Chapter 6 - Column
Chapter 6 - Column
Chapter 6 - Column
Reinforced
Concrete
Detailing 6
1. INTRODUCTION
The re-bars in column are mainly used to enhance the compression capacity of the
column. They are in the form of vertical bars. In some situations, if the column
has to resist large bending moment, the bars have to resist the flexural tensile
stress similar to the longitudinal bars in beam.
Large diameter Grade 500 high tensile steel bars are usually used.
As the vertical bars are designed to take up compression, they have to be
restrained from buckling. Restraint in the form of horizontal links (or called
binders) is used. For ease of fixing, small sizes Grade 250 mild steel bars are
usually used for the links.
The vertical bars together with the links forms a steel cage. The steel cages are
usually spliced or lapped at the floor level.
2. VERTICAL BARS
Column 6
HK COP of Structural Use of Concrete 2013 requirements
on column re-bars
Minimum area of vertical steel 0.8%
Maximum area of vertical steel if vertically cast 6%
Maximum area of vertical steel if horizontally 8%
cast
Maximum area of vertical steel if laps in 10%
vertically or horizontally cast
Minimum size of vertical bars 10
Minimum number of vertical bars 4 for rectangular section
6 for circular section
Example
A 450 x 450 column, the designer specified that the vertical steel required is
8200mm2 evenly distributed within the column. Determine the number and size of
re-bars for the column.
Check minimum steel area required: 0.8% x 450 x 450 = 1620 mm2
Check maximum steel area allowed: 6% x 450 x 450 = 12150 mm2
Try 4T40 + 4T32, Asc provided = 8244mm2, 4.07%.
(Comment: pay attention to the maximum percentage of steel at the lap)
Vertical bars of column are seldom curtailed. Vertical bars are usually continuous
from the floor to floor. They extend above the upper floor level to lap with the
bars of the upper floor column.
Column 6
At foundation level, re-bars are provided for lapping with the column bars. They
are called starter bars. As the starter bars are usually exposed for a long time
before the commencement of the superstructure work and they are usually located
at ground level, in order to reduce the risk of being damaged, it is recommended
that the size of starter bars should not be less than T20.
At the roof, the vertical bars have to terminate with adequate anchorage length
into the roof beams.
It is common practice not to provide re-bar lapping details for each individual
column and instead a typical lapping and anchorage details of re-bars as shown in
DWG 601 is provided.
The vertical bars are subjected to compression and have to be restrained from
buckling by links (or binders).
Column 6
The detail of the links is similar to the shear links used in beam.
Example
A 500 x 500 column, the area of steel specified = 8200 m2. The bars can be
evenly distributed. Grade 30 concrete, moderate exposure. FRP =2hrs. Provide
the re-bar details.
Concrete cover to all bars required = 30mm (appendix A of Chapter 3)
Use 4T40 + 4T32 vertical bars, Asc = 8244mm2, 3.3%, ok.
Arrangement of bars: T40 at corners, T32 at mid of the column face.
Check the distance of the T32 from the corner bars: (500 – 2x30 – 2x10 – 40)/2 =
190mm > 150mm. Therefore the T32 has to be restrained.
R10-200 links to be provided. There are two possible arrangements of the links
as shown in Alternatives A and B of DWG603. Although both arrangements are
theoretically acceptable, some engineers prefer alternative A because it renders
the steel cage more rigid and not easily dislocated during concreting.
An additional alternative C, 4T32 + 12T25 can be used and the arrangement of
the re-bars is also shown in DWG 603.
4. PRESENTATION
The presentation of the re-bar details for column is usually in the tabular form
called ‘Column Schedule’. An example is shown in DWG 602 This column
schedule should be read together with the typical details shown in DWG 601.
In some situations where the typical detail is not applicable, elevations and
sections of the column should be provided.
The recommended scale is 1:50 for elevations and 1:25 for sections. Depending
on the size of the column and the complexity of the re-bars fixing, scale of 1:100
or 1:10 may be used.