០8. Club Study - - 008 - - BoQ Preparation
០8. Club Study - - 008 - - BoQ Preparation
០8. Club Study - - 008 - - BoQ Preparation
CLUB STUDY-008
BOQ PREPARTION
2
TENDERING
1 MAIN
CONTRACTOR
CEO
Tendering Manager
Client ARC Team
QS Manager
STR Team
MEP Team
QS Team
Consultant
MEP TEAM
Contract Staffs
1 2 3
Tendering Preparation
1. TENTATIVE MASTER SCHEDULE
Drawing
Method Statement
Experiences
TOTAL Total Amount
NO. Work Scopes UNIT C.QTY L.RATE M.RATE
RATE (USD) Risk Analysis Rate (L)+Rate (M)
1 PRELIMINARY
Master Schedule
Included % of Wastage
1 PRELIMINARY X Y 𝛂 𝛃 𝛂𝐗 𝛃𝐘
2 STR WORK
3 ARC WORK
4 MEP WORK
គម្រោងៈ
ោាស់ គម្រោងៈ
ររុមហ៊ុ នទទួលការសាងសងៈ
1 105.00 $ 6.89 $ 9.10 $ 15.99 $ 1,678.95 100.00 5.00% 105.00 $ 5.00 $ 5.30 $ 7.00 30.00% 30.00% 6.00% $ 6.89 $ 9.10 $ 15.99
4 105.00 $ 6.89 $ 9.10 $ 15.99 $ 1,678.95 100.00 5.00% 105.00 $ 5.00 $ 5.30 $ 7.00 30.00% 30.00% 6.00% $ 6.89 $ 9.10 $ 15.99
10
11
12
តម្មលស រ ៊ុរម្នការងារម្រគឿ ងរង្ុុំ (ដ៊ុល្លល) $ 3,357.90 $ 1,050.00 $ 1,113.00 $ 1,470.00 $ 1,446.90 $ 1,911.00 $ 3,357.90
DIMENSION
NO. TYPE OF STRUCTURE AREA (M2) VOLUME (M3) NOS TOTAL VOLUME (M3) REMARK
B (Width) L (Length) H (Height)
A SUB-STRUCTURAL WORK
1 PILING 54.00
Type-1 0.30 0.30 12.00 0.09 1.08 50.00 54.00 Driven Pile
Type-2 0.00 0.00 12.00 0.00 0.00 50.00 0.00 Driven Pile
Type-3 0.00 0.00 12.00 0.00 0.00 50.00 0.00 Driven Pile
2 FOOTING 15.15
4 GF 35.88
GROUND BEAM
COLUMN
Column-2
BEAM
Beam-2
SLAB
Block-2
STAIRCASE
DIMENSION
NO. TYPE OF STRUCTURE SLAB THICK (M) PERIMETER (M) AREA (M2) NOS TOTAL AREA (M2) % OF FABRICATION FABRICATION AREA (M2) REMARK
B (Width) L (Length) H (Height)
Type-1 1.50 1.50 0.70 6.00 4.20 5.00 21.00 Rectangle Footing
Type-2 1.50 1.50 0.70 6.00 4.20 6.00 25.20 Rectangle Footing
Type-3 1.50 1.50 0.70 6.00 4.20 7.00 29.40 Rectangle Footing
Type-2
Type-3
4 GF 9.00 9.00
Type-2
Type-3
Beam-2
Block-2
LIFT WALL
STAIRCASE
FORMWORK Page 1
Create Your Life Goal !