage data it should ensure that the desired conditions of vector group and
polarity are fulfilled.
Document No: RPS/Testing/001. Rev. 00
CONNECT 1U to 2U
MEASURE 1W-2V, 1W-2W, 1U-2W, 1V-2V, 1V-2W
VOLTAGE RELATION
1W-2V= 1W-2W
1W-2V< 1U-1W
1V-2V<1V-2W
1V-2V <1U-1W
8.5 For other combinations please refer the connection diagram for verifying the vector group
as given in next page.
Document No: RPS/Testing/001. Rev. 00
Document No: RPS/Testing/001. Rev. 00
This test is conducted only in three phase transformers to check the imbalance in the
magnetic circuit
Pre-commissioning activity.
7.0 Precautions
7.1 No winding terminal should be grounded; otherwise results would be erratic and confusing.
8.3 Apply single phase 230 V across one phase of Highest Voltage (HV) winding terminal and
neutral (call it v1) then measure voltage in other two HV terminals across neutral (call them v2
and v3 respectively). Repeat the test for each of the three phases.
8.4 Repeat the above test for Intermediate Voltage (IV) winding also
10.1 From the measurement carried out as per 8.3 ensure that v1 ~= v2 + v3 respectively.
10.2 Zero voltage or very negligible voltage induced in other two windings should be investigated.
10.3 Also the applied voltage may be expressed as 100 % and the induced voltages as percentage of
applied voltage. This will help in comparison of two results when applied voltages are different.
The voltage induced in the centre phase shall be 50 to 90% of the applied voltage. However,
when the centre phase is excited then the voltage induced in the outer phases shall be 30 to 70%
Document No: RPS/Testing/001. Rev. 00
3.0 Definitions
Turns Ratio: The Turns Ratio of a transformer is the ratio of the number of turns in a higher
voltage winding to that in a lower voltage winding.
Pre-commissioning activity
Ensure the isolation of Transformer from High Voltage & Low voltage side with physical
inspection of open condition of the concerned isolators/disconnectors. In case tertiary is also
connected, ensure the isolation of the same prior to commencement of testing.
7.0 Precautions
7.1 The voltage should be applied only in the High voltage winding in order to avoid
unsafe voltage.
8.1 Keep the tap position in the lowest position and IV and LV terminals open.
8.2 Apply 3 phase 415 V or single phase 230 V supply according to transformer type on
HV terminals.
8.3 Measure the voltages applied on each phase (Phase-Phase) on HV and IV terminals
simultaneously.
Repeat Steps 8.2 and 8.3 for each of the tap position separately.
8.5 Repeat the steps 8.1 to 8.4 after interchanging the voltmeters of HV and IV windings and then
average the readings for final calculation of ratio.
8.6 The above tests can also be performed by Transformer turns ratio (TTR) meter available in
convenient portable form. They have a hand crank power supply, with the voltages commonly
used being very low, such as 8-10 V and 50-60 Hz, so that the test may be performed on a
transformer even when the oil is removed. Two windings on one phase of a transformer are
Document No: RPS/Testing/001. Rev. 00
connected to the instrument, and the internal bridge elements are varied to produce a null
Document No: RPS/Testing/001. Rev. 00
indication on the detector, with exciting current also being measured in most cases.
Please refer manufacturer’s operating instructions for the instrument available at site
10.1 Results of the transformation turns or voltage ratio are absolute, and may be compared with the
specified values measured during factory testing. The turns ratio tolerance should be within 0.5
% of the nameplate specifications. For three phase Y connected winding this tolerance applies
to phase to neutral voltage. If the phase-to-neutral voltage is not explicitly indicated in the
nameplate, then the rated phase-to-neutral voltage should be calculated by dividing the phase-
to-phase voltage by √3.
10.2 If there are shorted winding turns, the measured ratio will be effected. Out-of -tolerance ratio
measurements may be symptomatic of shorted turns, especially if there is an associated high
excitation current. Out-of -tolerance readings should be compared with prior tests because in
some instances, the design turns ratio may vary from the nameplate voltage ratio on some taps
because of the need to utilise an incremental number of winding turns to make up the taps while
nameplate voltage increments may not exactly correspond. This error may combine with
measurement error to give a misleading out-of-tolerance reading.
10.3 Ratio measurements must be made on all taps to confirm the proper alignment and operation of
the tap changers. It should be noted that, on transformers with OLTC that operate on positions
bridging two tap contacts (Check the nameplate chart for tap connections), there will be a
circulating current in the tap section being bridged. This circulating current is limited in some
manner, usually by a reactor or resistance device. The losses due to this circulating current will
cause an increase in exciting current and some voltage regulation. It is therefore important to
have prior data with the measurement system employed to properly analyse these transformers.
Open turns in the excited winding will be indicated very low exciting current and no output
voltage. Open turns in the output winding will be indicated by normal levels of exciting current,
but no or very low levels of unstable output voltage.
10.4 Open turns in the excited winding will be indicated very low exciting current and no output
voltage. Open turns in the output winding will be indicated by normal levels of exciting current,
but no or very low levels of unstable output voltage.
10.5 The turns ratio test also detects high-resistance connections in the lead circuitry or high contact
resistance in tap changers by higher excitation current and a difficulty in balancing the bridge.
Document No: RPS/Testing/001. Rev. 00
To find out the short circuit impedance (%Z) of transformer and can be compared with name
plate reading or factory test results. This test is used to detect winding movement that usually
occurs due to heavy fault current or mechanical damage during transportation or installation
since dispatch from the factory.
Ensure the isolation of Transformer from High Voltage & Low voltage side with physical
inspection of open condition of the concerned isolators/Disconnector. In case tertiary is also
connected, ensure the isolation of the same prior to commencement of testing.
The measurement is performed in single phase mode. This test is performed for the combination
of two winding. The one of the winding is short circuited and voltage is applied to other
winding. The voltage and current reading are noted.
The test shall be conducted with variac of 0-280 V, 10 A, precision RMS voltmeter and
ammeter. The conductors used for short-circuiting one of the transformer windings should have
low impedance (less than 1m-ohm) and short length. The contacts should be clean and tight.
The acceptable criteria should be the measured impedance voltage having agreement to within 3
percent of impedance specified in rating and diagram nameplate of the transformer. Variation in
impedance voltage of more than 3% should be considered significant and further investigated.
Document No: RPS/Testing/001. Rev. 00
PURPOSE
ON-LOAD TAP CHANGERS (OLTCs) are designed to be operated while the transformer is energised.
OLTCs may be located in either the high voltage winding or the low voltage winding, depending on the
requirements of the user, the cost effectiveness of the application and tap changer availability. OLTC
being a current interrupting device requires periodic inspection and maintenance. The frequency of
inspections is based on time in service, range of use and number of operations.
DEFINITIONS:
Diverter Switch
A switching device used in conjunction with a tap selector to carry, make and break currents in circuits
which have already been selected. Diverter switch of spring-operated type include an independent
means of storing energy for their operation.
Tap Selector
A device designed to carry, but not to make or break, current, used in conjunction with a diverter
switch, to select tapping connections.
Selector Switch.
A switching device capable of making, carrying and breaking current, combining the duties of a tap-
selector and a diverter switch.
Change-over selector
A device designed to carry, but not to make or break, current, used in conjunction with a tap selector or
selector switch to enable its contacts, and the connected tapping, to be used more than once when
moving from one extreme position to the other.
Transition impedance
A resistor or reactor consisting of one or more units bridging the tapping next to be used, for the
purpose of transferring load from one tapping to the other without interruption or appreciable change in
the load current, at the same time limiting the circulating current for the period that both tapping are
used.
Driving mechanism
The means by which the drive to the tap-changer is actuated.
Motor-drive mechanism
A driving mechanism as defined above which incorporates an electric motor and control circuit.
Document No: RPS/Testing/001. Rev. 00
Step-by-step control
Electrical and mechanical devices stopping the motor-drive mechanism after completion of a tap-
change, independently of the operating sequence of the control switch.
Limit switches
Electro-mechanical devices preventing operation of the tap-changer beyond either end position, but
allowing operation towards the opposite direction.
Operation counter
A device indicating the number of tap changes accomplished.
ISOLATION REQUIRED:
The maintenance is carried out on full shut down of the transformer where both the side breakers &
Isolators are opened and necessary earthing is done. All protections for the transformer are kept out by
switching off the DC supply. The transformer bushings are connected to earth as an additional
precaution.
SAFETY REFERENCE:
This testing shall be carried out during Shut down period and all testing shall be done under PTW
(Permit To Work).
PRECAUTIONS:
This testing shall be carried out during Shut down period and all testing shall be done under PTW
(Permit To Work). Ensure the isolation of Transformer for High Voltage & Low voltage side with
physical inspection of open condition of the concerned isolators/ Disconnector. In case tertiary is also
connected, ensure the isolation of the same prior to commencement of testing
Document No: RPS/Testing/001. Rev. 00
PROCEDURES:
Check hand operation of the tap changer up and down the full range before electrical operation is
attempted and that the handle interlock switch will not allow electrical operation while the handle is
inserted. In addition where single phase tap changers are employed check their tap positions agree and
are reached simultaneously at motor drive unit head. Continuity check should be done for any
discontinuity during tap changing operation by connecting an analogue multi meter across HV& IV
bushing and change the tap positions from maximum to minimum.
Maintaining Circuit
Check the maintaining circuit for correct sequence by hand winding unit half way through a tap and
then remove the handle. Energise the drive motor and ensure that the motor continues to drive the tap
changer in the same direction.
Limit Switches
Check the operation of the limit switches at both ends of the range.
Drive Motor
With the tap changer in mid position check the direction of rotation and measure the start and running
currents in both the raise and lower mode of operation and record their values. Set the motor overload
to 10% above running current.
Check accurate indication of mechanical position indicator in all positions. Also check the remove
instrument operates in the same sequence to the same accuracy. Without remote instrument connected
operate the tap changer and measure the output from each binary coded matrix.
Document No: RPS/Testing/001. Rev. 00
Check the operation of the tap changer incomplete alarm, including the flag relay, by winding the unit
by hand half way through a tap change and monitoring their correct operation and time to operate.
Operation Counter
Check the tap changer counter operates correctly and record reading
Remote Indication
Check the remote indication and control facility is proved to the outgoing terminals of the marshalling
kiosk.
3. DEFINITION
Dissipation
Factor
Dissipation factor/loss factor (Tan delta) is defined as the ratio of resistive component(I r ) of current to that of capacitive current
(I c ) flowing in an insulating material.
Power Factor
Power factor is the ratio of resistive current to that of total current. For very low
value of resistive currents, values of dissipation factor and power factor are same
(upto 2%).
Tan delta = Ir / Ic
Capacitance C = eA/ d, where e = permittivity, A = Area and d = distance
between Capacitance electrode/ terminals
test is used with GST test to confirm the test readings made using the UST mode.
4. ABBREVIATIONS
PTW : PERMIT TO WORK
EHV : EXTRA HIGH VOLTAGE
HF TERMINAL : HIGH FREQUENCY TERMINAL AC
: ALTERNATING CURRENT
UST : UNGROUNDED SPECIMEN TEST MODE
GST : GROUNDED SPECIMEN TEST MODE
6. TEST EQUIPMENT
10 kV Capacitance and Tan Delta test set having normal and reverse mode of operation as well as Interference Suppression
Units.
7. ISOLATION
REQUIRED CTs
a) Open jumper from HV terminal of CT (not provided with test tap) and line CTs.
b) Test tap of CT should be disconnected from ground.
Circuit Breakers
c) CB should be in open condition with isolators on both the sides should also be in open
condition.
CVTs
d) Open jumper from HV terminal of line/bus CVTs.
e) Remove earth connection/earth from neutral point/bushing of EMU tank.
8. PRECAUTIONS
a) Ensure that PTW is taken as per norms.
b) There should be no joints in testing cables.
c) HV lead should be double shielded / screened. Both the shields should not get shorted otherwise tests in
GST/GSTg modes, shall not be possible. Check the same by Insulation Tester(100V)
d) Test leads should not touch any live part.
e) Never connect the test set to energized equipment.
f) The ground cable must be connected first and removed at last
g) High voltage plugs should be free from moisture during installation and operation.
Document No: RPS/Testing/001. Rev. 00
h) It should be ensured that whole testing equipment along with Operation Manual of the kit testing
procedures are available at testing site. Testing must be carried out in presence of testing personnel
only.
i) After testing with high voltage (10 kV), test terminals must be grounded before being touched by any
personnel.
Note: Before carrying out the measurement, the insulator petticoats of CTs/CVTs/Grading Capacitor should be cleaned
from moisture, sand, dust particles or salt deposition etc. otherwise measured values shall not be accurate.
Test tap of CTs/ Earth connection of CVTs should be re-connected to ground after the test.
9. TESTING PROCEDURE:
Typical arrangement for Tan delta measurement is given
A) CURRENT TRANSFORMERS
a) CT’s with test taps:
1. Tan delta tap should be disconnected from ground.
2. High voltage lead from tan delta kit should be connected to primary(HV) Terminal and LV lead should be
connected to the Tan delta test tap.
3. Before applying HV, interference is to be nullified using Interference suppression unit (ISU).
4. Measurements have to be taken in UST – Mode.
5. Standard procedure(as specified by kit supplier) for measuring Capacitance and Tan delta in charged
switchyard/induced voltage conditions should be followed for measurement of Capacitance and Tan delta values.
6. Measurement to be carried out at 2kV and then at 10kV.
7. Carry out the measurements in main and reverse mode/polarity and then compute the average value.
Document No: RPS/Testing/001. Rev. 00
temperature even for a particular make / type shall be different. Hence, no standardized temperature correction factors can be
used for practical purpose.
Significance of Humidity
The exposed surface of the CT/CVT Insulators bushings may under adverse humidity conditions, acquire a deposit of surface
moisture which can have a significant effect on surface losses and consequently on the results. Dielectric strength of insulation
decreases with increase in moisture content. Surface leakage errors can be minimize if dissipation factor measurements are
made under conditions where the weather is clear and sunny and where the relative humidity does not exceed 80%.
Surface Leakage
Any leakage over the insulation surfaces of the specimen will be add to the losses in the insulation and may give false impression
of the condition of the test specimen. Surfaces of insulators should be clean and dry when making a measurement. CTs
provided with power factor test tap, the effect of leakage current over the surface of porcelain bushings may be eliminated by
measuring in UST mode.
Electrostatic Interference
When tests are conduct in energized Substations, the readings may be influence by electrostatic interference currents
resulting from the capacitive coupling between energized lines and the specimen. Jumpers connected need to be open while
carrying out the measurement in GST and GSTg modes to avoid effect of high interference. In EHV Substation, the effect of
electrostatic interference currents can also be cancel by using the interference suppression circuit. Measurements are to be taken
in Normal and Reverse polarity to cancel any residual interference currents.
Negative Tan delta
In isolated case, negative tan delta is record in measurement of dielectric specimen of low capacitance. This condition most likely
arises when making UST and GSTg measurements on specimen, which have capacitance of a few hundred Pico-farads such
as bushings, Circuit breaker grading capacitors. Sometimes Tan delta of CVTs may give negative values. This may be due to the
tan delta value of the EMU transformer winding being higher.
(B) Interpretation of test results
Main reason for increase of tan delta value is because of presence of inherent air voids which are created during manufacturing
process. In course of application of high voltage, these voids are ionized which result in deterioration of insulating properties of
the insulation. Increase in the value of tan delta will indicate the following conditions:
a) Chemical deterioration due to age and temperature, including certain cases of acute deterioration caused
by localized overheating.
b) Contamination by water, carbon deposits, bad oil, dirt and other chemicals.
c) Severe leakage through cracks and surfaces.
d) Ionization.
Adverse effect of moisture in Paper insulation
Dielectric strength of insulation decreases with increase in moisture content. And also, moisture in cellulose insulation can lead to
bubble formation under high load conditions. Moisture accelerates the ageing of paper insulation. If moisture content in paper
insulation increases from 1% to about 2%, it will lead to increase in ageing of the insulation by almost two times.
At high temperature, moisture is pushed out of the paper insulation into the oil. As insulation cools down, water begins
to migrate slowly from the oil into the paper. The time for the temperature drop in the oil may be much quicker than the water
Document No: RPS/Testing/001. Rev. 00
can return to the cellulosic insulation. Hence depending upon these conditions, dissipation factor also changes.
Monitoring of dissipation factor/capacitance value
A large number of equipment insulation failures can be anticipated in advance by carrying out testing of Tan delta/dissipation
factor and capacitance measurement. Changes in the value of capacitance indicate abnormal conditions such as presence of
moisture, layer short circuits or open circuits in the capacitor elements of CVT stacks.
An increase in only tan delta value (not appreciable change in capacitance value) indicates deterioration of cellulosic
insulation whereas increase in both tan delta and capacitance values indicates entry of moisture in the insulation.
Effect of ambient temperature
If tan delta measurement is carried out at Ambient other than 20ºC, then there is likely hood that the values may vary since tan
delta values are temperature sensitive. In absence of temperature correction factors, effort should be made to carry out this
measurement at 20 to 40 °C. Correction factors may not be applicable for all make/types of equipments and hence may not be
applied. However, it is must to record the ambient temperature while carrying out the measurement for future references.
Effect of system frequency
Tan delta values are also affected by system frequency since capacitive current is directly proportional to system frequency. If tan
delta kit is not provided with device which produces output voltage of constant frequency, then it is essential to record the system
frequency at the time of carrying out these tests.
11. Duration of Testing: Two hrs. Per Equipment (Average)
Document No: RPS/Testing/001. Rev. 00
6. TEST EQUIPMENT
5 kV Motorized Megger and associated accessories like test leads etc.
7. ISOLATION REQUIRED
a) CB should be in open position.
b) Isolators from both sides of CT should be in open position.
c) Earth switch should be open at the time of IR measurement.
8. PRECAUTIONS
a) Ensure that PTW is taken as per norms.
b) There should be no joints in testing cables.
c) Test leads should not touch any live part.
d) Megger body should be earthed (if separate terminal is provided).
e) Surface/terminals should be cleaned.
f) IR measurement should be carried out preferably in dry and sunny weather.
g) Never connect the test set to energized equipment.
h) The ground terminal must be connected first and removed at last.
i) High voltage plugs should be free from moisture during installation and operation.
Document No: RPS/Testing/001. Rev. 00
j) If oil traces are found on the surface of CT, the same should be cleaned by Methyl Alcohol only. Petrol
or diesel should never be used.
k) It should be ensured that whole testing equipment along with testing procedures are available at testing
site. Testing must be carried out in presence of testing engineer only.
l) After testing with high voltage, test terminals must be grounded before being touched by any
personnel.
m) Test leads should be properly screened/ shielded.
9. TESTING PROCEDURE
Connect the Megger as per figure given below. Connect the HV terminal to the Primary terminal of CT by using crocodile
clip for firm grip.
Carry out the measurement as per standard procedure given by the kit supplier. Note down the values as per format.
A test voltage as specified is applied as per the above connections and successive readings are taken. Values of IR should be
recorded after 15 seconds, 60 seconds and 600 seconds. Ambient temperature and weather conditions are to be recorded.
10. EVALUATION OF TEST RESULTS
Changes in the normal IR value of CT indicate abnormal conditions such as presence of moisture, dirt, dust, crack in insulator of
CT and degradation of insulation. Changes in IR value of CT are also based on the weather conditions. It is advised to carry
out IR measurement during sunny & dry weather preferably. Insulation Resistance changes with deterioration in insulating
properties. Absolute value of IR is important to monitor but the rate of change is equally important.
Analysis of IR values
If readings of IR increase with time, the insulation is good. However, if readings remain same over the time span, insulation is
contaminated. This is due to the fact that charging current and absorption currents subside with time and only conduction current
remains. This indicates that total current taken by insulation changes with time. However, if there is no appreciable change in
the total current drawn by the insulation, it is an indication of domination of conduction current over charging and
Document No: RPS/Testing/001. Rev. 00
absorption currents. The different currents involved in IR measurement are given below:
Document No: RPS/Testing/001. Rev. 00
a) Charging Current
Due to the application of Voltage to a Capacitance, it gets charge to the applied voltage. The length of time it would take to
charge the capacitance would vary according to the magnitude of the capacitance and the resistance of the voltage source.
b) Dielectric Absorption Current
When capacitor is insulated with material other than vacuum or air, the current that flows when a direct voltage is applied is
no longer the charging current alone. The additional current is known as dielectric absorption current. This current is due to
the presence of polar molecules in the insulation system.
c) Conduction current
When a direct voltage is applied to a capacitor, the steady state value of the current is known as the conduction current.
This is if one waits until the dielectric absorption current has decayed to zero, the remaining current is the conduction
current. Conduction current is directly affected by temperature, humidity, contaminants and voltage stress. In solid insulating
materials which have absorbed moisture, there will be a non-linear large increase of the conduction current for increase in
the voltage stress. This is known as the EVERSHED affect.
IR value after 60 seconds
1. Dielectric absorption ratio = ————————————
IR value after 15 seconds
IR value after 600 seconds
2. Polarization Index = ————————————
IR value after 60 seconds
If Dielectric Absorption Ratio is above 1.5 then insulation quality is assumed to be good. If Polarization Index is more than 1.3
then also insulation quality is assumed to be good.
2. PURPOSE
To measure secondary winding resistance for 400/220 kV Current Transformers.
3. DEFINITION
Document No: RPS/Testing/001. Rev. 00
4. ABBREVIATIONS
PTW : PERMIT TO WORK EHV
: EXTRA HIGH VOLTAGE
AC : ALTERNATING CURRENT
5. TESTING SCHEDULE AND FREQUENCY
As per Maintenance Schedule Doc.
6 TEST EQUIPMENT
Current source and volt meter, winding resistance meter with appropriate leads.
7 REQUIRED.ISOLATION
• CB should be in open position.
• Isolators from both sides of CT should be in open position.
8. PRECAUTIONS
a) Ensure that PTW is taken as per norms.
b) There should be no joints in testing leads/cables.
c) It should be ensured that whole testing equipment along with testing procedures are available at testing site.
Testing must be carried out in presence of testing personnel only.
d) Test links should be opened in the CT MB prior to measurement of secondary resistance.
e) It should be ensured that associated CTs are not in charged condition. For example, Main and Tie CTs for
differential relays should not be in charged condition.
f) If any earth is provided in the secondary circuit of CT, same is to be removed prior to measurement.
Document No: RPS/Testing/001. Rev. 00
12. FORMATS
As per DOC.
Document No: RPS/Testing/001. Rev. 00
7. MEGNETIZATION CHARACTERISTIC OF
CURRENT TRANSFORMERS
2. PURPOSE
To carry out Magnetization Characteristics of CT cores for 400/220 kV Current Transformers.
3. DEFINITION
KNEE POINT VOLTAGE
Knee Point Voltage is defined as the voltage at which a 10 % increase in flux density would cause 50% increase in
exciting ampere-turns.
4. ABBREVIATIONS
PTW : PERMIT TO WORK EHV :
EXTRA HIGH VOLTAGE
AC : ALTERNATING VOLTAGE
6. TEST EQUIPMENT
Voltage source of 5 kV, Voltmeter of range 0 to 5 kV, Ammeter, of range 0 to 100 Amps, testing leads/cables etc.
7. ISOLATION REQUIRED
• CB should be in open position.
• Isolators from both sides of CT should be in open position.
8. PRECAUTIONS
a) Ensure that PTW is taken as per norms.
b) There should be no joints in testing leads/cables.
c) It should be ensured that whole testing equipment along with testing procedures are available at testing
site. Testing must be carried out in presence of testing personnel only.
Document No: RPS/Testing/001. Rev. 00
12. FORMATS
As per DOC.
Document No: RPS/Testing/001. Rev. 00
9. MAINTENANCE/TESTING PROCEDURE
a) Make the connections to the kit from CB pole ensuring that regulating valve is fully close at the time of
connections of the Dew Point kit
b) By regulating the flow rate of SF6 gas (0.2 liter/min to 0.5 liter/min - ref. IEC 60480), the value of dew
Saturation Vapor Pressure decreases with increase in Pressure of the SF6 gas. Hence, dew point of SF6 gas at higher
pressure is lower than dew point at atmospheric pressure. Therefore, it is to be ensured that if measurement has been
done at a pressure other than the Atmospheric pressure, same is to be converted to the atmospheric pressure as given in the table
below for various CB manufacturers: Method for converting dew point at different gas pressures is given/described in IEC-
60480.
Sl. No. Make Dew point at Dew point at Remarks
of CB rated pressure Atmospheric Pressure
pressure (limits)
1. BHEL - 15° C - 36° C At the time of commissioning
- 7° C - 29 ° C During
- 5° C - 27 °C
O&M Critical
6. For all make - 15°C (-) 35°C To be followed for wagoora s/s or
of CBs substations having ambient temperature
less than zero degree centigrade
8. MAINTENANCE/TESTING PROCEDURE
a) Make connections as shown in the figure. It is to be ensured that R, Y, B phase marking cables is connected
with the proper place in the CB analyzer and color codes are to be maintained for all the three poles of CB.
b) Make connections for recording operating timings of Auxiliary contacts.
c) Extend power supply to Circuit Breaker Analyzer.
d) Give closing command to closing coil of CB and note down the PIR and main contact closing time. Take the
print out from the analyzer.
e) Give tripping command to trip coil-I of CB and note down the main contact tripping time.
f) Give tripping command to trip coil-II of CB and note down the main contact closing time.
g) Note down the timings for ‘CO’, and ‘OCO’ by giving respective commands. CO command to be given
without time delay but 300ms time delay to be given between O and CO operations in testing for OCO.
h) To find out opening time of PIR contacts, PIR assembly has to be electrically isolated from Main contacts
and then PIR contacts are to be connecting to separate digital channels of the Analyzer.
Document No: RPS/Testing/001. Rev. 00
It is also important to measure timings of auxiliary contacts from the point of view of variations w.r.t. the main contacts.
2. PURPOSE
To Measure Contact Resistance of 400 & 220 kV Circuit Breaker and Isolator Main Contacts.
3. ABBREVIATIONS
PTW : PERMIT TO WORK EHV :
EXTRA HIGH VOLTAGE
AC : ALTERNATING CURRENT
5. TEST EQUIPMENT
Contact resistance kit (100A DC minimum)
6. ISOLATION REQUIRED
• CB should be in open position.
• Isolator on either side of CB should be in open position.
• Earth switch of both side of the CB should be in closed position.
7. PRECAUTIONS
a) Ensure that proper PTW is taken as per norms.
b) There should be no joints in testing leads/cables.
c) It should be ensured that whole testing equipment along with testing procedures are available at testing site.
Testing must be carried out in presence of testing personnel only.
At the time of connections, both sides of isolator should be earthed by closing earth switches or by temporary earths. After the
connections, earthlings should be removed.
8. MAINTENANCE/TESTING PROCEDURE
The measurement is taken at CB in closed position. The Ohm Meter operates on the four wire measurement principle.
To measure the contact resistance connect the respective leads and adjust the vary A.C. so that app. 100 amps current flow
through the contacts. Value of contact resistance is directly displayed on the digital LED display screen. By using four terminal
method, we can nullify the resistance of test leads if input impedance of measuring device (IC) is very high.
Document No: RPS/Testing/001. Rev. 00
11. FORMATS
As per DOC.
Document No: RPS/Testing/001. Rev. 00
6. ISOLATION REQUIRED
a) CB should be in open position.
b) Isolator of both sides of CB should be in open position.
c) Earth switch of one side of CB should be in open position.
7. PRECAUTIONS
a) Ensure that proper PTW is taken as per norms.
b) There should be no joints in testing leads/cables.
c) It should be ensured that whole testing equipment along with testing procedures are available at testing site. Testing
must be carried out in presence of testing personnel only.
d) Current leads should be connected such that voltage leads are not outside area of current flow.
8. MAINTENANCE/TESTING PROCEDURE
a) Follow the standard procedure as given in instruction manual of DCRM kit.
b) The tightness of connections at CB flanges is most important to ensure error free measurement. CB during CO
operation generates lot of vibrations and failure of connections during this period can dramatically change the
dynamic signature of CB resistance.
Document No: RPS/Testing/001. Rev. 00
c. DCRM signatures should be recorded for CO operation. Open command should be extended after
300 ms from the close command.
d. Clean portions of incoming and outgoing flanges of CB with polish paper to remove paint,
oxidation etc, at points where Current clamps are mounted.
e. Select this point of connection, as close as possible to the end of porcelain insulator to ensure
that minimum resistance is offered by flanges, bolts, terminal connectors etc.
f. It should be ensured that Travel Transducers are properly fitted.
g. Sampling frequency during measurement should be 10 KHz.
Transducers are attached to the operating rod or interrupting chamber in order to record the contact travel. When CB closes, contact
travel is recorded. Contact bounces or any other abnormality is also clearly indicated by the Contact Travel Measurement.
If contact travel, contact speed and contact acceleration signature are compared with the original signatures, then it may indicate
problems related with the operating mechanism, operating levers, main/ arcing contacts, alignments etc.
DCRM along with Contact Travel measurement is useful in monitoring length of Arcing contacts. Erosion of Arcing contacts may
lead to commutation failures and current may get transferred to Main contacts. Due to heat of arc, main contacts may get
damaged.
10. DURATION OF TESTING
Four Hours per CB
11. FORMATS - As per DOC.
Document No: RPS/Testing/001. Rev. 00
3. ABBREVIATIONS
PTW : PERMIT TO WORK
4. TESTING SCHEDULE AND FREQUENCY
As per maintenance schedule document.
5. TEST EQUIPMENT
Leakage Current Monitor suitable to filter out third harmonic resistive current from total leakage current.
6. ISOLATION REQUIRED
No isolation required since it is an On line measurement.
7. PRECAUTIONS
• Ensure that PTW is taken as per norms.
• Test leads should be fully screened to nullify the effect of electromagnetic interference.
• Ensure that Arrester is mounted on isolated base.
8. MAINTENANCE / TESTING PROCEDURE
a. The kit should be properly earthed as per the recommendations of the kit suppliers.
b. Clamp On type CT should be placed above the surge monitor to pick up the total leakage current.
c. Carryout the measurements as per standard procedure supplied by the test kit manufacturer.
d. Note down the system voltage and ambient temperature along with the test current value.
e. Avoid measurement during monsoon.
9. EVALUATION OF TEST RESULTS
A. ZnO Surge Arrester continuously conducts a small leakage current. The resistive component of this
leakage current may increase with time due to different stresses causing ageing and finally cause arrester failure.
B. Arresters are to be removed from service if norms are violated.
C. While monitoring third harmonic resistive current, temperature and voltage correction
Document No: RPS/Testing/001. Rev. 00
factors are to be applied because leakage resistive current also depends on these factors apart
from ageing of the arrester discs. As Indian manufacturers are yet to develop the correction
factors and still working on to it, it is advisable to carry out the measurements at
temperature from 20ºC to 30ºC.
D. If Harmonics are present in the system voltage, it shall effect the value of measured third
harmonic current. Compensating device provided to be used to nullify the effect.
10. DURATION OF TESTING - Half an hour per Surge Arrester