100% found this document useful (2 votes)
1K views2 pages

Problems On Network Diagram and Critical Path, CPM 1

The document discusses the activities, predecessors, and durations of 5 different projects. For each project, it asks questions about drawing the network diagram, finding the critical path and project duration, calculating float, and exploring the impacts of changing activity durations or predecessors on the project completion time.

Uploaded by

Shahriar Kabir
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
100% found this document useful (2 votes)
1K views2 pages

Problems On Network Diagram and Critical Path, CPM 1

The document discusses the activities, predecessors, and durations of 5 different projects. For each project, it asks questions about drawing the network diagram, finding the critical path and project duration, calculating float, and exploring the impacts of changing activity durations or predecessors on the project completion time.

Uploaded by

Shahriar Kabir
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 2

1. Activities of a project are summarized in the following table.

Activity Immediate Duration Activity Immediate Duration


Predecessor(s) (Weeks) Predecessor(s) (Weeks)
A 4 F C, E 2
B 5 G C, E 3
C A 2 H C, D, E 7
D B 2 I C, D, E 5
E B 3 J G, H 6

a) Draw a network diagram and find the critical path and project completion time.
b) Calculate float/ slack of the all activities.
c) Can activity I be delayed without delaying the project completion time? If so, how many weeks?
d) Activity G needs a delayed time of two weeks and an extra time of one week. Is it possible by keeping the project
completion time unchanged? Explain.
e) The PM wants to shorten the duration of the activity E from 3 weeks to 1 week. What is the impact of this change on the
project completion time?
2. Activities of a project are summarized in the following table.

Activity Immediate Duration Activity Immediate Duration


Predecessor(s) (Weeks) Predecessor(s) (Weeks)
A 4 H B 16
B 10 I H 4
C 7 J H 8
D A 5 K I, J, L 5
E D, G 3 L C 9
F E 6 M J, L 11
G B 2 N F, K, M 7

a) Draw the network diagram and find the critical path and project completion time.
b) Calculate float/ slack of the all activities.
c) Can activity I be delayed without delaying the project completion time? How many weeks?
d) What is the impact on the project if activity F needs extra 5 weeks?
e) The PM wants to shorten the duration of the activity H from 16 weeks to 10 weeks. What is the impact of this change on the
project completion time?
3. Activities of a project are summarized in the following table.

Activity Immediate Duration Activity Immediate Duration


Predecessor(s) (Weeks) Predecessor(s) (Weeks)
A 4 F B 6
B 10 G C 2
C 7 H F 8
D A 5 I F, G 11
E B 3 J D, E 8

a) Draw a network diagram and find the critical path and project completion time.
b) Calculate float/ slack of the all activities.
c) If $1000 can be saved for each delayed day of activity H, then how much dollar can be saved keeping the project completion
time unchanged?
d) Activity G needs a delayed time of two weeks and an extra time of five weeks. Is it possible by keeping the project
completion time unchanged? Explain.
e)The PM wants to shorten the duration of the activity I from 11 weeks to 9 weeks. What is the impact of this change on project
completion time?
4. Schedules and activities of a project are shown below. Answer the questions.

Activity Predecessor(s) Duration (days) Activity Predecessor(s) Duration (days)


A 4 G B 2
B 3 H C, E, G 6
C 2 I H 8
D A 3 J C 4
E D 5 K J 7
F D 3 L F, I, K 3
Questions:
a) Draw CPM chart and show, which tasks are on the critical path?
b) Calculate float/ slack of the all activities.
c) The person working on task K tells the PM he can’t start work until two days after the schedule starting date.
What impact would this have on the completion date of the project? Why?

5. The activities for a project are summarized in the following table.

Activity Immediate Duration Activity Immediate Duration


Predecessor(s) (Weeks) Predecessor(s) (Weeks)
N 5 G B 2
A N 4 H B 16
B N 10 I H 4
C N 7 J H 8
D A 5 K I, J, L 5
E D, G 3 L C 9
F E 6 M J, L 10

a) Draw the network diagram and find the critical path and project completion time.
b) Calculate float/ slack of the all activities.
c) Can activity I be delayed without delaying the project completion time? If so, how many weeks? How much dollar
can be saved by keeping the project completion time unchanged, if $2500 can be saved for each delayed week of
activity I?
d) What is the impact on the project if activity F needs a delayed time 2 weeks and extra time 5 weeks?
e) The PM wants to delay the duration of the activity M from 10 weeks to 16 weeks. What is the impact on the project
completion time?

You might also like