CLUB STUDY-008

BOQ PREPARTION

Instructed by: Mr. Voek Pitou


Lecturer of Project Management Class
BOQ CONCEPT PREPARTION

2
TENDERING
1 MAIN
CONTRACTOR
CEO

Tendering Manager
Client ARC Team

QS Manager
STR Team

MEP Team
QS Team
Consultant

ARC TEAM Contract Team

Design Team STR TEAM


Contract Manager

MEP TEAM
Contract Staffs

Instructed by: Mr. Voek Pitou


Lecturer of Project Management Class 1
BOQ CONCEPT PREPARTION CLIENT/CONSULTANT

MAIN CONTRACTOR MAIN CONTRACTOR

ACTIVITY INFORMATION DOCUEMNTATION

1 2 3

Tendering Preparation
1. TENTATIVE MASTER SCHEDULE

1. SITE VISIT 1. ARC DRAWING 2. ESTIMATION BOQ

2. SITE SURVEYING 2. STR DRAWING 3. MATERIAL/LABOR PLANING

3. SOIL INVESTIGATION 3. MEP DRAWING 4. METHOD STATEMENT

4. SITE STATUS ANALYSIS 4. MATERIAL SPEC. 5. QA/QC PLANNING


5. WORK SPEC. 6. HSE PLANNING
6. TECHNICAL REQUIREMENTS 7. BUDGET PLANNING
7. REQUIREMENT STANDARD 8. ORGANIZATION
Instructed by: Mr. Voek Pitou
Lecturer of Project Management Class 2
9. WORK FLOW
BOQ CONCEPT PREPARTION Site Visit

Drawing

Method Statement

Experiences
TOTAL Total Amount
NO. Work Scopes UNIT C.QTY L.RATE M.RATE
RATE (USD) Risk Analysis Rate (L)+Rate (M)

1 PRELIMINARY
Master Schedule

2 STR WORK Accurate Quantity

Included % of Wastage

3 ARC WORK Method to do the work


Material Specification
Work productivity

4 MEP WORK Material Quantity


Work Quantity
Supplier’s Quotations
Experiences
TOTAL BUDGET AMOUNT (USD) USD

Instructed by: Mr. Voek Pitou


Lecturer of Project Management Class 3
(FOR CLIENT/OWNER)
BOQ CONCEPT PREPARTION

DIRECT COST SELL COST

TOTAL Total Amount Labor Material Prof.(L) Prof.(M) LABOR MATERIAL


NO. Work Scopes UNIT C.QTY L.RATE M.RATE
RATE (USD)

1 PRELIMINARY X Y 𝛂 𝛃 𝛂𝐗 𝛃𝐘

2 STR WORK

3 ARC WORK

4 MEP WORK

TOTAL BUDGET AMOUNT (USD) USD

Instructed by: Mr. Voek Pitou (FOR CONSTRUCTION OPERATION)


Lecturer of Project Management Class 4
@Copyright by: Prof. Voek Pitou
Telegram Channel: Professional Engineering (PMP)

BILL OF QUANTITY ការលមអិតម្នការគណនា

គម្រោងៈ

ោាស់ គម្រោងៈ

ររុមហ៊ុ នទទួលការសាងសងៈ

ររម្េទការងារៈ ការងារម្រគឿ ងរង្ុុំ កាលររិម្ចាទៈ Rev.No.: 5.00% 30.00% 30.00% 6.00%

តម្មលឯ រតាា (ដ៊ុល្លល) ររិោណ ឯរតាាតម្មលម្ដើ ម ភាគរយចុំម្នញ តម្មលឯ រតាាលរ់


តម្មលឯ រតាាសរ ៊ុរ
No. ការលមអិតការងារ ឯរតាា ររិោណ តម្មលស រ ៊ុរ ការរត់ ចុំណុំ ររិោណគណនា ពលរមម
រោលុំ ង ពលមម សោារៈ (ដ៊ុល្លល) ភាគរយរុំហាតរង ររិោណសុំ រារ់ ការសាងសង ពលរមម សោារៈ ពលមម សោារៈ ការថែមម្ោ៉ោង ពលរមម សោារៈ សរ ៊ុរ
តាមរលង ថែមម្ោ៉ោង

I. ការងារម្រគឿ ងរង្ុុំម្រកាម ដី $ 1,678.95

1 105.00 $ 6.89 $ 9.10 $ 15.99 $ 1,678.95 100.00 5.00% 105.00 $ 5.00 $ 5.30 $ 7.00 30.00% 30.00% 6.00% $ 6.89 $ 9.10 $ 15.99

II ការងារម្រគឿ ងរង្ុុំម្លើ ដី $ 1,678.95

4 105.00 $ 6.89 $ 9.10 $ 15.99 $ 1,678.95 100.00 5.00% 105.00 $ 5.00 $ 5.30 $ 7.00 30.00% 30.00% 6.00% $ 6.89 $ 9.10 $ 15.99

10

11

12

តម្មលស រ ៊ុរម្នការងារម្រគឿ ងរង្ុុំ (ដ៊ុល្លល) $ 3,357.90 $ 1,050.00 $ 1,113.00 $ 1,470.00 $ 1,446.90 $ 1,911.00 $ 3,357.90

Prepared by Mr. Voek Pitou 1/18/2023 Page 1


@Copyright by: Prof. Voek Pitou
Telegram Channel: Professional Engineering (PMP)

QUANTITY TAKE-OFF FOR CONCRETE WORK

DIMENSION
NO. TYPE OF STRUCTURE AREA (M2) VOLUME (M3) NOS TOTAL VOLUME (M3) REMARK
B (Width) L (Length) H (Height)

A SUB-STRUCTURAL WORK

1 PILING 54.00

Type-1 0.30 0.30 12.00 0.09 1.08 50.00 54.00 Driven Pile

Type-2 0.00 0.00 12.00 0.00 0.00 50.00 0.00 Driven Pile

Type-3 0.00 0.00 12.00 0.00 0.00 50.00 0.00 Driven Pile

2 FOOTING 15.15

Type-1 1.50 1.50 0.70 2.25 1.58 5.00 7.88

Type-2 1.00 1.00 0.50 1.00 0.50 5.00 2.50

Type-3 1.20 1.20 0.50 1.44 0.72 5.00 3.60

Lean Concrete 0.05 1.17

3 STUMP COLUMN 0.60

Type-1 0.30 0.30 0.30 0.09 0.03 5.00 0.14

Type-2 0.50 0.50 0.30 0.25 0.08 5.00 0.38

Type-3 0.25 0.25 0.30 0.06 0.02 5.00 0.09

B SUPPER STRUCTURAL WORK

4 GF 35.88

GROUND BEAM

Type-1 0.30 0.50 6.00 0.15 0.90 3.00 2.70

Type-2 0.30 0.50 6.00 0.15 0.90 4.00 3.60

Type-3 0.30 0.50 6.00 0.15 0.90 5.00 4.50

Lean Concrete 0.05 1.08

GROUND SLAB 24.00

Block-1 4.00 5.00 0.15 20.00 3.00 1.00 3.00

Block-2 4.00 5.00 0.15 20.00 3.00 2.00 6.00

Block-3 4.00 5.00 0.15 20.00 3.00 3.00 9.00

Lean Concrete 0.05 6.00

6 1st FLOOR (1F) 106.50

COLUMN

Column-1 0.50 0.50 3.00 0.25 0.75 5.00 3.75

CONCRETE WORK Page 1


@Copyright by: Prof. Voek Pitou
Telegram Channel: Professional Engineering (PMP)

Column-2

BEAM

Beam-1 0.35 0.50 6.00 0.18 1.05 5.00 5.25

Beam-2

SLAB

Block-1 5.00 7.00 0.15 35.00 5.25 10.00 52.50

Block-2

LIFT WALL 0.25 10.00 3.00 2.50 7.50 6.00 45.00

STAIRCASE

TOTAL CALCULATED QUANTITY OF CONCRETE (M3) 212.13

CONCRETE WORK Page 2


@Copyright by: Prof. Voek Pitou
Telegram Channel: Professional Engineering (PMP)

QUANTITY TAKE-OFF FOR CONCRETE WORK

DIMENSION
NO. TYPE OF STRUCTURE SLAB THICK (M) PERIMETER (M) AREA (M2) NOS TOTAL AREA (M2) % OF FABRICATION FABRICATION AREA (M2) REMARK
B (Width) L (Length) H (Height)

A SUB-STRUCTURAL WORK 77.40 38.34

2 FOOTING 75.60 50% 37.80

Type-1 1.50 1.50 0.70 6.00 4.20 5.00 21.00 Rectangle Footing

Type-2 1.50 1.50 0.70 6.00 4.20 6.00 25.20 Rectangle Footing

Type-3 1.50 1.50 0.70 6.00 4.20 7.00 29.40 Rectangle Footing

3 STUMP COLUMN 1.80 30% 0.54

Type-1 0.30 0.30 0.30 1.20 0.36 5.00 1.80

Type-2

Type-3

B SUPPER STRUCTURAL WORK 281.50

4 GF 9.00 9.00

GROUND BEAM 9.00 100% 9.00

Type-1 0.30 0.50 6.00 3.00 3.00 9.00

Type-2

Type-3

6 1st FLOOR (1F) 272.50 239.50

COLUMN 66.00 50% 33.00

Column-1 0.50 0.50 3.00 2.00 6.00 5.00 30.00

Column-2 0.50 0.50 3.00 2.00 6.00 6.00 36.00

BEAM 31.50 100% 31.50

Beam-1 0.35 0.50 6.00 0.15 1.05 6.30 5.00 31.50

Beam-2

SLAB 175.00 100% 175.00

Block-1 5.00 7.00 0.15 0.15 35.00 5.00 175.00

Block-2

LIFT WALL

STAIRCASE

TOTAL CALCULATED QUANTITY OF CONCRETE (M3) 358.90 286.84

FORMWORK Page 1