Checklist - Quality Gate Review
Checklist - Quality Gate Review
I. Objectives
- To verify objectives of project stages/milestones/processses against project target and plan
- To evaluate project performance against project target and plan
II. How to use
1. Work flow
Customize Quality
Lead
Conduct Stage/
Summarize Report Quality Get confirmation
Milestone Evaluate Project Log issues to Follow-up
Quality Gate Gate Review on issues and
Accomplishment Performance PMS (Process_Correction)
Review Result Result corrective actions
Verification
2.2 Steps
Step 1 Develop Quality Gate Review Checklist
Project QA Lead customizes Quality Gate Review Checklist specific for the project based on customer requirement, WO, QA Plan and the standard Quality
Gate Review Checklist. This activity shall be conducted within 15 days from the Project Start Date.
- Mark N/A for items that are approved to be waiver for the project. Reason for N/A must be recorded in column "Observation" and correspondent
tailoring/deviation must be recorded in FI and be reviewed and approved by authorized persons in accordance with Guideline_Process Tailoring prior to
the implementation.
Project QA verifies accomplishment of the defined stages/milestones/processes using the checklist in sheet "Milestone Verification", then mark 'OK', 'NOK',
or 'NA'
- 'OK' means that the item content is in the project work, mandatory requested for checking, and is satisfied
- 'NOK' means that the item content is in the project work, mandatory requested for checking, and is
NOT satisfied
- 'N/A' means that the item content is out of the project work, therefore it does not need checking
Project QA evaluates performance of the defined stages/milestones/processes using the sheet "Performance Evaluation".
Project QA summarizes result of quality gate review, identify issues and suggestions using the sheet "Quality Gate Summary Report".
Step 5 Report Quality Gate Review Result
Project QA sends Quality Gate Review Result to Project QA Lead, SM, PM and other relevant persons to get confirmation on issues and corrective actions.
If there is a conflict of opinion, escalate the issue to Project QA Lead, QA Lead for resolution.
Step 6 Follow up
Project QA logs issues detected into PMS and follow up the issues & corrective actions to closure in accordance with Process_Correction and
Process_Prevention. Escalate to appropriate QA Leader, QA Manager when the issues not resolvable with the responsible people or when the issues are
pending more than 1 week from the deadline.
2. Guideline
Normally, a project performance analysis report contains four main parts as following:
- Header of report
- Quality evaluation
- Cost evaluation
- Delivery evaluation
- Conclusion
- Suggestions
2.1 Header of Report
This part provide brief information of project and the report
2.2 Quality Evaluation
Target Value: the information could be gotten from PM. It is normally recorded in standards supplied by
Customer or Work Order, Project Plan
Actual Values: the information is gotten from PM, or gotten from project records (DMS or equivalent - Defect)
Analysis:
1) Comparing actual performance against target for quality related metrics (defect rate, number of
defects found, % of defect detected, leakage, etc), you can evaluate whether the project performance
reaches the target or not. If deviation between the actual performance and the target >10% (this
threshold could be customized by projects), causal analysis/explanation is required.
2.3 Cost Evaluation
Target Value: the information could be gotten from PM. It is normally recorded in standards supplied by
Customer or Work Order, Project Plan
Actual Values: the information is gotten from PM, or gotten from project records (Effort Efficiency, Effort
Effectiveness, Productivity, Effort distribution, etc).
Analysis:
Comparing actual performance against target, you can evaluate whether the project performance
reaches the target or not. If deviation between the actual performance and the target >10% (this
threshold could be customized by projects), causal analysis/explanation is required.
Serious If actual value is better than or equal to the target.
Actual value is worse than the target but there is no impact to the next step/phase/stage.
Medium
For example: actual project size is lower than planned.
Cosmetic If it’s actual value is worse than the target and it will affect to next step/phase/stage quality.
2.4 Delivery Evaluation
Target Value: the information could be gotten from PM. It is normally recorded in standards supplied by
Customer or Work Order, Project Plan
Actual Values: the information is gotten from PM, or gotten from project records (Project schedule - Delivery)
Analysis:
Cosmetic If it’s actual value is worse than the target and it will affect to next step/phase/stage quality.
2.5 Conclusion
Basing on evaluation result on project performance in term of Q-C-D, the author has to make a conclusion on
project performance in the report period. The project performance could be summarized in "Traffic Light
Reporting" format to provide quick snapshots to the reader on the project status and drive the readers to pay-
attention on important issues.
2.6 Suggestions
Basing on project performance evaluation result, the author has suggestions to the project. Action/solution is
mandatorily required if evaluation result is "Not pass"
1. Conclusion
<Summarize conclusions get from Milestone Verification & Performance Evaluation here>
a. Stage/Milestone Accomplishment
[x] Satisfied [] Un-Satisfied [] Other
Enter rationale to derive to the conclusion "Not Achieved" or "Other"
b. Project Performance
Quality Cost Delivery
Raised
No Project Code Customer PM AM QA Issue Description Cause Impact
Week
Criteria #1
Criteria #2
Criteria #3
Are work products of the
stage/milestone/process completed?
Work product #1
Work product #2
Work product #3
1. Quality Evaluation
1.1 Metrics
2. Cost Evaluation
2.1 Cost Metrics
1 #DIV/0!
2 #DIV/0!
2.3 Analysis
<Enter analysis here>
3. Delivery Evaluation
3.1 Delivery Metrics
1
2
3.2 Deliverable status (could be referred to Project schedule)
1
2
3
4. Conclusion
5. Suggestion
<List issues together with your suggestions>
1
2