CO DRPNo6290320231306 PDF
CO DRPNo6290320231306 PDF
CO DRPNo6290320231306 PDF
Order of the Commission dated this the 28th Day of March 2023
PRESENT:
Vs
1
5. The Accounts Officer / Revenue
CEDC/ North, TANGEDCO
Chennai – 600 002.
….Respondents
Thiru.N.Kumanan and
Thiru.A.P.Venkatachalapathy,
Standing Counsel for TANGEDCO
first effect adjustment of the wind energy generated from the petitioner‟s captive
windmills operating under the REC scheme against the petitioner‟s service in terms
Thiru Rahul Balaji, Advocate for the Petitioner and Tvl. N.Kumanan and
consideration of the submission made by the Counsel for the Petitioner and
ORDER
T.O. No.6 of 2012 dated 31.07.2012. Consequent to this Tariff order, TANGEDCO
by the windmills covered under REC scheme. Aggrieved over this impugned letter
dated 14.09.2012, this petition has been filed to stay this communication and all
calculated on the basis of this letter. And also, sought to direct the TANGEDCO to
first effect adjustment of the wind energy generated from the petitioner‟s captive
2
windmills operating under the Renewable Energy Certificate (REC) scheme against
the petitioner‟s service and thereafter adjust the energy generated by the other
The prayer of the petitioner in I.A. No.1 of 2014 in D.R.P. No. 69 of 2014 is
2012 dated 14.09.2012 and all proceedings pursuant thereto for alleged excess
demand and excess energy calculated on the basis of such Circular as evident in
the current consumptions bills issued by the 5th Respondent for the year 2012-13
manufacturing cotton yarn and has invested in captive generation windmills with a
total installed capacity of 0.750 MW towards meeting its power requirement and in
addition, also consumers group captive power under arrangement with M/s. Beta
Wind Farm Private Limited from its Tuticorin, Tirunelveli and Udumalpet wind farms
under REC and non-REC scheme. It has consumed a total of 8,06,991 REC units
from M/s. Beta Wind Farm Private Limited from its Tuticorin and Tirunelveli EDC.
3.2. The petitioner sets out below details of the Non-REC WEG (s) supplying
power to it:-
Hon. Prime Minister of India on June 30, 2008 envisages several measures to
country. NAPCC has set the target of 5% renewable energy purchase for FY 2009-
10 against current level of around 3.5%. Further, NAPCC envisages that such
target will increase by 1% for next 10 years. This would mean NAPCC envisages
renewable energy to constitute approximately 15% of the energy mix of India. This
country.
3.4. Under the Electricity Act 2003, the State Electricity Regulatory Commissions
their total power requirement from renewable energy sources. This target is termed
national level.
3.5. The existing legal framework under Electricity Act 2003 puts responsibility
developed by the SERCs differ from each other on many counts. Further, these
regulations do not recognize purchase of renewable energy from outside the State
for the purpose of fulfilment of RPO target set by the SERC for the distribution utility
in the State. The requirement of scheduling and prohibitive long term open access
4
charges poses major barrier for Renewable Energy ("RE") abundant States to
undertake inter-State sale of their surplus RE based power to the States which do
not have sufficient RE based power. Consequently, the States with lower RE
"CERC") has notified 'Terms and Conditions for Recognition and Issuance of
renewable energy sources are not evenly spread across the country and the very
Energy sources, the Renewable Energy Certificate mechanism evolved and notified
by CERC seeks to address this and many such issues connected with the
sources and the requirement of the obligated entities to meet their renewable
purchase obligation (RPO), the Hon'ble CERC, vide order no. L-/12/2010-CERC
dated 9.11.2010 notified the detailed procedure for registration of eligible entities,
verification of generation of electricity and its injection into the grid by the eligible
entity and issuance of certificates, etc. under REC Scheme wherein cost of
5
electricity generation from renewable energy sources is divided into two parts as
cost for environmental attributes, containing inter alia the following distinct features
A. Not have any Power Purchase Agreement for the capacity related to such
Commission;
3.8. The clause 5 of (amended) CERC Terms and Conditions for recognition and
Regulations, 2010, describes the eligibility criteria for issuance of REC as under:
(b) it does not have any power purchase agreement for the capacity
related to such generation to sell electricity at a preferential tariff
determined by the Appropriate Commission; and
(c) it sells the electricity generated either (i) to the distribution licensee of
the area in which the eligible entity is located, at a price not exceeding
the pooled cost of power purchase of such distribution licensee, or (ii)
to any other licensee or to an open access consumer at a mutually
agreed price, or through power exchange at market determined price.
Provided also that if such a CPP forgoes on its own, the benefits of
concessional transmission or wheeling charges, banking facility benefit and
waiver of electricity duty, it shall become eligible for participating in the REC
scheme only after a period of three years has elapsed from the date of
forgoing such benefits.
Provided also that the abovementioned condition for CPPs for participating
in the REC scheme shall not apply if the benefits given to such CPPs in the
form of concessional transmission or wheeling charges, banking facility
benefit and waiver of electricity duty are withdrawn by the State Electricity
Regulatory Commission and/or the State Government. The dispute, if any,
on the question as to whether such concessional/promotional benefits were
availed by a CPP or not shall be referred to the Appropriate Commission.
2010, in line with the CERC regulations and 'draft model regulations for SERCs'
7
mandatory for all obligated entities to 'purchase not less than defined minimum
percentage of its consumption of energy from renewable energy sources under the
time …..” These Regulations also provide that 'the Certificates issued under the
Regulations, 2010 shall be the valid instruments for the discharge of the mandatory
obligations set out in these regulations for the obligated entities to purchase
alia, has to sell electricity component to the Utility at the 'pooled cost of power
TANGEDCO for the year 2009-10 and fee and charges payable under regulation of
8
TNERC (Renewable Energy Purchase Obligation) Regulations, 2010' and has fixed
the 'pooled cost of power purchase' by TANGEDCO for the year 2009-10 as
Rs.2.37 / kWh. Thereafter, the pooled cost of power is being notified for the
subsequent periods.
3.12. In addition, for avoidance of doubt, the TNERC has reiterated the definition
"Pooled cost of power purchase " means the weighted average pooled price
at which the distribution licensee has purchased the electricity cost of self-
generation in the previous year from all the long term energy suppliers but
excluding those based on liquid fuel, purchase from traders, short term
purchases and renewable energy sources.”
3.13. The relevant clauses, for the purpose of present petition in respect of the
“6. Billing
(2) The distribution licensee shall raise bills on the REG or the captive
consumer, as the case may be, for the charges payable towards
startup power and power drawn for other purpose, wheeling charges,
(3) The STU shall raise bills on the REG holder for the charges payable
charges, etc. As per the order / regulations of the commission for the
9
(4) Wherever the renewable energy generation in a billing month is in
3.14. In this regard, it would be relevant to state that under the provisions of the
generating plant and he shall have the right to open access for carrying such
3.15. For over one and a half years, the adjustment of the Wind energy has been
done by adjusting the units generated by the REC Windmills first and thereafter the
preferential tariff based Windmills. Wherever there is any excess, the same is
banked (limited to the generation of the preferential tariff windmills). The adjustment
of the units generated from the annual installed WTG under the REC Scheme is
also in consonance with Tariff Order No.6 of 2012 relating to Wind Energy, wherein
specifically provided under para-5 E Rule 6 that if a consumer wheels energy for
adjustment from more than one Windmill, with such Wind Mill having been
commissioned on different dates, priority for first adjustment shall be given to the
Windmill Commissioned on a latter day. The energy generated from the wind mill
commissioned on an earlier date can be adjusted last. The petitioner had therefore,
consequent upon the Comprehensive Wind Tariff Order No.6 dated 31.7.2012 that
the order coming into effect on 1.8.2012 necessary working instructions had also
been issued. By virtue of the tariff order, the said adjustment priority attained
finality.
3.16. The petitioner was therefore surprised to receive an audit demand notice
dated 19-06-2014 for the year 2012-13 in respect of its HTSC No.203 wherein the
adjustment was made in a manner contrary to the specific provisions of the contract
3.17. Upon enquiry of such change in manner of billing it appears that the Chief
Financial Controller upon a request for a clarification vide his letter dated 14.9.2012
follows:-
(a) The TNERG order on wind energy & order on REC does not have any
(b) The TANGEDGO in principle adopting the procedure of adjusting the high
cost power first and lesser cost power later i. e the first priority given for
power generator from the later date agreement and vice versa.
(c) In clause 8.2.15 of TNERC Order No.6 dated 31.07.2012 on Wind Energy
11
power. The unutilized REC energy will get lapsed as in the case of
conventional power.
d) As long as the banking facilities are not extended to the WEG availing REC,
this power will become cheaper than the power generated from the WEG
e) The Wind Energy Generator who avail banking facilities can utilize their
banked energy during the period of power scarcity and TANGEDGO is liable
to supply power to them by procuring in the open market at higher cost and
hence this power is costlier than power generated from Wind Energy
f) In line with the above, the higher cost power has to be adjusted first (i.e)
Wind Energy generated from wind mills with banking facilities and lesser
cost power shall be adjusted later i.e Wind Energy generated from wind mills
under REC.
Hence, it is clarified that the wind energy generated by wind mills with banking
facility shall be adjusted first and the wind energy generated from wind mills under
3.18. An entirely incorrect clarification has been issued wherein wind energy
generated by wind mill by banking facility was directed to be adjusted first and wind
energy generated from REC scheme be adjusted later. The said manner of
adjustment is contrary to the principle enshrined in the wind tariff order which
always mandates adjustment from the last unit first. It is only logical that REC wind
mills are permitted adjustment first since they operate on month to month lapsing of
energy and if any generator already has wind mills under the preferential regime
installed earlier, adjustment of units from Wind mills under the preferential regime
12
prior to the adjustment of units generated by Wind Mills under the REC scheme
would result in a situation contrary to the express purpose and intention of the REC
would, therefore, continue to invest only in preferential tariff based wind energy
its own interest as it would continue to get persons interested only in preferential
tariff rate WEG - if such an interpretation is given leading to the failure of the very
adjusted first. Therefore they ought to have approached the Commission before
arriving at any adjustment if they had any doubts rather than taking a decision by
3.20. The REC power is liable to lapse if not adjusted. Additionally, REC power
operating charges, wheeling charges etc. The issue of banking of REC power is
subject matter of proceedings on remand by the Hon'ble APTEL in the case of MIS
3.21. Since the generation of REC power attracts levying of higher charges (on
generation itself) and the fact that it is liable to lapse if not adjusted, this should
have the first priority of adjustment and not otherwise. The act of TANGEDCO in
adjusting the REC generation last amounts to unjust enrichment as any quantum
13
not adjusted will lapse and will be of no use to the consumer or the generator and
TANGEDCO will gain by such lapsing. The right of banking what rightfully belongs
3.22. The above mentioned circular of the 3rd respondent bearing Ref.No.CFC/
Madras in WP 33439 of 2013, and the Hon'ble High Court vide its order dated
9.12.2013 was pleased to grant an interim stay of the said circular. The relevant
extract from the Hon'ble High Court's order is set out below:
"As the submission of the learned counsel for the petitioner appears to be
3.23. The apparent position of the TANGEDCO that wind energy with banking
unreasonable considering the fact that the Banking charges are being recovered.
This is to be seen in the context of the current Tariff order (TR No.6 of 2012) which
clearly states that fixing of RS.0.94 per kWhr has been arrived at by calculating the
difference between the Average Power Purchase Cost and maximum Preferential
Tariff for wind energy that is being allowed. In other words, in the event of drawl of
14
banked energy, the cost is being recovered from the consumer itself and
3.24. The respondent TANGEDCO is, by its arbitrary and illegal actions, enjoying
allowing the units to get lapsed and not paying for such lapsed units ( the units
which have already stood generated and utilised by TANGEDCO) thereby resulting
in unjust enrichment.
3.25. The adjustment that is sought to be changed and revised has been filed
leave the petitioner with the REC Windmills' generation being entirely not being
used for the benefit of the petitioner and the entire generation wasted. The
agreements entered into since the energy wheeling agreement itself specifically
provided for sale of the surplus units, the same ought to be done on month to
month basis in respect of the said REC WEG since lapsing of banked units in
respect of WTG covered under the REC scheme take place on a month to month
basis rather than on annual basis as in the case of preferential tariff based WTGs.
The said manner of adjustment is contrary to the principle enshrined in the wind
tariff order which always mandates adjustment from the last unit first. It is only
logical that REC wind mills are permitted adjustment first since they operate on
month to month lapsing of energy and if any generator already has wind mills under
15
the preferential regime installed earlier, adjustment of units from Wind mills under
the preferential regime prior to the adjustment of units generated by Wind Mills
under the REC scheme would result in a situation contrary to the express purpose
and intention of the REC Scheme i.e encourage investment in market determined
NCES and generators would, therefore, continue to invest only in preferential tariff
3.27. The Petitioner therefore prays that the Commission may allow the Petition as
prayed for and render justice. The Petitioner has made out a prima facie case and
the balance of convenience is also in its favour in the grant of Orders as prayed for.
is allowed. On the contrary, grave prejudice, irreparable loss and hardship would be
caused to the members of the Petitioner if the present Petition is not allowed. The
4.1. TNEB‟s practice until the issuance of the Commission‟s Order No.3 dated
15-05-2006 in respect of wind mill has been that the wind mill generators may
either sell the surplus energy available after adjustment to TNEB at an outright
price of Rs 2.70 per unit or bank the surplus energy by deducting Banking charges
@ 5% of the energy banked. The banking period starts from 1st April of every year
Generation Plants, after taking into account the existing practices adopted by Tamil
Nadu Electricity Board (TNEB) and the guidelines from the Ministry for Non-
4.3. In the said order the Commission had issued banking provision,
Classification of WEG:
1. Group I Projects:
Wind power projects Commissioned, and to be commissioned based on
agreements executed prior to the date of this order (i.e) 15.05.2006.
2. Group II Projects:
Wind power projects to be commissioned based on future agreements after
the date of this order (i.e).15.05.2006.
Tariff computation:
As followed by most of the other States/ the Commission retains the existing
practice of one year (from April to March) banking period of TNEB, for the NCES
based wind electric generators. However, for the Biomass and Bagasse based co-
gen generators, banking provisions shall not apply. The Commission fixes the
banking charges as 5% for WEG. The Licensee shall pay at a rate of 75% of
normal purchase rate for the unutilized portion of energy banked by the NCES
Slot wise banking is permitted to enable unit to unit adjustments for the
respective slots towards rebate/ extra charges. However, 'the unutilized portion at
17
the expiry of banking period will not be distinctly dealt with for adjustment. Such
4.4. Pursuant to the above, the Member/Generation had issued detailed working
“II) 5. If the Wind Energy wheeled for one (or) more than one HT service at
wheeling end from more than one Wind Electric Generator and Wind Electric
higher tariff units have to be adjusted first. For the payment of unutilized
banked energy; the lower tariff rate has to be paid to the Generator at
While wheeling the power from more than one Wind Electric Generator
towards the adjustment in one HT service, the adjustment has to be done in the
descending order of the wind tariff (i.e)., the higher tariff units have to be adjusted
first. It is to be noted that the same procedure was followed even for the
subsequent Order No.1, dt.20.03.2009 and there was no dispute by the generators.
2009, dated.20.03.2009 on Wind Energy on classification of the WEG and tariff for
Classification of WEG:
1. Group I Projects:
Wind power projects commissioned, and to be commissioned based on
agreements executed prior to the date of this order (i.e). 15.05.2006.
18
2. Group II Projects:
The windmills commissioned between 15.05.2006 and 19.03.2009
3. Group Ill:
The Windmills commissioned on or after 20.03.2009.
Tariff Computation:
1. The wind mills commissioned prior to 15-5-2006 shall be eligible for a
tariff of Rs.2.75 per unit.
2. The wind mills commissioned between 15-5-2006 and 18-9-2008
shall be eligible for a tariff of Rs.2.90 per unit.
3. The wind mills commissioned between 19-9-2008 and 19-3-2009
shall be eligible for a tariff of Rs.2.90 per unit. These windmills shall
be eligible for Rs.3.24 per unit from 20-3-2009 to 31-3-2009 and
Rs.3.39 per unit from 01.04.2009.
4. The windmills commissioned on or after 20-3-2009 shall be eligible for
tariff of Rs.3.24 per unit up to 31-3-2009 and the tariff of Rs.3.39 per
unit from 01-04-2009”.
4.6. In this connection to implement the above order, the Director/ Generation/
TANGEDCO had issued instruction vide Circular Memo. No. CE/NCES/ EE/WPP/
Hence, all the Superintending Engineer/EDCs are requested to adhere all the
provisions of the TNERC Comprehensive Tariff Order on Wind Order No.1
dt.20.03.2009 in Toto with retrospective effect".
4.7. In this regard, it is relevant to note that with regard to adjustment of wind
energy for captive use is same for Order No.3 dt.15.05.2006 and Order No.1 dated
19
20.03.2009, the detailed working instructions already issued vide Circular
dated.11.12.2007 for Order No.3 dt.15.05.2006 is followed for Order No.1 of 2009
also.
4.8. The Central Electricity Regulatory Commission has notified Terms and
Subsequently vide its notification dt.29.09.2010, the REC benefit extended for
4.9. The relevant clause 5 (Amended) of the CERC Terms and conditions for
Generation Regulations, 2010, describes the eligibility criteria for issuance of REC
as under:-
“(i) It sells electricity generated either (i) to the distribution licensee of the
area in which the eligible entity is located, at a price not exceeding the
pooled cost of power purchase of such distribution licensee, or (ii) to
any other licensee or to an open access consumer at a mutually
agreed price, or through power exchange at market determined price.
(i) to the distribution licensee of the area in which the eligible entity is located, at a
price not exceeding the pooled cost of power purchase of such distribution
there is no major change in the Tariff Order No.3 dated 15.05.2006 and Order
11.12.2007 issued for Order No.3, dt.15.05.2006 is utilized for Order No.1
dt.20.03.2009 also. As such for Order No.3 dt.15.05.2006 there are two tariff rate
i.e, Rs.2.75 & Rs.2.90/unit and for Order No.1, dt.20.03.2009 one rate Rs.3.39/-
unit. If a captive generator having the above 3 type of WEGs and wheels for his HT
service, the instruction was the higher tariff rate i.e. Rs.3.39/unit to be adjusted first,
Rs.2.90/unit to be adjusted second and Rs.2.75/unit is the last. At the end of the
banking period, for the unutilized banked energy, the 75% (or) 100% payment is
being made with lower tariff rate of Rs.2.75/unit. This was the procedure adopted
4.12. The petitioner is having some of its WF HT Services under preferential tariff
and other WF HT services under REC. The petitioner entered EWA and adjusting
4.13. Under Tariff Order No.3, dt,15.05.2006 and Order No.1, dt.20.03.2009, the
adjustment was carried out as per instructions dt: 11.12.2007 i.e, the higher tariff
rate units to be adjusted first to be banked. For the unutilized banked energy the
21
lower tariff rate was paid. The petitioner had accepted the payments from 2007
4.14. Now the Commission issued Tariff Order No.6 dt.31.07.2012. The
the above order. With regard to adjustment of wind energy from more than one
wind mill with different tariff rate is concerned, the instructions issued are that if a
consumer wheeled energy for adjustment from more than one windmill, which is
commissioned in different dates, the priority for first adjustment shall be given to the
windmill commissioned in later date and that the energy generated from the wind
4.15. From the above, TANGEDCO has not deviated its procedure from one order
to other.
4.16. The Commission has issued the Comprehensive Tariff Order on Wind
Energy (Order No.6 of 2012, dt.31.07.2012), wherein it has been stated with regard
4.17. From the above it is clear that the WEGs availing REC does not avail any
banking facility benefit and waiver of electricity duty in order to avail the benefit of
REC.
22
4.18. If the banking facility has been extended to the WEGs availing REC as in the
case of WEGs non-availing REC, the petitioner might not request to adjust the REC
Commission to dispense the banking facility, and the Commission in the Tariff
“xxx
8.2.4. In response to the public notice dated 27-04-2011, the TANGEDCO in
its letter dated 13-06-2011 has stated the following:-
4.20. In their letter dated 07-12-2011, the TANGEDCO have stated that the cash
outflow for payment of unutilized banked units is increasing every year and the full
requested the Commission to dispense with the banking provision not only to future
23
projects but also to the existing projects commissioned before and after 15-05-
2006.
(1) As stated already, the WEGs are allowed to supply power to captive
user and third party consumers in addition to sale to TANGEDCO, as has
been allowed to conventional generators. Hence, there is no need to
continue banking facility to wind sector. In fact, provision of banking is
alien to the Electricity Act, 2003 and on this ground a/one banking of wind
energy need to be dispensed with.
(2) As has been stated already, wind energy generators by virtue of
natural consequences and, fortunately, for the WEGs the wind blows
during summer season, in TANGEDCOs experience, it is seen that the
WEG generates energy, during May to September, without putting any
effort but encashes by adjustment at a later time by virtue of banking that
too when the Distribution Licensee is experiencing power deficit due to
high demand. It is an open secret that the power deficit is prevailing in
most of the States in India and of late, experiencing shortage of coal &
gas, difficulties in transportation of coal for various reasons, etc.
Therefore, it is a right time to dispense with the banking facility. In fact,
while the Wind Energy Generators withdrawing the banked energy, the
Distribution Licensee is forced to make purchase of power from open
market at much higher cost. Thereby also, the Distribution Licensee is
made to suffer financially.
(3) In addition to dispensing with the banking system, the existing
requirement on the part of Distribution Licensee to make payment for any
excess energy left over after adjustment also requires to be dispensed
with, in view of the position that WEG have been provided with all
adequate options of distributing their energy through captive use and
third party consumer in addition to Sale to TANGEDCO.
24
(4) Further provision of encashment of unutilized banked energy, leads
to additional financial burden to TANGEDCO. The quantum of unutilized
banked energy increasing every year exponentially.
In 10/2008, it was 315 MU, in 31.03.2009 it was 251.3 MU and in
31.03.2010 it was 350.658 MU. Hence cash outflow for payment of
unutilized banked units is high every year. Such dispensing with may be
made applicable to the existing WEGs and to prospective WEGs from the
date of such tariff order irrespective of the category to which it belongs.
(5) Further, as per CERC and TNERC REC Regulations, for wheeling of
wind energy for captive consumption under REC scheme, they have to
forego banking. Since TANGEDCO proposed to purchase the future wind
power from REC projects only, the banking may be dispensed with.
Further based on the recommendation of the TANGEDCO full Board
meeting held on 15.11.2011, a petition MP No.1 of 2012 filed at the
Commission to dispense the banking. However, TNERC on 16.02.2012
directed the TANGEDCO to file a fresh petition by impleading the affected
parties. Filing fresh petition is in the process.
25
However, the Commission could continue the banking in pursuant to
section 86(1)(e) of the Electricity Act 2003 to promote the renewable
energy in the State, subject to the adjustment of energy rates between
the two periods relating to banking of energy and drawal of energy from
the banking."
4.22. In view of above, the banking facility has to be dispensed since in view of the
position that WEGs have been provided with all adequate options of distributing
their energy through captive use and third party consumer in addition to sale to
TANGEDCO. In fact, while the Wind Energy Generators withdrawing the banked
energy; the Distribution Licensee is forced to make purchase of power from open
market at much higher cost. Thereby also, the Distribution Licensee is made to
as follows:
“If the Wind Energy wheeled for one (or) more than one HT service at
wheeling end from more than one Wind Electric Generator and Wind Electric
Generators were commissioned before 15.05.2006 and after 15.05.2006, the
higher tariff units have to be adjusted first. For the surplus energy sale after
adjustment, the lower tariff rate has to be paid to the Generator at
Generating end………."
4.23. While factual position being so, the petition is not sustainable one. If the
4.24. Subsequently the Commission vide its RPO amendment regulations dated
29.07.2011 extended the REC benefits to captive generators also with the condition
26
order held that the transmission charges, wheeling charges and banking in order
No.1, dated 20.03.2009 are concessional one. Hence after adjustment in the
month, the surplus energy was paid at Rs.2.37 per unit at APPC rate. While issuing
NOC to the petitioner, the same condition was imposed. Up to 31.07.2012 the
REC captive generator. Hence as per the agreement, the surplus energy after
31.07.2012. With regard to REC project is concerned, the project under sale to
Board is governed by the CERC's REC Regulation 2010 and TNERC RPO
Regulation 2010 and TNERC Order on APPC rate. With regard to REC captive
Regulations 2010 only. Now only it is covered under Order No.6, dt.31.07.2012.
4.26. In the recent Tariff Order No.6, dated 31.07.2012, the Commission, it is
stated that:
4.27. Even in the earlier instructions dated 11.12.2007 issued by the respondent,
the adjustment of energy was ordered to be carried out in the same manner
higher tariff rate units are to be adjusted first and the balance to be banked. Since,
27
the banking of energy in respect of REC scheme having been withdrawn. The
petitioner has now questioned the manner of adjustment of energy. On the other
hand, this respondent never changed the manner of adjustment right from 2007.
Hence, the above clarification is not contrary (or) deviations from the procedure
already followed from 2007 vide instruction dated 11.12.2007 and the recent
between project under preferential tariff and project under REC scheme, the
Commission issued direction in Order No.6, dt. 31.07.2012 to treat the surplus
energy as lapsed without giving banking facility. Hence to give banking facility to
the non REC WEGs, the energy generated by the non REC WEGs adjusted first,
with higher tariff rate at first and lower tariff rate at later. In order to give effect
direction of the Commission for REC WEGs to treat surplus energy as lapsed, the
REC units adjusted last. Even though the TANGEDCO has not deviated from the
procedure followed for adjustment from one order to other. Since the REC rate is
4.28. For implementing Order No.6, dated 31.07.2012, TANGEDCO issued Order
on 01.09.2012, wherein from more than one Wind Mills commissioned in different
"If a consumer wheeled energy for adjustment from more than one windmill,
which is commissioned in different dates, the priority for first adjustment shall
be given to the windmill commissioned in later date. The energy generated
from the wind mill commissioned in earlier date shall be adjusted in later.”
4.29. The same procedure adopted for implementation of TNERC Order No.3, dt:
"If the Wind Energy wheeled for one (or) more than one HT service at
wheeling end from more than one Wind Electric Generator and the Wind
Electric Generators were commissioned before 15.05.06 and after 15.05.06,
28
the higher tariff units have to be adjusted first. For the surplus energy sale
after adjustment, the lower tariff rate has to be paid to the Generator at
Generating end. Similarly for the lapsed banked unit the lower tariff rate only
to be paid to the Generators".
4.30. For the instructions dt: 11.12.2007, there was no dispute and no objection
from the generators including the petitioner and received the payment without any
objection.
4.31. Consequent to the instruction dated 01.09.2012 issued for Order No.6,
Cements Limited, Indian Wind Power Association (IWPA) and The Southern India
Madras and prayed to stay the circular instruction dt. 01.09.2012 and Madurai
Bench of Hon'ble High Court of Madras on 26.09.2012 has issued interim stay
order. Madurai Bench of Hon'ble High Court of Madras on 08.10.2012 directed the
17.10.2012 extended the stay order until disposal of the petition by the
Commission, and with the said orders, the above said W.Ps stand disposed.
petition M.P. No.38 of 2012 filed by TANGEDCO before the Commission. The
29
4.33. As per the direction of the Commission, the TANGEDCO hosted the petition
In the above writ petitions (MD) No.12650/2012 etc. the Wind Association have not
raised objection for the above said adjustment procedure including the petitioner.
4.34. As per the provisions of the CERC‟s REC Regulations, wind power projects
installed for captive use are allowed to avail RECs on total generation including
generated from WEGs avail REC shall be adjusted first is not legitimate and
sustainable.
4.35. In view of the facts and circumstances of the case on hand and position of
law as stated above, the petitioner has no prima facie case to further pursue the
above petition. Therefore, the petitioner is not entitled to any relief as prayed for in
respondents herein. Hence, considering all the above and more particularly
Certificate [REC] tradable in power exchange between the floor price and
forbearance price.
5.1. During the year 2012, the Commission issued a Comprehensive Tariff Order
on Wind Energy vide order No.6, dt.31.07.2012 (effect from 01.08.2012) wherein
30
the banking facility for the Wind Energy Generators [“WEGs”] commissioned under
and traded for a value. The buyers of such renewable energy certificates [REC] will
be the users who fall short of their Renewable Purchase Obligation [RPO].On the
other hand, wind energy generators i.e. commissioned under preferential tariff
clarifications on the adjustment priority among the WEGs having banking facility
and not having banking facility (i.e. between REC and non-REC category). Based
dated 14.09.2012 to adjust the energy wheeled from the WEGs with banking facility
first and other WEGs later Aggrieved to the above circular, M/s. Century Floor Mills
had filed a Dispute Resolution Petition before the Commission vide Dispute
Resolution Petition No.19 of 2013 and the Commission has passed the order on
“ xxxxx
5.6. The Commission has not issued any specific instruction for fixing
the priority of adjustment at the user end for the energy generated from
WEGs under REC scheme and WEG’s under normal captive / third party
scheme. The priority imposed by the TANGEDCO vide its letter dated 14-
09-2012 for adjustment of energy in this case is arbitrary. Since such
decision of the TANGEDCO affects the electricity charges to be paid by
the consumers / open access consumers, the TANGEDCO’s letter dated
14-09-2012 is not legally valid as mandated by Section 45 of the
Electricity Act 2003. In the absence of expressed law, the best option for
the TANGEDCO should have been approaching the Commission for
issue of such orders. This has not been done by the TANGEDCO.
Therefore we have no hesitation to declare that the TANGEDCO’s letter
No.CEC/FC/REV/AAO/HT/D.606/2012, dated 14-09-2012 is arbitrary and
not legally valid.
5.7. xxxxx”.
31
5.3. Pursuant to the above, Tamil Nadu Generation and Distribution Corporation
Limited [“TANGEDCO”] filed an appeal before the Hon‟ble APTEL vide Appeal No.
53 of 2016 and I.A No.138 of 2016. Meantime, the Commission in its order vide
R.A.No.6 of 2013, dt.31.03.2016 has extended the banking benefit for the REC
generators also though the original order dt.31.07.2012 did not provide 12 months
banking for such category. However, the Hon‟ble APTEL passed order on
“….We are of the considered opinion that the issues raised in the
present Appeal have no merits and Appeal and I.A. are hereby dismissed.
The Impugned Order dated 19.01.2015 passed by the State Commission
is hereby upheld.”
5.4. The Commission initiated R.A. No. 6 of 2013 pursuant to the Orders of the
Hon‟ble APTEL dated.24.05.2013 made in Appeal No. 197,198, 200, 201, 208 of
2012 and Appeal No. 6 of 2013 and passed an Order dated 31.03.2016 in R.A. No.
6 of 2013 and the Comprehensive Wind Energy Tariff Order No. 3 of 2016 dated
respectively, in respect of REC WEGs extended the banking provision for one year
at par with the WEGs under preferential tariff and TANGECO has implemented the
said Order No. 3 dated 31.03.2016 vide Memo No. CE/NCES/ SE/EE/ WPP/ AEE2/
F.Order No. 3, dated 31.03.2016/ D.1553/2016 dt. 18.08.2016 and the said position
has been submitted before the APTEL during course of the hearing and also
pleaded by filing Written Submission, to dispose off the appeal by granting liberty to
the TANGEDCO to file Miscellaneous Petition before the Commission for framing
issue and also not passed any remarks in this issue in the judgment. On the other
hand, it has been ordered erroneously that in respect of the WEGs under REC,
energy after one month shall be available to TANGEDCO at the free of cost giving
un-due benefit to the Appellant. In view of WEGs under REC scheme have the
banking provision at par with the WEGs under preferential tariff which has a
banking provision of one year with effective from 01.08.2012. Therefore, the said
observation is against the core of the issue in the present case and said
observation may be termed as mistake of fact and error on the face of the record.
5.6. Considering the above fallacy and the failure of the Hon‟ble APTEL in
noticing its own previous Order dated 24.05.2013 and also the Commission‟s Order
dated 31.03.2016 in R.A. No. 6 of 2013 and Comprehensive Wind Energy Tariff
Order while deciding Appeal No. 53 of 2016, it is arguable that Impugned Order
dated 23.09.2016 is per incuriam. Therefore, the TANGEDCO could not implement
5.7. Hence, aggrieved by the above order, Civil Appeal has been filed by
TANGEDCO before this Hon‟ble Supreme Court of India vide C.A. No. 15618 of
2017 and this Hon‟ble Court has ordered (vide order dt.18.09.2017) to maintain
‟status-quo‟.
5.8. In this connection, it is relevant to mention that M/s. Ambika Cotton Mills filed
Miscellaneous Petition before the Ld TNERC vide M.P.No.14 of 2017 in the matter
33
adjustment priority between wind energy generators based on principal of First In
First Out [FIFO] method against the procedure which had been followed by
TANGEDCO that higher purchase tariff has to be adjusted first. In this regard, the
follows:
5.9. TANGEDCO has filed a miscellaneous petition before the Commission vide
MP No.24 of 2021 seeking order of adjustment among various sources (viz. IEX,
3rd Party, Wind, Thermal, Solar, etc) of open access energy wheeled/purchased by
the HT consumers. The same has been admitted on 29.06.2021 and it has been
ordered to TANGEDCO to webhost the said petition and obtain the stakeholders
03.08.2021. Based on the above, the following stake holders furnished their
comments.
The above stakeholder‟s comments have been submitted on 11.08.2021 before the
Commission. Further, it is stated that while hearing of the said Civil Appeal, the
ORDER
We are pained to note that despite our noticing in the order,
dated 25.01.2022 that the Regulations to be put in place is an
aspect of utmost urgency and for the counsel for respondent
No. 2 to take instructions in that behalf considering that the
stakeholders had given their suggestions by 03.08.2021
and almost six months have expired, we are now
informed that the Regulators will need another eight weeks
for the said purpose. We seek to emphasize to the
Regulators the importance of their function which they are
required to perform and should perform andthis kind of hiatus
of time period does not reflect well. We give the Regulators,
the last opportunity to bring the fresh Regulations in place
on or before 31.03.2022.
We are conscious that the Regulations will apply prospectively
but learned counsel agree that this may reflect to some
extent, the approach of the Commission on the aspect in
question.
List for directions on 06.04.2022.
35
The Regulations duly notified to be placed before us by that
date.
5.10. In continuation to the above, the Hon‟ble Supreme Court of India passed an
order on 11.04.2022, the relevant portion which held as follows:
ORDER
From the above, the only issue which is pending before the Hon‟ble Supreme Court
of India is whether it should apply for the past. In this regard, TANGEDCO filed
affidavit before the Hon‟ble Supreme Court of India on 25.08.2022. Based on the
above, the Hon‟ble Supreme Court of India passed following order on 26.08.2022:
ORDER
An affidavit has been filed on 25.08.2022/affirmed on 18.08.2022 on behalf
of the appellant Para 7 of the affidavit reads as under:
“ It is submitted that the appellant is following certain procedure of
adjustment right from the year 2008 which is one and the same as ordered
by the Ld. TNERC vide notification dated 21.03.2022. With regard to the
priority among WEGs under REC and Non- REC, the appellant is following
the order of the Ld.TNERC dated 19.01.2015 in D.R.P.No.19 of 2013. In
36
this connection, it is relevant to mention that the Respondents herein had
also not disputed the adjustment procedure. Hence, it is respectfully
submitted that it may be construed that the appellant has adopted
procedure laid down in the notification dated 21.03.2022 for adjustment
priority among WEGs under REC and Non-REC with effect from 01.08.2012
retrospectively. Per contra, the abovementioned notification dated
21.03.2022 shall be adopted prospectively for other energy sources of the
High Tension consumers.”
5.11. In view of the above reasons stated, it is humbly prayed that this
mentioned lines and pass such further or other orders as this Commission may
6.1. This Commission issued the Comprehensive Tariff order on Wind Energy in
T.O. No.6 of 2012 dated 31.07.2012. Consequent to this Tariff order, TANGEDCO
by the windmills covered under REC scheme. Aggrieved by the Circular dated
14.09.2012, the petitioner has filed this petition to stay the implementation of the
circular and all proceedings pursuant thereto including the Excess demand/energy
charges calculated on the basis of this letter and also sought direction to the
TANGEDCO to first effect adjustment of the wind energy generated from the
(REC) scheme against the petitioner‟s service and thereafter adjust the energy
37
6.2. The operative portion of the TANGEDCO‟s letter (dt.14.09.2012) challenged
a. The TNERC order on wind energy and order on REC does not have any
provision in regard to adjustment priority of banked energy and REC power.
d. As long as the banking facilities are not extended to the WEG availing REC,
this power will become cheaper than the power generated from the WEG
availing banking facilities.
e. The Wind Energy Generator who avail banking facilities can utilize their
banked energy during the period of power scarcity and TANGEDCO is liable to
supply power to them by procuring in the open market at higher cost and
hence this power is costlier than power generated from Wind Energy Generator
availing REC.
f. In line with the above, the higher cost power has to be adjusted first (i.e.)
Wind Energy generated from wind mills with banking facilities and lesser cost
power shall be adjusted later i.e. Wind Energy generated from wind mills under
REC.
Hence, it is clarified that the wind energy generated by wind mills with banking
facility shall be adjusted first and the wind energy generated from wind mills
under REC shall be adjusted later.”
Order No.6 dated 31.07.2012 that, if any generator already has wind mills under
the preferential regime installed, adjustment of units from Windmills under the
38
the REC scheme would result in a situation contrary to the express purpose and
NCES and generators would, therefore, continue to invest only in preferential tariff
TANGEDCO itself admits that there is no priority stipulation from the Commission
regarding which energy to be adjusted first. Before arriving at such conclusion the
respondent ought to have approached this Commission. The REC power plant‟s
System Operation charges, Wheeling charges etc., Since the generation of REC
power attracts levying of higher charges and it is also liable to lapse if not adjusted,
6.4. The Respondent has stated that even in the earlier instructions dated
carried out in the same manner as ordered in the circular No. CFC/Rev/ FC/AAO/
HT/D.606/12, dt.14.09.2012 (viz.,) with higher tariff rate units are to be adjusted first
and the balance to be banked. Since, the banking of energy in respect of REC
scheme having been withdrawn, the petitioner has now questioned the manner of
adjustment of energy. On the other hand, the respondent never changed the
manner of adjustment right from 2007. Hence the circular dated 14.09.2012 is not
contrary or inconsistent with the procedure already followed from 2007 vide
Energy Certificate (REC) tradable in the Power Exchanges between the floor price
Vs TANGEDCO) dated 19.01.2015, a case similar to the case on hand, wherein the
5.5. ..... On the other hand, the respondent’s letter dated 14-09-2012
compares notional cost of energy to be adjusted under REC scheme with the
preferential tariff of other WEGs for fixing the priority for adjustment of energy
generated by the WEGs under different schemes. However both the
TANGEDCO’s circular dated 11-12-2007 and the letter dated 14-09-2012
have not been approved by the Commission.
5.6. The Commission has not issued any specific instruction for fixing the
priority of adjustment at the user end for the energy generated from WEGs
under REC scheme and WEG’s under normal captive / third party scheme.
The priority imposed by the TANGEDCO vide its letter dated 14-09-2012 for
adjustment of energy in this case is arbitrary. Since such decision of the
TANGEDCO affects the electricity charges to be paid by the consumers /
open access consumers, the TANGEDCO’s letter dated 14-09-2012 is not
legally valid as mandated by Section 45 of the Electricity Act 2003. In the
absence of expressed law, the best option for the TANGEDCO should have
been approaching the Commission for issue of such orders. This has not
been done by the TANGEDCO. Therefore we have no hesitation to declare
that the TANGEDCO’s letter No.CEC/ FC/ REV/AAO/HT/D.606/2012, dated
14-09-2012 is arbitrary and not legally valid.
5.7. .....we Order that the TANGEDCO shall first adjust the wheeled energy
generated from the petitioner’s WEG under REC scheme which has an
adjustment or banking period of one month and then adjust the energy
generated from other captive / third party generators which have a banking
period of one year. The TANGEDCO is directed to revise the bill of the
petitioner based on the energy adjustment priority specified in this Order and
40
settle the account within a period of three months from the date of issue of
this order.”
6.6. The appeal preferred by the TANGEDCO before the Hon‟ble Appellate
Tribunal for Electricity against the Order of the Commission was disposed by the
Hon‟ble APTEL vide order dated 23.09.2016 passed in Appeal No. 53 of 2016. The
ix. As per the provisions of the Section 61(h) and Section 86(1)(e) of the
Act, one of the functions of the State Commission is to provide measures
for promotion of renewable energy. Considering the facts specified in the
Impugned Order and the provisions of the Act, we are of the considered
opinion that the State Commission has rightly held that the
communication dated 14.09.2012 issued by CFC, TANGEDCO regarding
adjustment priority is not legally valid. Further on the question that
whether the State Commission can pass an order specifying the mode of
adjustment, we reply in affirmative. The State Commission in its
Impugned Order has specified the mode of adjustment which is in line
with the Regulation 8 of the “Power Procurement from New and
Renewable Sources of Energy Regulations 2008.
41
b) On the second issue for our consideration i.e. Whether the State
Commission is required to amend the Regulations relating to procurement of
wind energy and related issues?, we observe as follows;
6.7. Aggrieved by the above order, the TANGEDCO preferred an appeal before
the Hon‟ble Supreme Court of India in Civil Appeal No.15618/2017. In the course
of hearing the appeal, the Apex court directed, the Commission to bring out the
the TNERC (Grid Connectivity and Intra State Open Access) Regulations 2014, in
the matter of fixing priority of adjustment of energy drawn by the Open Access
consumer from different sources, it was notified vide Notn.No. TNERC/ISOA/ 11/2-
6.9. In the Appeal C.A.No.15618/2017 then pending before the Hon‟ble Supreme
Court of India, TANGEDCO filed an affidavit, and based on that the Apex Court
42
“ORDER
An affidavit has been filed on 25.08.2022/affirmed on 18.08.2022 on behalf
of the appellant Para 7 of the affidavit reads as under:
“ It is submitted that the appellant is following certain procedure of
adjustment right from the year 2008 which is one and the same as ordered
by the Ld. TNERC vide notification dated 21.03.2022. With regard to the
priority among WEGs under REC and Non- REC, the appellant is following
the order of the Ld. TNERC dated 19.01.2015 in D.R.P.No.19 of 2013. In
this connection, it is relevant to mention that the Respondents herein had
also not disputed the adjustment procedure. Hence, it is respectfully
submitted that it may be construed that the appellant has adopted
procedure laid down in the notification dated 21.03.2022 for adjustment
priority among WEGs under REC and Non-REC with effect from
01.08.2012 retrospectively. Per contra, the abovementioned notification
dated 21.03.2022 shall be adopted prospectively for other energy sources
of the High Tension consumers.”
6.10. The order passed by the Hon‟ble APTEL in Appeal No. 53 of 2016 dated
23-09-2016 and the order passed by the Hon‟ble Supreme Court in C.A. No. 15618
/2017 dated 26-08-2022 not only confirmed the order passed by TNERC in D.R.P.
No. 19 of 2013 dated 19-01-2015 but also approved the procedure recommended
by the Commission with regard to adjustment priority among WEG‟s under REC
admitted that the procedures are adopted retrospectively with effect from
6.11. Hence, the prayer of the petitioner to stay the operation of letter no. CFC/FC/
generated by the WEGs under REC scheme, by now is a settled issue as the
43
ORDER
This Commission directs that the wind energy generated from the
Petitioner‟s WEG‟s under REC Scheme during the period covered under the
203 as against the other generators and such adjustment shall be made within a
month from the date of this order. The TANGEDCO shall revise / raise the current
consumption charges for the relevant period as per this order. No order as to cost.
/True Copy /
Secretary
Tamil Nadu Electricity
Regulatory Commission
44