Study of maintenance of railway track
1
MAHARASHTRA STATE BOARD OF
TECHNICAL EDUCATION
Certificate
2
ACKNOWLEDGEMEMT
3
BRIEF INFORMATION ABOUT MICROPROJECT:
Railway track maintenance and renewal are vital for railway safety, train
punctuality, and travel comfort. Therefore, having cost-effective maintenance is
critical in managing railway infrastructure assets. There has been a considerable
amount of research performed on mathematical and decision support models for
improving the application of railway track maintenance planning and
scheduling. This article reviews the literature in decision support models for
railway track maintenance planning and scheduling and transforms the results
into a problem taxonomy. Furthermore, the article discusses current approaches
in optimising maintenance planning and scheduling, research trends, and
possible gaps in the related decision-making models.
Course outcomes:
Understand Study of maintenance of railway track
4
Sr. Name of Group
Activity Start date Due date
No. members
Resources required:
5
Theory
6
Annual Programme of Regular Track Maintenances
7
The length track opened in day should not be more than the efficient
maintenance to be done to that track at the end of the day.
> Ballast should be opened on either sides of rail seats, depth upto 50 mm
>They should not disturb cores under sleeper.
Opening length on either sides is different for different
gauges
8
b)Examination of Rails, Sleepers and Fastenings
Rails should be checked for wear and tear, corrosion, Cracks at rail
Joints, cracks at ends.
Sleepers condition at rail seats
Check for loose Fastenings and fittings.
C) Squaring of Sleepers
Gauge variations and kinks inevitably Results from sleepers getting out of
square.
It is done by planting the crow bars firmly against the sleeper and pushing
it
e) Gauging
9
It is to maintain uniform gauge distance. For B.G. 1676 mm, M.G. 1000
mm and 762 mm for N.G
It is done only if the sleepers are truly square.
Because of aging and different conditions of sleeper it is not Possible to
maintain exact gauge distance.
10
Conclusion
From this topic I came to know that track maintenance is essential for safe,
economic and smooth running of a rail. Indian Railways is taking special care
about track maintenance, introducing new ideas to do track maintenance more
efficiently.
Skill Developed:
QOur Leadership developed when we work for micro project with our team
members.
Reference
http://tsurbandashboard.in/online_applications/2.List-of-documents-to-
befurnished-along-with-building-application.pdf
11
Signature
12