004 - Gas Analyzer Cal Procedure

This document provides a standard calibration procedure for gas analyzers. It outlines the necessary equipment, preliminary operations, calibration process, and related documents. The calibration procedure involves maintaining the gas analyzer at a controlled temperature, taking initial readings, calibrating the sensor against a gas cylinder standard, recording results, and generating a calibration certificate.

Uploaded by

Manzoor Ahmad
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
109 views3 pages

004 - Gas Analyzer Cal Procedure

This document provides a standard calibration procedure for gas analyzers. It outlines the necessary equipment, preliminary operations, calibration process, and related documents. The calibration procedure involves maintaining the gas analyzer at a controlled temperature, taking initial readings, calibrating the sensor against a gas cylinder standard, recording results, and generating a calibration certificate.

Uploaded by

Manzoor Ahmad
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

International Agent Group

Calibration, NDT, Trading, Inspection, Testing, QMS


Consultancy, IT Solutions and Contracting

Standard Calibration Procedure for Doc. No.:


Rev. 00 June 2014
Gas Analyzer INAT/CHEM/SCP-004

CALIBRATION PROCEDURE

FOR

GAS ANALYZER

Prepared by

Reynaldo Nava Signature Date :

Reviewed by

Ravikumar Ronanki Signature Date :

Approved by

Manzoor Ahmad Signature Date :

Controlled Copy No: Uncontrolled Copy:

Issued to:

This document is the property of INAT and is issued only for persons or entity as written on this
manual. It is not to be retransmitted, printed or copied without prior written permission of company.

Issue June 2014 Page 1 of 3 CHEM/SCP-004

P.O. Box: 30060, Al-Khobar 31952, Tel: 00966 3 8933250, Fax: 00966 3 8643351,
Email: [email protected], [email protected], www.inatt.com
International Agent Group
Calibration, NDT, Trading, Inspection, Testing, QMS
Consultancy, IT Solutions and Contracting

Standard Calibration Procedure for Doc. No.:


Rev. 00 June 2014
Gas Analyzer INAT/CHEM/SCP-004

Table of Contents

Sr. No. Title Page No(s).


1.0 Scope 03
2.0 Standard Equipment 03
3.0 Preliminary Operations 03
4.0 Calibration Procedure 03
5.0 Related Documents 03

Issue June 2014 Page 2 of 3 CHEM/SCP-004

P.O. Box: 30060, Al-Khobar 31952, Tel: 00966 3 8933250, Fax: 00966 3 8643351,
Email: [email protected], [email protected], www.inatt.com
International Agent Group
Calibration, NDT, Trading, Inspection, Testing, QMS
Consultancy, IT Solutions and Contracting

Standard Calibration Procedure for Doc. No.:


Rev. 00 June 2014
Gas Analyzer INAT/CHEM/SCP-004

1.0 Scope

This procedure provides guidelines for calibration of Gas Analyzer.

2.0 Standard Equipment

2.1 Gas Cylinder traceable to international standard reference materials shall be used as
standard for calibration.
2.2 The standard shall be kept under controlled environmental conditions e.g. dust free
environment and Lab Temperature 22°C ± 2°C, Humidity 60%RH ± 20%RH.

3.0 Preliminary Operations

3.1 The details of Gas Analyzer received for calibration shall be entered in the Calibration
Job Form .
3.2 Inspection of Gas Analyzer for general condition shall be carried out.
3.3 The Gas Analyzer shall be inspected and marked () in relevant block of equipment's
primary inspection section of Calibration Data Sheet .

4.0 Calibration Procedure

4.1 The Gas Analyzer to be calibrated shall be maintained at laboratory temperature for 02
hours minimum.
4.2 The Measurements of Gas Analyzer shall be taken against the standard Gas Cylinder.
4.3 Apply the needed Gas into the UUT as initial reading before conducting the calibration of
sensor.
4.4 Select CAL Mode on the instrument after initial reading.
4.5 Apply the Gas needed on the calibration.
4.6 The Unit Under Test will show if the calibration is PASS or FAILED. Recalibrate the UUT
if FAILED until it shows PASS.
4.7 Record the results on the data sheet and calculate for error.
4.8 A calibration certificate shall be generated according to data gathered listed on the data
sheet.
4.7 A Calibration Sticker containing following information shall be affixed on the calibrated
pH Meter.
a) Item code
b) Calibrated on
c) Next calibration date

5.0 Related Documents

All the latest formats are documented in Master List of Document / Record and placed in CQF
file for reference.
All the latest Standard Calibration Procedures (SCP) are controlled and issued to concerned
Calibration Engineers.

Issue June 2014 Page 3 of 3 CHEM/SCP-004

P.O. Box: 30060, Al-Khobar 31952, Tel: 00966 3 8933250, Fax: 00966 3 8643351,
Email: [email protected], [email protected], www.inatt.com