CUCF Consultant Design Guidelines 10.5.20 PDF
CUCF Consultant Design Guidelines 10.5.20 PDF
CUCF Consultant Design Guidelines 10.5.20 PDF
DESIGN GUIDELINES
October 5, 2020
CITY UNIVERSITY CONSTRUCTION FUND
CONSULTANT DESIGN GUIDELINES - TABLE OF CONTENTS
INTRODUCTION 1
CHAPTER I – DESIGN APPROACH AND KEY DESIGN CRITERIA 3
A. Design Excellence 3
B. Sustainable Design and Construction 4
C. Regulatory Agency Requirements 5
D. Functional and Performance Requirements 6
APPENDIX 53
A. Cost Estimating 53
B. Submission Standards 55
C. Interdisciplinary Coordination Reviews 59
D. Classification of Building Areas 70
E. Historic Preservation 74
F. Environmental Engineering 76
G. Lab Design Criteria 80
H. Fire Alarm Systems 95
I. Energy Code 97
J. Shop Drawing Stamp 98
K. Special Inspections 99
L. Design Preferences and Requirements 103
M. Lighting Performance Requirements 107
N. Lighting and Lighting Commissioning Specifications 114
O. Water Treatment Procedure 134
P. Boiler Startup Procedure 137
Q. Chiller Startup Procedure 141
The City University Construction Fund (CUCF) is a public benefit corporation established in
1966 by the New York State Legislature. The mission of the CUCF is to manage the
resources necessary for the design and construction of space required to support the
educational mandate of the City University of New York.
The City University of New York’s Department of Design, Construction and Management
(DDCM) in the office of Facilities Planning, Construction and Management (FPCM) compiled
and edited these guidelines. DDCM updates the guidelines as requirements change.
Although there may be several offices and departments within the University, the colleges
and the other agencies involved with the development of a project, DDCM is the primary
contact for guidance on design criteria and requirements.
The Consultant is also responsible for initiating and sustaining an integrated design process
with the entire design team. The Consultant will coordinate the work of all subconsultants
and all other entities involved in the project during all phases of design. The Consultant will
be proactive in identifying and recommending additional, different, innovative or technically-
refined design criteria for application to a specific project, which DDCM welcomes for its
consideration and approval. Early in the design process, the Consultant will determine the
requirements of all regulatory agencies having jurisdiction and will develop an action plan for
compliance.
The Consultant is totally responsible for all design and is required to deliver a design that is
approved by DDCM/CUCF. Regardless of any periodic review that DDCM may perform, the
Consultant is professionally and contractually responsible for the correctness and
completeness of the contract documents and for conformance with the scope of work,
budget, and applicable codes, zoning requirements and laws.
The Guidelines begin with a general outline of DDCM’s Design Approach and Design Criteria.
Subsequently, there are chapters that delineate requirements for each of five possible design phases –
Feasibility, Pre-Schematic (Conceptual), Schematic, Design Development and Construction
Documents. Each of these chapters summarizes general requirements for the particular design phase
and lists some specific requirements and items to consider for each of the major disciplines. In addition,
there is an appendix on various special topics, some of which contain considerable detailed
requirements.
The Guidelines primarily cover the design requirements and do not include specific information on
procedures, other contract requirements, project management functions and responsibilities during
construction. Project-specific requirements are as per Contract.
A. DESIGN EXCELLENCE
1. Design Intent: The Consultant is responsible for the design of facilities of excellent
quality within the budget and on schedule. Designs shall inspire the public, incorporate
ecological and durable materials and systems, and reflect the cost-effective use of public
funds.
2. Promoting Learning Communities: A primary goal is the creation of environments
that are conducive to learning, teaching and the exchange of ideas and that enhance a
sense of community.
3. Campus Master Plan: Each campus has a Physical Master Plan, approved by the
CUNY Board of Trustees, which is updated periodically and provides the basis for the
development of new facilities and renovation of existing facilities for that campus. In
working on a specific building project, the Consultant will expand upon the site and
building concepts in the current campus Physical Master Plan and further develop site
and planning relationships in conjunction with programmatic needs.
4. Site Planning/Orientation: The Consultant shall site and orient a new facility to take
advantage of natural light and exterior views in conjunction with consideration of other
concerns such as noise, privacy, location of utilities, campus circulation, local
transportation routes, security, and accessibility.
5. Context: The Consultant will take into account the massing, scale, and predominant
materials of surrounding buildings and consider the effect of any new construction on
adjacent buildings and spaces.
6. Planning/Design Concepts: The design of a facility shall adhere to the CUNY/CUCF-
approved program of spaces and reflect required adjacencies and space relationships. It
shall be efficient with a high ratio of net to gross square footage, minimizing the gross
square footage while providing the specified spaces, space relationships, service areas,
and clearly defined circulation. The design shall maximize flexibility to meet the needs of
current and future users.
7. Design Quality in Specifications and Details: The design shall specify materials and
systems that are durable, cost-effective, well-suited for their application and easily
maintained. The design details shall be straightforward and aim to facilitate the ease of
quality construction and installation.
8. Commitment to Accessibility/Universal Design: The University is committed to
providing dignified equal access to all buildings for those with disabilities. All new
construction and renovations must comply with the Americans with Disabilities Act (ADA)
and all applicable codes and shall aim to promote universal design principles. Designs
shall provide the same means of use, identical whenever possible, and equivalent when
not, and avoid conditions that segregate persons with disabilities. The main entrance of
each facility shall be accessible and reachable by an accessible path.
9. Maintenance: Designs shall ensure that maintenance can be routinely performed efficiently.
10. Design Responsibility and Constructability: The Consultant is fully responsible for
providing a comprehensive, accurate, clearly detailed, and coordinated set of contract
documents. The Consultant shall not delegate any design to others without the written
13. Certificate of Operations for Laboratory Units: The Consultant is responsible for
preparing and filing design and installation drawings for laboratory units as required by the
NYC Fire Department (FDNY) and for obtaining the initial Certificate of Operations for
laboratory units from the FDNY.
E. CONCEPTUAL DESIGN
1. Review the program with respect to net/gross planning efficiency.
2. Develop a design concept and define a proposed project scope with options. Incorporate
conceptual recommendations for architectural, structural, mechanical, electrical, plumbing,
fire protection, lighting, energy management, telecommunications, and security systems as
applicable.
3. Perform vertical transportation analysis, where required, and make recommendations.
4. Include analysis of accessibility requirements.
5. Provide conceptual space planning drawings and diagrams.
6. Provide a description of proposed major materials, finishes and equipment.
1. Pre-Schematic Design and Report: When required by the Contract with CUCF, the
Consultant shall perform Pre-Schematic conceptual design work and provide a Pre-
Schematic Report. The Consultant shall investigate a full range of architectural design
options and site possibilities and include appropriate analysis and alternative designs for all
project-specific requirements and systems (i.e., structural, mechanical, electrical, plumbing,
fire protection, communications, swing space, etc.).
2. Drawings: The Consultant shall provide Pre-Schematic drawings at a scale appropriate to
delineate the general nature of the designs envisioned for all applicable disciplines and
suitable for preparation of a Pre-Schematic estimate.
3. Other Submission Materials: The Pre-Schematic submission shall include descriptive
materials to complement the graphic information on the plans as well as outline
specifications, schedules for all phases of design, an outline construction schedule and a
conceptual estimate.
4. Existing Conditions and Code Analysis: If the Consultant was not required to perform a
feasibility study for the project, he/she shall gather and review any existing documents and
reports, survey existing conditions, and perform a code and zoning analysis during this phase
of the project. (Refer to Chapter II for specifics.)
5. Program: Typically, DDCM/CUCF provides the space program. If any programming work is
required, it will be project-specific as per Contract, require DDCM/CUCF approval, and
comprehensively take into account CUCF space standards and the college’s needs,
projected needs and utilization of space.
1. Proposed Project Approach: Establish and recommend the best approach for
program elements and critical relationships between program elements.
2. Building and Site Development Solutions: Unless otherwise directed by
DDCM/CUCF, develop a minimum of three (3) options or alternate building and site
development solutions for the full range of possibilities and generate appropriate
illustrative drawings.
3. Systems Solutions: Develop a minimum of three (3) alternative HVAC, electrical and
structural system configurations and considerations for the proposed solutions. Use
twenty (20) year life cycle cost analysis for determining the feasibility of each alternative,
including initial investment, thermal and electrical energy demand and operating
personnel and plant maintenance costs.
C. ARCHITECTURAL CONCEPT
1. The development of an architectural concept shall be guided by the key design criteria
described in Chapter I, taking into account design excellence, sustainability, regulatory
agency requirements, and functional and performance requirements.
3. The Consultant shall investigate design alternatives and typically present a minimum of
three solutions, with drawings and diagrams, and provide a justification for the
recommended design.
21. Location, type and approximate size of cooling towers; preference is for forced draft cooling
tower with water side economizer cycle
22. Type of air distribution system (i.e., constant volume, variable air volume, etc.).
a. The Schematic Design is critical to the success of the project. The Consultant shall make
every effort to thoroughly analyze all aspects of the project and provide comprehensive
documentation to DDCM for evaluation and determination of the design parameters.
b. During the Schematic phase, the Consultant shall develop study drawings and
documents to illustrate design concepts, typically investigating at least three alternative
schemes.
c. When a project’s first phase is Schematics, there will likely be project-specific tasks or
analyses typically performed in Pre-Schematics that the Consultant will handle in
Schematics and for these, the Consultant shall reference all prior Chapters of these
Guidelines.
d. The Consultant will discuss and review with DDCM the schematic planning relationships,
site planning relationships, scale, systems, and zoning, code and jurisdictional
requirements as well as the material and information to be included in the presentation of
the Schematic Design.
a. Provide a list of the program spaces with actual net assignable square feet, showing
compliance with the DDCM/CUCF-approved program.
b. If there is any deviation from the approved program, the consultant is responsible for
highlighting this to DDCM; no changes in the program will be in effect without DDCM’s full
review and written approval of the changes.
c. Provide color-coded program drawings to indicate space types/usage. Include
occupancy numbers per space and square footage that corresponds to the program list.
D. SYSTEMS ANALYSIS
1. Detailed economic analysis, including life-cycle cost analysis, and engineering
recommendations for systems shall be presented to DDCM before acceptance of the
Schematic Design.
2. The design requirements shall conform to DDCM and ASHRAE conservation standards
F. STRUCTURAL
1. Subsurface Investigation:
a. Review existing subsurface information, provided by DDCM/CUCF and other sources,
from projects on or near the site.
b. Analyze data from all available sources and from site investigations and determine if
subsurface investigations are recommended or necessary to meet the requirements of
the NYC Construction Codes or those of other regulatory agencies with jurisdiction or to
resolve uncertainties about subsurface conditions, rock excavation and ground water
conditions.
c. Develop and submit a subsurface investigation plan for DDCM/CUCF approval.
d. Provide and submit bid documents, prepared by a soils engineer, who will provide
continuous field inspection during the investigation.
e. Provide a soils report with recommendations.
2. Structural Schematic Documents shall include, but not be limited to the following:
a. Design Criteria
b. Loads with different combinations
c. Structural Framing Plans, developed sufficiently to show the selected comparative
systems and associated costs.
d. Foundation plan showing basic foundation system based on available geotechnical
information
e. Lateral load resisting system
f. Typical Structural Sections showing the structural design intent and materials of the
various systems
g. Outline specifications delineating materials for various structural systems
h. Costs for each structural system.
G. MECHANICAL/HVAC
1. Provide a comprehensive narrative description of the mechanical systems that indicates, but
is not limited to:
a. Design Intent/Basis of Design
b. Design Criteria and Calculations
Temperature and relative humidity criteria for inside and outside design conditions for
summer and winter
H. ELECTRICAL
1. Provide a brief description of the electrical system and major electrical equipment.
2. Provide Schematic Drawings, Diagrams and Calculations, including:
a. Block diagrams of the proposed major electrical equipment arrangement and locations
and electrical utility interconnect requirements
b. Schematic riser diagrams for emergency power, fire alarm, low voltage master clock,
signal & security systems and telecommunications (if applicable)
c. Basic one line diagrams indicating all services, voltage levels, spare capacity for future
expansion and emergency power system and indicating existing utility and building
system interconnection points.
3. Design Criteria include, and are not limited to:
a. Coordination with mechanical design in specification of adjustable speeddrives where
possible, such as for fans and centrifugal pumps
b. Use of reduced voltage starters where required
c. Branch voltage design drop as per NYC Code, 2-1/2% to distribution point
d. Panel and switchboard copper design to a maximum of 1000 a/s.i. unless reduced by
NEC Design Requirements
e. For above 3000 KVA service, specification of 480 volt Con Edison supply
f. Allowance of 25% project load growth factor
g. Avoidance of complex, elaborate maintenance requirements
h. For facilities with extreme nonlinear loading, use of double sized neutral and K-rated
transformers and no undersizing of neutrals
i. Lighting illumination design criteria in foot candles per square feet for each area in
compliance with IES (Illuminating Engineering Society) design criteria and the latest
Ashrae 90.1. See Appendix M.
1. Basis: Following DDCM’s approval of the Schematic documents, DDCM/CUCF will direct
the Consultant to proceed to the Design Development Phase and fully develop the design of
the selected option and approved concepts from the Schematic phase.
3. Regulatory Agency Approvals: In general, the Consultant will follow New York City
regulations, including the New York City Construction Codes, Energy Conservation Code,
Fire Code, Zoning Code, etc. The Consultant’s responsibility includes providing a
comprehensive list to DDCM/CUCF of all regulatory agencies having jurisdiction, identifying
the necessary filings, and submitting a final schedule for submissions to these agencies that
allows ample time for obtaining any approvals to comply with the project schedule.
B. ARCHITECTURAL
1. Space Requirements: Resolve important space requirements at this stage of design, such
as major equipment layouts and clearances, mechanical shaft sizes, and circulation, egress,
stair and toilet requirements. Provide sufficient gross area for central mechanical facilities to
assure adequate flexibility of design.
2. Program: Submit a comparison of actual space square footages in the Design Development
documents with the approved Schematics program per space.
C. SITE DESIGN
1. Site Design Development Drawings shall include, but not be limited to:
a. Site plan including streetscape design:
Clearly delineate accessibility elements including ramps, handrails, lighting, bicycle
storage, special parking provisions, accessible routes and such other features as
are required by code or federal ADA standards.
Take into account fire department truck access requirements.
Indicate site lighting.
Provide grade elevations
b. Grading and drainage plan:
Combined utilities site plan at 1” = 40’
Indicate site drainage, sewer, water, gas, fire sprinkler mains, electrical distribution
lines, steam and hot water heat distribution systems, chilled water distribution
systems, fire hydrants and all other existing and proposed utility systems connecting
to the project building and in the area of the project, noting appropriate elevations.
Provide Cathodic protection systems for direct buried doublewall metallic steam and
hot water distribution lines, subject to DDCM approval.
c. Soil erosion and sediment control plan.
2. Provide specifications in latest CSI format for all site materials and surfaces, including
surfaces cut/and or damaged by project construction.
D. STRUCTURAL: In the Design Development phase, clearly indicate the selection of all structural
systems, both superstructure and foundations.
1. The selection of structural systems shall be guided by the following parameters:
a. Soil conditions and associated impact and selection of foundation design as it pertains to
spread footings versus pile footings, mat foundations, drilled piers, soil liquification, etc.
b. Site conditions and the impact on adjoining structures on selection of foundation
c. Lateral load resisting system
d. Intended use of the building
e. Impact of structural system on the project schedule
f. Evaluation of possible construction problems
g. Availability of materials
h. A scheme which allows the College flexibility to make alterations and additions in the
future
i. Resistance to moisture penetration and corrosion
j. System that requires less maintenance.
E. MECHANICAL/HVAC: Items for consideration in the Design Development Phase include, but
are not limited to the following:
1. Individual Building System Considerations:
a. Single duct, normal velocity, constant volume with reheat
b. Single duct, normal velocity, with multi-zone assembly
c. Single duct, normal velocity, variable air volume systems with associated controls
d. Unit ventilators
e. Fan coil units
f. Induction units
g. Packaged equipment
F. ELECTRICAL
1. Provide a list of codes applicable to this project, including but not limited to New York City
Electrical Code, New York City Construction Codes, New York City Fire Code, New York
State Energy Conservation Code, NFPA 72 and 72d, and all applicable Local Laws. Where
the National Electrical Code is more stringent than the New York City codes, it shall be
complied with, as approved by DDCM.
2. Provide a list of required regulatory agency approvals of the final plans and specifications.
3. Electrical Design Development Drawings shall include, but not be limited to:
5. Electrical Design Development Specifications, in the latest CSI format, shall include, but
not be limited to descriptions of the following:
a. Electrical service
b. Service and distribution equipment and metering
c. Panel boards, light and power
d. Motor control centers and starters
e. Light and power distribution
f. Extent of electrical work and controls in connection with equipment supplied under other
contracts, such as motors, boilers, starters, etc.
g. Wiring and raceways
h. Wiring devices
i. Lighting systems including listing the types of fixtures to be used in various areas, foot
candle intensities and methods of control for each. See Appendix M.
j. Various systems to be furnished and installed under the electrical contract such as
telephone, fire alarm, clock and program annunciation system, etc.
k. Emergency light and power provisions
l. Temporary light and power system
m. Special systems and equipment in accordance with College program requirements
n. Security systems
o. Electrical generation.
G. PLUMBING AND FIRE PROTECTION
1. Design toilet rooms so that the plumbing fixtures can be installed back-to-back to minimize
mains and runouts and vertically stack toilet rooms on consecutive floors.
1. When documents are required by Contract for these or any other disciplines, the Design
Development drawings and specifications shall delineate the full extent of the work.
2. The documents shall be fully coordinated with other disciplines and any existing
infrastructure.
3. The Consultant shall confirm specific requirements with the College and DDCM.
I. COST ESTIMATE
1. Submit a comprehensive Design Development cost estimate by trade, using the latest CSI
format. (See Appendix A.)
2. This estimate shall be based on the systems and equipment indicated on the drawings and
specifications.
3. Describe methods used for estimating various components– quantity take-off, contractor’s
estimate, vendor’s estimate, previous similar project, Means, Dodge, etc.
4. Indicate assumed bid date, construction start date, and duration of construction on the
estimate and escalate costs to the midpoint of construction, taking into account market
conditions
5. Include comparisons to previous estimates and to the project budget.
B. 60% CONSTRUCTION DOCUMENTS: Typical requirements at this phase shall include, but not
be limited to the following:
8. Regulatory Agency Approvals: The Consultant shall submit the approvals from all
government agencies having jurisdiction with the submission of the final Contract Documents.
9. Review of Submission: DDCM/CUCF will review this submission and provide the
Consultant with comments for inclusion in the bid set. In that the goal is for the Consultant
b. Sections and details at 3/8” = 1’ -0” scale or larger, with sufficient detailing to indicate
complete structural systems and systems for resisting lateral loads.
Foundation Sections and details including footings, piles, pile caps, foundation walls,
waterproofing
Special details for unique or complicated construction
Reinforcement details for all concrete members including precast members, with
clear dimensioning including size, spacing, and length of reinforcement as well as
concrete and reinforcing strength
Precast concrete connection details
Typical steel structure details
Typical concrete structure details
c. Schedules:
Column and foundation schedules, with location, size and height of each column,
cumulative loads and lateral loads per floor.
Beam, pier, slab, footing, lintel and design-load schedules.
d. Where the existing structure or part of the structure may be temporarily unstable during
any phase of construction, and the condition is unusual or not obvious, the contract
documents shall clearly indicate the existence of this condition to the Contractor.
3. The Consultant shall check the structural drawings for or provide the following:
a. Coordination between specifications and drawings.
b. Coordination of all structural drawings with architectural, mechanical, and all other trade
drawings.
c. Cross reference notes on each drawing to locate typical detail sheet, general notes,
column schedules, etc.
d. Shaded key plan or area covered by a particular drawing
e. Type and frequency of necessary special inspections noted in specifications
f. Floor loading schedule, Itemizing all loads
g. Where lifting hooks and beams are shown such as for elevators, etc., indication of load
capacities of hooks.
4. Foundations
a. Foundation design consistent with boring data information and recommendations of soils
consultants (soil bearing capacity; footing elevations, etc.)
b. Review adjacent structures for underpinning, sheeting, etc. Show method of protecting
existing structures.
c. Where ground water conditions exist either permanently (above the lowest cellar or pit
level) or only temporarily during construction, specify drainage and pumping systems and
provide waterproofing for permanent water conditions and:
5. Piping:
a. Layout shall include at a minimum:
All pipe runs indicating size, direction of flow and pitch,
Trenches, pits, etc.
J. BID DOCUMENTS
1. Upon CUCF’s written approval of the final Contract Documents, either the Consultant or the
Construction Manager will assemble bid packages, in accordance with the Contracts,
CUCF’s Procurement requirements and DDCM’s direction.
2. The Bid Documents typically comprise the drawings and the project manual that contains the
CUCF “boiler plate” items and the specifications.
3. Every final drawing shall include the identification, professional seal and signature of the
Consultant and all sub-consultants responsible for work thereon and shall be in conformance
with the New York City Administrative Code.
4. Project Manual Typical Components: may include, but are not limited to:
a. Advertisement for Bid.
b. Bid Form & Sheets
c. Information for Bidders
d. Form of Bid Bond
e. Form of Performance and Payment Bonds.
f. Contract Agreement
g. Schedule - Contractor’s Monthly Requisition Form
h. General Conditions.
i. Additional Supplemental General Conditions (where federal funds will be used.)
j. Specifications
k. Equal Employment Opportunity, Minority and Women-Owned Business Enterprises, and
Service Service-Disabled Veteran-Owned Businesses clauses.
l. NYC/NYS Prevailing Wage Rates
6. In addition to the submission of the original signed documents, the Consultant shall also
provide an electronic submission, in a format approved by DDCM/CUCF, of all the Bid
Documents.
SUBTOTAL
General Conditions
Overhead /Profit
Design Contingency*
Bid Contingency
Construction Contingency
Escalation – midpoint of Construction
TOTAL
*Not used in final estimate
A. GENERAL
1. Appendix B outlines some general standards applicable for all phases of design. Included
are some requirements for drawings, specifications, presentations, electronic submissions
and schedules and a list of industry sources for various trade standards.
2. For specific requirements for a particular design phase, reference the phase-specific chapters
in the main text of these Guidelines.
3. For project-specific requirements, reference the Contract.
4. For estimating requirements, reference Appendix A in these Guidelines.
B. DRAWINGS FORMAT
1. Drawings Organization: Follow industry best practices in the organization of the drawings,
ensure consistency of orientation, full dimensioning, and clear cross referencing, and fully
delineate the work including providing all necessary details.
2. Recommended Drawing Size: 24” high x 36” wide (min size unless otherwise approved by
DDCM and meets NYC DOB requirements).
3. Cover sheet shall contain:
a. Title of project, college and location; Project No.
b. The City University Construction Fund (with CUCF logo)
c. Index of all drawings
d. Abbreviations List
e. Small scale site plan indicating locations of the work with North arrow
f. One inch borders except at left side, provide 2 ½” border for screw/post binding only.
4. Drawing Numbers: Use drawing numbering system that is consistent with New York City
Department of Buildings requirements.
5. Title Box – In the same location on each drawing, provide a suitable title box acceptable
to DDCM/CUCF and complying with NYC DOB requirements showing:
a. Project title, college and location that is official address of the building(s)
b. Drawing Number
c. Drawing Title
d. Consultant’s and Sub-Consultants’ names & addresses
e. Space for seal
f. Project number
g. Scale
h. Date
i. Space for revisions, date and remarks
j. The City University Construction Fund (with CUCF Logo)
k. Designated space for NYC DOB employee stamps and signature, minimum 3”x3”
l. Designated space for NYC DOB Bscan sticker (application #), minimum 3” X 1”
C. SPECIFICATION FORMAT
1. Provide Specifications in accordance with the latest format developed by the Construction
Specifications Institute (CSI).
2. The Specification Submissions shall become increasingly detailed with each submission.
3. For each item specified, list at least three products/manufacturers “and or approved equal”
unless the item is sole-source (requiring justification) or is on state-contract.
1. DDCM will review Consultant submissions of design documents and provide comments.
2. Other team members such as the Construction Manager, the Commissioning Authority and
the College may also provide comments.
3. It is the Consultant’s responsibility to respond to all comments in writing within two weeks of
receiving them. The Consultant will alert DDCM in writing of any conflicts in the comments,
any deviations from previously accepted scope, and any cost implications.
4. DDCM will evaluate the Consultant responses to comments to determine if they are
acceptable, resolve any conflicts or issues and provide direction prior to accepting any
subsequent Consultant submission.
5. The Consultant is responsible for incorporating comments, as per DDCM’s direction, in the
next submission and will make that submission only after any issues raised in prior comments
have been satisfactorily resolved.
E. ELECTRONIC SUBMISSIONS
1. At each review phase, provide an electronic version of the full submission. At a minimum,
this will include the drawings, specifications, estimate, and any design narrative.
2. Provide electronic submissions of the full bid documents including all addenda and the final
as-built documents.
3. There may be additional electronic submissions (i.e., presentations) that are project-specific.
4. For major projects that will include Building Information Modeling (BIM), the requirements will
be as per Contract.
5. Consult with DDCM for the latest DDCM/CUCF format requirements for electronic
submissions.
H. INDUSTRY STANDARDS – The Consultant shall reference Industry Standards including, but not
necessarily limited to those from the following entities:
A. GENERAL
DDCM/CUCF requires that, in addition to all other checking and quality controls established, the
Consultant perform interdisciplinary reviews on all projects. This is not intended to be a technical
review. Single disciplinary reviews are also essential for assuring technical accuracy.
Approximately 50% of all construction change orders are due to interdisciplinary errors that could
have been avoided. A major source of design errors and omissions is the point of interface
between disciplines.
B. STRUCTURAL DRAWINGS
1. Verify that column grid lines on structural, architectural and other disciplines match. Check
that the structural foundation plan matches the ground floor architectural plan and structural
floor framing plans.
2. Verify that footings are within property lines.
3. Verify that structural and corresponding architectural floor plans show consistent edge of slab
dimensions. Look for recesses and protrusions that do not match. Verify that depressed or
raised slabs are indicated and match architectural. Locate depressed or raised slabs by
checking the architectural finish schedule for floor materials such as quarry tile, ceramic tile,
and raised computer access floors. Check structural floor plans against the drawings for all
disciplines to see that the areas for floor depressions, raised slabs and all slab elevations
match.
4. Verify that foundation piers are identified and sized on a schedule or plan. Locate foundation
piers on structural plans and check that each pier is on a schedule. Piers are usually
identified by a letter/number symbol such as “F-1”. Look for symbol omissions and obvious
typos. Check location of piers with those shown on the architectural drawings
5. Verify that foundation beams are identified and sized on a schedule or plan. Locate beams
on foundation plans and check that each beam is on a schedule. Foundation beams are
usually identified by a letter/number symbol such as “B-1”. Look for symbol omissions and
obvious typos. Check location of beams with architectural drawings.
6. Check mechanical and electrical drawings for pipe and conduit penetrations. Verify that there
are no penetrations through piers, footings or beams.
7. Verify that locations of roof framing plan column lines and columns match foundation plan
column lines and columns.
8. Verify that structural perimeter roof line matches architectural roof plan. Make sure the
structural framing plan is adjusted for unusual architectural features such as concealed
gutters or skylights. Check if roof slopes on structural match architectural roof plan slopes.
C. ARCHITECTURAL DRAWINGS
1. Verify that property line dimensions on survey and civil site plans match architectural. Match
the survey and site plans with the architectural site plans to ensure that overall dimensions
are the same.
2. Verify that the building is located behind setback lines. Location of setback lines on survey
should be outside of the building as positioned on the civil or architectural site plans. Ensure
that building location is clearly defined and coordinated with civil site plans.
3. Verify that overall building dimensions and locations of columns and bearing walls match
structural. Verify that architectural overall building dimensions and elevator and stair core
dimensions match structural. Make sure all columns, bearing wall and shear wall locations
are identical on architectural and structural plans.
4. Verify that existing and new work is clearly identified on site plans. Existing and new work
should be identified in legends and linework.
5. Verify that building elevations match floor plans. In particular, check roof lines, window and
door openings, louver openings, exterior light fixtures, and expansion joints. Also match
E. ELECTRICAL DRAWINGS
1. Verify that electrical floor plans match architectural and mechanical. Check that the location
of floor mounted equipment is consistent between disciplines. Check the architectural floor
plans with the electrical power and HVAC floor plans to make sure that wall locations and
door swings are the same. If the door swings don’t match there may be light switches
located on the wrong side of the door, behind door swings. Check the architectural,
mechanical, and electrical plans for matching location of pumps, compressors, air handling
units, and other equipment.
2. Verify that the location of light fixtures matches architectural reflected ceiling plan and that
light fixtures do not conflict with the structure or mechanical HVAC system. Match electrical
light plans and architectural reflected ceiling plans and check for conflicts with columns,
ceiling diffusers, ceiling grids, skylights, expansion joints, drapery, folding partition tracks,
sprinklers, and soffits. Make sure that recessed or surface mounted light fixtures are suitable
for the ceiling. A common problem is to indicate a surface mounted fixture for an acoustical
tile ceiling where a recessed fixture was desired. Match electrical light plans with structural
and mechanical plans to locate possible areas of conflict with recessed lights, structure, and
ducts. Check that sizes and types of light fixtures are the same in the specifications and
drawing schedules.
3. Verify that major equipment has electrical power connections and that horsepower ratings,
phases, and voltages are consistent with other disciplines schedules. Check mechanical,
plumbing, and kitchen schedules for major pieces of equipment that require electrical service
and verify that these pieces of equipment are included in electrical line diagrams, power
plans, and/or panel schedules. Check horsepower ratings, voltages, and phases for
inconsistencies on mechanical schedule sheets, electrical power plans and riser diagrams,
and specifications.
4. Verify that locations of panel boards are consistent with architectural, mechanical, and
plumbing floor plans and that the panel boards are indicated on the electrical riser diagram.
Match the electrical power plans with architectural floor plans to find conflicts in the location of
the panel boards. Check for the same number and designation of electrical panels on the
electrical plans and riser diagram.
5. Check notes. If a note indicates to see sheet E-11 for additional details, check that the details
are on sheet E.11. Avoid duplicating the same notes in the drawings and specifications.
F. KITCHEN/DIETARY DRAWINGS
1. Verify that the equipment layout matches other discipline floor plans and that there are no
conflicts with columns. Compare kitchen/dietary plans with architectural, plumbing,
mechanical, and electrical plans to make sure the equipment layout is the same. Check that
the location of columns on structural plans does not interfere with the equipment
2. Verify that equipment is connected to utility systems. Check that water service lines, steam
lines, drain lines, gas lines, electrical services, and exhaust and make-up hoods, connect to
utility systems on electrical, plumbing, mechanical and civil plans.
3. Verify that kitchen equipment as shown on the drawings matches kitchen floor plans and
specifications. Check kitchen equipment item numbers, quantities, manufacturer names and
model numbers between the drawings and specifications.
4. Verify that floor depressions and floor troughs are coordinated with other disciplines. Check
architectural and structural plans to verify locations and depths of depressions at
coolers/freezers and locations and sizes of floor troughs. Check drawings and specifications
for freezer insulation requirements and the impact on the structure.
G. SPECIFICATIONS
1. Although more interdisciplinary problems are associated with drawings than with
specifications, there are some coordination issues that the consultant shall check in order to
minimize change orders.
2. Guide specifications indicate a large variety of materials and systems, which could be used
on any project. These guide specifications should be edited to remove all items that are not
specifically required for the particular project. This is also true for using specifications from a
previous project.
The following definitions of building areas shall be used by the Consultant to establish their cost
estimates and to identify the physical space and function of each area.
F. MECHANICAL AREA
1. Definition: The sum of all areas on all floors of a building designed to house mechanical
equipment, utility services, and shaft areas.
2. Basis for Measurement: Mechanical area is computed by physically measuring or scaling
measurements from the inside faces of surfaces that form the boundaries of the designated
areas. Exclude areas having less than six-foot, six-inch clear ceiling height unless the criteria
of a separate structure are met.
3. Description: Included should be mechanical areas such as central utility plants, boiler
rooms, mechanical and electrical equipment rooms. fuel rooms, meter and communications
closets, and each floor’s footprint of air ducts, pipe shafts, mechanical service shafts, service
chutes, and stacks.
4. Limitations: Deductions should not be made for necessary building columns and projections
unless they are larger than 2’ x 2’ in area. Areas designated as private toilets are not
included.
H. STRUCTURAL AREA
1. Definition: The sum of all areas on all floors of a building that cannot be occupied or put to
use because of structural building features.
2. Basis for Measurement: Precise computation by direct measurement is not possible under
these definitions. It is determined by calculating the difference between the measured gross
area and the measured net usable area.
Measured in terms of area.
Structural Area = Gross Area - Net Usable Area
3. Description: Examples of building features normally classified as structural areas include
exterior walls, fire walls, permanent partitions, unusable areas in attics or basements, or
comparable portions of a building with ceiling height restrictions, as well as unexcavated
basement
A. GENERAL
1. Historic Preservation work can apply to an entire project, large or small, including all trades
and engineering disciplines, or to any part of a project that includes preservation and
conservation components.
2. Historic Preservation is required at those sites, structures, interiors and works of art that are
officially designated landmarks by the New York City Landmarks Commission and those that
are listed in the National Register or State Register of Historic Places. In addition,
DDCM/CUCF generally applies similar historic preservation criteria to other sites, structures,
interiors and works of art that are of landmark quality, may be eligible for governmental
designation, or have historic, cultural, artistic and/or architectural features of merit and
significance; this may protect their future eligibility for historic status. All these projects, those
officially designated and those of landmark quality, shall hereafter be referred to as
Preservation Projects.
3. It is the Consultant’s Responsibility to determine the applicable regulatory agency
requirements for a specific Preservation Project and to comply with the requirements,
including preparing documentation and filing for and obtaining applicable approvals.
4. The United States Secretary of the Interior provides key resources—standards, guidelines,
and technical information—for developing Preservation Projects. The New York State
Historic Preservation Office and the New York City Landmarks Commission also offer
important resources.
5. The goals of a project (protection, stabilization, rehabilitation, restoration or reconstruction)
will determine the most pertinent design criteria, standards and guidelines. The Consultant
is responsible for delineating those that apply to a specific project.
B. CONSULTANT SERVICES
1. A Preservation Project requires that the Consultant provide a full range of preservation and
conservation services by qualified experts for every phase of the project. The Consultant is
therefore required to have on his/her team all the specialists necessary to carry out the scope
of the work, such as, historian, archaeologist, architectural conservator, art conservator,
materials specialist, historic systems engineers etc.
2. The services will be project-specific and are generally required for the entire duration of the
project, including all phases of design and construction. Some services which are normally
expected during a Preservation Project include:
a. Documentary, historic and field research sufficient to inform the scope and intent of the
project, and to verify conditions that are exposed during construction.
b. An assessment report of features that are significant with respect to preservation,
including an inventory and description of special elements, spaces, materials, systems,
details, furnishings, equipment etc.
c. An evaluation of existing conditions based on probes and tests that are necessary to
achieve accurate construction documents and a detailed cost estimate. The Consultant
is expected to identify and plan the probes and tests. Upon approval, tests and or probes
that require specialized equipment, scaffolding, laboratory conditions etc. may be
A. DESIGN PARAMETERS
1. The following design parameters must be established for a laboratory space:
a. Temperature and humidity, both indoor and outdoor
b. Air quality from both process and safety perspectives, including the need for air filtration
and special treatment (e.g., charcoal, HEPA, or other filtration of supply or exhaust
c. Equipment and process heat gains, both sensible and latent
d. Minimum ventilation rates
e. Equipment and process exhaust quantities
f. Exhaust and air intake locations
g. Style of the exhaust device, capture velocities, and usage factors
h. Need for standby equipment and emergency power
i. Alarm requirements.
j. Potential changes in the size and number of fume hoods
k. Anticipated increases in internal loads
l. Room pressurization requirements.
2. It is important to:
a. Review design parameters with the College safety officers and scientific staff
b. Determine limits that should not be exceeded
c. Establish the desirable operating conditions. For areas requiring variable temperature or
humidity, these parameters must be carefully reviewed with the users to establish a clear
understanding of expected operating conditions and system performance.
d. Determine and comply with all specific regulatory agency (DOB, FDNY, etc.)
requirements, such as fire rating of perimeter lab walls and doors
e. Submit diagrams indicating extent of boundary of rated walls and doors to
DDCM/CUCF/College for posting in the labs
B. LABORATORY VENTILATION
1. The total airflow rate for a laboratory is dictated by one of the following:
a. Total amount of exhaust from containment and exhaust devices
b. Cooling required to offset internal heat gains
c. Minimum ventilation rate requirements.
2. Fume hood exhaust requirements (including evaluation of alternate sash configurations shall
be determined in consultation with the safety officers. The HVAC engineer must determine
the expected heat gains from the research equipment after consulting with the research staff
(see the section on Internal Thermal Considerations). Minimum airflow rates are generally in
the range of 6 air changes per hour when the space is occupied; however, some spaces
(e.g., animal holding areas) may have minimum airflow rates established by specific
standards or by internal facility policies. For example, the National Institutes of Health (NIH
1999a, 1999b) recommend a minimum of 6 air changes per hour for occupied laboratories
but a minimum of 15 air changes per hour for animal housing treatment areas. The
maximum airflow rate for the laboratory should be reviewed to ensure that appropriate supply
air delivery methods are chosen such that supply airflows do not impede the performance of
the exhaust devices. Laboratory ventilation systems be arranged for either constant-volume
or variable-volume airflow. The specific type should be selected with the research staff, be
C. EXHAUST SYSTEMS
1. Laboratory exhaust systems remove air from containment devices and from the laboratory
itself. The exhaust system must be controlled and coordinated with the supply air system to
maintain correct pressurization. Additional information on the control of exhaust systems is
included in the section on Control. Design parameters must be well defined for selection,
sizing, and layout of the exhaust air system. Installation and setup should be verified as part
of the commissioning process. See the sections on Design Parameters and Commissioning.
Laboratory exhaust systems should be designed for high reliability and ease of maintenance.
This can be achieved by providing multiple exhaust fans that are not necessarily redundant or
by sectionalizing equipment so that maintenance work may be performed on an individual
exhaust fan while the system is operating. Another option is to use predictive maintenance
procedures to detect problems prior to failure and to allow for scheduled shutdowns for
maintenance. To the extent possible, components of exhaust systems should allow
maintenance without exposing maintenance personnel to the exhaust airstream. Access to
filters and the need for bag-in, bag-out filter housings should be considered during the design
process. Depending on the effluent of the processes being conducted, the exhaust airstream
may require filtration, scrubbing, or other emission control to remove environmentally
D. ANIMAL FACILITIES
1. Temperature and Humidity: Due to the nature of research programs, air-conditioning
design temperature and humidity control points may be required. Research animal facilities
require more precise environmental control than farm animal or production facilities because
variations affect the experimental results. A totally flexible system permits control of the
temperature of individual rooms to within ±2°F for any set point in a range of 64 to 85°F. This
flexibility requires significant capital expenditure, which can be mitigated by designing the
facility for selected species and their specific requirements. Table 1 lists dry-bulb
temperatures recommended for several common species. In the case of animals in confined
spaces, the range of daily temperature fluctuations should be kept to a minimum. Relative
humidity should also be controlled. ASHRAE Standard 62 recommends that the relative
humidity in habitable spaces be maintained between 30 and 60% to minimize growth of
pathogenic organisms.
2. Ventilation: A guideline of 10 to 15 outside air changes per hour (ach) has been used for
secondary enclosures for many years. Although it is effective in many settings, the guideline
does not consider the range of possible heat loads; the species, size, and number of animals
involved; the type of bedding or frequency of cage changing; the room dimensions; or the
efficiency of air distribution from the secondary to the primary enclosure. In some situations,
such a flow rate might over-ventilate a secondary enclosure that contains few animals and
Animal Temperature, °F
Rabbit 61 to 72
Cat, dog 64 to 84
Note: These ranges permit scientific personnel who will use the facility to select optimum conditions
(set points). The ranges do not represent acceptable fluctuation ranges.
7. Caging Systems: Animal facilities use a number of different caging systems that can
significantly affect the environment within the cage or the total heat load in the room.
a. The purpose of the caging systems is to:
Protect the health and wellbeing of animals
Protect support staff from antigens released or shed by the animals
Minimize exposure of animals to pheromones released by other animals in the space
b. To provide the appropriate design, the HVAC engineer must be aware of the type of
caging system to be used. Some common caging systems include the following:
Cage boxes made of sheet metal, plastic, or wire mesh, with the space inside the
cage open to the room so that the room’s macro environment is essentially identical
to the cage’s microenvironment.
Cage boxes made primarily of plastic, with the top shielded from the room by a filter
material to provide some level of isolation from the room. The filter is usually not
sealed to the cage, so some open space between the room and the interior of the
cage remains. Exchange of air, vapors, particulates, and gases between the room
and the cage interior does occur, but the rate of exchange is reduced by the filter. The
microenvironment of the interior of the cage is usually different from that of the room.
Plastic and wire cages that are part of a cage rack assembly, which provides varying
degrees of isolation from the room. These usually provide filtered (generally HEPA-
filtered) air directly to each individual or shelf of cage boxes. In some cases, both a
fan-powered supply and an exhaust unit are used. In other cases, cage units are
connected to the facility exhaust system to provide airflow. Facilities with this kind of
caging system must be designed to accommodate the heat gain in the space if the
exhaust is released in the room. Some heat gain may be excluded if the caging
assembly is connected directly to the facility exhaust system. When the facility is used
to provide the exhaust by direct connection to the caging assembly, the design must
include provisions to control the airflow to ensure that the overall proper airflow and
relative static pressure of the room and each cage rack assembly is maintained,
especially when caging and rack connections may be changed over time. The
temperature and specific humidity within each cage will be higher than the ambient
conditions of the room.
8. Ancillary Spaces for Animal Laboratories: In addition to animal holding rooms, a facility
intended to provide for an animal colony generally requires other areas, such as:
F. CONTROL
Laboratory controls must regulate temperature and humidity, control and monitor laboratory
safety devices that protect personnel, and control and monitor secondary safety barriers used to
protect the environment outside the laboratory from laboratory operations (West 1978).
Reliability, redundancy, accuracy, and monitoring are important factors in controlling the lab
environment. Many laboratories require precise control of temperature, humidity, and airflows.
Components of the control system must provide the necessary accuracy and corrosion
G. COMMISSIONING
In addition to HVAC systems, electrical systems and chemical handling and storage areas must
be commissioned. Training of technicians, scientists, and maintenance personnel is a critical
aspect of the commissioning process. Users must understand the systems and their operation. It
should be determined early in the design process whether any laboratory systems must comply
with Food and Drug Administration (FDA) regulations because these systems have additional
design and commissioning requirements. Commissioning process is outlined in ASHRAE
Guideline 1. Laboratory commissioning is more demanding than that described in ASHRAE
Guideline 1 because areas must be considered that are not associated with the normal office
complex. Requirements for commissioning should be clearly understood by all participants,
including the contractors and the owner’s personnel. Roles and responsibilities should be
defined, and responsibilities for documenting results should be established. Laboratory
commissioning starts with the intended use of the laboratory and should include development of
a commissioning plan, as outlined in ASHRAE Guideline 1. The validation of individual
components should come first; after individual components are successfully validated, the entire
system should be evaluated.
This requires verification and documentation that the design meets applicable codes and
standards and that it has been constructed in accordance with the design intent. Before general
commissioning begins, the following data must be obtained:
1. Complete set of the laboratory utility drawings
2. Definition of the use of the laboratory and an understanding of the work being performed
3. Equipment requirements
4. All test results
5. Understanding of the intent of the system operation - For HVAC system commissioning, the
following should be verified and documented
6. Fume hood design face velocities have been met.
7. Manufacturer’s requirements for airflow for biological safety cabinets and laminar flow clean
benches have been met.
8. Exhaust system configuration, damper locations, and performance characteristics, including
any required emission equipment, are correct.
9. Control system operates as specified. Controls include fume hood alarm; miscellaneous
safety alarm systems; fume hood and other exhaust airflow regulation; laboratory
pressurization control system; laboratory temperature control system; and main ventilation
unit controls for supply, exhaust, and heat recovery systems. Control system performance
verification should include speed of response, accuracy, repeatability, turndown, and stability.
10. Desired laboratory pressurization relationships are maintained throughout the laboratory,
including entrances, adjoining areas, air locks, interior rooms, and hallways. Balancing
terminal devices within 10% of design requirements will not provide adequate results.
Additionally, internal pressure relationships can be affected by airflow around the building
itself. See Chapter 16 of the 2005 ASHRAE Handbook—Fundamentals for more information.
H. ECONOMICS
1. In laboratories, HVAC systems make up a significant part (often 30 to 50%) of the overall
construction budget. The design criteria and system requirements must be reconciled with
the budget allotment for HVAC early in the planning stages and continually throughout the
design stages to ensure that the project remains within budget. Every project must be
evaluated on both its technical features and its economics. The following common economic
terms are defined as follows:
2. Initial cost: Costs to design, install, and test an HVAC system such that it is fully operational
and suitable for use.
3. Operating cost: Cost to operate a system (including energy, maintenance, and component
replacements) such that the total system can reach the end of its normal useful life.
4. Life-cycle cost: Cost related to the total cost over the life of the HVAC system, including
initial capital cost, considering the time value of money.
5. Many technical considerations and the great variety of equipment available influence the
design of HVAC systems. Factors affecting design must be well defined to ensure appropriate
comparisons between various systems and to determine the impact on either first or
operating costs.
A. GENERAL
1. Fire alarm system design shall be in accordance with the latest rules and regulations of the
New York City Buildings Department (NYC DOB), the New York City Fire Department
(FDNY) and the Americans with Disabilities Act (ADA).
2. The design of fire alarm systems shall be closely coordinated with FDNY in order to obtain
approval for the applicable fire alarm classification of the building.
3. The Consultant must obtain the approval from FDNY and NYC DOB prior to project bidding.
4. If the existing building does not have a certificate of occupancy, the consultant must prepare
a narrative to describe the occupancy/use of the building, the classification of the existing fire
alarm system, type of fire suppression system, etc. in lieu of the certificate of occupancy.
5. If the building has an existing fire pump, the consultant must evaluate the condition of the
pump and show the pump on the fire alarm drawings, file the pump as part of the fire alarm
filing application with DOB and FDNY and obtain approvals.
A. OVERVIEW
1. DDCM/CUCF requires the consultant to comply completely with the latest New York City
Energy Conservation Code (NYCECC).
2. It is the Consultant’s responsibility to determine the NYCECC requirements, compliance
procedures and the correct forms to be filed with the NYC Department of Buildings.
3. The Consultant will be proactive in initiating the required energy analyses and developing
energy-reduction strategies early in the design process.
4. DDCM/CUCF requires compliance with New York City Local Law 86 energy reductions for its
community colleges and Executive Order 88 for its senior colleges.
A. Shop drawings, after having been reviewed by the Consultant, shall be stamped and signed by
the Consultant. The stamp shall have the following approval designations and text listed below.
APPROVED
DISAPPROVED
APPROVED AS NOTED
REVISE AND SUBMIT
B. The above approval shall not relieve the Contractor of responsibility for any deviation from the
requirements of the Contract. The Contractor shall be responsible for the accuracy of the Shop
Drawings and samples and for the conformity of Shop Drawings and samples with the Contract
unless the Contractor has notified the Consultant of the deviation in writing at the time of
submission and has received the Consultant’s written approval of the specified deviations. The
above approval shall not relieve the Contractor of responsibility for errors or omissions in the
Shop Drawings or samples.
C. The above approval is given subject to any corrections noted on the drawings, and subject to the
condition that the Contractor is not relieved of the responsibility for correct measurements,
dimensions, quantities, material, proper connection or requisite fitting of parts either to adjacent
work or to parts of the same work, or for fully complying with the requirements of the contract
drawings and specifications.
D. Drawings have been checked for conformances with over-all design requirements and in
particular, where applicable, as to structural strength of permanent structure and electrical current
characteristics of electrically operated equipment.
E. All measurements and conditions shall be checked and verified by the Contractor at the site.
F. Corrections shown on this drawing shall not be deemed an order for extra work.
G. No change shall be made on any approved drawing without the written authorization of
DDCM/CUCF.
D. QUALITY CONTROL
1. High Standards: Special Inspection firms must be responsible for inspections of a high
standard by virtue of their in depth knowledge of the subject.
2. Supervision: Special inspection firms shall be responsible for supervising all special inspectors
and testing technicians. Each firm shall assign only trained, experienced, City of New York approved,
special inspector and/or testing technician to projects requiring special inspection and/or testing.
The firm is responsible for all actions of their approved special inspectors and testing technicians.
3. Technical Services Requirement: The NYC Construction Codes require that inspection and
testing of piling, drilled piers and caissons, grading, excavation, and filling shall be inspected by a
NYC professional Engineer
4. Negligence: If CUCF determines that an approved special inspector is negligent in the performance
of his assigned duties through a failure to be present to perform necessary inspections, or failure to
provide acceptable daily reports, or is engaged in a conflict of interest, or fails to conform to the
requirements of the technical guidelines, than that inspector shall be subject to removal from the
approved DDCM/CUCF list for the particular inspection item involved in the negligent act until the
negligent act is resolved. All negligent items must be cleared up and resolved within three working
days. A second negligent act would require the firm inspector's supervisor or Quality Control Manager
to present a training plan to cover the areas of deficiency. A third negligent act within a quarter will
result in the removal or suspension of the special inspector from the approved list for the item or items
involved. Failure of the firm to correct the deficiency causing the removal of the firm special inspector
will result in disciplinary action and/or suspension from the NYC DOB approved list.
5. Inspector Independence: Firm special inspectors cannot be in the employ of the contractor,
subcontractor or material supplier.
E. FINAL REPORTS
1. Submittal to DDCM/CUCF: The special inspection firm shall initially submit final signed reports
to DDCM/CUCF stating whether all work requiring special inspection was inspected, reported and
found to be in substantial compliance with the approved plans, specifications and the NYC DOB’s
Rules and Regulations.
2. Non-compliance items: The final reports shall not be submitted to the NYC DOB until all non-
compliances have been cleared or have been identified in the final report as being unresolved and
accepted by DDCM/CUCF.
3. Certification: ANYS-licensed professional Engineer or Architect, working for the special inspection
firm in the appropriate discipline, must stamp, sign and date each final report. Final report and report
packages shall include all inspection, testing and engineer signed reports. The final report certifies that
all inspections, engineering and testing tasks required by the project were completed as required or
exceptions taken and documented as being acceptable to the NYC DOB.
4. DOB Forms. The Special Inspection Consultant is responsible for using the latest DOB forms in
filing reports.
5. Submittal of Final Report to DOB: Special inspectors or inspection agencies shall submit a
final signed report to the NYC Department of Buildings stating that all items requiring special
inspection and testing were fulfilled and reported and, to the best of their knowledge in
A. General: To assist the Consultant, DDCM identified some, not all, design preferences and
requirements. Highlighted below are interior finishes preferences, exterior design preferences,
design approach considerations, lighting concerns, specific items for various types of spaces
(classrooms, lecture halls/auditoria, offices, lounge/study areas, restrooms, and labs) and
requirements for HVAC specifications, UVC lighting/HEPA filters and elevator/escalator
manufacturer qualifications. DDCM will periodically supplement and update these listings.
1. Cool roofs
2. Pervious paving
3. No exterior horizontal surfaces that lend themselves to pigeon roosting
D. Design Approach:
1. Main entrance at grade level or only slightly above grade level; avoid below grade main
entrance
2. Stairs: Encourage active use of stairs
a. Stairs: Visible placement and design of stairs in locations to encourage active use – near
entrances and integral to circulation; consider use of fire stairs for travel between floors
and include attractive design elements.
b. Elevators: Locate elevators to discourage their use for travel that can easily occur with
stairs.
c. Escalators: Do not include or limit including escalators.
3. Daylighting Enhancement: Optimize daylight and views in regularly occupied spaces and
maximize daylight into corridors wherever possible.
4. Interior soffits: Ensure that soffits are accessible for cleaning or design soffits to limit dust
accumulation.
5. Accessible entrances: Preference is for manual rather than mechanical access.
6. Electromagnetic Shielding: Evaluate electromagnetic shielding requirements when there is
high tension service and use results in determining layout of program spaces.
E. Lighting:
1. Maximize the use of LED fixtures.
2. Limit the number of different types of lamps in a project.
F. Classrooms:
G. Lecture Halls/Auditoria:
1. Perform a detailed analysis, with calculations, to ensure compliance with all regulatory
agency and code requirements, including but not limited to:
a. Lighting (i.e., exit, emergency, footcandles along all egress paths, etc.)
b. Egress, doors, and travel distances
c. ADA (i.e., dispersed seating, access to raised platforms and pools, etc.)
d. Safe areas
e. Ventilation and life safety systems
2. File comprehensive PA Documents (including seating plan options) with NYC Department of
Buildings to obtain a Public Assembly Certificate of Operation.
3. Filing documents with DOB shall reflect compliance with regulations from other agencies
(Fire Department, Department of Health, etc.) For example, pool capacity calculations from
the DOH may be more stringent that those in the DOB Construction Codes.
I. Offices:
1. Provide a minimum of two duplex or one quad outlet at each desk, in addition to any other
outlets in the room.
J. Lounges/Study Areas:
K. Restrooms:
L. Lab Standards:
1. Casework:
3. Equipment:
a. Do not anchor sensitive equipment (NMRs) to bedrock; isolation slabs are preferred.
b. Always assume equipment will be operated at maximum resolution/tolerances and
environment designed to allow for operation at least 95% of the time.
c. Provide continuous power for all critical equipment required for research continuity.
1. For general lighting, specify LED flat panel lighting fixtures with dimming capability and provide
occupancy sensors.
1. Specify pressure-independent valves for heating and cooling systems including hot water and
chilled water coils on all air handling units. The valves shall be pressure- independent,
modulating 2-way control valves.
2. Specify stainless steel cooling towers with sweeper system.
1. For all HVAC projects that include the design and installation of air handling unit systems,
the consultant must include the installation of a UL Certified UVC light system and HEPA
filter as an integral part of the air handling unit systems where feasible. This includes all
the active HVAC projects that are in design or construction.
2. In addition to the UVC light system and HEPA filter, the consultant may recommend other
effective industry approved indoor air quality enhancement systems for CUNY review,
consideration and approval.
1. In reference to projects that are involved with the installation/modernization of elevators and
escalators, the following clause must be included in the design documents as part of the
qualification requirements for the elevator/escalator manufacturer:
2. “Among other requirements for approving the proposed elevator/escalator manufacturer by the
contractor, the contractor must provide a certified statement from the manufacturer that their
elevator/escalator can be fully serviced and maintained by at least three local qualified service
companies. The approval of the proposed service companies will be at the owner and/or the
consultant’s discretion. Third party components are allowed only if they are approved by the
owner and/or the consultant. If the proposed elevators/escalators have proprietary components,
they must be made available to the recommended service companies by the elevator/escalator
manufacturer and their distributers including the method of operation, diagnostic and
maintenance procedures.”
B. DESIGN PARAMETERS
1. Refer to the sample lighting form at the end of the appendix.
2. The following design parameters must be established for each major interior space:
a. Activity within the space
b. Age of users of the space; identified within categories of classification as
required by the lighting design reference standards utilized for the project type;
specifically, the age of the human eye provides important information relative to
the quality of the illumination required in a space.
c. Usage profile for the space, including hours of use and percentage of usage
time allocated to each user age group
d. Baseline ambient illuminance values (without electric light)
e. Furniture and Equipment layouts within the space
f. Absorption values for architectural surfaces and finishes
g. Sequence of control and operation
h. Time of Use control
i. Horizontal maintained Illuminance values
j. Vertical maintained illuminance values for primary orientation
k. Required standards that must be referenced for compliance.
3. DDCM/CUCF Criteria:
a. Lighting design must be performed relative to and accommodating of ambient
daylight conditions in the space.
b. With the exception of integrated lighting technologies, lighting system components in
new spaces shall not be utilized for non-lighting tasks. (For example, air handling
luminaires must not be utilized; however, luminaires with integrated sensor
technologies for daylight accommodation and vacancy sensing that can be integrated
with BACnet building controls systems for the purpose of campus operational
analytics may be utilized.)
c. Localized control systems must be expandable to allow future remote control
from a centralized campus control system.
d. Energy considerations that are designed to exceed (i.e., be better than) NYC/NYS
code requirements shall be made in the context of lowering waste stream and
maintaining – or improving – a quality educational environment.
e. The spectrum and color rendering ability of sources shall meet the requirements of
the educational environment in which they are employed. Spectral Power Distribution
(SPD) curves for each source must be provided during submittals for evaluation.
f. Minimum acceptable CRI for Interior Spaces must be 80.
E. LIGHTING CONTROL
1. Type and amount of control must meet minimum requirements of DDCM/CUCF and/or
the authority or regulatory agencies having jurisdiction – whichever is most stringent.
2. Unless compliance standards indicate otherwise (for example, NCAA), if daylight is
available in the space, lighting shall be reactive (that is, responsive) to amount of
daylight in the space.
3. Additional control requirements for specific spaces include:
a. Classrooms and Small Lecture Rooms shall have instructor adjustable controls.
Minimum light level adjustments shall include dimming and on-off control of luminaires
for projection, lecture, and general lighting scenes. General lighting must provide
control to create a minimum of two illumination levels; one to accommodate young
adults and the second to accommodate advanced adult visual acuity. In a standard
classroom, one (1) control location, near the main entrance and in proximity to the
teaching area, may be provided. For larger area rooms, two (2) control locations may
be provided; one (1) at primary room entrance and one (1) at the primary teaching
area.
b. Lecture Theaters shall have instructor and A/V professional adjustable controls
(found in a control room and utilized by trained individuals). Control locations shall be
at front of theatre (podium) and at control room. Minimum light level adjustments
shall include dimming and on-off control of luminaires for projection,
lecture/presentation, general, and egress lighting scenes. General lighting must
provide control to create a minimum of two illumination levels; one to accommodate
young adults and the second to accommodate advanced adult visual acuity.
c. Performance Spaces, Theatres, and Concert Halls shall have adjustable controls
that are managed and operated by an A/V professional. Lighting control shall be
separated into house luminaires and theatrical luminaires.
d. Laboratories General lighting must include control to create a minimum of two active
work zones in the space to allow localized lighting such that fewer work benches can
be utilized and lit.
e. Libraries and Media Centers shall have local control for task lighting.
f. Computer and Technology Labs shall include dimming and on-off control of
luminaires near technology equipment and screens. Task lighting on work surfaces
shall be locally controlled.
g. Physical Education and Gymnasium Spaces must have control that will provide
cucf/ddcm/ksx Page 110 of 143 October 5, 2020
lower illumination levels for general education and higher illumination levels for
competitive sports and televised broadcast. Controls must be accessible, only, to
authorized personnel including, but not limited to, coaches and facility staff
members.
h. Offices shall include local control of task lighting.
i. Lobbies, Atriums, Corridors, and Circulation Spaces shall include dimming and scene
control as appropriate for use. For example, gallery wall installations in these areas
will need specialized control zoning considerations.
j. Mechanical and Maintenance Spaces shall include occupancy control where
feasible and safe to do so.
2. The Lighting Consultant shall provide the information delineated in the form to DDCM.
Project: [Name]
(Number)
Design Team Assumptions (Include relevant given information about the space that impacts lighting decisions)
GENERAL
C. Consultants may use these specifications as a basis, refining and adding any project-specific
criteria as required.
PART 1 - GENERAL
1.1 SUMMARY
B. There are a variety of space types for consideration in CUNY campuses and
facilities. Specific philosophy for lighting control for these areas can be found in
Appendix M of the DDCM/CUCF Consultant Design Guidelines. In general, these
spaces include – but are not limited to – the following:
1. Classrooms and Small Lecture Rooms
2. Lecture Theaters
3. Performance Spaces, Theaters, and Concert Halls
4. Laboratories
5. Libraries and Media Centers
6. Computer and Technology Labs
7. Physical Education and Gymnasium Spaces
8. Offices
9. Lobbies, Atriums, Corridors, and Circulation Spaces
10. Mechanical and Maintenance Spaces
C. Section Includes:
1. Daylight Controls
2. Dimming Controls
3. Smart Classroom Controls
4. Occupancy/Vacancy Controls
1.3 DEFINITIONS
1.6 SUBMITTALS
B. Shop Drawings: For the following interior lighting control equipment, components,
and accessories. Include plans, elevations, sections, details, and attachments to
other work as required to accurately depict intent.
1. Custom enclosures and cabinets.
2. Interconnection diagrams showing field installed wiring.
3. Riser Diagrams for power, signal, and control wiring.
C. Components that make-up the interior lighting control system (devices, modules,
panels, interfaces, software, and wired or wireless connectivity) must be
guaranteed to perform as a system.
PART 2 - PRODUCTS
2.1 GENERAL
B. Electronic, solid state device. Wired or wireless. Open Loop control that provides
linear response to sensed light level.
1. Sensitivity 0 – 107,000 Lux
2. Control of up to 10 devices.
3. 10- year battery life guarantee.
4. RoHS compliant.
5. Operating Temperature 32 degrees to 104 degrees F.
6. Non-Volatile Memory
2.7 CONNECTIVITY
2.8 MODULES
A. Modules for dimming and system control must be coordinated with the loads to
which they are assigned.
cucf/ddcm/ksx Page 118 of 143 October 5, 2020
B. Provide manufacturer confirmation that control module has been tested with
system, source, and luminaire to which it is assigned.
C. User Interface Terminals and Devices (Insert project specific Requirements and
Manufacturer(s) here.)
A. All software for the programming and operation of control systems, both open
source and proprietary, must be provided to DDCM/CUCF with licenses for
unabated use.
PART 3 - EXECUTION
3.1 GENERAL
A. Coordinate device layout and installation on ceilings and walls with other
construction trades.
B. Prioritize device locations based on transmission limitations of each device and
system.
A. Ensure modules are properly loaded for source type to which they are connected
and that minimum loading requirements of the module are met.
B. Provide manufacturer documentation indicating that module has been tested and
operation confirmed for system, headend equipment, sources, and luminaires to
which it is connected.
A. Install control program and provide initial scene set-up and sequencing per
operation directives indicated in the contract documents.
B. During commissioning, demonstrate pre-set control scenes and modify as directed
by lighting designer and Owner.
3.8 COMMISSIONING
B. Perform operational testing after device installation and after electrical circuitry has
been energized. Confirm proper unit operation.
C. Test and adjust controls. Replace damaged and malfunctioning controls and
equipment.
D. When requested within 12 months from date of Substantial Completion, provide on-
site assistance in adjusting of sensors to meet actual occupancy conditions.
Provide up to two after-hour commissioning visits after substantial completion.
E. Train Owner’s maintenance personnel to adjust, operate, and maintain lighting
control devices.
PART 1 - GENERAL
1.1 SUMMARY
A. This Section identifies the lighting philosophy of The City University of New York
(CUNY) and outlines the intent of the specification(s) relative to emerging lighting
technologies and the implementation of the same throughout the CUNY system of
facilities.
B. This Section identifies the basis of design for interior lighting and controls and must
be utilized as the reference standard for project specific modifications to
specification sections related to interior lighting.
C. Suggestions for alternatives, substitutions, and value engineering must retain the
original design balance of energy and lighting considerations.
1.4 DEFINITIONS
1.7 SUBMITTALS
A. Product Data
1. For each specified luminaire, candlepower distribution, photometric information, and
manufacturer cut sheet indicating:
a. Total Lumens
b. Luminaire Efficiency
c. Luminaire Lumens per Watt
d. Color Temperature of Source
e. CRI of Source
f. Spectral Power Distribution Curve of Source
g. For LED sources, R1 through R14 values for CIE defined colors
C. Luminaires of the same type, purchased under the same contract, must be from the
same manufacturer.
PART 2 - PRODUCTS
2.1 GENERAL
A. Product manufacturers must have a minimum of ten (10) years of experience in the
manufacturer, testing, and listing of luminaires.
D. Minimum acceptable Manufacturer’s Product Warranty must be five (5) years for all
lighting system components.
PART 3 - EXECUTION
3.1 COMMISSIONING
B. Provide a minimum of two (2) after-hour commissioning sessions for a total of eight
(8) contact hours.
A. Provide luminaire and source warranty and manufacturer and distributor contact
information for each luminaire and source type provided under this contract.
PART 1 - GENERAL
1.1 SUMMARY
B. There are a variety of space types for consideration in CUNY campuses and
facilities. Specific philosophy for interior lighting for these areas can be found in
Appendix M of the DDCM/CUCF Consultant Design Guidelines. In general, these
spaces include – but are not limited to – the following:
1. Classrooms and Small Lecture Rooms
2. Lecture Theaters
3. Performance Spaces, Theaters, and Concert Halls
4. Laboratories
5. Libraries and Media Centers
6. Computer and Technology Labs
7. Physical Education and Gymnasium Spaces
8. Offices
9. Lobbies, Atriums, Corridors, and Circulation Spaces
10. Mechanical and Maintenance Spaces
D. This Section must be read in conjunction with other Division 26 sections relative to
Interior Lighting.
1.3 DEFINITIONS
1.6 SUBMITTALS
A. Product Data: For interior lighting sources, luminaires, and components, arranged
in order of fixture designations. Include candlepower distribution, photometric
information, and manufacturer cut sheet indicating the following:
1. Total Lumens
2. Luminaire Efficiency
3. Luminaire Lumens per Watt
4. Color Temperature of Source
5. CRI of Source
6. Spectral Power Distribution Curve of Source
7. For LED sources, R1 through R14 values for CIE defined colors
8. For LED sources, manufacturer compliance for luminaire emergency performance
expectations.
9. For replacement lamps, compliant with luminaire manufacturer.
B. Shop Drawings: For the following interior lighting sources, luminaires, and
components. Include plans, elevations, sections, details, and attachments to other
work as required to accurately depict intent.
1. Custom luminaires.
2. Custom attachments, hangers, and assemblies.
D. Qualification Data: For manufacturer and testing agency. Manufacturer must have
ten (10) years of demonstrated experience in the research, design, and/or
construction of associated interior lighting emerging technology(ies). Testing
agency must be independent from manufacturer and must perform certified test
reports for the products submitted. Calculated test reports, reports generated by
numerical methods alone, and software-derived estimates of luminaire performance
shall not be accepted.
D. All products supplied under this contract shall be Energy Star Qualified.
2.1 GENERAL
A. LED
1. Remote phosphor technology to eliminate pixilation. Alternatively, the luminaire must
come supplied with a softening lens and associated accessory holder.
2. Light engine - consisting of LED array, driver, and control – must have the ability to
maintain lumen output and uniform beam spread over the life of the installation
regardless of (despite the) increases in technology efficiencies.
3. Must be tested in accordance with IES LM 79 and LM 80.
4. Luminaire input watts must be identified. LED wattage will not be acceptable in the
absence of luminaire input wattage.
5. Color binning must be within maximum bin size per ANSI C78 377A.
B. CMH
1. Lamp to lamp color consistency over life, for same lamp types by same
manufacturer.
2. Color stability over life of lamp within +/- 200K.
3. Color binning must be within maximum bin size per ANSI C78 377A.
4. Universal mounting position.
A. Submitted products and manufacturers must have a minimum of three (3) CCTs
available in their standard available product line.
1. 3000 K, 3500 K, and 4000 K nominal
B. For exterior products, comply with recommendations from relevant agencies.
A. R1 through R14 values must be provided for each lamp type on this contract.
PART 3 - EXECUTION
3.1 GENERAL
PART 1 - GENERAL
A. The Contract Documents, including but not limited to the Drawings and individual
Specification Sections and the Commissioning Plan, apply to this Section.
C. References:
1. Illuminating Engineering Society: IES DG-29-11 “The Commissioning Process
Applied to Lighting and Control Systems”
2. Dormitory Authority State of New York: Building Commissioning Guidelines – 2013
3. ASHRAE Guideline 0-2005: The Commissioning Process
4. ASHRAE Guideline 1.1-2007: HVAC & R Technical Requirements for the
Commissioning Process.
1.2 SUMMARY
1.3 DEFINITIONS
1. Contract Documents: A collection of documents that record concepts, calculations,
decisions, and product selections to meet DDCM/CUCF requirements and to satisfy
applicable regulatory requirements, standards, and guidelines. The documents
include, but may not be limited to: drawings, specifications, sketches, instructions,
calculations, and similar items that support the design process.
2. Commissioning (Cx): A quality assurance process that documents specified
systems and components are provided and tested to meet the Owner’s needs and
the design intent in accordance with the Contract Documents.
3. Commissioning Proposal: A document that outlines the organization, schedule,
allocation of resources, and documentation requirements of the commissioning
process.
4. Commissioning Agent (CA): The individual (or company) with expertise related to
the systems identified for commissioning, engaged by the contractor to perform the
commissioning activities identified in the contract documents. The CA is
independent of the CxA.
5. Commissioning Authority (CxA): The Professional, appointed by the Owner, to
direct and coordinate the commissioning process.
6. Commissioning Plan (Cx Plan): A document, prepared by the Commissioning
Authority, defining the commissioning process including schedules, responsibilities,
documentation requirements, and functional performance test requirements.
cucf/ddcm/ksx Page 130 of 143 October 5, 2020
7. Functional Initiation Agent (FIA): The individual (or company) engaged to perform
initial system setup, including but not limited to: aiming, dimming, establishing
scenes of control, and establishing initial dimmed scene settings.
8. Commissioning Team: Individuals assigned by the Contractor, the CxA, and the
Owner to implement the commissioning process as identified in the contract
documents and the Commissioning Plan.
PART 3 - EXECUTION
A. Following the work of the FIA, each lighting system component shall be commissioned to
demonstrate design performance criteria are met. Commissioning of lighting systems will
include both daytime and nighttime work.
3.2 SUBMITTALS
A. Testing
1. Procedure for testing of each sensor and control type.
2. Final test report documenting results of all testing procedures for each sensor and
control type.
3. Final report documenting three-month luminaire inspection.
4. Final reports shall document final condition after all deficiencies have been cleared.
3.3 PRE-COMMISSIONING
B. Testing of Controls
1. Test and adjust controls.
2. Replace damaged and malfunctioning controls and equipment.
D. Verification
1. The FIA will be verifying all applicable commissioning attributes (e.g. illumination
levels, control scene setting, daylight accommodation, occupancy/vacancy settings)
for a minimum of 25% of the space included in the scope of work. No fewer than
one (1) of each space type will be verified for each building.
2. If, upon verification of 25% of the space, deficiencies are discovered, a larger
sample size will be commissioned to determine if the deficiencies are localized or
systemic.
3.4 COMMISSIONING
A. CxA
1. Provide commissioning plan.
2. Convene commissioning meetings.
3. Provide project-specific functional procedures and checklists.
4. Prepare and Maintain an Issues Log.
5. Verify execution of the commissioning process activities by random sample of
spaces for compliance. Non-Compliances will be recorded on the Issues Log or
Punch List. Verification will include, but may not be limited to:
a. Equipment submittals
b. Training
c. O&M data
d. Tests and Test Reports
6. Compile commissioning documentation, inspection reports, and certificates into a
systems manual.
B. CA
1. Perform commissioning activities as outlined in the commissioning plan.
2. Attend commissioning meetings.
3. Submit completed functional test reports to the CxA.
A. Controls
1. Luminaires and rooms with sensors and timer controls will be tested immediately
after the space is fully occupied.
2. Approximately three (3) months after Substantial Completion, and prior to Final
Completion, confirm proper operation of sensors and timer controls.
3. When requested, but within 12-months from date of Substantial Completion,
provide on-site assistance in adjusting of sensors to meet actual occupancy
conditions. Provide up to two (2) after-hour commissioning visits after substantial
completion for these adjustments. A minimum of one (1) after-hour visit for on-site
assistance in adjusting must be performed.
A. DESIGN PHASE
1. The design consultant shall retain a qualified sub-consultant with expertise in the design of
HVAC water treatment systems to provide all required design documents including
drawings, specifications, testing procedures, training requirements, etc. for the following
HVAC systems:
a. Chilled water
b. Hot water
c. Reclaim water
d. Glycol water
e. Cooling towers/Condenser water
f. Steam boiler water
g. Steam condensate
2. For each of the above noted systems, the water treatment design documents must include
floor plan drawings, schematic drawings, flow diagrams, specifications, details, required
water treatment program and specific testing procedure. The floor plan schematic drawing
and the flow diagram for each system must be comprehensive to show all of the HVAC
system equipment, water treatment equipment, piping, controllers, etc.
3. The design documents must include the complete, specific procedure for cleaning and
flushing of the new equipment, new chilled water, new condenser water, new hot water,
new steam, new condensate, and new glycol piping systems. The procedure for
cleaning and sanitization of the new cooling towers must also be included. The
sanitization of the cooling towers must be in accordance with the latest requirements of
NYC Local Law 77 to be complied with during the sanitization of the cooling towers.
4. The sub-consultant must prepare a separate set of schematic equipment and piping flow
diagrams to show all the required isolation valves, temporary pump(s), bypass piping,
injection ports and drainage connections for the purpose of cleaning and flushing of the
condenser and chilled water systems. The flow diagram must be reviewed and approved
by DDCM. Isolation valves must be provided to isolate the new chilled water, hot water,
condenser water, steam, and condensate piping systems from the existing building
distribution systems.
5. Electrical devices, motors, wiring and conduit in accordance with the applicable sections of
the electrical specifications must be provided.
6. The design documents must include an initial treatment program for all new equipment and
piping systems to be implemented during the construction phase on a complete system fluid
analysis prior to the equipment installation.
7. The final design documents must be reviewed and approved by DDCM/CUCF’s water
treatment consultant.
8. The quantity of all required chemicals for each system for all water treatment to be
implemented during construction must be included in the contract specifications.
9. Once the water treatment system design is completed by the sub-consultant and reviewed
and approved by DDCM/CUCF’s independent water treatment consultant, the design
B. CONSTRUCTION PHASE
1. During the construction phase, for each system, once the isolation valves are opened to
test, operate, and connect the new equipment to the existing building distribution piping
system, the water treatment services will be turned over to the college. From this point
forward, the college must utilize and pay their own vendor to provide water treatment
services for the entire system under the supervision of DDCM/CUCF’s independent
consultant.
2. The cleaning/flushing of the existing piping distribution systems is the responsibility of the
college and must be scheduled and performed prior to connecting the new equipment and
piping to the existing distribution systems. Once the installation of the isolation valve is
completed, the CM/contractor must immediately inform the college in writing to schedule
the cleaning/flushing of the existing piping distribution systems. The college must be given
at least a minimum of 60 days to schedule and perform the flushing and cleaning of the
existing piping systems.
3. The contractor must provide shop drawings in accordance with the contract specifications.
The shop drawings must show the exact dimensions and location of the water treatment
equipment, devices, controllers, piping, conduits such as chemical tanks, pumps, control
panels, etc. The shop drawings must be reviewed and approved by the sub-consultant
and DDCM/CUCF’s independent water treatment consultant.
4. The water treatment vendor retained by the contractor shall provide and store all the
required chemicals for each system. The proposed chemicals must be reviewed and
approved by both the water treatment sub-consultant and DDCM/CUCF’s water
treatment consultant.
5. The water treatment system installation must be performed by the contractor under the
supervision of the water treatment sub-consultant and DDCM/CUCF’s water treatment
consultant. Any water treatment system installation guidance proposed by the water
treatment vendor must be reviewed and approved by the consultants.
6. As per contract specifications, the service visits, water treatment analysis, equipment
inspection, chemical treatment requirements, corrective actions, technical assistance, and
field report must be provided by the water treatment vendor. The vendor must also provide
all required laboratory and technical services during the construction phase.
B. SHIPMENT REQUIREMENTS
1. After the performance test and once the boilers are accepted for shipment by DASNY and
DDCM, the boilers are to be readied for shipping dry as described below. One additional
set of Dry Layup product will be supplied for each boiler, to be used after the boil-out or
setup if deemed necessary.
B. SHIPMENT REQUIREMENTS
1. After the performance test and once the chillers are accepted for shipment by DASNY
and DDCM, the chillers are to be readied for shipping as described below.
2. Chiller Layup Procedure:
a. The chillers shall be shipped either with a full refrigerant charge or with nitrogen (if the
refrigerant is shipped separate from the chiller). Either method is acceptable. Nitrogen
tank assembly must be installed in the chiller room to recharge the nitrogen if deemed
necessary. The wetted surfaces should be coated with a corrosion-resistant finish in
accordance with the manufacturer’s recommendations. The chillers must be fully
protected by the manufacturer during shipping to prevent the weather from
encroaching into the chiller components.
b. If possible, all horizontal and non-drainable sections including the condenser section of
the chiller are to be blown out with compressed air. Particular care must be taken to
purge water from long horizontal sections.
c. Heat should be applied to dry the condenser section of the chiller, and then the unit
should be closed to reduce air circulation. Whenever necessary, to maintain the
temperature of all surfaces above the dew point, heaters should be installed.
d. Immediately after surfaces are dried, one of the two following desiccants is to be
spread on water-tight wood or corrosion-resistant trays:
Silica Gel-used at a rate of 8 pounds per 100 cubic feet of volume
Activated Alumina-used at a rate of 8 pounds per 100 cubic feet of volume.
e. Tightly blank and close all open connections.
1. For all HVAC projects that include the design and installation of air handling unit
systems, the consultant must include the installation of a UL Certified UVC light system
and HEPA filter as an integral part of the air handling unit systems where feasible. This
includes all the active HVAC projects that are in design or construction.
2. In addition to the UVC light system and HEPA filter, the consultant may recommend
other effective industry approved indoor air quality enhancement systems for CUNY
review, consideration and approval.
1. In reference to projects that are involved with the installation/modernization of elevators and
escalators, the following clause must be included in the design documents as part of the
qualification requirements for the elevator/escalator manufacturer:
2. “Among other requirements for approving the proposed elevator/escalator manufacturer by
the contractor, the contractor must provide a certified statement from the manufacturer that
their elevator/escalator can be fully serviced and maintained by at least three local qualified
service companies. The approval of the proposed service companies will be at the owner
and/or the consultant’s discretion. Third party components are allowed only if they are
approved by the owner and/or the consultant. If the proposed elevators/escalators have
proprietary components, they must be made available to the recommended service
companies by the elevator/escalator manufacturer and their distributers including the method
of operation, diagnostic and maintenance procedures.”