2 Altimeter:
Shows altitude in feet MSL (Mean Sea Level). The drogue shutes deploy at
about 20.000 ft. The Main chutes should fully open at about 10.000 ft MSL.
6 G-Meter Gauge
Displays the G-acceleration of the space craft during SPS burn’s and entry
interface. Normal readout during re-entry should be ~6 G’s.
7 LV alpha/SPS Pc Gauge
Displays the engine pressure of the LV (Launch Vehicle) or SPS (Service
Propulsion System).
10 Launch Lights
The 6 launch lights indicate the lift off, LES (Launch Escape System) tower
jettison and the opening sequences of the CM parachutes for entry and
splashdown.
11 LV Engines Lights
1,2,3,4 and 5 lights up when all five engines of the saturn’s first and/or second
stage are running. LV GUID lights up when the guidance is controlled by the
CMC (Crew Module Computer) depending on switch 36 (if it’s switched to
AUTO the guidance is controlled by the CMC auto system, FREE disengages
the auto guidance). SII SEP lights up when the second stage will separate. LV
RATE lights up as long as fuel flows.
20, 21 20 changes between SM-RCS thrust power 100% (HIGH) and 50%
(LOW). 21 changes between TRANSLATION mode and ROTATION
mode.
25, 26, 27 These switches turn on or of the S-IVB RCS (Third Stage-Reaction
Control System) Roll, Pitch and YAW mode.
28, 29 The two S-IVB GIMBAL MOTOR switches turn on or off the
PITCH/YAW gimbal motors of the third stage.
30 These switch activates the SPS for burn procedures. The four
INJECTOR VALVE indicators on panel 3 (right hand panel) should
indicate “OPEN”!
31, 32, 33, 34 The four switches should be used to enable the SPS gimbal
motors.
35 Open the guard (right mouse click) and push the button CSM/LV SEP
to separate the CSM from S-IVB after Trans Lunar Injection or S-IVB
shutdown.
7, 8 The two TWR JET switches jettison the launch escape tower (LES)
manually after first stage interstage separation, when the LES doesn’t
jettison automatically.
9 Use these switch to separate the SII from S-IVB if you want to abort
second stage without pressing the abort push button.
10 X-LUNAR INJECTION is used to activate and fire the S-IVB for Trans
Lunar Injection.
1 This indicator indicates the temperature (left scale) and He press (right
scale) of the SM-RCS. Simulation not realistic yet!
3-10 SM RCS HELIUM 1 and 2 switches are used to pressurize the SM RCS
Helium tanks. They should be switched to CLOSE before activating the
SM RCS.
11-18 The propellant switches should be switched to OPEN before activating
the SM RCS.
19 Once you have docked the CSM to the LEM open the guard of the
DOCKING PROBE switch and switch it to EXTD/REL. The TB (Talk
Back Indicator) should change from gray to BP (Barber Pole). Before
CSM/LM separation switch it back to RETRACT.
1 C/W lamps are not simulated yet. But the lamps can be light up during a
test by switching the test switch (2) to LAMP TEST.
3 Mission Timer
Cabin Pressurization and EVA, Panel 2 (center panel)
The simulation of the cabin pressurization is still very simple on version 1.0 beta.
EVA :
1 switch the cabin press to decrease. The indicator needles of gauge 4, 5 and 6
(CABIN, CABIN and PART PRESS O2) go down. Then simply open the hatch (2)
and start you EVA (3).
Switch 7 and 8 are used to switch on or of the cabin fans. You can here them!
SPS Gauges, Panel 3 (right hand panel)
1 Indicates the temperature and He press of the SPS fuel (not realistic
yet).
The docking window is 1152x864 pixels for those who using 19 inch monitors. With a
resolution of 1152x864 it works perfect. For a resolution of 1024x768 the docking
procedure should work as followed:
Simply scroll to the upper left corner. The COAS (Crewman Optical Align Sight)
should point the right way to the LM docking target.