Upgrade of ArcelorMittal Indiana Harbor #2 Galvanizing Line Making 2CGL Great Again
Upgrade of ArcelorMittal Indiana Harbor #2 Galvanizing Line Making 2CGL Great Again
Upgrade of ArcelorMittal Indiana Harbor #2 Galvanizing Line Making 2CGL Great Again
1
ArcelorMittal
3300 Dickey Road
East Chicago, IN 46312
Tel.: +1 219-399-3519
E-mail: [email protected]
2
Superior Engineering, LLC
2345 – 167th St.
Hammond, IN 46323
Tel: + 219-399-7085
E-mail: [email protected]
3
ArcelorMittal
3210 Watling St.
East Chicago, IN 46312
Tel.: +1 219-399-1499
[email protected]
INTRODUCTION
The #2CGL at the Indiana Harbor was built in 1964 by Youngstown Sheet and Tube. The line is a 72” wide horizontal
furnace line capable of running heavy and light gauge products. The line has undergone several upgrades over the years to
improve capacity, quality and reliability. These upgrades included:
• 1988 – 25% productivity increase which included tower and furnace improvements
• 1992 – Shape improvements which included in-line temper mill and tension leveler
• 1994-97 – Several electrical upgrades to various parts of the line to improve the reliability.
2CGL is a line with demonstrated capacity of 585,000 tons per year depending on the product mix placed on the line. In the
past the line produced a large amount of automotive product as well as non-automotive sheet. The amount of automotive
production has decreased over the years as newer galvanizing lines have been commissioned.
The relevant specifications of the line are contained in Table 1 below.
Entry End Upgrade: The first scope area to be addressed was the entry end. The entry end coil preparation was a bottleneck
which decreased line efficiency. Cutting off gauge strip prior to welding was a manual system with inadequate scrap pushing
equipment that malfunctioned causing delays.
The project installed an improved scrap pusher unit at the entry end. Also, the feed and cut function was automated.
Welder: The welder was 54 years old and did not provide thin welds that could be rolled through the temper mill causing
yield loss. Reliability was poor causing weld breaks which affected working ratio and resulted in product rejects. Welding
and notching were manual operations which was a safety concern and affected the quality of the weld and weld cycle time.
The welder was replaced with a new welder and notcher which has planishing to provide thin welds and allow for rolling of
the welds through the temper mill, leveler, and coater. The new welder is the first of its kind that can handle the wide
diversity of material at 2CGL. This new welder & notcher is safer, reduces yield loss and improves the reliability of the
welds leading to an improved working ratio.
Wedge Pyrometer: 2CGL was the only coating line at ArcelorMittal without a wedge pyrometer in the hot bridle. Without
a wedge pyrometer, temperature measurement at the hot bridle was inaccurate due to background radiation. An inaccurate
strip temperature caused inefficient process control and strip temperature variation entering the zinc pot. This increased dross
formation and reduced coatability.
A wedge pyrometer was installed and has improved temperature measurement at the hot bridle. This reduces strip
temperature variation and improves pot temperature control leading to less dross formation.
Pre-Melt Pot: The main zinc pot at 2CGL is relatively small (186 tons) for a 72-inch-wide line. 2CGL did not have a pre-
melt pot and productivity was greatly limited when producing heavy coatings. Coating weights greater than G145 (1.45
oz./square foot) were required by customers. The existing pot could not melt zinc fast enough on heavy coating material so
2CGL was slowed down to keep zinc at an appropriate level. Zinc consumption charts for 50-inch-wide sheets are included
below to show the magnitude of this issue.
Tension Leveler: The 2CGL tension leveler was removed years ago and 2CGL could not provide the flatness required by
customers. Customer requirements for the expected product mix are a maximum of 5 I-Units of shape (I-Units are found by
measuring the height of the off flat condition and the interval between each peak). 2CGL struggled to deliver the required
shape, especially on hot roll direct product. The figure below shows strip cross bow produced on the line without a leveler.
Stencil System: The existing stencil machines were not capable of printing required by customers and new stencil machines
were installed along with required production software changes.
Exit End Upgrade: The exit end scrap cutting system was entirely manual and not capable of cutting enough strip at each
weld. This resulted in reprocessing of coils. Due to the very manual operation at the delivery end of the line, we experienced
an unusually high number of line-stops which reduced working ratio as well.
The slow-down, stopping, spotting and cutting at the weld functions were automated. A scrap handling system capable of
cutting 2 meters at each weld was installed.
Furnace PLC & I/O Upgrade: The project replaced the annealing furnace PLC system and I/O with a new system
including Ethernet based I/O which supports the latest National Fire Protection Agency standards for burner management and
control. This solution provides better heat control for the furnace and the latest safety standards for furnace control required
by the NFPA reducing safety and reliability risks.
Furnace motor field supplies replacement: The old Motor Protection Electronics field exciters were obsolete. The system
was split into 4 sections with one speed feedback per section. The new field supplies give us individual control for every
motor eliminating the need to stop the line for equipment failure while providing us with better speed control in the furnace
and enhanced trouble shooting capabilities. We also eliminated risk for downtime with replacement of the old drives and the
risk of scratches on light gage with the enhancement in speed controls with the new drives.
Entry, Delivery Automax and GE Rx7i PLC and Genius I/O Block Replacement Upgrade: the Automax and GE Fanuc
Rx7i PLC processors and the Genius I/O blocks were no longer supported. The project installed new controllers and I/O with
improved diagnostics and historical trending capabilities.
The new solution eliminated the risks of unsupported hardware and third party required equipment with new equipment all on
the same control platform. The new equipment provides improved control of the line with enhanced diagnostic I/O, increased
troubleshooting tools and expanded historical data analysis capabilities. The new I/O has vibration free connections and all
the equipment has a 20-year support guarantee.
Entry, Center and Delivery Drives Upgrade: the old DC2000 drives were not supported by the OEM. We replaced them
with new drives with better control and diagnostic capabilities and real-time high-speed trending capabilities. The new
equipment provides better line control and almost eliminates any questions of cause during drive trips. It also reduces the
risk of down time.
Figure 11 – Overcoating
CONCLUSION
The upgrade project has increased the marketability of innovative products and operational availability of the equipment at
2CGL. The project also improved safety, reduced costs and provided better control of the process.
ACKNOWLEDGEMENTS
The authors would like to thank our colleagues at ArcelorMittal Indiana Harbor Finishing, 2CGL, Engineering, Sales,
Quality, Safety, Process Automation and Environmental groups for their efforts on this project.