Costing Project PDF
Costing Project PDF
Costing Project PDF
A
PROJECT REPORT
ON
“CONTRACT COSTING”
FOR
ARK ASSOCIATES ENGINEERS CONTRACTORS, AHMEDNAGAR
SUBMITED BY
MISS. POKHARNA NIKITA MAHAVIR
PEMRAJ SARDA COLLEGE
AHMEDNAGAR
2022-23
2
DECLARATION
Acknowledgement
GUIDE CERTIFICATE
MAY-2023
MRS.PRIYA SARDA MAM
PROJECT GUIDE
5
9 BIBLIOGRAPHY 52-53
10 QUESTIONAIRE 54-56
7
CONTRACT
COSTING
8
1. INTRODuCTION
9
Contract
Meaning
A contract is a legally binding agreement. The term ‘contract’ has been defined by
various authors in different ways. Some of the definitions are given below:
(1) 3)According to sir William Anson, “ a contract is a legally binding agreement
between two or more person by which rights acquired by one or more to acts
or forbearances on the part of the other or others . “
(2) According to section 2(h) of the Indian contract act, “an agreement
enforceable by law is a contract.” This definition is based on Pollock’s
definition.
If we analyses the above definitions of the contract, given in section 2(h) of the
Indian contract act, we can say with conviction that a contract must have following
two elements.
(1) An agreement , and
(2) Enforceability of an agreement, we may put it as under:
Contract = an agreement + enforceable by law
10
Costing
Meaning
Computation of cost on scientific basis and thereafter cost control and cost reduction has
become of Paramount importance. Hence it has become essential to study the basic
principles and concepts of cost Accounting. These are discussed in the subsequent
paragraphs.
As compared to the financial accounting, the focus of cost accounting is different. In the
modern days of Cut throat competition, any business organization has to pay attention
towards their cost of production.
Cost
Meaning
According to ICMA London, Cost can be defined as the expenditure (actual or notional)
incurred on or attributable to a given thing. It can also be described as the resources that
have been sacrificed or must be sacrificed to attain a particular objective. In other words,
cost is the amount of resources used for something which must be measured in terms of
money. For example – Cost of preparing one cup of tea is the amount incurred on the
elements like material, labor and other expenses; similarly cost of offering any services like
banking is the amount of expenditure for offering that service.
Thus cost of production or cost of service can be calculated by ascertaining the resources
used for the production or services.
11
Costing
Meaning
According to ICMA London, Costing may be defined as, ‘the technique and process of
ascertaining costs’. According to Weldon, ‘Costing is classifying, recording, allocation and
appropriation of expenses for the determination of cost of products or services and for the
presentation of suitably arranged data for the purpose of control and guidance of
management. It includes the ascertainment of every order, job, contract, process, service
units as may be appropriate. It deals with the cost of
Production, selling and distribution.
If we analyze the above definitions, it will be understood that costing is basically the
procedure of ascertaining the costs. As mentioned above, for any business organization,
ascertaining of costs is must and for this purposes a scientific procedure should be followed.
‘Costing’ is precisely this Procedure which helps them to find out the costs of products or
services.
The procedure of ascertaining costs. As mentioned above, for any business organization,
ascertaining of costs is must and for this purpose a scientific procedure should be followed.
‘Costing’ is precisely this procedure which helps them to find out the costs of products or
services.
12
Contract costing
Meaning
“Contract or terminal costing is adopted by those business undertakings which undertake
definite contract which take long period of time to complete e.g. builders and contractors,
civil engineering firms, ship building companies etc.”
The same principles of job costing are applicable to contract costing. The cost are
ascertained and analyzed with respect to the contract expected for execution. this method
of costing is adopted by those concern undertaking definite contracts e.g. builders ,
contractors and civil engineers who undertake long term projects like construction of roads ,
bridges , houses , large estates , irrigation schemes etc. it is also being adopted by the
concerned where the unit output is heterogeneous e.g. ship building companies , turbines
and boilers manufacturing companies , motion pictures etc. the operation of contract
costing is comparatively simpler than job costing
Contract costing is a type of job costing in which a contact costing constitutes a unit of cost.
It is further development of the job costing. In this method it is desired to find cost of
carrying out a complete contract for a customer involving numerous jobs and batches of
jobs.
13
2.COMpANy
pROFIlE
14
COMPANY PROFILE
NAME OF FIRM : ARK ASSOCIATES ENGINEERS
CONTRACTORS
MOBILE NO : 9503367444
3.ObjECTIvES OF
STuDy
16
The objectives of the different things are the different. So, it is necessary to define the objective of the study
before doing the study. The objective of the study of the contract costing are stated as follows,
(1) To understand how contract cost is ascertained-the next and the most important point or objective of
the study of contract costing is that to understand how the cost of a contract is calculated in the
contract costing.
(2) To be familiarized with the term-The first and the most important objective of the study of the
contract costing is to be familiarized with the work done in the contract related to the contract
costing
(3) To study how cost are apportion in the contract- apportionment of the cost of a whole thing to a
certain particular thing is very important in the contract costing, so it is very important to study how
the cost are apportioned in the contract costing.
(4) To study how cost are allocated in the contract- allocation of the cost of a whole thing to a certain
particular thing is very important in the contract costing, so it is very important to study how the cost
are allocated in the contract costing
(5) To find out that the firm follows the DSR rules given by the government or not in his actual practice.
(6) To study how the apportionment of the profit on incomplete contract is done- apportionment of the
profit on the incomplete contract is very difficult to be apportioned according to the accounting year
.so, it is very important objective of the study of the contract costing is to have the familiarize with
how the profit of the contract is apportioned according to the accounting period in which they are
commenced.
17
4 RESEARCH
METHODOlOGy
18
(3) Observation
Observation is the main sources of data collection for contract costing .because
there is something which cannot be asked or answered. By having observation in the
company I tried to find out the actual procedure and mental thinking of the person
doing contract costing.
Secondary Data Collection
The secondary data is collected from different literature related to the subject like books,
hand books and pamphlet, in-house journals. The data collected is interpreted by scale wise.
The secondary was used to study and understand the terminologies used in the contract
costing .to have better and in depth understanding of the subject of the project. The
methods used for collecting the secondary data are as follows,
(1) Reference Of Library
The various books available in the library related to the topic of contract costing are
referred to have in depth knowledge of the subject matter and to make the study in
the perfect manner of the project.
5.REvIEw OF
lITERATuRE
20
METHODS OF COSTING
process
job costing
costing
PROCESS
JOB COSTONG
COSTING
BATCH OPRETING
COSTING COSTING
CONTRACT
COSTING OPRETION
COSTING
OUTPUT OR
MULTIPEL
SINGLE
COSTING
COSTING
22
Methods of Costing
Basically, there are two methods of cost ascertainment viz. job costing and process costing. The remaining
methods costing are either the variants of this basic methods or techniques of cost accumulation used
specifically for a particular purpose.
(A)Job Costing:
It is concerned with the costing of job that are made to a customer’s particular requirements. It is
applicable where individual jobs are identifiable and each of the jobs becomes a cost centre. It is used
when non standard jobs are made according to customer specifications.
(B)Batch Costing:
This method of costing is used where similar or identical products are manufactured in definite batches
and held in stock for assembling process or for sell to customer.
(C)Contract Costing:
This method aims to find the cost of carrying out a complete contract for a customer probably involving
numerous jobs and batches of jobs. It is used in undertaking carrying out building or constructional
contract.
(D)Multiple Costing:
It relates to system used in such business which makes a variety of goods. These goods differed both in
value and in kind and I the number of variety of the processes necessary for completion. It is used in
automobile industries which produce numbers of components to be subsequently assembled into a final
product.
(E)Process Costing:
It is the method of costing where by cost incurred for process are collected according to the period of time
and are divided by the production of that period. It is employed in cases where there is a variety of
process or operation before a finished product is turn out and where it is necessary to find out cost of
each variety of operations. It is particularly necessary whereby products occurred or where one article out
of batch losses its identity during the process of manufactured.
(G)Operation Costing:
This form of process costing is used in case of mechanical products involved in production process of
continuous and repetitive nature, consisting of number of operation. Under this method, costs are
ascertained and analyses with respect to each and every operation carried out, treating every operation as
a separate cost centre.
23
(I)Operating Costing:
It is essential method of costing where only the services are rendered. It ascertains the cost of a one unit
of service rendered, e.g. railways, hospitals, hotels, schools, colleges, etc.
Contract Costing
Introduction
Contract costing is a type of job costing in which a contact costing constitutes a unit of cost.
It is further development of the job costing. In this method it is desired to find cost of
carrying out a complete contract for a customer involving numerous jobs and batches of
jobs.
The cost are ascertained and analyzed with respect to the contract expected for execution.
this method of costing is adopted by those concern undertaking definite contracts e.g.
builders , contractors and civil engineers who undertake long term projects like construction
of roads , bridges , houses , large estates , irrigation schemes etc. it is also being adopted by
the concerned where the unit output is heterogeneous e.g. ship building companies ,
turbines and boilers manufacturing companies , motion pictures etc. the operation of
contract costing is comparatively simpler than job costing . Under this method individual
numbers are given against each contract undertaken and a separate ledger account is
opened for the purpose of finding of the profit or loss for the same. As the major part of the
network perform on each contract is done on the side of itself, particularly most of the
expenses are direct in nature and are charged to the contract as and when they are
incurred. The indirect expenses such office and administrative expenses are very small in
amount and are recovered on the reasonable bases such as percentage of direct material,
direct wages or of prime cost the principle applied are the same as those used in job costing,
except that certain modification are made to suit the specific requirements of the contracts.
Thus, the accumulation analysis, apportionment, allocation and control of cost are more
simplified in this method of costing.
Meaning
Contract costing is a type of job costing in which a contact costing constitutes a unit of cost.
It is further development of the job costing. In this method it is desired to find cost of
carrying out a complete contract for a customer involving numerous jobs and batches of
jobs.
“ contract or terminal costing is adopted by those business undertakings which undertake
definite contract which take long period of time to complete e.g. builders and contractors ,
civil engineering firms , ship building companies etc. “
The same principles of job costing are applicable to contract costing.
24
Accounting Procedure
A contract ledger is kept in which a separate account for each contracts opened. A
contract is known by number allotted to it e.g. contract no. 41, contract no. 42 etc. the
recording procedure for the following items may be noted carefully:
Materials
Materials required for the contract may be received from the following sources:
Value of material stolen or destroyed by fire is debited to profit and loss A/c. and credited to
contract A/c. similarly any profit/loss on sale of materials is shown in contract A/c
separately.
In case of any compensation received from insurance company for loss of materials, the
amount due from the insurance company is shown in the balance sheet. The loss which is
not compensated is debited to profit and loss A/c.
Direct Labour
Generally, the cost of labour working at the contract Is direct charge to the contract.
Otherwise a wage analysis sheet should be prepared wherein particulars of the daily or
weekly time sheets should be entered. The total labour cost alone with labour cost
outstanding at the end of the accounting period should be debited to the contract A/c.
salary of supervisory staff is apportioned on equitable basis. Wages accrued will also be
debited to the contract account.
Direct Expenses
The expenses incurred for a particular contract only are direct expenses and charge directly
to that contract.
The contract account is debited with such expenses distributed on several contracts on
some suitable basis such as percentage of materials or labour etc.
26
Contract A/c.
Year Particulars Rs. Year Particulars Rs.
1990 1990 By loss by accident Xx
jan.1 To plant issued to site Xx dec.31 By value of plant Xx
To profit on sale of Xx returned’ Xx
plant _ By sale of plant
Xx
1991 To plant b/d By value of plant
(b)Contract account is debited with depreciation only calculated at the rate mentioned.
Where a certain plant is used on several contracts simultaneously then for the period which
the plant is used is ascertained and depreciation is calculated on time basis or when certain
plant is used for a few days or few hours only e.g. cranes, then depreciation is calculated on
hourly rate basis and the contract account is debited with depreciation.
Sub Contract Cost
A contractor may not be expert in all the work e.g. installation of lift, electrical fittings, door
fittings, etc. which may be passed on by main contractors. Such sub contract costs are
treated as direct cost and recorded on the debit side of the contract account.
Extra Work Done
When extra work or variation of work originally contracted for is required to bedone, such
additional work is subjected to a separate charge,
(a)If the extra work is substantial, it should be treated as a separate contract and a separate
account should be opened for it.
(b) If the extra work done is not substantial the cost of such work is debited to contract
account and the extra amount which the contractee has agreed to pat should be added to
contract price.
Escalation Clause
The clause is provided in the contract to cover up any changes in the price of the material,
labour etc. since, the contract takes more than one year to complete, the object of the
incorporating this clause is to safeguard the interest of both the parties against unfavorable
changes in the prices. The contractor has to produce sufficient proof of excess cost before
the customer agrees to reimburse such cost. The contractor is entitled to increase the
contract price if cost increases beyond a certain specified percentage. This clause is of
important especially when the price of material and labour are likely to be increased or
where it is difficult to estimate accurately the quantity of material and labour time.
The de-escalation clause may be inserted in the agreement to take care of the interest of
the contractee. It provides for downward revision of the contract price in case cost goes
down beyond a certain agreed level.
28
(5) When incomplete contract A/c shows loss, the entire amount of loss is transferred
(debited) to profit/loss A/c. irrespective of the stage of completion.
(6) For the contracts which are almost complete :
In this case, the estimated profit is ascertained by deducting the aggregate of the
costs to date and additional expenditure to complete the contract from the contract
price. A portion of this estimated profit is credited to P/L A/c.
This portion may be calculated by adopting any one of the following formula:
a) Estimated profit x work certified/contract price
b) Estimated profit x work certified/contract price x cash received/work certified
OR
Estimated profit x cash received /contract price
c) Estimated profit x cost till date/estimated total cost
d) Estimated profit x cost till date/estimated total cost x cash received/work
certified
32
Architect Certificate
In case of large contracts which take a long period, it is normal practice for the contractor to
get interim advance payments against the actual portion of contract completed by him. The
contractee appoints the architect or surveyor or engineer who works as a technical assessor
and issues the certificate as to the value of work so performed. Thus, as per the contract
agreement the periodical payment is made to the contractor on the basis of such architects
certificate.
33
Xx Xx
Dr. Cr.
Note: in the final year or when the contract is complete, then instead of W.I.P. A/c. we have
contractee`s A/c. (at contract price) on the credit side of contract A/c.
34
Contractee`s A/c
Rs. Rs.
To contract A/c. ( work Xx By cash/bank A/c. Xx
certified) _ By balance c/d Xx
Xx Xx
Contractee`s A/c.
year Rs. Year Rs.
1 To balance c/d xx 1 By bank/cash A/c. xx
Defective Work:
If the work done by the contractor is defective it will not be paid by the contractee. Cost of
rectification such defective work is debited to the contract A/c.
35
Rs. Rs.
To loss by accident Xx By contract A/c.(profit) Xx
To depreciation on plant at stores Xx By profit on sale of assets Xx
building Xx
To general expenses Xx
To loss on sale of assets Xx
To net profit Xx Xx
Xx Xx
36
6.DATA
ANAlySIS AND
INTERpRETATION
38
Estimate
Name of Work: proposed construction of bungalow on Gat No. 9/3, Plot No.18 at
pathardi Tal. Shevgaon, Dist. Ahmednagar for Mr. Khan Sami
In this the contract price is Rs. 24, 00,000 and the work certified is Rs. 18, 00,000. The
contract account shows the notional profit Rs. 3, 20,000 . the profit transferred to the profit
and loss A/c is calculated on the base of the work certified i.e. the work certified is Rs. 18,
00,000 and the contract price is Rs. 24,00,000 then the contract work certified is more than
half but less than 80% of the contract so, the amount transferred to the P/L A/c is Rs.
1,60,000 and the reserve is Rs. 1,60,000 .
42
Contractee`s A/c
Particulars Rs. Particulars Rs.
To contract A/c. ( work 18,00,000 By cash/bank A/c. 13,50,000
certified) _ By balance c/d 4,50,000
18,00,000 18,00,000
The amount paid by the contractee is 75% because the retention money is 25% of
the work certified. In the above A/c the work certified is Rs. 18, 00,000 so, payment
to be made is 75% of Rs.18, 00,000 i.e. Rs. 13, 50,000. The contractee A/c shows that
the contractee is in strong position because the contractee has a huge amount as a
safety for the completion of the contract.
Extract Of P& L A/C. For The Year Ended 31st March 2022
Particulars Rs. Particulars Rs.
To loss by sale of items 80,000 By contract A/c.(profit) 1,60,000
To depreciation on plant and 1,60,000 By profit on sale of assets 1,00,000
building By net loss 50,000
To general expenses 40,000
3,10,000 3,10,000
Total Total
The contractor suffers a loss of Rs. 50.000 in the above contract because there is loss by sale of items and loss
by sale of asset is Rs. 1,10,000, and the amount of profit transfer in P/L A/c is not that much sufficient to
absorb all the losses in the contract.
43
7.ObSERvATIONS
AND FINDINGS
45
For the data analysis, I have taken 11 things which I have asked to the contractor and about
which they have given me answered I wanted with the solution. I have taken the
observation regarding how the contractor conducted to make the contract costing of the
different contract at different time and what are the problem arise in the study of the topic
contract costing. The observation are regarding the starting point of the ascertainment of
the contract price till the calculation of the profit at the end of the accounting period.
Following are the various observation which are observe in the period of the study, they are
as follows,
(1) The contractor takes generally the private contract and not the government
contract.
(2) The contract cost is calculated according to the estimated cost of the contract and
the particular margin is added in the estimated contract price of the contract.
(3) There are also such formats of ascertainment of the contract where the contractor
uses the area for the calculation of the contract price i.e. the contractor measures
the area of the contractee’s construction and then uses his area wise contract price
according to his experience or market rate.
(4) The allocation of the cost in the contract costing is very difficult. So the contractor
uses the contractor uses the method of absorption of the expenses by the contract
to have the allocation of the cost. The costs are allocated in the contract costing as
per the usefulness of that expense according to the contract.
(5) There are some costs which cannot be allocated directly to the contract, so it is very
difficult to find contract cost. So, in the contract costing the methods of
apportionment are used to apportion this cost according to the proportion or the
percentage of the use in the various contract.
(6) The apportionment of the profit of incomplete contract is the biggest and the most
competitive job in the contract costing. Because the contractor have to find the
profit of him for one accounting period to used it to submit it to the government for
the return.
The profit of the incomplete contract is finding according to the following formulas
used according to the condition followed by the formula. They are as follows,
(i) When the work done is less than 25% or 1/4 complete no profit is taken.
(ii) If the certified work is 1/4 or more than 1/4th but less than 1/2 of the contract price,
then 1/3rd of the notional profit as reduced to the percentage of cash received is
credited to profit and loss A/c. the balance sheet of the notional profit is credited to
reserve which is a part of work in progress.
Profit = 1/3 x notional profit x cash received/work certified
(iii) If the value of work certified is ½ or more than ½ of the contract value, then 2/3 rd of
the notional profit as reduced to the percentage of cash received to work certified is
credited to profit or loss A/c.
Profit = 2/3 x notional profit x cash received/work certified
(iv) When work certified is 100% or when the contract is complete, the entire profit is
credited to the profit and loss A/c.
(v) When incomplete contract A/c shows loss, the entire amount of loss is transferred
(debited) to profit/loss A/c. irrespective of the stage of completion.
46
8.CONCluSIONS
AND SuGGESTIONS
48
SuGGESTIONS
49
After the study of the contract costing of the company, following are the suggestions which
are as follows,
(1) The company can use the method of having low retention money amount when
making a new account with the contractee to have less amount of retention money
with the contractee and to have the more generation of the fund or income for the
contractor to have more funds with him to complete a contract in well time.
(2) The company can used the new software to make them compatible in the market
and to be more competitive in the market. Because there are some software which
provide the useful information to the contractor about the contract where he is
lacking behind in the contract work.
(3) The company can use the different method of calculating the contract price by used
of new innovation and techniques formed by the national institute and the different
contractors for having the accuracy of finding the cost. There are also scientific
methods which can be used for the finding or the ascertainment of the contract
price.
(4) The company can used the different method of allocation of the expenses according
the base use to allocate the expenses. The company can use the different bases
according to their convenience to allocate the expenses incurred in the contract.
(5) The company can used the bases of proportion to apportion the expenses incurred
for the contract according to the need like cost of contract, the proportion of the
work certified, state of profit etc.
(6) The company can use the competitor’s rate to define their own rate. It is useful for
the company to be competitive in the market and to have its survival in the market
for longer period of time. The company can use the competitor’s price to decide
their own price.
(7) The company can follow the regulation given by the government of India to have to
be compliance with the format and procedure given by the government to be
followed in the India. It is helpful for the company to survive in the market for long
lasting period.
(8) The company can used the method of being cost consciousness in the contract to be
more competitive in the market for having a long time survival in the market.
(9) The company can try to make the low amount of work in progress to have to make
more amount of money in the hand to make it useful somewhere else in the
construction work or to make the full utilization of the money.
(10) The company can used the method of the optimum utilization of resources to have
the greater usefulness of each and every thing related to the contract.
50
CONCluSIONS
51
The following are the conclusions which are given to the company after the study.
They are as follows,
(1) The contract costing is a term related to the costing of the contract. It means it is
very much useful to the contractor for the purpose of finding out the cost of a
particular contract and what is the proportion of the profit he has earned by doing
the contract. It means the contract costing is very much useful from the side of the
contractor regarding the maintenance of the records for his accounting profit and
contract profit.
(2) The contract costing is also used for the contractee in the way of checking the
accuracy of the contract price charged by the contractor. If the contract price is
based on the cost plus certain amount of profit then the contractee can used the
contract costing maintained by the contractor for the purpose of checking of the cost
incurred by the contractor to give the amount of price after the calculation of the
cost incurred for the contract and certain amount of profit.
(3) The allocations of the cost incurred by the contractor to the different contracts are
directly allocated to the contracts for which they are incurred. It is the job of the
contractor to maintain the books of accounts to know which cost are incurred for
which purpose.
(4) The apportionment of the total cost which is used for the many contract by one cost
is to be apportioned to the different contracts according to the cost incurred for the
different contracts according to the cost incurred for them.
(5) The main and the most important problem which are to be focused in the contract
costing is apportionment of the profit in the incomplete contracts. The profits in the
incomplete contracts are apportioned on the basis of the work of the contract
completed by the contractor and certified by the architects.
(6) The whole study of the contract costing state that the contract costing is very useful
thing both for the contractor, contractee and to the whole society at large because
it gives clear and accurate information of the contract to the all parties.
(7) The contract conducted by the contractor is not beneficial for him for this accounting
period because he is suffering various losses due to this contract as the reason
behind that is the retention money.
(8) The contract conducted by the contractor will be beneficial for him in the next
accounting year as the contractor will connect full amount from the contractee and
he will be in good position of the huge profit.
(9) The main and basic problem in this contract is the retention money brought back by
the contractee in this contract.
(10) The other main issue for the contract to be made loss making is that there is a huge
amount of the work in progress in the contract.
(11) The firm follows the DSR given by the government from time to time in its practice.
52
9.bIblIOGRApHy
53
www.icsi.edu
www.icmai.in
www.mhapwd.com
Khan, M.Y., Jain, P.K., Cost Accounting (15thedition) Delhi, Tata McGraw-Hill,
2011.
Jagtap, K.N., Zagade, Jare, Ghorpade, Cost and Works Accounting 2
(overheads and methods of costing) (5th edition) Pune, Success publication,
2013.
Patkar,M.G.,Joshi,C.M.,Advanced Cost Accounting And Cost Systems(1st
edition)Kolhapur,Phadke publication,2003.
54
10.
QuESTIONNAIRES
55
(2) Which method you used for calculating the contract price?
(a) Cost plus contracts (b) construction area based contracts
(3) How you deal with the material used in the contract?
(a) As direct material (b) As indirect material
(4) How you deal with the labour used in the contract?
(a) As direct labour (b) As indirect labour
(5) How you deal with the expenses related to the contract?
(a) As direct expenses (b) As indirect expenses
(6) Where you make the entry of the overheads in the contract account?
(a) Debit side (b) Credit side
(7) On what basis you make the apportionment of overheads in contract costing?
(a) On percentage of usefulness (b) On proportionate basis of contract
(8) Which depreciation method you used for treating the plant and machinery in
contract account?
(a) Written down value method (b) Full depreciation
(9) How you deal with the work in progress in the contract ?
(a) Debited in contract account (b) Credited in contract account
(10) How you deal with the profit on incomplete contract with respect to the
transfer of proportion of profit to balance sheet?
(a) Full transfer (b) Partial transfer
(11) Which methods of costing you used for treatment of the contractees
account?
(a) Memorandum A/c method (b) Advance A/c method
(12) How you deal with the defective work in the contract account?
(a) Credited in contract A/c (b)Debited in contract A/c
56
(13) Which method of balance sheet you used for the preparation and
presentation purpose?
(a) Horizontal method (b) Vertical method
(14) How much percentage you normally accept the retention money in the
contract?
(a) 10% of work certified (b) 20% of work certified
(15) Do you use the retention money clause in the contract agreement?
(a) Yes (b) No
(16) What is the treatment of the sub-contract cost in the contract account?
(a) Debited In contract A/c (b) Credited in contract A/c
(17) Do You Follow the DSR Rules Given By the Government From Time to Time?
(a) Yes (b) No