OR Model Paper
OR Model Paper
Operation Research
Time: 3 hours Mechanical- 7th Semester Full Marks: 70
Instructions:
The marks are indicated in right hand margin.
There are total Nine questions in the paper.
Question No. 1 is compulsory.
Attempt any Five questions in all.
1. Chose the correct answer/fill in the blanks (any seven) of the following. 2*7=14
(i) Comment on the LP and graphical method for aggregate planning
a) Graphical- Optimization approach, LP –Optimization approach
b) Graphical- Optimization approach, LP –Evaluative approach
c) Graphical- Evaluative approach, LP –Optimization approach
d) Graphical- Evaluative approach, LP –Evaluative approach
(ii) The difference between total float and head event slack is
a) free float
b) independent float
c) interference float
d) linear float
(iii) Every basic feasible solution of a general assignment problem, having a square pay-off
matrix of order, n should have assignments equal to
a) 2n+1
b) 2n-1
c) m+n-1
d) m+n+1
(v) When the lead time and demand are deterministic, reorder level is
a) Lead time
b) Sum of lead time and demand
c) Demand during lead time
d) Economic Order Quantity
(vii) Johnson’s rule for scheduling is applicable for planning a job shop for
a) n machines 2 jobs
b) n machines n jobs
c) 2 machines n jobs
d) 1 machine n jobs
(viii) In a single server queuing model, the arrival rate is A, and the service rate is μ. What is the
probability of system being idle?
a) λ/µ
b) 1- λ/µ
c) (1-λ)/µ
d) µ/λ
3. A dentist schedules all his patients for 30 minutes appointments. Some of the patients
take more or less than 30 minutes depending upon the type of dental work to be done.
The table shows the various categories of work their probabilities and the actual time to
complete the work.
4. (a) Use simplex method to solve the following Problem: Maximize Z = 3x1+2 x2+5x3
Subjected to: x1 + x2 + x3 ≤ 9
2x1+3x2 +5x3 ≤ 30
2x1- x2 - x3 ≤ 8
x1, x2, x3 ≥ 0 10
(b) Write the Dual of following LPP: Minimize Z = 3x1- 2x2 + x3
Subjected to: 2x1-3x2 +x3≤ 5
4x1-2x2+ ≥ 9
-8x1+4x2 + 3x3 = 7
x1, x2, ≥ 0 x3 is unrestricted. 4
5. Solve the following transportation problem and check for optimality using MODI
method to determine the optimum transportation cost. 14
To P Q R S T Supply
From
A 68 35 4 74 15 18
B 57 88 91 3 8 17
C 91 60 75 45 60 19
D 52 53 24 7 82 13
F 51 18 82 13 7 15
Demand 16 18 20 14 14
6. (a) A company purchases bottles from the market. The per day demand of bottles is 60.
The cost per order is ₹ 50 and carrying cost is 15% of the unit cost. Assuming 300
working days a year calculate the EOQ and minimum inventory cost for the price break
given below: 7
Lot Size Unit price in ₹
0 < q < 1999 ₹ 65
2000 ≤ q <4999 ₹ 60
5000 ≤ q< 9999 ₹ 55
Over 9999 ₹ 50
(b) State and explain ABC analysis with an example. 7
7. (a) There are seven jobs each of which has to go through the machines A & B in the
order AB. Processing times in hours are given as:
Job 1 2 3 4 5 6 7
Machine A 3 12 15 6 10 11 9
Machine B 8 10 10 6 12 1 3
Determine the sequence of these jobs that will minimize total elapsed time. Also
determine the idle time for both the machines A & B. 7
(b) The table given below gives the list of activity with predecessors and the three time
estimates in weeks. 7
Activity Predecessors activity Optimistic time Most Likely time Pessimistic time
A - 1 2 9
B A 2 3 4
C A 2 4 6
D A 3 5 7
E C 5 7 9
F D 1 3 5
G B 1 4 7
H G 2 6 10
I E,H 4 8 6
J F 2 6 1
Draw the project network and find critical path. Also find the probability of completion
in 21 weeks and 25 weeks.