0% found this document useful (0 votes)
429 views31 pages

Back Up Computations

1) The document provides details on back-up computations for various earthworks, concrete works, and formworks involved in a construction project. It includes calculations for clearing and grubbing, excavation quantities, backfill volumes, concrete mixes and quantities for footings, columns, slabs and beams. 2) Formwork calculations are also presented for footings, column footings and wall footings involving plywood and lumber quantities. 3) Scaffolding lumber needs are computed based on number and height of column footings.

Uploaded by

Lester Bialog
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
429 views31 pages

Back Up Computations

1) The document provides details on back-up computations for various earthworks, concrete works, and formworks involved in a construction project. It includes calculations for clearing and grubbing, excavation quantities, backfill volumes, concrete mixes and quantities for footings, columns, slabs and beams. 2) Formwork calculations are also presented for footings, column footings and wall footings involving plywood and lumber quantities. 3) Scaffolding lumber needs are computed based on number and height of column footings.

Uploaded by

Lester Bialog
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 31

Back-up Computations

Earthworks
A clearing and Grubbing
A = 18 X 15 = 270 sq.m
B. Soil Poisoning
A = 18 X 15 = 270m sq.m
C. Batter Board and Layouting
P = 18(1) + 15(2) = 36 + 80 = 66m
D. Excavation
Footings
I = 1.2m, W = 1 - 2m
Allowance 0.3m
H0-35m+1:05 = 14m N = 15 footings
L = 1.8mw = 1 x 8m
Volume: 1.8 x 1.8x1.4= 4.3536 cu.m
VTOTAL = 4.3536 X 18 = 68.04 m³

WALL Footing L=?? W = 0.4m ,H=0.85m


Allowance: 0.3; w = 0.4 + 0.6' = 1m
2.5 meter : 2 pcs
4 meter: 4 pcs
3 meter: 5 pcs
Column 0.30

L=1.8-0.30= 1.5m/2 = 0.75m


0.15 + 0.75 = 0.9m
L1 = 4 - 0.9(2) = 2.2 x 4 = 8.8m
L2 = 2.5-0.9(2) = 07 x 2 = 1.4 m
L3 = 3 - 0.9(2) = 1.2 x 6 = 7.2m
Total length 8.8+1.4+7.2 = 17.4 m
Volume 0.85 X 1 X 17.4 = 14.79 m³
TOTAL VOLUME OF EXCAVATION: 14.79 +68.04
Excavation = 82.83 cu.m

Backfill
Footing
Volume of Excavation of footing = 4.3536 cu.m
Volume of Footing = 0.504 cu.m
Buried Column= 0.3 x 0.3 x 1.05= 0.0945 cu.m
Volume For Backfill= 4.3536 - 0.504 - 0.0945 = 3.7551 m
VTOTAL= 3.7551 X 15 = 56.3265 cu.m

Wall Footing
Volume of Excavation of Wall Footing= 14.79m³
Volume of Wall Footing = 0.4 x 0.4 x 0.25 = 0.04 cu.m.
Volume of Buried Wall = 0.792 +0.126 +0.648 = 1.566 m³
Wall 1 = 8.8 x 0.15 X 0.6 = 0.792 m³
Wall 2 = 1.4 x 0.15 x 0.6 = 0.126 m³
Wall 3 = 7.2 x 0.15 x 0.6 = 0·648 m³
Volume For Backfill = 14.79 - 0.04 - 1.566 = 13.184 m³
TOTAL BACKFILL VOLUME = 56.3265+ 13.184 = 69.5105 m³

CONCRETE WORKS

A.Footings

𝐿 = 1.2𝑚,𝑊𝑊 = 1.2𝑚,𝑇𝐻𝐾 = 0.35,# = 15

𝑉 = 1.2𝑚 𝑥 1.2𝑚 𝑥 0.35𝑚 = 0.504cu.m.

𝑉𝑡𝑜𝑡𝑎𝑙 = 0.504 cu.m. 𝑥 15 footings = 7.56cu.m.

B. Columns

𝐿 = 0.3𝑚,𝑊𝑊 = 0.3𝑚,𝐻 = 6.75,# = 15

𝑉 = 0.3𝑚 𝑥 0.3𝑚 𝑥 6.75𝑚 = 0.6075cu.m.

𝑉𝑡𝑜𝑡𝑎𝑙 = 0.6075 cu.m. 𝑥 15 footings = 9.11cu.m.

Class A 1:2:4

Quantity of cement = 7.56cu.m. 𝑥 9 = 68.04 bags - 40kg.

Quantity of cement = 68 bags

Quantity of sand = 7.56 cu.m. 𝑥 0.5 = 3.78 cu.m.

Quantity of sand = 3.78 cu.m.

Quantity of gravel = 7.56 cu.m. 𝑥 1 = 7.56 cu.m.


Quantity of gravel = 7.56 cu.m.

C.Column Footings

𝐿 = 0.3𝑚, 𝑊𝑊 = 0.3𝑚, 𝐻 = 1.05𝑚

𝑉 = 0.3 𝑚 𝑥 0.3 𝑚 𝑥 1.05 𝑚 = 0.0945 cu.m.

𝑉𝑡𝑜𝑡𝑎𝑙 = 0.0945 cu.m. 𝑥 15 = 1.42 cu.m.

Class A 1:2:4

Quantity of cement = 1.42 cu.m. 𝑥 9 = 12.78 bags - 40kg.

Quantity of cement = 13 bags

Quantity of sand = 1.42 cu.m. 𝑥 0.5 = 0.71 cu.m.

Quantity of sand = 0.71 cu.m.

Quantity of gravel = 1.42 cu.m. 𝑥 1 = 1.42 cu.m.

Quantity of gravel = 1.42 cu.m.

D. Wall Footing

𝑇𝐻𝐾 = 0.25𝑚, 𝑊𝑊 = 0.4𝑚, 𝐿 = 0.4𝑚, 𝐿𝑡𝑜𝑡𝑎𝑙 = 57m

𝑉 = 0.4 𝑚 𝑥 0.4 𝑚 𝑥 0.25 𝑚 = 0.04 cu.m.

𝑉𝑡𝑜𝑡𝑎𝑙 = 0.04 cu.m. 𝑥 57 = 2.28 cu.m.

Class A 1:2:4

Quantity of cement = 2.28 cu.m. 𝑥 9 = 20.52 bags - 40kg.

Quantity of cement = 21 bags

Quantity of sand = 2.28 cu.m. 𝑥 0.5 = 1.14 cu.m.

Quantity of sand = 1.14 cu.m.

Quantity of gravel = 2.28 cu.m. 𝑥 1 = 2.28 cu.m.

Quantity of gravel = 2.28 cu.m.


E. Slab

𝑆1, 𝑆3, 𝑆4, 𝑆5: 3𝑚 𝑥 4𝑚 𝑥 0.15𝑚 = 1.83cu.m. 𝑥 4 = 7.2 cu.m.

𝑆2, 𝑆6: 3𝑚 𝑥 3𝑚 𝑥 0.15𝑚 = 1.35𝑚3 𝑥 2 = 2.7cu.m.

S7, S8: 2.5m x 4m x 0.15m = 1.5cu.m. x 2 = 3cu.m.

𝑉𝑡𝑜𝑡𝑎𝑙 = 12.9 cu.m.

Class A 1:2:4

Quantity of cement = 12.9 cu.m. 𝑥 9 = 116.1 bags - 40kg.

Quantity of cement = 116 bags

Quantity of sand = 12.9 cu.m. 𝑥 0.5 = 6.45 cu.m.

Quantity of sand = 6.45 cu.m.

Quantity of gravel = 12.9 cu.m. 𝑥 1 = 12.9 cu.m.

Quantity of gravel = 12.9 cu.m.

F. Beams

𝐿𝐵1: 9𝑚 𝐿 = 0.25𝑚, 𝑊𝑊 = 0.15𝑚

𝑉𝑡𝑜𝑡𝑎𝑙 = 9𝑚 𝑥 0.25𝑚 𝑥 0.15𝑚 = 0.3375 cu.m.

𝑅𝐶𝐵1: 69.5𝑚, 𝐿 = 0.3𝑚 𝑊𝑊 = 0.25𝑚

𝑉𝑡𝑜𝑡𝑎𝑙 = 69.5m x 0.3m x 0.25m = 5.2125cu.m.

𝑅𝐵1: 69.5m L = 0.25m W = 0.2m

𝑉𝑡𝑜𝑡𝑎𝑙 = 69.5 𝑥 5.2125 + 3.475 = 9.025cu.m.

Class A 1:2:4

Quantity of cement = 9.025 cu.m. 𝑥 9 = 81.225 bags - 40kg.

Quantity of cement = 81 bags

Quantity of sand = 9.025 cu.m. 𝑥 0.5 = 4.513 cu.m.


Quantity of sand = 4.513 cu.m.

Quantity of gravel = 9.025 cu.m. 𝑥 1 = 9.025 cu.m.

Quantity of gravel = 9.025 cu.m.

FORMWORKS

A. Footing

𝐿 = 1.2𝑚,𝑊𝑊 = 1.2𝑚,𝑇𝐻𝐾 = 0.35,# = 15

P = 2a+2b+4(0.05)= 2(1.2)+ 2(1.2) + 4(0.05)= 5

Total Area = Perimeter 𝑥 h 𝑥 number of pcs.

Total Area = 5 𝑥 0.35 𝑥 15 pcs. = 26.25 sq.m.

26.25 𝑠𝑞.𝑚.
Plywood = 2.88
= 9. 11 ≈ 10 𝑝𝑐𝑠.

● Let’s use the plywood 2 times:

9.11 𝑥 50% = 4.5 ≈ 5 pcs.

Quantity of Plywood: 5 pcs. - 4’𝑥 8’ 𝑥 ½” PLYWOOD

Bracing (2”𝑥 2” 𝑥 ½’ Lumber)

26.25 sq.m. 𝑥 12.71 sq.m. = 333.64 BF

333.64 𝐵𝐹.
No. of 2”𝑥 2” 𝑥 ½’= 4 𝐵𝐹/𝑝𝑐.
= 83. 41 ≈ 84𝑝𝑐𝑠.

● Let’s use the lumber 2 times:

84.31 𝑥 50% = 41.70 ≈ 42 pcs.

Quantity of Plywood: 42 pcs. - 2”𝑥 2” 𝑥12’ Lumber

B. Column Footing

𝐿 = 0.3𝑚, 𝑊𝑊 = 0.3𝑚, 𝐻 = 1.05𝑚, # = 15

P = 2a+2b+4(0.05)= 2(0.3)+ 2(0.3) + 4(0.05)= 1.4


Total Area = Perimeter 𝑥 h 𝑥 number of pcs.

Total Area = 1.4 𝑥 1.05 𝑥 15 pcs. = 22.05 sq.m.

22.05 𝑠𝑞.𝑚.
Plywood = 2.88
= 7. 65 ≈ 8 𝑝𝑐𝑠.

● Let’s use the plywood 2 times:

7. 65 𝑥 50% = 3.82 ≈ 4 pcs.

Quantity of Plywood: 4 pcs. - 4’𝑥 8’ 𝑥 ½” PLYWOOD

Bracing (2”𝑥 2” 𝑥 ½’ Lumber)

22.05 sq.m. 𝑥 12.71 sq.m. = 280.26 BF

280.26 𝐵𝐹.
No. of 2”𝑥 2” 𝑥 ½’= 4 𝐵𝐹/𝑝𝑐.
= 70. 06 ≈ 71𝑝𝑐𝑠.

● Let’s use the lumber 2 times:

70. 06 𝑥 50% = 35.03 ≈ 36 pcs.

Quantity of Plywood: 36 pcs. - 2”𝑥 2” 𝑥12’ Lumber

Scaffolding ( 2”𝑥 3” 𝑥 12’Lumber)

1.05 𝑥 15pcs = 15.75m

15.75 𝑥 7.0 = 110.25 BF

110.25 𝐵𝐹.
No. of 2”𝑥 3” 𝑥 12’= 4 𝐵𝐹/𝑝𝑐.
= 18. 38 ≈ 19𝑝𝑐𝑠.

● use it 2 times:

18. 38 𝑥 50% = 9.19 ≈ 10 pcs.

Quantity of Plywood: 10 pcs. - 2”𝑥 2” 𝑥12’ Lumber

C. Wall Footing
𝑇𝐻𝐾 = 0.25𝑚, 𝑊𝑊 = 0.4𝑚, 𝐿 = 0.4𝑚

P = 2a+2b+4(0.05)= 2(0.4)+ 2(0.4) + 4(0.05)= 1.8

Total Area = Perimeter 𝑥 h 𝑥 number of pcs.

Total Area = 1.8 𝑥 0.25 𝑥 15 pcs. = 6.75 sq.m.

6.75 𝑠𝑞.𝑚.
Plywood = 2.88
= 2. 34 ≈ 3 𝑝𝑐𝑠.

● Let’s use the plywood 2 times:

2. 34 𝑥 50% = 1.17 ≈ 2 pcs.

Quantity of Plywood: 2 pcs. - 4’𝑥 8’ 𝑥 ½” PLYWOOD

Bracing (2”𝑥 2” 𝑥 ½’ Lumber)

6.75 sq.m. 𝑥 12.71 sq.m. = 85.79 BF

85.79𝐵𝐹.
No. of 2”𝑥 2” 𝑥 ½’= 4 𝐵𝐹/𝑝𝑐.
= 21. 44 ≈ 22 𝑝𝑐𝑠.

● Let’s use the lumber 2 times:

21. 44 𝑥 50% = 10.72 ≈ 11 pcs.

Quantity of Plywood: 11 pcs. - 2”𝑥 2” 𝑥12’ Lumber

D. Column (1st Floor)

𝐿 = 0.3𝑚, 𝑊𝑊 = 0.3𝑚, 𝐻 = 3.6𝑚, # = 15

P = 2a+2b+4(0.05)= 2(0.3)+ 2(0.3) + 4(0.05)= 1.4 m

Total Area = Perimeter 𝑥 h 𝑥 number of pcs.

Total Area = 1.4 𝑥 3.6 𝑥 15 pcs. = 75.6 sq.m.

75.6 𝑠𝑞.𝑚.
Plywood = 2.88
= 26. 25 ≈ 27𝑝𝑐𝑠.

● Let’s use the plywood 2 times:


26. 25 𝑥 50% = 13. 12 ≈ 14 pcs.

Quantity of Plywood: 14 pcs. - 4’𝑥 8’ 𝑥 ½” PLYWOOD

Bracing (2”𝑥 2” 𝑥 ½’ Lumber)

75.6 sq.m. 𝑥 20.33 sq.m. = 1536.95 BF

1536.95 𝐵𝐹.
No. of 2”𝑥 2” 𝑥 ½’= 4 𝐵𝐹/𝑝𝑐.
= 384. 24 ≈ 385𝑝𝑐𝑠.

● Let’s use the lumber 2 times:

384. 24 𝑥 50% = 192.12 ≈ 193 pcs.

Quantity of Plywood: 193 pcs. - 2”𝑥 2” 𝑥12’ Lumber

Scaffolding ( 2”𝑥 3” 𝑥 12’Lumber)

3.6m 𝑥 15pcs = 54m

54 𝑥 7.0 = 378 BF

378 𝐵𝐹.
No. of 2”𝑥 3” 𝑥 12’= 6 𝐵𝐹/𝑝𝑐. = 63𝑝𝑐𝑠.

● use it 2 times:

63 𝑥 50% = 31.5 ≈ 32 pcs.

Quantity of Plywood: 32 pcs. - 2”𝑥 2” 𝑥12’ Lumber

E. Column (2nd Floor)

𝐿 = 0.3𝑚, 𝑊𝑊 = 0.3𝑚, 𝐻 = 3.75𝑚, # = 15

P = 2a+2b+4(0.05)= 2(0.3)+ 2(0.3) + 4(0.05)= 1.4 m

Total Area = Perimeter 𝑥 h 𝑥 number of pcs.

Total Area = 1.4 𝑥 3.75 𝑥 15 pcs. = 78.75 sq.m.


78.75 𝑠𝑞.𝑚.
Plywood = 2.88
= 27. 34 ≈ 28𝑝𝑐𝑠.

● Let’s use the plywood 2 times:

27. 34 𝑥 50% = 13. 67 ≈ 14 pcs.

Quantity of Plywood: 14 pcs. - 4’𝑥 8’ 𝑥 ½” PLYWOOD

Bracing (2”𝑥 2” 𝑥 ½’ Lumber)

78.75 sq.m. 𝑥 20.33 sq.m. = 1600.98 BF

1600.98 𝐵𝐹.
No. of 2”𝑥 2” 𝑥 ½’= 4 𝐵𝐹/𝑝𝑐.
= 400. 25 ≈ 401 𝑝𝑐𝑠.

● Let’s use the lumber 2 times:

400. 25 𝑥 50% = 200.12 ≈ 201 pcs.

Quantity of Plywood: 201 pcs. - 2”𝑥 2” 𝑥12’ Lumber

Scaffolding ( 2”𝑥 3” 𝑥 12’Lumber)

3.75m 𝑥 15pcs = 56.25m

56.25 𝑥 7.0 = 393.75 BF

393.75 𝐵𝐹.
No. of 2”𝑥 3” 𝑥 12’= 6 𝐵𝐹/𝑝𝑐.
= 65. 63 ≈ 66 𝑝𝑐𝑠.

● use it 2 times:

65. 63 𝑥 50% = 32.82 ≈ 33 pcs.

Quantity of Plywood: 33 pcs. - 2”𝑥 2” 𝑥12’ Lumber

F. Beams
1. RCB1

𝐿 = 0.3𝑚 𝑊𝑊 = 0.25𝑚

1. 4m – 8pcs
0.3𝑚 0.3𝑚
L= 4- 2
- 2
= 3.7m

P = 2a+2b+4(0.05)= 2(0.3)+ 0.25 + 0.1= 0.95 m

Total Area = Perimeter 𝑥 h 𝑥 number of pcs.

Total Area = 0.95𝑥 3.7 𝑥 32 pcs. = 112.48 sq.m.

112.48 𝑠𝑞.𝑚.
Plywood = 2.88
= 19. 53 ≈ 20𝑝𝑐𝑠.

Quantity of Plywood: 20 pcs. - 4’𝑥 8’ 𝑥 ½” PLYWOOD

Bracing (2”𝑥 2” 𝑥 ½’ Lumber)

112.48 sq.m. 𝑥 18.66 sq.m. = 2098.88 BF

2098.88 𝐵𝐹.
No. of 2”𝑥 2” 𝑥 ½’= 4 𝐵𝐹/𝑝𝑐.
= 524. 72 ≈ 525 𝑝𝑐𝑠.

● Let’s use the lumber 2 times:

524. 72 𝑥 50% = 262.36 ≈ 263 pcs.

Quantity of Plywood: 263 pcs. - 2”𝑥 2” 𝑥12’ Lumber

Scaffolding ( 2”𝑥 3” 𝑥 12’Lumber)

4m 𝑥 8pcs = 32m

32 𝑥 6.0 = 192 BF

192 𝐵𝐹.
No. of 2”𝑥 3” 𝑥 12’= 6 𝐵𝐹/𝑝𝑐. = 32𝑝𝑐𝑠.

● use it 2 times:

32 𝑥 50% = 31.5 ≈ 16 pcs.

Quantity of Plywood: 16 pcs. - 2”𝑥 2” 𝑥12’ Lumber

2. 3m – 10pcs
0.3𝑚 0.3𝑚
L= 3- 2
- 2
= 2.7m

P = 2a+2b+4(0.05)= 2(0.3)+ 0.25 + 0.1= 0.95 m

Total Area = Perimeter 𝑥 h 𝑥 number of pcs.

Total Area = 0.95𝑥 2.7 𝑥 30 pcs. = 76.95 sq.m.

76.95 𝑠𝑞.𝑚.
Plywood = 2.88
= 26. 718 ≈ 27𝑝𝑐𝑠.

● Let’s use the lumber 2 times:

26. 718 𝑥 50% = 13.35 ≈ 14 pcs.

Quantity of Plywood: 14 pcs. - 2”𝑥 2” 𝑥12’ Lumber

Bracing (2”𝑥 2” 𝑥 ½’ Lumber)

76.95 sq.m. 𝑥 18.66 sq.m. = 1435.88 BF

1435.88 𝐵𝐹.
No. of 2”𝑥 2” 𝑥 ½’= 4 𝐵𝐹/𝑝𝑐.
= 358. 97 ≈ 359 𝑝𝑐𝑠.

● Let’s use the lumber 2 times:

359 𝑥 50% = 179. 49 ≈ 180 𝑝𝑐𝑠.

Quantity of Plywood: 180 pcs. - 2”𝑥 2” 𝑥12’ Lumber

Scaffolding ( 2”𝑥 3” 𝑥 12’Lumber)

3m 𝑥 10pcs = 30m

30 𝑥 6.0 = 180 BF

180 𝐵𝐹.
No. of 2”𝑥 3” 𝑥 12’= 6 𝐵𝐹/𝑝𝑐. = 30𝑝𝑐𝑠.

● use it 2 times:

30 𝑥 50% = 15 pcs.
Quantity of Plywood: 15 pcs. - 2”𝑥 2” 𝑥12’ Lumber

3. 2.5m - 3pcs

0.3𝑚 0.3𝑚
L= 2.5- 2
- 2
= 2.2m

P = 2a+2b+4(0.05)= 2(0.3)+ 0.25 + 0.1= 0.95 m

Total Area = Perimeter 𝑥 h 𝑥 number of pcs.

Total Area = 0.95𝑥 2.2 𝑥 7.5 pcs. = 15.675 sq.m.

15.675 𝑠𝑞.𝑚.
Plywood = 2.88
= 5. 443 ≈ 6 𝑝𝑐𝑠.

● Let’s use the lumber 2 times:

5. 443 𝑥 50% = 2.72 ≈ 3 pcs.

Quantity of Plywood: 3 pcs. - 2”𝑥 2” 𝑥12’ Lumber

Bracing (2”𝑥 2” 𝑥 ½’ Lumber)

15.675 sq.m. 𝑥 18.66 sq.m. = 292.50 BF

292.50 𝐵𝐹.
No. of 2”𝑥 2” 𝑥 ½’= 4 𝐵𝐹/𝑝𝑐.
= 73. 125 ≈ 74 𝑝𝑐𝑠.

● Let’s use the lumber 2 times:

73. 125 𝑥 50% = 36. 56 ≈ 37 𝑝𝑐𝑠.

Quantity of Plywood: 37 pcs. - 2”𝑥 2” 𝑥12’ Lumber

Scaffolding ( 2”𝑥 3” 𝑥 12’Lumber)

2.5m 𝑥 3pcs = 7.5m

7.5 𝑥 6.0 = 45 BF

45 𝐵𝐹.
No. of 2”𝑥 3” 𝑥 12’= 6 𝐵𝐹/𝑝𝑐. = 7. 5 ≈ 8 𝑝𝑐𝑠.
● use it 2 times:

7. 5 𝑥 50% = 3.75 ≈ 4 𝑝𝑐𝑠.

Quantity of Plywood: 4 pcs. - 2”𝑥 2” 𝑥12’ Lumber

2. RB1

1. 4m-8pcs

L = 0.25m W = 0.2m

L= 3.75m

P = 2a+2b+4(0.05)= 2(0.25)+ 0.2 + 0.1= 0.8 m

Total Area = Perimeter 𝑥 h 𝑥 number of pcs.

Total Area = 3.75 𝑥 0.8𝑥 32 pcs. = 96 sq.m.

96 𝑠𝑞.𝑚.
Plywood = 2.88
= 16. 67 ≈ 17 𝑝𝑐𝑠.

● Let’s use the lumber 2 times:

5. 443 𝑥 50% = 2.72 ≈ 3 pcs.

Quantity of Plywood: 3 pcs. - 2”𝑥 2” 𝑥12’ Lumber

Bracing (2”𝑥 2” 𝑥 ½’ Lumber)

96 sq.m. 𝑥 18.66 sq.m. = 1719.3648 BF

1719.3648 𝐵𝐹.
No. of 2”𝑥 2” 𝑥 ½’= 4 𝐵𝐹/𝑝𝑐.
= 429. 84 ≈ 430 𝑝𝑐𝑠.

● Let’s use the lumber 2 times:

1791. 36 𝑥 50% = 223. 92 ≈ 224 𝑝𝑐𝑠.

Quantity of Plywood: 224 pcs. - 2”𝑥 2” 𝑥12’ Lumber

Scaffolding ( 2”𝑥 3” 𝑥 12’Lumber)


4m 𝑥 8pcs = 32m

32 𝑥 6.0 = 192 BF

192 𝐵𝐹.
No. of 2”𝑥 3” 𝑥 12’= 6 𝐵𝐹/𝑝𝑐. = 32 𝑥 80% ≈ 25. 6 ≈ 26 𝑝𝑐𝑠.

● use it 2 times:

25. 6 𝑥 50% = 12.8 ≈ 13 𝑝𝑐𝑠.

Quantity of Plywood: 13 pcs. - 2”𝑥 2” 𝑥12’ Lumber

2. 3m-10pcs

𝐿 = 2.75𝑚, 𝑊𝑊 = 0.25𝑚, 𝐻 = 0.2𝑚, # = 10

P = 0.8

Total Area = Perimeter 𝑥 h 𝑥 number of pcs.

Total Area = 2.75 𝑥 0.8 𝑥 10 pcs. = 66 sq.m.

66 𝑠𝑞.𝑚.
Plywood = 2.88
𝑥 50% = 11. 46 ≈ 12𝑝𝑐𝑠.

Quantity of Plywood: 12 pcs. - 4’𝑥 8’ 𝑥 ½” PLYWOOD

Bracing (2”𝑥 2” 𝑥 ½’ Lumber)

66 sq.m. 𝑥 18.66 sq.m. = 1231.56 BF

1231.56 𝐵𝐹.
No. of 2”𝑥 2” 𝑥 ½’= 4 𝐵𝐹/𝑝𝑐.
𝑥 50% = 153. 95 ≈ 154 𝑝𝑐𝑠.

Quantity of Plywood: 154 pcs. - 2”𝑥 2” 𝑥12’ Lumber

Scaffolding ( 2”𝑥 3” 𝑥 12’Lumber)


3m 𝑥 10pcs = 30m

30 𝑥 6 = 180 BF

180 𝐵𝐹.
No. of 2”𝑥 3” 𝑥 12’= 6 𝐵𝐹/𝑝𝑐. 𝑥 50% = 15 𝑝𝑐𝑠.

Quantity of Plywood: 15 pcs. - 2”𝑥 2” 𝑥12’ Lumber

3. 2.5m - 3pcs

𝐿 = 2.25𝑚, 𝑊𝑊 = 0.25𝑚, 𝐻 = 0.2𝑚, # = 3

P = 0.8

Total Area = Perimeter 𝑥 h 𝑥 number of pcs.

Total Area = 2.25 𝑥 0.8 𝑥 10 pcs. = 13.5 sq.m.

13.5 𝑠𝑞.𝑚.
Plywood = 2.88
𝑥 50% = 3𝑝𝑐𝑠.

Quantity of Plywood: 3 pcs. - 4’𝑥 8’ 𝑥 ½” PLYWOOD

Bracing (2”𝑥 2” 𝑥 ½’ Lumber)

13.5 sq.m. 𝑥 18.66 sq.m. = 251.91 BF

2591.91 𝐵𝐹.
No. of 2”𝑥 2” 𝑥 ½’= 4 𝐵𝐹/𝑝𝑐.
𝑥 50% = 32 𝑝𝑐𝑠.

Quantity of Plywood: 32pcs. - 2”𝑥 2” 𝑥12’ Lumber

Scaffolding ( 2”𝑥 3” 𝑥 12’Lumber)

2.5m 𝑥 3pcs = 7.5m

7.5 𝑥 6 = 45BF
45𝐵𝐹.
No. of 2”𝑥 3” 𝑥 12’= 6 𝐵𝐹/𝑝𝑐. 𝑥 50% = 3. 75 ≈ 4 𝑝𝑐𝑠.

3. LB1 (3m - 3pcs)

𝐿 = 2.75𝑚, 𝑊𝑊 = 0.25𝑚, 𝐻 = 0.15𝑚, # = 3

P = 0.8

Total Area = Perimeter 𝑥 h 𝑥 number of pcs.

Total Area = 2.75 𝑥 0.8 𝑥 3 pcs. = 19.8 sq.m.

19.8 𝑠𝑞.𝑚.
Plywood = 2.88
𝑥 50% = 4𝑝𝑐𝑠.

Quantity of Plywood: 4 pcs. - 4’𝑥 8’ 𝑥 ½” PLYWOOD

Bracing (2”𝑥 2” 𝑥 ½’ Lumber)

19.8 sq.m. 𝑥 18.66 sq.m. = 369.47BF

369.47 𝐵𝐹.
No. of 2”𝑥 2” 𝑥 ½’= 4 𝐵𝐹/𝑝𝑐.
𝑥 50% = 47 𝑝𝑐𝑠.

Quantity of Plywood: 47pcs. - 2”𝑥 2” 𝑥12’ Lumber

Scaffolding ( 2”𝑥 3” 𝑥 12’Lumber)

3m 𝑥 3pcs = 9m

9 𝑥 6 = 54BF

54𝐵𝐹.
No. of 2”𝑥 3” 𝑥 12’= 6 𝐵𝐹/𝑝𝑐. 𝑥 50% = 4. 5 ≈ 5 𝑝𝑐𝑠.
REINFORCEMENT:

Footing:

L= 1200mm, W= 1200mm, Ø= 16mm, Cover= 75mm

1200mm - 75mm - 75mm + 256mm + 256mm = 1562 mm or 1.562m

Along direction of length x-axis:

# of cut bars =

Along direction of y-axis:

# of cut bars =

Total pcs: 16 pcs × 15 footings = 240 pcs

Using 9 meters commercial length:

Computing wastage:

9m - (5 × 1.56) = 1.2 m

How many 9m to order?

(48 pcs - 9m × 16mm Ø)


Tie wires

# Of intersections: 8 × 8 = 64

Total intersection for 15 footings: 15 × 64 = 960

Total length of the tie wire: 960 × 0.4 = 384m

Tie wire in kilogram:

(7.25kg of G.I. Tie Wire #16)

Wall footing

L= 400mm, W= 400mm, Ø= 16mm, Cover= 75mm

400mm - 75mm - 75mm + 100mm + 100mm = 450 mm or 0.450m

Along direction of length-axis:

# of cut bars =

Along direction of y-axis:

# of cut bars =

Total pcs: 6 pcs × 15 footings = 90 pcs

Using 9 meters commercial length:

Computing wastage:
9m - (20 × 0.45) = 1.2 m

How many 9m to order?

(5 pcs - 6m × 12mm Ø)

Tie wires

# Of intersections: 3 × 3 = 9

Total intersection for 15 footings: 15 × 9 = 135

Total length of the tie wire: 135 × 0.3 = 40.5m

Tie wire in kilogram:

(0.76kg of G.I. Tie Wire #16)

Columns

L= 300mm, W= 300mm, Ø= 16mm, 8pcs - 16mm Ø

l Set 1 = 1 - 16mm Ø × 6m

l Set 2 = 2 - 16mm Ø × 7.5m

Per columns:

4pcs - 16mm Ø × 6m

8pcs - 16mm Ø × 7.5m

For 15 columns:
4 × 15 = 60 pcs - 16mm Ø × 6m

8 × 15 = 120 pcs - 16mm Ø × 7.5m

Lateral and cross tie:

10mm Ø , L = 300mm, W = 300mm, Hook length = 90mm

x = 300mm - 75mm - 75mm = 150mm

y = 300mm - 75mm - 75mm = 150mm

Lateral tie length:

150 + 150 + 150 +150+ 90 + 90 = 780mm or 0.78m

Max spacing: 300mm

23 pcs × 15 columns = 345pcs - 10mm Ø × 9m

Using a 9m commercial length

400mm - 75mm - 75mm + 100mm + 100mm = 450 mm or 0.450m

Along direction of length x-axis:

# of cut bars =

Along direction of y-axis:


# of cut bars =

Total pcs: 6 pcs × 15 footings = 90 pcs

Using 9 meters commercial length:

Computing wastage:

9m - (11 × 0.78) = 0.42 m

How many 9m to order?

(5 pcs - 6m × 12mm Ø)

Tie wires

Total length of the tie wire: 345 × 0.3 = 103.5m

Tie wire in kilogram:

(1.95kg of G.I. Tie Wire #16)

Beams

RCB1: W = 250mm. L = 300mm, cover = 40mm, 8- 16mm Ø

1. 4m - 8pcs

Bar length = 4000mm + 300mm + 300mm + 256mm + 256mm-40mm - 40mm


= 5032mm or 5.032m

Total pcs = 8 × 8 = 64 pcs


Using 6m: : = 64 pcs -

(64pcs - 16mm Ø × 6m)

2. 3m - 10pcs

Bar length = 3000mm + 300mm + 300mm + 256mm + 256mm-40mm - 40mm


= 4032mm or 4.032m

Total pcs = 8 × 10 = 80pcs

Using 9m: : = 40 pcs -

(40pcs - 16mm Ø × 9m)

3. 2.5m - 3pcs

Bar length = 2500mm + 300mm + 300mm + 256mm + 256mm-40mm - 40mm


= 3532mm or 3.532m

Total pcs = 8 × 3 = 24pcs

Using 7.5m: : = 12pcs

(12pcs - 16mm Ø × 7.5m)

LB1: L = 250mm, W = 150mm, Cover = 40mm, 4 - 12mm Ø

1. 3m - 3pcs

Bar length = 3000mm + 300mm + 300mm + 256mm + 256mm - 40mm -


40mm = 4032mm or 4.032m

Total pcs= 4 × 3 = 12pcs

Using 9m:

6pcs - 12mm Ø × 9m
RB1: L= 250mm, W = 200mm, Cover = 40mm, 6 - 12mm Ø

1. 4m - 8pcs

Bar length = 4000mm + 300mm + 300mm + 256mm + 256mm - 40mm -


40mm = 5032mm or 5.032m

Total pcs= 8 × 8 = 64 pcs

Using 6m:

64pcs - 16mm Ø × 6m

2. 3m - 10pcs

Bar length = 3000mm + 300mm + 300mm + 256mm + 256mm - 40mm -


40mm = 4032mm or 4.032m

Total pcs= 8 × 10 = 80pcs

Using 9m:

40pcs - 16mm Ø × 9m

3. 2.5m - 3pcs

Bar length = 2500mm + 300mm + 300mm + 256mm + 256mm - 40mm -


40mm = 3532mm or 3.532m

Total pcs= 8 × 3 = 24pcs

Using 7.5m:

12pcs - 16mm Ø × 7.5m

LB1: L = 250mm, W = 150mm, Cover = 40mm, 4 - 12mm Ø

1. 3m - 3pcs
Bar length = 3000mm + 300mm + 300mm + 256mm + 256mm - 40mm -
40mm = 4032mm or 4.032m

Total pcs= 4 × 3 = 12pcs

Using 9m:

6pcs - 12mm Ø × 9m

RB1: L= 250mm, W = 200mm, Cover = 40mm, 6 - 12mm Ø

1. 4m - 8pcs

Bar length = 4000mm + 300mm + 300mm + 256mm + 256mm - 40mm -


40mm = 5032mm or 5.032m

Total pcs= 6 × 8 = 48pcs

Using 6m:

48pcs - 12mm Ø × 6m

2. 3m - 10pcs

Bar length = 3000mm + 300mm + 300mm + 256mm + 256mm - 40mm -


40mm = 4032mm or 4.032m

Total pcs= 6 × 10 = 60pcs

Using 9m:

30pcs - 16mm Ø × 9m

3. 2.5m - 3pcs

Bar length = 2500mm + 300mm + 300mm + 256mm + 256mm - 40mm -


40mm = 3532mm or 3.532m

Total pcs= 6 × 3 = 18pcs


Using 7.5m:

9pcs - 16mm Ø × 7.5m

TOTAL ESTIMATION:

1. 64pcs – 16mm Ø x 6m
2. 48pcs – 12mm Ø x 6m
3. 12pcs – 16mm Ø x 7.5m
4. 9 pcs – 12mm Ø x 7.5m
5. 36 pcs – 12mm Ø x 9m
6. 40pcs – 16mm Ø x 9m

BEAMS STIRRUPS

Stirrups= 10mm Ø

RCB1: W = 250mm. L = 300mm, cover = 40mm, 8- 16mm Ø

1. 4m - 8pcs

Hook length = 90mm

x = 250mm - 40mm - 40mm = 170mm

y = 300mm - 40mm - 40mm = 220mm

Stirrups length = 170mm + 170mm + 220mm + 220mm + 90mm + 90mm =


960mm or 0.90m

Spacing:
Effective depth = 300mm - 40mm - 10mm - 8mm = 242mm or 0.242m

Max spacing:

# of stirrups =

Total stirrups = 34 pcs × 8 = 272 pcs

Using 6m: :

46 pcs - 10mm Ø × 6m

2. 3m - 10pcs

Hook length = 90mm

x = 250mm - 40mm - 40mm = 170mm

y = 300mm - 40mm - 40mm = 220mm

Stirrups length = 170mm + 170mm + 220mm + 220mm + 90mm + 90mm =


960mm or 0.96m

Spacing:

Effective depth = 300mm - 40mm - 10mm - 8mm = 242mm or 0.242m

Max spacing:

# of stirrups =

Total stirrups = 26 pcs × 10 = 260 pcs

Using 6m: :

44 pcs - 10mm Ø × 6m

3. 2.5m - 10pcs

Hook length = 90mm


x = 250mm - 40mm - 40mm = 170mm

y = 300mm - 40mm - 40mm = 220mm

Stirrups length = 170mm + 170mm + 220mm + 220mm + 90mm + 90mm =


960mm or 0.90m

Spacing:

Effective depth = 300mm - 40mm - 10mm - 8mm = 242mm or 0.242m

Max spacing:

# of stirrups =

Total stirrups = 22 pcs × 3 = 66 pcs

Using 6m: :

11 pcs - 10mm Ø × 6m

LB1: W = 150mm. L = 250mm, cover = 40mm, Main bar - 4- 12mm Ø,


stirrups - 10mm Ø

1. 3m - 3pcs

Hook length = 90mm

x = 150mm - 40mm - 40mm = 70mm

y = 250mm - 40mm - 40mm = 170mm

Stirrups length = 70mm + 70mm + 170mm + 170mm + 90mm + 90mm =


660mm or 0.660m

Spacing:

Effective depth = 250mm - 40mm - 10mm - 6mm = 194mm or 0.194m

Max spacing:
# of stirrups =

Total stirrups = 32 pcs × 3 = 96 pcs

Using 6m: :

11 pcs - 10mm Ø × 6m

RB1: W = 200mm. L = 250mm, Main bar - 6m- 12mm Ø

1. 4m - 8pcs

Hook length = 90mm

x = 200mm - 40mm - 40mm = 120mm

y = 250mm - 40mm - 40mm = 170mm

Stirrups length = 120mm + 120mm + 170mm + 170mm + 90mm + 90mm =


760mm or 0.760m

Spacing:

Effective depth = 250mm - 40mm - 10mm - 6mm = 194mm or 0.194m

Max spacing:

# of stirrups =

Total stirrups = 42 pcs × 8 = 336 pcs

Using 6m: :

48 pcs - 10mm Ø × 6m

2. 3m - 10pcs

Hook length = 90mm

x = 200mm - 40mm - 40mm = 120mm


y = 250mm - 40mm - 40mm = 170mm

Stirrups length = 120mm + 120mm + 170mm + 170mm + 90mm + 90mm =


760mm or 0.760m

Spacing:

Effective depth = 250mm - 40mm - 10mm - 6mm = 194mm or 0.194m

Max spacing:

# of stirrups =

Total stirrups = 32 pcs × 10 = 320 pcs

Using 6m: :

46 pcs - 10mm Ø × 6m

3. 2.5m - 3pcs

Hook length = 90mm

x = 200mm - 40mm - 40mm = 120mm

y = 250mm - 40mm - 40mm = 170mm

Stirrups length = 120mm + 120mm + 170mm + 170mm + 90mm + 90mm =


760mm or 0.760m

Spacing:

Effective depth = 250mm - 40mm - 10mm - 6mm = 194mm or 0.194m

Max spacing:

# of stirrups =

Total stirrups = 27 pcs × 3 = 81 pcs


Using 6m: :

12pcs - 10mm Ø × 6m

Total estimation:

RCB1 = 598pcs × 8 = 4784 pcs

LB1 = 96 pcs × 4 = 384 pcs

RB1 = 737 × 6 = 4422 pcs

Total pcs: 9590 pcs

Total length = 9590 × 0.30m = 2877m

2788𝑚
Tiewire in kg: 53𝑘𝑔/𝑚
= 54. 28𝑘𝑔

You might also like