Accelerated Corrosion in Benfield Absorber
Accelerated Corrosion in Benfield Absorber
Accelerated Corrosion in Benfield Absorber
Upper half of Benfield absorber at FFC-MM has had a problematic history from corrosion
point of view. The paper discusses the problem identification, root cause determination, results
of progressive inspections carried out, remaining life assessment, solutions considered and
tried, and factors behind the decision to change the damaged portion of the Vessel
The new vessel was made available by rehabilitation of an old redundant shell by FFC-MM
using local facilities. An account of various issues faced during this phase and solutions
adopted with costs, activity durations and lessons learned is also presented. Information given
will be of interest to all those operators facing similar situation and wish to embark on a
comparable project.
Suhail Khalid Khawaja (Unit Manager Process), Fakhar Ul Hasan (Unit Manager Maintenance),
Mehmood Raza Gillani (Unit Manager operations, Ali Abrar (Section Head Inspection)
Fauji Fertilizer Company Limited
1N
Mechanical Details
OEM is M/S Hitachi Zosen Corporation, 40 mm
CW-19
Osaka Japan, Benfield Solution Absorber
Column C-302 stands tall almost 54.4 meters CW-18 1ME
high at FFC Plant III. The shell material is CW-17 5N
53 mm
History: CW-10
This equipment was commissioned in 1980. 4N 1MC
CW-9
The leakage through the reinforcement pad of
one of the manhole (1MD), between bed no.1 CW-8 47 mm
and 2 was observed in 1992. Major areas 3500
CW-7
affected by the corrosion are indicated as C1 2MB 1MB
& C2 in figure-1. Various measures were CW-6
adopted to control the problem including CW-5 Bed-4 48.5 mm
application of SS lining inside the vessel on CS Paul Rings
affected regions. The SS lining welds failed CW-4 2MA
0.24
0.25
0.22
problem 0.20
4. Determination of corrosion root 0.20 0.18
0.16
cause and remedial measures
0.15
It is evident from the history of this column
that the previous plant operators were not 0.10 0.08
able to identify the root cause of the 0.06
At area C1, points of low thicknesses were Based on the thickness mapping, the vessel
selected in North, South, East and West sides was analyzed on API-579 for the fitness for
for precision thickness monitoring on service evaluations. The results on Level- I
monthly basis. Based on this average and Level –II assessments were negative.
corrosion rate was determined. Note This meant Level-III assessment was
significant drop in corrosion rate after necessary to further analyze the integrity of
improvement in Hot and Cold solution ratio equipment against the thickness loss.
and replacement of distributor in Nov 2004.
Options for restoring vessel integrity
Figure Precision thickness monitoring to All the options were deliberated upon.
evaluate corrosion rate Following were the considerations and
reasons for acceptance/rejection.
Coating inspection in Nov 2004
Solution 1 to 4 required level 3 remaining life
During an emergency shutdown, after 20 assessment for which in house expertise was
months of operation, the applied belzona not available. Cost of external engineering
coating was inspected again. This time cracks assistance though not very high in absolute
and detachment was noted on the coating terms was not feasible to incur in view of low
surface. This was considered a serious cost of solution No. 5.
condition as it could result in aggravated
corrosion and more likely development of APPLICATION OF EPOXY COATING:
SCC. Epoxy coating had been applied in TA-2003.
It was an attractive option as it did not
require extended down time. However its
durability remained a cause for concern.
Lining was inspected in August 2003 (5
months operation) and was found in average
condition with slight wrinkles. It was
therefore concluded that the lining needed
continuous monitoring and inspections,
sometimes by removing the lining. This was
found impractical. Later in November 2004
(after 20 months operation) it was found in
deteriorated condition. By that time decision
Figure Cracks and detachment of the
to replace the vessel had been taken. The
Belzona epoxy coating.
observation confirmed the apprehension that engineering and material ordering were
Epoxy coating is not a permanent/long undertaken. In November 2004 final go
lasting solution. In itself the coating is ahead was given. The rehabilitation project
expensive. (See the cost chart)
Cost Comaprison of Different Options
REPLACEMENT OF DAMAGED 92,000
PORTION: 90,000
90,000
Cost in US$
by repair contractor and SP on that basis that 86,000
82,000
APPLICATION OF EXTERNAL
BANDING: 80,000
Banding Replacement Expoxy Coating
Solution
External Banding to reinforce the vessel was
proposed by engineering consultant. Detailed
analysis was required which was cost was to be completed before March 2005 (the
intensive. In any case the solution would not scheduled Turnaround)
have catered for the internal uneven surface To ensure on time implementation all pre TA
resulting in uneven wetting / passivation. activities were identified and planned. See
Epoxy coating could have been applied but attached bar chart. The job was completed
would require frequent inspections. two and half months after receipt of metal
sheets in Karachi even though it involved two
PROVISION OF S.S. LINING: trips to HMC-3 once for fabrication and then
This solution was tried in 1991. Could not be for Heat treatment.
implemented as the base metal was uneven
and required extensive stress relieving FABRICATION
MANUFACTURING
Only two agencies in Pakistan had the
facility to roll 4m wide and 35 mm thick
sheet. The order was placed on HMC-3 who
not only rolled but also welded the shell.
The tolerances were specified as per SP
specifications. New shell was finally joined
with existing shell courses without
significant difficulty.
HEAT TREATMENT
The whole vessel (20m length) was
transported to HMC-3 who performed the INSTALLATION
heat treatment. FFC provided the heat
treatment procedure and reviewed the data
RIGGING
before dispatch of the vessel.
UNLOADING OF PACKING
Packing had to be unloaded to reduce
the load to be lifted. To speed up this activity
an additional davit was bolted on the 2nd bed
packing loading flange. Pre TA simulation
were carried out to ensure safety of operation
and reliability of winch.
WELDING
Transportation
• Know the highway rules for
transportation.
• Length, height, width diameter and
weight of all objects to be transported
should be carefully reviewed and
communicated to the transportation
contractor.
Figure Pre-heating elements being fixed on • Consider prime mover engine power
the main joint. while reviewing the quotations.
• Discuss the transportation route with
the contractor.
• Run pilot vehicle provided with
communication equipment on all
critical transportations including
crane.
Crane and Rigging
• The crane should be accompanied by
specialist technicians to provide
instant services in case of a break
down. The crane contractor should
have a system of dispatching any
required spare part at a short notice.
Figure Welding of field joint in progress. • In addition to drawings carefully
measure actual height of lifting lug
OVERALL PROJECT SCHEDULE from ground.
• In cases where the crane is operating
The planned mechanical activity time was at the limits, size of slings should be
305 hrs. Job was completed in 299 hrs. carefully calculated.
TIME SAVING • Fabrication
To three main following activities were • Cooperation from HMC-3 was of
planned to reduce execution time: high level. Job has handled by them
Parallel unloading/loading of Pall rings from in a professional manner.
bed no. 1 and 2. • Before dispatch of vessel for furnace
Cutting of shell with track mounted shell heat treatment verify that all internal
cutting machine. and external attachments have been
Pre installation of platforms on new shell to welded
cut scaffolding time. • Size of new vessel should be kept 1 to
1.5 m extra to cater for welding of
hydraulic test blind and final
adjustments.
• For field joint Vessel should be cut at
a distance from the weld joint.
Cutting exactly from the weld joint
would result in problems in re-
welding and subsequent inspections.
• Review position of jack bolts lugs etc.
with agency carrying out heat
treatment to avoid any later
difficulties.
Conclusion
Total = $ 90,000
• Total = $ 88,600