Shear Analysis and Design Group 2

This document summarizes the shear analysis and design of horizontal beams for 4 grids on the ground floor of a structure. Maximum shear values were calculated for each beam using the approximate method. The maximum shear was 248.745 kN for Grid 3.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
35 views166 pages

Shear Analysis and Design Group 2

This document summarizes the shear analysis and design of horizontal beams for 4 grids on the ground floor of a structure. Maximum shear values were calculated for each beam using the approximate method. The maximum shear was 248.745 kN for Grid 3.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 166

Shear Analysis and

Design

Group 2

Michael Amistoso

Juan Miguel Amoranto

Karl Vincent Argañosa

Ann Loraine Banzon

Alexandra Nicole Echapare

Richee Crown Jewel Faller

Pio Herrera

Winbelle Magsino
Structural Analysis
(Horizontal Beams)
GROUND FLOOR

(Grid 1)

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐴 − 𝐵) = 27.43387347 + 17.604 = 45.03787347 ≈ 46
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐵 − 𝐶) = 30.794904 + 17.604 = 48.398904 ≈ 49
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐶 − 𝐷) = 36.37362857 + 17.604 = 53.97762857 ≈ 54
𝑚 𝑚 𝑚 𝑚
DESIGN SHEAR:

APPROXIMATE METHOD

𝟏. 𝟏𝟓𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑬𝒙𝒕𝒆𝒓𝒊𝒐𝒓 𝒇𝒂𝒄𝒆 𝒐𝒇 𝒇𝒊𝒓𝒔𝒕 𝑰𝒏𝒕𝒆𝒓𝒊𝒐𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕) =
𝟐

𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑭𝒂𝒄𝒆 𝒐𝒇 𝒐𝒕𝒉𝒆𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕𝒔) =
𝟐

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(46 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 111.09 𝑘𝑁
2 2

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(54 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 130.41 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (49 𝑚 )(3 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 73.5 𝑘𝑁
2 2

MAXIMUM SHEAR 𝟏𝟑𝟎. 𝟒𝟏 𝒌𝑵


(Grid 2)

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐴 − 𝐵) = 27.43387347 + 29.85854694 + 17.604 = 74.89642041 ≈ 75
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐵 − 𝐶) = 30.794904 + 15.624 + 17.604 = 64.022904 ≈ 65
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐶 − 𝐷) = 36.37362857 + 42.47177143 + 17.604 = 96.4494 ≈ 97
𝑚 𝑚 𝑚 𝑚 𝑚
DESIGN SHEAR:

APPROXIMATE METHOD

𝟏. 𝟏𝟓𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑬𝒙𝒕𝒆𝒓𝒊𝒐𝒓 𝒇𝒂𝒄𝒆 𝒐𝒇 𝒇𝒊𝒓𝒔𝒕 𝑰𝒏𝒕𝒆𝒓𝒊𝒐𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕) =
𝟐

𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑭𝒂𝒄𝒆 𝒐𝒇 𝒐𝒕𝒉𝒆𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕𝒔) =
𝟐

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(75 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 181.125 𝑘𝑁
2 2

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(97 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 234.255 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (65 𝑚 )(3 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 97.5 𝑘𝑁
2 2

MAXIMUM SHEAR 𝟐𝟑𝟒. 𝟐𝟓𝟓 𝒌𝑵


(Grid 3)

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐴 − 𝐵) = 29.85854694 + 29.85854694 + 17.604 = 77.32109388 ≈ 78
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐵 − 𝐶) = 15.624 + 15.624 + 17.604 = 48.852 ≈ 49
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐶 − 𝐷) = 42.47177143 + 42.47177143 + 17.604 = 102.5475429 ≈ 103
𝑚 𝑚 𝑚 𝑚 𝑚
DESIGN SHEAR:

APPROXIMATE METHOD

𝟏. 𝟏𝟓𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑬𝒙𝒕𝒆𝒓𝒊𝒐𝒓 𝒇𝒂𝒄𝒆 𝒐𝒇 𝒇𝒊𝒓𝒔𝒕 𝑰𝒏𝒕𝒆𝒓𝒊𝒐𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕) =
𝟐

𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑭𝒂𝒄𝒆 𝒐𝒇 𝒐𝒕𝒉𝒆𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕𝒔) =
𝟐

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(78 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 188.37 𝑘𝑁
2 2

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(103 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 248.745 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (49 𝑚 )(3 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 73.5 𝑘𝑁
2 2

MAXIMUM SHEAR 𝟐𝟒𝟖. 𝟕𝟒𝟓 𝒌𝑵


(Grid 4)

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐴 − 𝐵) = 29.85854694 + 29.85854694 + 17.604 = 77.32109388 ≈ 78
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐵 − 𝐶) = 15.624 + 15.624 + 17.604 = 48.852 ≈ 49
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐶 − 𝐷) = 42.47177143 + 42.47177143 + 17.604 = 102.5475429 ≈ 103
𝑚 𝑚 𝑚 𝑚 𝑚
DESIGN SHEAR:

APPROXIMATE METHOD

𝟏. 𝟏𝟓𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑬𝒙𝒕𝒆𝒓𝒊𝒐𝒓 𝒇𝒂𝒄𝒆 𝒐𝒇 𝒇𝒊𝒓𝒔𝒕 𝑰𝒏𝒕𝒆𝒓𝒊𝒐𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕) =
𝟐

𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑭𝒂𝒄𝒆 𝒐𝒇 𝒐𝒕𝒉𝒆𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕𝒔) =
𝟐

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(78 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 188.37 𝑘𝑁
2 2

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(103 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 248.745 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (49 𝑚 )(3 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 73.5 𝑘𝑁
2 2

MAXIMUM SHEAR 𝟐𝟒𝟖. 𝟕𝟒𝟓 𝒌𝑵


(Grid 5)

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐴 − 𝐵) = 29.85854694 + 42.47177143 + 17.604 = 89.93431837 ≈ 90
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐵 − 𝐶) = 15.624 + 15.624 + 17.604 = 48.852 ≈ 49
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐶 − 𝐷) = 42.47177143 + 42.47177143 + 17.604 = 102.5475429 ≈ 103
𝑚 𝑚 𝑚 𝑚 𝑚
DESIGN SHEAR:

APPROXIMATE METHOD

𝟏. 𝟏𝟓𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑬𝒙𝒕𝒆𝒓𝒊𝒐𝒓 𝒇𝒂𝒄𝒆 𝒐𝒇 𝒇𝒊𝒓𝒔𝒕 𝑰𝒏𝒕𝒆𝒓𝒊𝒐𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕) =
𝟐

𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑭𝒂𝒄𝒆 𝒐𝒇 𝒐𝒕𝒉𝒆𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕𝒔) =
𝟐

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(90 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 217.35 𝑘𝑁
2 2

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(103 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 248.745 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (49 𝑚 )(3 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 73.5 𝑘𝑁
2 2

MAXIMUM SHEAR 𝟐𝟒𝟖. 𝟕𝟒𝟓 𝒌𝑵


(Grid 6)

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐴 − 𝐵) = 42.47177143 + 42.47177143 + 17.604 = 102.5475429 ≈ 103
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐵 − 𝐶) = 15.624 + 15.624 + 17.604 = 48.852 ≈ 49
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐶 − 𝐷) = 42.47177143 + 42.47177143 + 17.604 = 102.5475429 ≈ 103
𝑚 𝑚 𝑚 𝑚 𝑚
DESIGN SHEAR:

APPROXIMATE METHOD

𝟏. 𝟏𝟓𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑬𝒙𝒕𝒆𝒓𝒊𝒐𝒓 𝒇𝒂𝒄𝒆 𝒐𝒇 𝒇𝒊𝒓𝒔𝒕 𝑰𝒏𝒕𝒆𝒓𝒊𝒐𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕) =
𝟐

𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑭𝒂𝒄𝒆 𝒐𝒇 𝒐𝒕𝒉𝒆𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕𝒔) =
𝟐

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(103 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 248.745 𝑘𝑁
2 2

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(103 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 248.745 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (49 𝑚 )(3 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 73.5 𝑘𝑁
2 2

MAXIMUM SHEAR 𝟐𝟒𝟖. 𝟕𝟒𝟓 𝒌𝑵


(Grid 7)

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐴 − 𝐵) = 42.47177143 + 21.8736 + 17.604 = 81.94937143 ≈ 82
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐵 − 𝐶) = 15.624 + 15.624 + 17.604 = 48.852 ≈ 49
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐶 − 𝐷) = 42.47177143 + 21.8736 + 17.604 = 81.94937143 ≈ 82
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐷 − 𝐸) = 18.7488 + 17.604 = 36.3528 ≈ 37
𝑚 𝑚 𝑚 𝑚
𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐸 − 𝐹) = 18.7488 + 17.604 = 36.3528 ≈ 37
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐹 − 𝐺) = 18.7488 + 17.604 = 36.3528 ≈ 37
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐺 − 𝐻) = 18.7488 + 17.604 = 36.3528 ≈ 37
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐻 − 𝐼) = 18.7488 + 17.604 = 36.3528 ≈ 37
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐼 − 𝐽) = 14.0616 + 17.604 = 31.6656 ≈ 32
𝑚 𝑚 𝑚 𝑚

DESIGN SHEAR:

APPROXIMATE METHOD

𝟏. 𝟏𝟓𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑬𝒙𝒕𝒆𝒓𝒊𝒐𝒓 𝒇𝒂𝒄𝒆 𝒐𝒇 𝒇𝒊𝒓𝒔𝒕 𝑰𝒏𝒕𝒆𝒓𝒊𝒐𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕) =
𝟐

𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑭𝒂𝒄𝒆 𝒐𝒇 𝒐𝒕𝒉𝒆𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕𝒔) =
𝟐

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(82 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 198.03 𝑘𝑁
2 2

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(32 𝑚 )(2.7 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 49.68 𝑘𝑁
2 2
𝑘𝑁
𝑤𝑢 𝑙𝑛 (49 𝑚 )(3 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 73.5 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (82 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 172.2 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (37 𝑚 )(3.6 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 66.6 𝑘𝑁
2 2

MAXIMUM SHEAR 𝟏𝟗𝟖. 𝟎𝟑 𝒌𝑵


(Grid 8)

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐴 − 𝐵) = 21.8736 + 38.90057143 + 17.604 = 78.37817143 ≈ 79
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐵 − 𝐶) = 15.624 + 15.624 + 17.604 = 48.852 ≈ 49
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐶 − 𝐷) = 21.8736 + 38.90057143 + 17.604 = 78.37817143 ≈ 79
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐷 − 𝐸) = 18.7488 + 36.022 + 17.604 = 72.3748 ≈ 73
𝑚 𝑚 𝑚 𝑚 𝑚
𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐸 − 𝐹) = 18.7488 + 36.022 + 17.604 = 72.3748 ≈ 73
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐹 − 𝐺) = 18.7488 + 36.022 + 17.604 = 72.3748 ≈ 73
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐺 − 𝐻) = 18.7488 + 36.022 + 17.604 = 72.3748 ≈ 73
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐻 − 𝐼) = 18.7488 + 36.022 + 17.604 = 72.3748 ≈ 73
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐼 − 𝐽) = 14.0616 + 14.0616 + 17.604 = 45.7272 ≈ 46
𝑚 𝑚 𝑚 𝑚 𝑚

DESIGN SHEAR:

APPROXIMATE METHOD

𝟏. 𝟏𝟓𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑬𝒙𝒕𝒆𝒓𝒊𝒐𝒓 𝒇𝒂𝒄𝒆 𝒐𝒇 𝒇𝒊𝒓𝒔𝒕 𝑰𝒏𝒕𝒆𝒓𝒊𝒐𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕) =
𝟐

𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑭𝒂𝒄𝒆 𝒐𝒇 𝒐𝒕𝒉𝒆𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕𝒔) =
𝟐

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(79 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 190.785 𝑘𝑁
2 2

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(46 𝑚 )(2.7 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 71.415 𝑘𝑁
2 2
𝑘𝑁
𝑤𝑢 𝑙𝑛 (49 𝑚 )(3 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 73.5 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (79 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 165.9 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (73 𝑚 )(3.6 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 131.4 𝑘𝑁
2 2

MAXIMUM SHEAR 𝟏𝟗𝟎. 𝟕𝟖𝟓 𝒌𝑵


(Grid 9)

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐴 − 𝐵) = 38.90057143  + 21.8736  + 17.604  = 78.37817143  ≈ 79
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐵 − 𝐶) = 15.624  + 15.624  + 17.604  = 48.852  ≈ 49
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐶 − 𝐷) = 38.90057143  + 21.8736  + 17.604  = 78.37817143  ≈ 79
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐷 − 𝐸) = 36.022  + 18.7488  + 17.604  = 72.3748  ≈ 73
𝑚 𝑚 𝑚 𝑚 𝑚
𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐸 − 𝐹) = 36.022  + 18.7488  + 17.604  = 72.3748  ≈ 73
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐹 − 𝐺) = 36.022  + 18.7488  + 17.604  = 72.3748  ≈ 73
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐺 − 𝐻) = 36.022  + 18.7488  + 17.604  = 72.3748  ≈ 73
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐻 − 𝐼) = 36.022  + 18.7488  + 17.604  = 72.3748  ≈ 73
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐼 − 𝐽) = 14.0616  + 14.0616  + 17.604  = 45.7272  ≈ 46
𝑚 𝑚 𝑚 𝑚 𝑚

DESIGN SHEAR:

APPROXIMATE METHOD

𝟏. 𝟏𝟓𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑬𝒙𝒕𝒆𝒓𝒊𝒐𝒓 𝒇𝒂𝒄𝒆 𝒐𝒇 𝒇𝒊𝒓𝒔𝒕 𝑰𝒏𝒕𝒆𝒓𝒊𝒐𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕) =
𝟐

𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑭𝒂𝒄𝒆 𝒐𝒇 𝒐𝒕𝒉𝒆𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕𝒔) =
𝟐

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(79 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 190.785 𝑘𝑁
2 2

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(46 𝑚 )(2.7 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 71.415 𝑘𝑁
2 2
𝑘𝑁
𝑤𝑢 𝑙𝑛 (49 𝑚 )(3 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 73.5 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (79 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 165.9 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (73 𝑚 )(3.6 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 131.4 𝑘𝑁
2 2

MAXIMUM SHEAR 𝟏𝟗𝟎. 𝟕𝟖𝟓 𝒌𝑵


(Grid 10)

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐴 − 𝐵) = 21.8736  + 17.604  = 39.4776  ≈ 40
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐵 − 𝐶) = 15.624  + 17.604  = 33.228  ≈ 34
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐶 − 𝐷) = 21.8736  + 17.604  = 39.4776  ≈ 40
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐷 − 𝐸) = 18.7488  + 17.604  = 36.3528  ≈ 37
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐸 − 𝐹) = 18.7488  + 17.604  = 36.3528  ≈ 37
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐹 − 𝐺) = 18.7488  + 17.604  = 36.3528  ≈ 37
𝑚 𝑚 𝑚 𝑚
𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐺 − 𝐻) = 18.7488  + 17.604  = 36.3528  ≈ 37
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐻 − 𝐼) = 18.7488  + 17.604  = 36.3528  ≈ 37
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐼 − 𝐽) = 14.0616  + 17.604  = 31.6656  ≈ 32
𝑚 𝑚 𝑚 𝑚

DESIGN SHEAR:

APPROXIMATE METHOD

𝟏. 𝟏𝟓𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑬𝒙𝒕𝒆𝒓𝒊𝒐𝒓 𝒇𝒂𝒄𝒆 𝒐𝒇 𝒇𝒊𝒓𝒔𝒕 𝑰𝒏𝒕𝒆𝒓𝒊𝒐𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕) =
𝟐

𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑭𝒂𝒄𝒆 𝒐𝒇 𝒐𝒕𝒉𝒆𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕𝒔) =
𝟐

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(40 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 96.6 𝑘𝑁
2 2

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(32 𝑚 )(2.7 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 49.68 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (34 𝑚 )(3 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 51 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (40 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 84 𝑘𝑁
2 2
𝑘𝑁
𝑤𝑢 𝑙𝑛 (37 𝑚 )(3.6 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 66.6 𝑘𝑁
2 2

MAXIMUM SHEAR 𝟗𝟔. 𝟔 𝒌𝑵


2ND FLOOR = 3RD FLOOR = 4TH FLOOR

(Grid 1)

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐴 − 𝐵) = 27.43387347 + 17.604 = 45.03787347 ≈ 46
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐵 − 𝐶) = 30.794904 + 17.604 = 48.398904 ≈ 49
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐶 − 𝐷) = 36.37362857 + 17.604 = 53.97762857 ≈ 54
𝑚 𝑚 𝑚 𝑚
DESIGN SHEAR:

APPROXIMATE METHOD

𝟏. 𝟏𝟓𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑬𝒙𝒕𝒆𝒓𝒊𝒐𝒓 𝒇𝒂𝒄𝒆 𝒐𝒇 𝒇𝒊𝒓𝒔𝒕 𝑰𝒏𝒕𝒆𝒓𝒊𝒐𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕) =
𝟐

𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑭𝒂𝒄𝒆 𝒐𝒇 𝒐𝒕𝒉𝒆𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕𝒔) =
𝟐

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(46 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 111.09 𝑘𝑁
2 2

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(54 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 130.41 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (49 𝑚 )(3 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 73.5 𝑘𝑁
2 2

MAXIMUM SHEAR 𝟏𝟑𝟎. 𝟒𝟏 𝒌𝑵


(Grid 2)

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐴 − 𝐵) = 27.43387347 + 29.85854694 + 17.604 = 74.89642041 ≈ 75
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐵 − 𝐶) = 30.794904 + 15.624 + 17.604 = 64.022904 ≈ 65
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐶 − 𝐷) = 36.37362857 + 29.85854694 + 17.604 = 83.83617551 ≈ 84
𝑚 𝑚 𝑚 𝑚 𝑚
DESIGN SHEAR:

APPROXIMATE METHOD

𝟏. 𝟏𝟓𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑬𝒙𝒕𝒆𝒓𝒊𝒐𝒓 𝒇𝒂𝒄𝒆 𝒐𝒇 𝒇𝒊𝒓𝒔𝒕 𝑰𝒏𝒕𝒆𝒓𝒊𝒐𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕) =
𝟐

𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑭𝒂𝒄𝒆 𝒐𝒇 𝒐𝒕𝒉𝒆𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕𝒔) =
𝟐

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(75 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 181.125 𝑘𝑁
2 2

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(84 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 202.86 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (65 𝑚 )(3 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 97.5 𝑘𝑁
2 2

MAXIMUM SHEAR 202.86 𝒌𝑵


(Grid 3)

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐴 − 𝐵) = 29.85854694 + 29.85854694 + 17.604 = 77.32109388 ≈ 78
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐵 − 𝐶) = 15.624 + 15.624 + 17.604 = 48.852 ≈ 49
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐶 − 𝐷) = 29.85854694 + 29.85854694 + 17.604 = 77.32109388 ≈ 78
𝑚 𝑚 𝑚 𝑚 𝑚
DESIGN SHEAR:

APPROXIMATE METHOD

𝟏. 𝟏𝟓𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑬𝒙𝒕𝒆𝒓𝒊𝒐𝒓 𝒇𝒂𝒄𝒆 𝒐𝒇 𝒇𝒊𝒓𝒔𝒕 𝑰𝒏𝒕𝒆𝒓𝒊𝒐𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕) =
𝟐

𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑭𝒂𝒄𝒆 𝒐𝒇 𝒐𝒕𝒉𝒆𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕𝒔) =
𝟐

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(78 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 188.37 𝑘𝑁
2 2

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(78 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 188.37 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (49 𝑚 )(3 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 73.5 𝑘𝑁
2 2

MAXIMUM SHEAR 188.37 𝒌𝑵


(Grid 4)

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐴 − 𝐵) = 29.85854694 + 29.85854694 + 17.604 = 77.32109388 ≈ 78
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐵 − 𝐶) = 15.624 + 15.624 + 17.604 = 48.852 ≈ 49
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐶 − 𝐷) = 29.85854694 + 29.85854694 + 17.604 = 77.32109388 ≈ 78
𝑚 𝑚 𝑚 𝑚 𝑚
DESIGN SHEAR:

APPROXIMATE METHOD

𝟏. 𝟏𝟓𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑬𝒙𝒕𝒆𝒓𝒊𝒐𝒓 𝒇𝒂𝒄𝒆 𝒐𝒇 𝒇𝒊𝒓𝒔𝒕 𝑰𝒏𝒕𝒆𝒓𝒊𝒐𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕) =
𝟐

𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑭𝒂𝒄𝒆 𝒐𝒇 𝒐𝒕𝒉𝒆𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕𝒔) =
𝟐

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(78 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 188.37 𝑘𝑁
2 2

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(78 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 188.37 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (49 𝑚 )(3 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 73.5 𝑘𝑁
2 2

MAXIMUM SHEAR 188.37 𝒌𝑵


(Grid 5)

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐴 − 𝐵) = 29.85854694 + 29.85854694 + 17.604 = 77.32109388 ≈ 78
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐵 − 𝐶) = 15.624 𝑚
+ 15.624 𝑚
+ 17.604 𝑚
= 48.852 𝑚
≈ 49 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐶 − 𝐷) = 29.85854694 + 29.85854694 + 17.604 = 77.32109388 ≈ 78
𝑚 𝑚 𝑚 𝑚 𝑚
DESIGN SHEAR:

APPROXIMATE METHOD

𝟏. 𝟏𝟓𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑬𝒙𝒕𝒆𝒓𝒊𝒐𝒓 𝒇𝒂𝒄𝒆 𝒐𝒇 𝒇𝒊𝒓𝒔𝒕 𝑰𝒏𝒕𝒆𝒓𝒊𝒐𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕) =
𝟐

𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑭𝒂𝒄𝒆 𝒐𝒇 𝒐𝒕𝒉𝒆𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕𝒔) =
𝟐

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(78 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 188.37 𝑘𝑁
2 2

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(78 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 188.37 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (49 𝑚 )(3 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 73.5 𝑘𝑁
2 2

MAXIMUM SHEAR 188.37 𝒌𝑵


(Grid 6)

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐴 − 𝐵) = 29.85854694 + 29.85854694 + 17.604 = 77.32109388 ≈ 78
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐵 − 𝐶) = 15.624 + 15.624 + 17.604 = 48.852 ≈ 49
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐶 − 𝐷) = 29.85854694 + 42.47177143 + 17.604 = 89.93431837 ≈ 90
𝑚 𝑚 𝑚 𝑚 𝑚
DESIGN SHEAR:

APPROXIMATE METHOD

𝟏. 𝟏𝟓𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑬𝒙𝒕𝒆𝒓𝒊𝒐𝒓 𝒇𝒂𝒄𝒆 𝒐𝒇 𝒇𝒊𝒓𝒔𝒕 𝑰𝒏𝒕𝒆𝒓𝒊𝒐𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕) =
𝟐

𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑭𝒂𝒄𝒆 𝒐𝒇 𝒐𝒕𝒉𝒆𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕𝒔) =
𝟐

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(78 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 188.37 𝑘𝑁
2 2

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(90 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 217.35 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (49 𝑚 )(3 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 73.5 𝑘𝑁
2 2

MAXIMUM SHEAR 217.35 𝒌𝑵


(Grid 7)

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐴 − 𝐵) = 29.85854694 + 21.8736 + 17.604 = 69.33614694 ≈ 70
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐵 − 𝐶) = 15.624 + 15.624 + 17.604 = 48.852 ≈ 49
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐶 − 𝐷) = 29.85854694 + 21.8736 + 17.604 = 69.33614694 ≈ 70
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐷 − 𝐸) = 18.7488 + 17.604 = 36.3528 ≈ 37
𝑚 𝑚 𝑚 𝑚
𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐸 − 𝐹) = 18.7488 + 17.604 = 36.3528 ≈ 37
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐹 − 𝐺) = 18.7488 + 17.604 = 36.3528 ≈ 37
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐺 − 𝐻) = 18.7488 + 17.604 = 36.3528 ≈ 37
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐻 − 𝐼) = 18.7488 + 17.604 = 36.3528 ≈ 37
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐼 − 𝐽) = 14.0616 + 17.604 = 31.6656 ≈ 32
𝑚 𝑚 𝑚 𝑚

DESIGN SHEAR:

APPROXIMATE METHOD

𝟏. 𝟏𝟓𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑬𝒙𝒕𝒆𝒓𝒊𝒐𝒓 𝒇𝒂𝒄𝒆 𝒐𝒇 𝒇𝒊𝒓𝒔𝒕 𝑰𝒏𝒕𝒆𝒓𝒊𝒐𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕) =
𝟐

𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑭𝒂𝒄𝒆 𝒐𝒇 𝒐𝒕𝒉𝒆𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕𝒔) =
𝟐

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(70 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 169.05 𝑘𝑁
2 2
𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(32 𝑚 )(2.7 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 49.68 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (49 𝑚 )(3 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 73.5 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (70 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 147 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (37 𝑚 )(3.6 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 66.6 𝑘𝑁
2 2

MAXIMUM SHEAR 169.05 𝒌𝑵


(Grid 8)

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐴 − 𝐵) = 21.8736 + 38.90057143 + 17.604 = 78.37817143 ≈ 79
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐵 − 𝐶) = 15.624 + 15.624 + 17.604 = 48.852 ≈ 49
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐶 − 𝐷) = 21.8736 + 38.90057143 + 17.604 = 78.37817143 ≈ 79
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐷 − 𝐸) = 18.7488 + 36.022 + 17.604 = 72.3748 ≈ 73
𝑚 𝑚 𝑚 𝑚 𝑚
𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐸 − 𝐹) = 18.7488 + 36.022 + 17.604 = 72.3748 ≈ 73
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐹 − 𝐺) = 18.7488 + 36.022 + 17.604 = 72.3748 ≈ 73
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐺 − 𝐻) = 18.7488 + 36.022 + 17.604 = 72.3748 ≈ 73
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐻 − 𝐼) = 18.7488 + 36.022 + 17.604 = 72.3748 ≈ 73
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐼 − 𝐽) = 14.0616 + 14.0616 + 17.604 = 45.7272 ≈ 46
𝑚 𝑚 𝑚 𝑚 𝑚

DESIGN SHEAR:

APPROXIMATE METHOD

𝟏. 𝟏𝟓𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑬𝒙𝒕𝒆𝒓𝒊𝒐𝒓 𝒇𝒂𝒄𝒆 𝒐𝒇 𝒇𝒊𝒓𝒔𝒕 𝑰𝒏𝒕𝒆𝒓𝒊𝒐𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕) =
𝟐

𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑭𝒂𝒄𝒆 𝒐𝒇 𝒐𝒕𝒉𝒆𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕𝒔) =
𝟐

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(79 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 190.785 𝑘𝑁
2 2

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(46 𝑚 )(2.7 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 71.415 𝑘𝑁
2 2
𝑘𝑁
𝑤𝑢 𝑙𝑛 (49 𝑚 )(3 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 73.5 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (79 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 165.9 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (73 𝑚 )(3.6 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 131.4 𝑘𝑁
2 2

MAXIMUM SHEAR 190.785 𝒌𝑵


(Grid 9)

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐴 − 𝐵) = 38.90057143  + 21.8736  + 17.604  = 78.37817143  ≈ 79
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐵 − 𝐶) = 15.624  + 15.624  + 17.604  = 48.852  ≈ 49
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐶 − 𝐷) = 38.90057143  + 21.8736  + 17.604  = 78.37817143  ≈ 79
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐷 − 𝐸) = 36.022  𝑚
+ 18.7488  𝑚
+ 17.604  𝑚
= 72.3748  𝑚
≈ 73 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐸 − 𝐹) = 36.022  + 18.7488  + 17.604  = 72.3748  ≈ 73
𝑚 𝑚 𝑚 𝑚 𝑚
𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐹 − 𝐺) = 36.022  𝑚
+ 18.7488  𝑚
+ 17.604  𝑚
= 72.3748  𝑚
≈ 73 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐺 − 𝐻) = 36.022  + 18.7488  + 17.604  = 72.3748  ≈ 73
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐻 − 𝐼) = 36.022  𝑚
+ 18.7488  𝑚
+ 17.604  𝑚
= 72.3748  𝑚
≈ 73 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐼 − 𝐽) = 14.0616  𝑚
+ 14.0616  𝑚
+ 17.604  𝑚
= 45.7272  𝑚
≈ 46 𝑚

DESIGN SHEAR:

APPROXIMATE METHOD

𝟏. 𝟏𝟓𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑬𝒙𝒕𝒆𝒓𝒊𝒐𝒓 𝒇𝒂𝒄𝒆 𝒐𝒇 𝒇𝒊𝒓𝒔𝒕 𝑰𝒏𝒕𝒆𝒓𝒊𝒐𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕) =
𝟐

𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑭𝒂𝒄𝒆 𝒐𝒇 𝒐𝒕𝒉𝒆𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕𝒔) =
𝟐

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(79 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 190.875 𝑘𝑁
2 2

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(46 𝑚 )(2.7 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 71.415 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (49 𝑚 )(3𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 73.5 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (79 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 165.9 𝑘𝑁
2 2
𝑘𝑁
𝑤𝑢 𝑙𝑛 (73 𝑚 )(3.6 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 131.4 𝑘𝑁
2 2

MAXIMUM SHEAR 190.875 𝒌𝑵


(Grid 10)

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐴 − 𝐵) = 21.8736  + 17.604  = 39.4776  ≈ 40
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐵 − 𝐶) = 15.624  + 17.604  = 33.228  ≈ 34
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐶 − 𝐷) = 21.8736  + 17.604  = 39.4776  ≈ 40
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐷 − 𝐸) = 18.7488  + 17.604  = 36.3528  ≈ 37
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐸 − 𝐹) = 18.7488  + 17.604  = 36.3528  ≈ 37
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐹 − 𝐺) = 18.7488  + 17.604  = 36.3528  ≈ 37
𝑚 𝑚 𝑚 𝑚
𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐺 − 𝐻) = 18.7488  + 17.604  = 36.3528  ≈ 37
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐻 − 𝐼) = 18.7488  + 17.604  = 36.3528  ≈ 37
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐼 − 𝐽) = 14.0616  + 17.604  = 31.6656  ≈ 32
𝑚 𝑚 𝑚 𝑚

DESIGN SHEAR:

APPROXIMATE METHOD

𝟏. 𝟏𝟓𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑬𝒙𝒕𝒆𝒓𝒊𝒐𝒓 𝒇𝒂𝒄𝒆 𝒐𝒇 𝒇𝒊𝒓𝒔𝒕 𝑰𝒏𝒕𝒆𝒓𝒊𝒐𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕) =
𝟐

𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑭𝒂𝒄𝒆 𝒐𝒇 𝒐𝒕𝒉𝒆𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕𝒔) =
𝟐

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(40 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 96.6 𝑘𝑁
2 2

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(32 𝑚 )(2.7 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 49.68 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (34 𝑚 )(3𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 51 𝑘𝑁
2 2
𝑘𝑁
𝑤𝑢 𝑙𝑛 (40 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 84 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (37 𝑚 )(3.6 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 66.6 𝑘𝑁
2 2

MAXIMUM SHEAR 96.6 𝒌𝑵


ROOF

(GRID 1)

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐴 − 𝐵) = 0.8102 + 5.184 = 5.9942 ≈6
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐴 − 𝐵) = 0.6859 + 5.184 = 5.8699 ≈6
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐶 − 𝐷) = 0.8102 + 5.184 = 5.9942 ≈6
𝑚 𝑚 𝑚 𝑚
DESIGN SHEAR:

APPROXIMATE METHOD

𝟏. 𝟏𝟓𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑬𝒙𝒕𝒆𝒓𝒊𝒐𝒓 𝒇𝒂𝒄𝒆 𝒐𝒇 𝒇𝒊𝒓𝒔𝒕 𝑰𝒏𝒕𝒆𝒓𝒊𝒐𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕) =
𝟐

𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑭𝒂𝒄𝒆 𝒐𝒇 𝒐𝒕𝒉𝒆𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕𝒔) =
𝟐

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(6 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 14.49 𝑘𝑁
2 2

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(6 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 14.49 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (6 𝑚 )(3 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 9 𝑘𝑁
2 2

MAXIMUM SHEAR 𝟏𝟒. 𝟒𝟗 𝒌𝑵


(GRID 2)

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐴 − 𝐵) = 0.8102 + 0.9460 + 5.184 = 6.9402 ≈7
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐵 − 𝐶) = 0.6859 + 0.3132 + 5.184 = 6.1831 ≈7
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐶 − 𝐷) = 0.8102 + 0.9460 + 5.184 = 6.9402 ≈7
𝑚 𝑚 𝑚 𝑚 𝑚
DESIGN SHEAR:

APPROXIMATE METHOD

𝟏. 𝟏𝟓𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑬𝒙𝒕𝒆𝒓𝒊𝒐𝒓 𝒇𝒂𝒄𝒆 𝒐𝒇 𝒇𝒊𝒓𝒔𝒕 𝑰𝒏𝒕𝒆𝒓𝒊𝒐𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕) =
𝟐

𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑭𝒂𝒄𝒆 𝒐𝒇 𝒐𝒕𝒉𝒆𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕𝒔) =
𝟐

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(7 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 16.905 𝑘𝑁
2 2

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(7 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 16.905 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (7 𝑚 )(3 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 10.5 𝑘𝑁
2 2

MAXIMUM SHEAR 16.905 𝒌𝑵


(GRID 3)

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐴 − 𝐵) = 0.6515 + 0.6515 + 5.184 = 6.487 ≈7
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐵 − 𝐶) = 0.348 + 0.348 + 5.184 = 5.88 ≈6
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐶 − 𝐷) = 0.6515 + 0.6515 + 5.184 = 6.487 ≈7
𝑚 𝑚 𝑚 𝑚 𝑚
DESIGN SHEAR:

APPROXIMATE METHOD

𝟏. 𝟏𝟓𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑬𝒙𝒕𝒆𝒓𝒊𝒐𝒓 𝒇𝒂𝒄𝒆 𝒐𝒇 𝒇𝒊𝒓𝒔𝒕 𝑰𝒏𝒕𝒆𝒓𝒊𝒐𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕) =
𝟐

𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑭𝒂𝒄𝒆 𝒐𝒇 𝒐𝒕𝒉𝒆𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕𝒔) =
𝟐

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(7 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 16.905 𝑘𝑁
2 2

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(7 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 16.905 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (6 𝑚 )(3 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 9 𝑘𝑁
2 2

MAXIMUM SHEAR 16.905 𝒌𝑵


(GRID 4)

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐴 − 𝐵) = 0.6515 + 0.6515 + 5.184 = 6.487 ≈7
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐵 − 𝐶) = 0.348 + 0.348 + 5.184 = 5.88 ≈6
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐶 − 𝐷) = 0.6515 + 0.6515 + 5.184 = 6.487 ≈7
𝑚 𝑚 𝑚 𝑚 𝑚
DESIGN SHEAR:

APPROXIMATE METHOD

𝟏. 𝟏𝟓𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑬𝒙𝒕𝒆𝒓𝒊𝒐𝒓 𝒇𝒂𝒄𝒆 𝒐𝒇 𝒇𝒊𝒓𝒔𝒕 𝑰𝒏𝒕𝒆𝒓𝒊𝒐𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕) =
𝟐

𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑭𝒂𝒄𝒆 𝒐𝒇 𝒐𝒕𝒉𝒆𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕𝒔) =
𝟐

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(7 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 16.905 𝑘𝑁
2 2

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(7 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 16.905 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (6 𝑚 )(3 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 9 𝑘𝑁
2 2

MAXIMUM SHEAR 𝟏𝟔. 𝟗𝟎𝟓 𝒌𝑵


(GRID 5)

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐴 − 𝐵) = 0.6515 + 0.6515 + 5.184 = 6.487 ≈7
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐵 − 𝐶) = 0.348 + 0.348 + 5.184 = 5.88 ≈6
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐶 − 𝐷) = 0.6515 + 0.6515 + 5.184 = 6.487 ≈7
𝑚 𝑚 𝑚 𝑚 𝑚
DESIGN SHEAR:

APPROXIMATE METHOD

𝟏. 𝟏𝟓𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑬𝒙𝒕𝒆𝒓𝒊𝒐𝒓 𝒇𝒂𝒄𝒆 𝒐𝒇 𝒇𝒊𝒓𝒔𝒕 𝑰𝒏𝒕𝒆𝒓𝒊𝒐𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕) =
𝟐

𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑭𝒂𝒄𝒆 𝒐𝒇 𝒐𝒕𝒉𝒆𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕𝒔) =
𝟐

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(7 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 16.905 𝑘𝑁
2 2

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(7 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 16.905 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (6 𝑚 )(3 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 9 𝑘𝑁
2 2

MAXIMUM SHEAR 16.905 𝒌𝑵


(GRID 6)

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐴 − 𝐵) = 0.6515 + 0.6515 + 5.184 = 6.487 ≈7
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐵 − 𝐶) = 0.348 + 0.348 + 5.184 = 5.88 ≈6
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐶 − 𝐷) = 0.6515 + 0.6515 + 5.184 = 6.487 ≈7
𝑚 𝑚 𝑚 𝑚 𝑚
DESIGN SHEAR:

APPROXIMATE METHOD

𝟏. 𝟏𝟓𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑬𝒙𝒕𝒆𝒓𝒊𝒐𝒓 𝒇𝒂𝒄𝒆 𝒐𝒇 𝒇𝒊𝒓𝒔𝒕 𝑰𝒏𝒕𝒆𝒓𝒊𝒐𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕) =
𝟐

𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑭𝒂𝒄𝒆 𝒐𝒇 𝒐𝒕𝒉𝒆𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕𝒔) =
𝟐

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(7 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 16.905 𝑘𝑁
2 2

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(7 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 16.905 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (6 𝑚 )(3 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 9 𝑘𝑁
2 2

MAXIMUM SHEAR 𝟏𝟔. 𝟗𝟎𝟓 𝒌𝑵


(GRID 7)

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐴 − 𝐵) = 0.6515 + 0.4872 + 5.184 = 6.3227 ≈7
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐵 − 𝐶) = 0.348 + 0.348 + 5.184 = 5.88 ≈6
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐶 − 𝐷) = 0.6515 + 0.4872 + 5.184 = 6.3227 ≈7
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐷 − 𝐸) = 0.4176 + 5.184 = 5.6016 ≈6
𝑚 𝑚 𝑚 𝑚
𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐸 − 𝐹) = 0.4176 + 5.184 = 5.6016 ≈6
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐹 − 𝐺) = 0.4176 + 5.184 = 5.6016 ≈6
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐺 − 𝐻) = 0.4176 + 5.184 = 5.6016 ≈6
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐻 − 𝐼) = 0.4176 + 5.184 = 5.6016 ≈6
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐼 − 𝐽) = 0.3132 + 5.184 = 5.4972 ≈6
𝑚 𝑚 𝑚 𝑚

DESIGN SHEAR:

APPROXIMATE METHOD

𝟏. 𝟏𝟓𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑬𝒙𝒕𝒆𝒓𝒊𝒐𝒓 𝒇𝒂𝒄𝒆 𝒐𝒇 𝒇𝒊𝒓𝒔𝒕 𝑰𝒏𝒕𝒆𝒓𝒊𝒐𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕) =
𝟐

𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑭𝒂𝒄𝒆 𝒐𝒇 𝒐𝒕𝒉𝒆𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕𝒔) =
𝟐

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(7 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 16.905 𝑘𝑁
2 2

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(6 𝑚 )(2.7 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 9.315 𝑘𝑁
2 2
𝑘𝑁
𝑤𝑢 𝑙𝑛 (6 𝑚 )(3 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 9 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (7 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 14.7 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (6 𝑚 )(3.6 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 10.8 𝑘𝑁
2 2

MAXIMUM SHEAR 𝟏𝟔. 𝟗𝟎𝟓 𝒌𝑵


(GRID 8)

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐴 − 𝐵) = 0.6515 + 0.696 + 5.184 = 6.5315 ≈7
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐵 − 𝐶) = 0.348 + 0.348 + 5.184 = 5.88 ≈6
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐶 − 𝐷) = 0.4176 + 0.348 + 5.184 = 5.9496 ≈6
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐷 − 𝐸) = 0.4176 + 0.348 + 5.184 = 5.9496 ≈6
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐸 − 𝐹) = 0.4176 + 0.348 + 5.184 = 5.9496 ≈6
𝑚 𝑚 𝑚 𝑚 𝑚
𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐹 − 𝐺) = 0.4176 + 0.348 + 5.184 = 5.9496 ≈6
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐺 − 𝐻) = 0.4176 + 0.348 + 5.184 = 5.9496 ≈6
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐻 − 𝐼) = 0.4176 + 0.348 + 5.184 = 5.9496 ≈6
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐼 − 𝐽) = 0.3132 + 0.6859 + 5.184 = 6.1831 ≈7
𝑚 𝑚 𝑚 𝑚 𝑚

DESIGN SHEAR:

APPROXIMATE METHOD

𝟏. 𝟏𝟓𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑬𝒙𝒕𝒆𝒓𝒊𝒐𝒓 𝒇𝒂𝒄𝒆 𝒐𝒇 𝒇𝒊𝒓𝒔𝒕 𝑰𝒏𝒕𝒆𝒓𝒊𝒐𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕) =
𝟐

𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑭𝒂𝒄𝒆 𝒐𝒇 𝒐𝒕𝒉𝒆𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕𝒔) =
𝟐

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(7 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 16.905 𝑘𝑁
2 2

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(7 𝑚 )(2.7 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 10.8675 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (6 𝑚 )(3 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 9 𝑘𝑁
2 2
𝑘𝑁
𝑤𝑢 𝑙𝑛 (6 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 12.6 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (6 𝑚 )(3.6 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 10.8 𝑘𝑁
2 2

MAXIMUM SHEAR 𝟏𝟔. 𝟗𝟎𝟓 𝒌𝑵


(GRID 9)

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐴 − 𝐵) = 0.8664 + 0.4872 + 5.184 = 6.5376 ≈7
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐵 − 𝐶) = 0.348 + 0.348 + 5.184 = 5.88 ≈6
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐶 − 𝐷) = 0.8664 + 0.4872 + 5.184 = 6.5376 ≈7
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐷 − 𝐸) = 0.8023 + 0.4176 + 5.184 = 6.4039 ≈7
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐸 − 𝐹) = 0.8023 + 0.4176 + 5.184 = 6.4039 ≈7
𝑚 𝑚 𝑚 𝑚
𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐹 − 𝐺) = 0.8023 + 0.4176 + 5.184 = 6.4039 ≈7
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐺 − 𝐻) = 0.8023 + 0.4176 + 5.184 = 6.4039 ≈7
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐻 − 𝐼) = 0.8023 + 0.4176 + 5.184 = 6.4039 ≈7
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐼 − 𝐽) = 0.3132 + 0.3132 + 5.184 = 5.8104 ≈6
𝑚 𝑚 𝑚 𝑚

DESIGN SHEAR:

APPROXIMATE METHOD

𝟏. 𝟏𝟓𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑬𝒙𝒕𝒆𝒓𝒊𝒐𝒓 𝒇𝒂𝒄𝒆 𝒐𝒇 𝒇𝒊𝒓𝒔𝒕 𝑰𝒏𝒕𝒆𝒓𝒊𝒐𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕) =
𝟐

𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑭𝒂𝒄𝒆 𝒐𝒇 𝒐𝒕𝒉𝒆𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕𝒔) =
𝟐

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(7 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 16.905 𝑘𝑁
2 2

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(6 𝑚 )(2.7 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 9.315 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (6 𝑚 )(3 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 9 𝑘𝑁
2 2
𝑘𝑁
𝑤𝑢 𝑙𝑛 (7 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 14.7 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (7 𝑚 )(3.6 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 12.6 𝑘𝑁
2 2

MAXIMUM SHEAR 𝟏𝟔. 𝟗𝟎𝟓 𝒌𝑵


(GRID 10)

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐴 − 𝐵) = 0.4872 + 5.184 = 5.6712 ≈6
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐵 − 𝐶) = 0.348 + 5.184 = 5.532 ≈6
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐶 − 𝐷) = 0.4872 + 5.184 = 5.6712 ≈6
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐷 − 𝐸) = 0.4176 + 5.184 = 5.6016 ≈6
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐸 − 𝐹) = 0.4176 + 5.184 = 5.6016 ≈6
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐹 − 𝐺) = 0.4176 + 5.184 = 5.6016 ≈6
𝑚 𝑚 𝑚 𝑚
𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐺 − 𝐻) = 0.4176 + 5.184 = 5.6016 ≈6
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐻 − 𝐼) = 0.4176 + 5.184 = 5.6016 ≈6
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (𝐼 − 𝐽) = 0.3132 + 5.184 = 5.4972 ≈6
𝑚 𝑚 𝑚 𝑚

DESIGN SHEAR:

APPROXIMATE METHOD

𝟏. 𝟏𝟓𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑬𝒙𝒕𝒆𝒓𝒊𝒐𝒓 𝒇𝒂𝒄𝒆 𝒐𝒇 𝒇𝒊𝒓𝒔𝒕 𝑰𝒏𝒕𝒆𝒓𝒊𝒐𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕) =
𝟐

𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑭𝒂𝒄𝒆 𝒐𝒇 𝒐𝒕𝒉𝒆𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕𝒔) =
𝟐

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(6 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 14.49 𝑘𝑁
2 2

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(6 𝑚 )(2.7 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 9.315 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (6 𝑚 )(3 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 9 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (6 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 12.6 𝑘𝑁
2 2
𝑘𝑁
𝑤𝑢 𝑙𝑛 (6 𝑚 )(3.6 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 10.8 𝑘𝑁
2 2

MAXIMUM SHEAR 14.49 𝒌𝑵


Structural Analysis
(Vertical Beams)
GROUND FLOOR

(GRID A)
𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (1 − 2) = 7.575428571 + 17.604 = 25.17942857 ≈ 26
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (2 − 3) = 9.414857143 + 17.604 = 27.01885714 ≈ 28
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (3 − 4) = 9.414857143 + 17.604 = 27.01885714 ≈ 28
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (4 − 5) = 9.414857143 + 17.604 = 27.01885714 ≈ 28
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (5 − 6) = 13.392 + 17.604 = 30.996 ≈ 31
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (6 − 7) = 13.392 + 17.604 = 30.996 ≈ 31
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (7 − 8) = 15.624 + 17.604 = 33.228 ≈ 34
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (8 − 9) = 11.16 + 17.604 = 28.764 ≈ 29
𝑚 𝑚 𝑚 𝑚

DESIGN SHEAR:

APPROXIMATE METHOD

𝟏. 𝟏𝟓𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑬𝒙𝒕𝒆𝒓𝒊𝒐𝒓 𝒇𝒂𝒄𝒆 𝒐𝒇 𝒇𝒊𝒓𝒔𝒕 𝑰𝒏𝒕𝒆𝒓𝒊𝒐𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕) =
𝟐

𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑭𝒂𝒄𝒆 𝒐𝒇 𝒐𝒕𝒉𝒆𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕𝒔) =
𝟐
𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(26 𝑚 )(2.7 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 40.365 𝑘𝑁
2 2

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(29 𝑚 )(3 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 50.025 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (28 𝑚 )(3.6 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 50.4 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (31 𝑚 )(3.6 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 55.8 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (34 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 71.4 𝑘𝑁
2 2

MAXIMUM SHEAR 𝟕𝟏. 𝟒 𝒌𝑵


(GRID B)
𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (1 − 2) = 7.575428571 + 14.0616 + 17.604 = 39.24102857 ≈ 40
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (2 − 3) = 9.414857143 + 36.022 + 17.604 = 63.04085714 ≈ 64
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (3 − 4) = 9.414857143 + 36.022 + 17.604 = 63.04085714 ≈ 64
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (4 − 5) = 9.414857143 + 36.022 + 17.604 = 63.04085714 ≈ 64
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (5 − 6) = 13.392 + 36.022 + 17.604 = 67.018 ≈ 68
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (6 − 7) = 13.392 + 36.022 + 17.604 = 67.018 ≈ 68
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (7 − 8) = 15.624 + 38.90057143 + 17.604 = 72.12857143 ≈ 73
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (8 − 9) = 11.16 + 15.624 + 17.604 = 44.388 ≈ 45
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (9 − 10) = 38.90057143 + 17.604 = 56.50457143 ≈ 57
𝑚 𝑚 𝑚 𝑚

DESIGN SHEAR:

APPROXIMATE METHOD

𝟏. 𝟏𝟓𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑬𝒙𝒕𝒆𝒓𝒊𝒐𝒓 𝒇𝒂𝒄𝒆 𝒐𝒇 𝒇𝒊𝒓𝒔𝒕 𝑰𝒏𝒕𝒆𝒓𝒊𝒐𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕) =
𝟐
𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑭𝒂𝒄𝒆 𝒐𝒇 𝒐𝒕𝒉𝒆𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕𝒔) =
𝟐

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(40 𝑚 )(2.7 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 62.1 𝑘𝑁
2 2

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(57 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 137.655 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (64 𝑚 )(3.6 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 115.2 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (68 𝑚 )(3.6 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 122.4 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (73 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 153.3 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (45 𝑚 )(3 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 67.5 𝑘𝑁
2 2

MAXIMUM SHEAR 𝟏𝟓𝟑. 𝟑 𝒌𝑵


(GRID C)
𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (1 − 2) = 14.0616 + 10.044 + 17.604 = 41.7096 ≈ 42
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (2 − 3) = 36.022 + 13.392 + 17.604 = 67.018 ≈ 68
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (3 − 4) = 36.022 + 13.392 + 17.604 = 67.018 ≈ 68
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (4 − 5) = 36.022 + 13.392 + 17.604 = 67.018 ≈ 68
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (5 − 6) = 36.022 + 9.414857143 + 17.604 = 63.04085714 ≈ 64
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (6 − 7) = 36.022 + 9.414857143 + 17.604 = 63.04085714 ≈ 64
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (7 − 8) = 38.90057143 + 15.624 + 17.604 = 72.12857143 ≈ 73
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (8 − 9) = 15.624 + 11.16 + 17.604 = 44.388 ≈ 45
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (9 − 10) = 38.90057143 + 15.624 + 17.604 = 72.12857143 ≈ 73
𝑚 𝑚 𝑚 𝑚 𝑚

DESIGN SHEAR:

APPROXIMATE METHOD

𝟏. 𝟏𝟓𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑬𝒙𝒕𝒆𝒓𝒊𝒐𝒓 𝒇𝒂𝒄𝒆 𝒐𝒇 𝒇𝒊𝒓𝒔𝒕 𝑰𝒏𝒕𝒆𝒓𝒊𝒐𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕) =
𝟐
𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑭𝒂𝒄𝒆 𝒐𝒇 𝒐𝒕𝒉𝒆𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕𝒔) =
𝟐

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(42 𝑚 )(2.7 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 65.205 𝑘𝑁
2 2

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(73 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 176.295 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (68 𝑚 )(3.6 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 122.4 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (64 𝑚 )(3.6 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 115.2 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (73 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 153.3 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (45 𝑚 )(3 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 67.5 𝑘𝑁
2 2

MAXIMUM SHEAR 𝟏𝟕𝟔. 𝟐𝟗𝟓 𝒌𝑵


(GRID D)
𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (1 − 2) = 10.044 + 17.604 = 27.648 ≈ 28
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (2 − 3) = 13.392 + 17.604 = 30.996 ≈ 31
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (3 − 4) = 13.392 + 17.604 = 30.996 ≈ 31
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (4 − 5) = 13.392 + 17.604 = 30.996 ≈ 31
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (5 − 6) = 9.414857143 + 17.604 = 27.01885714 ≈ 28
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (6 − 7) = 9.414857143 + 17.604 = 27.01885714 ≈ 28
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (7 − 8) = 15.624 + 42.47177143 + 17.604 = 75.69977143 ≈ 76
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (8 − 9) = 11.16 + 13.02 + 17.604 = 41.784 ≈ 42
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (9 − 10) = 15.624 + 42.47177143 + 17.604 = 75.69977143 ≈ 76
𝑚 𝑚 𝑚 𝑚 𝑚

DESIGN SHEAR:

APPROXIMATE METHOD

𝟏. 𝟏𝟓𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑬𝒙𝒕𝒆𝒓𝒊𝒐𝒓 𝒇𝒂𝒄𝒆 𝒐𝒇 𝒇𝒊𝒓𝒔𝒕 𝑰𝒏𝒕𝒆𝒓𝒊𝒐𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕) =
𝟐
𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑭𝒂𝒄𝒆 𝒐𝒇 𝒐𝒕𝒉𝒆𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕𝒔) =
𝟐

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(28 𝑚 )(2.7 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 43.47 𝑘𝑁
2 2

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(76 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 183.54 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (31 𝑚 )(3.6 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 55.8 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (28 𝑚 )(3.6 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 50.4 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (76 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 159.6 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (42 𝑚 )(3 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 108 𝑘𝑁
2 2

MAXIMUM SHEAR 𝟏𝟖𝟑. 𝟓𝟒 𝒌𝑵


(GRID E)

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (7 − 8) = 42.47177143 + 29.85854694 + 17.604 = 89.93431837 ≈ 90
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (8 − 9) = 13.02 + 13.02 + 17.604 = 43.644 ≈ 44
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (9 − 10) = 42.47177143 + 42.47177143 + 17.604 = 102.5475429 ≈ 103
𝑚 𝑚 𝑚 𝑚 𝑚
DESIGN SHEAR:

APPROXIMATE METHOD

𝟏. 𝟏𝟓𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑬𝒙𝒕𝒆𝒓𝒊𝒐𝒓 𝒇𝒂𝒄𝒆 𝒐𝒇 𝒇𝒊𝒓𝒔𝒕 𝑰𝒏𝒕𝒆𝒓𝒊𝒐𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕) =
𝟐

𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑭𝒂𝒄𝒆 𝒐𝒇 𝒐𝒕𝒉𝒆𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕𝒔) =
𝟐

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(90 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 217.35 𝑘𝑁
2 2

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(103 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 248.745 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (44 𝑚 )(3 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 66 𝑘𝑁
2 2

MAXIMUM SHEAR 𝟐𝟒𝟖. 𝟕𝟒𝟓 𝒌𝑵


(GRID F)

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (7 − 8) = 29.85854694 + 42.47177143 + 17.604 = 89.93431837 ≈ 90
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (8 − 9) = 13.02 + 13.02 + 17.604 = 43.644 ≈ 44
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (9 − 10) = 42.47177143 + 29.85854694 + 17.604 = 89.93431837 ≈ 90
𝑚 𝑚 𝑚 𝑚 𝑚
DESIGN SHEAR:

APPROXIMATE METHOD

𝟏. 𝟏𝟓𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑬𝒙𝒕𝒆𝒓𝒊𝒐𝒓 𝒇𝒂𝒄𝒆 𝒐𝒇 𝒇𝒊𝒓𝒔𝒕 𝑰𝒏𝒕𝒆𝒓𝒊𝒐𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕) =
𝟐

𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑭𝒂𝒄𝒆 𝒐𝒇 𝒐𝒕𝒉𝒆𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕𝒔) =
𝟐

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(90 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 217.35 𝑘𝑁
2 2

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(90 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 217.35 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (44 𝑚 )(3 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 66 𝑘𝑁
2 2

MAXIMUM SHEAR 𝟐𝟏𝟕. 𝟑𝟓 𝒌𝑵


(GRID G)

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (7 − 8) = 42.47177143 + 42.47177143 + 17.604 = 102.5475429 ≈ 103
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (8 − 9) = 13.02 + 13.02 + 17.604 = 43.644 ≈ 44
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (9 − 10) = 29.85854694 + 29.85854694 + 17.604 = 77.32109388 ≈ 78
𝑚 𝑚 𝑚 𝑚 𝑚
DESIGN SHEAR:

APPROXIMATE METHOD

𝟏. 𝟏𝟓𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑬𝒙𝒕𝒆𝒓𝒊𝒐𝒓 𝒇𝒂𝒄𝒆 𝒐𝒇 𝒇𝒊𝒓𝒔𝒕 𝑰𝒏𝒕𝒆𝒓𝒊𝒐𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕) =
𝟐

𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑭𝒂𝒄𝒆 𝒐𝒇 𝒐𝒕𝒉𝒆𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕𝒔) =
𝟐

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(103 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 248.745 𝑘𝑁
2 2

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(78 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 188.37 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (44 𝑚 )(3 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 66 𝑘𝑁
2 2

MAXIMUM SHEAR 𝟐𝟒𝟖. 𝟕𝟒𝟓 𝒌𝑵


(GRID H)

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (7 − 8) = 42.47177143 + 42.47177143 + 17.604 = 102.5475429 ≈ 103
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (8 − 9) = 13.02 + 13.02 + 17.604 = 43.644 ≈ 44
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (9 − 10) = 29.85854694 + 29.85854694 + 17.604 = 77.32109388 ≈ 78
𝑚 𝑚 𝑚 𝑚 𝑚
DESIGN SHEAR:

APPROXIMATE METHOD

𝟏. 𝟏𝟓𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑬𝒙𝒕𝒆𝒓𝒊𝒐𝒓 𝒇𝒂𝒄𝒆 𝒐𝒇 𝒇𝒊𝒓𝒔𝒕 𝑰𝒏𝒕𝒆𝒓𝒊𝒐𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕) =
𝟐

𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑭𝒂𝒄𝒆 𝒐𝒇 𝒐𝒕𝒉𝒆𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕𝒔) =
𝟐

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(103 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 248.745 𝑘𝑁
2 2

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(78 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 188.37 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (44 𝑚 )(3 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 66 𝑘𝑁
2 2

MAXIMUM SHEAR 𝟐𝟒𝟖. 𝟕𝟒𝟓 𝒌𝑵


(GRID I)

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (7 − 8) = 42.47177143 + 36.37362857 + 17.604 = 96.4494 ≈ 97
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (8 − 9) = 13.02 + 30.794904 + 17.604 = 61.418904 ≈ 62
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (9 − 10) = 29.85854694 + 27.43387347 + 17.604 = 74.89642041 ≈ 75
𝑚 𝑚 𝑚 𝑚 𝑚
DESIGN SHEAR:

APPROXIMATE METHOD

𝟏. 𝟏𝟓𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑬𝒙𝒕𝒆𝒓𝒊𝒐𝒓 𝒇𝒂𝒄𝒆 𝒐𝒇 𝒇𝒊𝒓𝒔𝒕 𝑰𝒏𝒕𝒆𝒓𝒊𝒐𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕) =
𝟐

𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑭𝒂𝒄𝒆 𝒐𝒇 𝒐𝒕𝒉𝒆𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕𝒔) =
𝟐

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(97 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 234.255 𝑘𝑁
2 2

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(75 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 181.125 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (62 𝑚 )(3 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 93 𝑘𝑁
2 2

MAXIMUM SHEAR 𝟐𝟑𝟒. 𝟐𝟓𝟓 𝒌𝑵


(GRID J)

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (7 − 8) = 36.37362857 + 17.604 = 53.97762857 ≈ 54
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (8 − 9) = 30.794904 + 17.604 = 48.398904 ≈ 49
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (9 − 10) = 27.43387347 + 17.604 = 45.03787347 ≈ 46
𝑚 𝑚 𝑚 𝑚
DESIGN SHEAR:

APPROXIMATE METHOD

𝟏. 𝟏𝟓𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑬𝒙𝒕𝒆𝒓𝒊𝒐𝒓 𝒇𝒂𝒄𝒆 𝒐𝒇 𝒇𝒊𝒓𝒔𝒕 𝑰𝒏𝒕𝒆𝒓𝒊𝒐𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕) =
𝟐

𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑭𝒂𝒄𝒆 𝒐𝒇 𝒐𝒕𝒉𝒆𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕𝒔) =
𝟐

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(54 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 130.41 𝑘𝑁
2 2

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(46 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 111.09 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (49 𝑚 )(3 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 73.5 𝑘𝑁
2 2

MAXIMUM SHEAR 𝟏𝟑𝟎. 𝟒𝟏 𝒌𝑵


2ND FLOOR = 3RD FLOOR = 4TH FLOOR

(GRID A)
𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (1 − 2) = 10.6056 + 17.604 = 28.2096 ≈ 29
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (2 − 3) = 13.808 + 17.604 = 31.412 ≈ 32
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (3 − 4) = 13.808 + 17.604 = 31.412 ≈ 32
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (4 − 5) = 13.808 + 17.604 = 31.412 ≈ 32
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (5 − 6) = 13.808 + 17.604 = 31.412 ≈ 32
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (6 − 7) = 13.808 + 17.604 = 31.412 ≈ 32
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (7 − 8) = 21.8736 + 17.604 = 39.4776 ≈ 40
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (8 − 9) = 10.984 + 17.604 = 25.588 ≈ 26
𝑚 𝑚 𝑚 𝑚
DESIGN SHEAR:

APPROXIMATE METHOD

𝟏. 𝟏𝟓𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑬𝒙𝒕𝒆𝒓𝒊𝒐𝒓 𝒇𝒂𝒄𝒆 𝒐𝒇 𝒇𝒊𝒓𝒔𝒕 𝑰𝒏𝒕𝒆𝒓𝒊𝒐𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕) =
𝟐

𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑭𝒂𝒄𝒆 𝒐𝒇 𝒐𝒕𝒉𝒆𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕𝒔) =
𝟐

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(29 𝑚 )(2.7 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 45.0225 𝑘𝑁
2 2

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(26 𝑚 )(3 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 44.85 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (32 𝑚 )(3.6 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 57.6 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (40 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 84𝑘𝑁
2 2

MAXIMUM SHEAR 84 𝒌𝑵
(GRID B)
𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (1 − 2) = 10.6056 + 14.0616 + 17.604 = 42.2712 ≈ 43
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (2 − 3) = 13.1808 + 36.022 + 17.604 = 66.8068 ≈ 67
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (3 − 4) = 13.1808 + 36.022 + 17.604 = 66.8068 ≈ 67
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (4 − 5) = 13.1808 + 36.022 + 17.604 = 66.8068 ≈ 67
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (5 − 6) = 13.1808 + 36.022 + 17.604 = 66.8068 ≈ 67
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (6 − 7) = 13.1808 + 36.022 + 17.604 = 66.8068 ≈ 67
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (7 − 8) = 21.8736 + 38.90057143 + 17.604 = 78.37817143 ≈ 79
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (8 − 9) = 10.984 + 10.984 + 17.604 = 39.572 ≈ 40
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (9 − 10) = 15.3776 + 27.34791837 + 17.604 = 60.32951837 ≈ 61
𝑚 𝑚 𝑚 𝑚 𝑚

DESIGN SHEAR:

APPROXIMATE METHOD

𝟏. 𝟏𝟓𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑬𝒙𝒕𝒆𝒓𝒊𝒐𝒓 𝒇𝒂𝒄𝒆 𝒐𝒇 𝒇𝒊𝒓𝒔𝒕 𝑰𝒏𝒕𝒆𝒓𝒊𝒐𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕) =
𝟐
𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑭𝒂𝒄𝒆 𝒐𝒇 𝒐𝒕𝒉𝒆𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕𝒔) =
𝟐

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(43 𝑚 )(2.7 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 66.7575 𝑘𝑁
2 2

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(61 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 77.165 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (67 𝑚 )(3.6 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 120.6 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (79 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 165.9 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (40 𝑚 )(3 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 60 𝑘𝑁
2 2

MAXIMUM SHEAR 165.9 𝒌𝑵


(GRID C)
𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (1 − 2) = 14.0616 + 14.0616 + 17.604 = 45.7272 ≈ 46
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (2 − 3) = 36.022 + 13.1808 + 17.604 = 66.8068 ≈ 67
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (3 − 4) = 36.022 + 13.1808 + 17.604 = 66.8068 ≈ 67
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (4 − 5) = 36.022 + 13.1808 + 17.604 = 66.8068 ≈ 67
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (5 − 6) = 36.022 + 13.1808 + 17.604 = 66.8068 ≈ 67
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (6 − 7) = 36.022 + 13.1808 + 17.604 = 66.8068 ≈ 67
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (7 − 8) = 38.90057143 + 15.3776 + 17.604 = 71.88217143 ≈ 72
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (8 − 9) = 10.984 + 15.624 + 17.604 = 44.212 ≈ 45
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (9 − 10) = 27.34791837 + 21.8736 + 17.604 = 66.82551837 ≈ 67
𝑚 𝑚 𝑚 𝑚 𝑚

DESIGN SHEAR:

APPROXIMATE METHOD

𝟏. 𝟏𝟓𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑬𝒙𝒕𝒆𝒓𝒊𝒐𝒓 𝒇𝒂𝒄𝒆 𝒐𝒇 𝒇𝒊𝒓𝒔𝒕 𝑰𝒏𝒕𝒆𝒓𝒊𝒐𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕) =
𝟐
𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑭𝒂𝒄𝒆 𝒐𝒇 𝒐𝒕𝒉𝒆𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕𝒔) =
𝟐

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(46 𝑚 )(2.7 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 71.415 𝑘𝑁
2 2

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(67 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 161.805 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (67 𝑚 )(3.6 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 120.6 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (72 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 151.2 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (45 𝑚 )(3 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 67.5 𝑘𝑁
2 2

MAXIMUM SHEAR 161.805 𝒌𝑵


(GRID D)
𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (1 − 2) = 14.0616 + 17.604 = 31.6656 ≈ 32
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (2 − 3) = 13.1808 + 17.604 = 30.7848 ≈ 31
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (3 − 4) = 13.1808 + 17.604 = 30.7848 ≈ 31
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (4 − 5) = 13.1808 + 17.604 = 30.7848 ≈ 31
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (5 − 6) = 13.1808 + 17.604 = 30.7848 ≈ 31
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (6 − 7) = 13.1808 + 17.604 = 30.7848 ≈ 31
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (7 − 8) = 15.3776 + 29.85854694 + 17.604 = 62.84014694 ≈ 63
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (8 − 9) = 15.624 + 15.624 + 17.604 = 48.852 ≈ 49
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (9 − 10) = 21.8736 + 29.85854694 + 17.604 = 69.33614694 ≈ 70
𝑚 𝑚 𝑚 𝑚 𝑚

DESIGN SHEAR:

APPROXIMATE METHOD

𝟏. 𝟏𝟓𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑬𝒙𝒕𝒆𝒓𝒊𝒐𝒓 𝒇𝒂𝒄𝒆 𝒐𝒇 𝒇𝒊𝒓𝒔𝒕 𝑰𝒏𝒕𝒆𝒓𝒊𝒐𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕) =
𝟐
𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑭𝒂𝒄𝒆 𝒐𝒇 𝒐𝒕𝒉𝒆𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕𝒔) =
𝟐

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(32 𝑚 )(2.7 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 49.68 𝑘𝑁
2 2

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(70 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 169.05 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (31 𝑚 )(3.6 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 55.8 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (63 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 132.3 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (49 𝑚 )(3 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 73.5 𝑘𝑁
2 2

MAXIMUM SHEAR 169.05 𝒌𝑵


(GRID E)

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (7 − 8) = 29.85854694 + 29.85854694 + 17.604 = 77.32109388 ≈ 78
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (8 − 9) = 15.624 + 15.624 + 17.604 = 48.852 ≈ 49
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (9 − 10) = 29.85854694 + 229.85854694 + 17.604 = 77.32109388 ≈ 78
𝑚 𝑚 𝑚 𝑚 𝑚
DESIGN SHEAR:

APPROXIMATE METHOD

𝟏. 𝟏𝟓𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑬𝒙𝒕𝒆𝒓𝒊𝒐𝒓 𝒇𝒂𝒄𝒆 𝒐𝒇 𝒇𝒊𝒓𝒔𝒕 𝑰𝒏𝒕𝒆𝒓𝒊𝒐𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕) =
𝟐

𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑭𝒂𝒄𝒆 𝒐𝒇 𝒐𝒕𝒉𝒆𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕𝒔) =
𝟐

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(78 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 188.37 𝑘𝑁
2 2

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(78 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 188.37 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (49 𝑚 )(3 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 73.5 𝑘𝑁
2 2

MAXIMUM SHEAR 188.37 𝒌𝑵


(GRID F)

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (7 − 8) = 29.85854694 + 29.85854694 + 17.604 = 77.32109388 ≈ 78
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (8 − 9) = 15.624 + 15.624 + 17.604 = 48.852 ≈ 49
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (9 − 10) = 29.85854694 + 229.85854694 + 17.604 = 77.32109388 ≈ 78
𝑚 𝑚 𝑚 𝑚 𝑚
DESIGN SHEAR:

APPROXIMATE METHOD

𝟏. 𝟏𝟓𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑬𝒙𝒕𝒆𝒓𝒊𝒐𝒓 𝒇𝒂𝒄𝒆 𝒐𝒇 𝒇𝒊𝒓𝒔𝒕 𝑰𝒏𝒕𝒆𝒓𝒊𝒐𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕) =
𝟐

𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑭𝒂𝒄𝒆 𝒐𝒇 𝒐𝒕𝒉𝒆𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕𝒔) =
𝟐

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(78 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 188.37 𝑘𝑁
2 2

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(78 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 188.37 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (49 𝑚 )(3 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 73.5 𝑘𝑁
2 2

MAXIMUM SHEAR 188.37 𝒌𝑵


(GRID G)

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (7 − 8) = 29.85854694 + 29.85854694 + 17.604 = 77.32109388 ≈ 78
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (8 − 9) = 15.624 + 15.624 + 17.604 = 48.852 ≈ 49
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (9 − 10) = 29.85854694 + 229.85854694 + 17.604 = 77.32109388 ≈ 78
𝑚 𝑚 𝑚 𝑚 𝑚
DESIGN SHEAR:

APPROXIMATE METHOD

𝟏. 𝟏𝟓𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑬𝒙𝒕𝒆𝒓𝒊𝒐𝒓 𝒇𝒂𝒄𝒆 𝒐𝒇 𝒇𝒊𝒓𝒔𝒕 𝑰𝒏𝒕𝒆𝒓𝒊𝒐𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕) =
𝟐

𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑭𝒂𝒄𝒆 𝒐𝒇 𝒐𝒕𝒉𝒆𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕𝒔) =
𝟐

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(78 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 188.37 𝑘𝑁
2 2

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(78 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 188.37 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (49 𝑚 )(3 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 73.5 𝑘𝑁
2 2

MAXIMUM SHEAR 188.37 𝒌𝑵


(GRID H)

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (7 − 8) = 29.85854694 + 29.85854694 + 17.604 = 77.32109388 ≈ 78
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (8 − 9) = 15.624 + 15.624 + 17.604 = 48.852 ≈ 49
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (9 − 10) = 29.85854694 + 229.85854694 + 17.604 = 77.32109388 ≈ 78
𝑚 𝑚 𝑚 𝑚 𝑚
DESIGN SHEAR:

APPROXIMATE METHOD

𝟏. 𝟏𝟓𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑬𝒙𝒕𝒆𝒓𝒊𝒐𝒓 𝒇𝒂𝒄𝒆 𝒐𝒇 𝒇𝒊𝒓𝒔𝒕 𝑰𝒏𝒕𝒆𝒓𝒊𝒐𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕) =
𝟐

𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑭𝒂𝒄𝒆 𝒐𝒇 𝒐𝒕𝒉𝒆𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕𝒔) =
𝟐

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(78 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 188.37 𝑘𝑁
2 2

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(78 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 188.37 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (49 𝑚 )(3 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 73.5 𝑘𝑁
2 2

MAXIMUM SHEAR 188.37 𝒌𝑵


(GRID I)

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (7 − 8) = 29.85854694 + 25.57142449 + 17.604 = 73.03397143 ≈ 74
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (8 − 9) = 15.624 + 30.794904 + 17.604 = 64.022904 ≈ 65
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (9 − 10) = 29.85854694 + 27.43387347 + 17.604 = 74.89642041 ≈ 75
𝑚 𝑚 𝑚 𝑚 𝑚
DESIGN SHEAR:

APPROXIMATE METHOD

𝟏. 𝟏𝟓𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑬𝒙𝒕𝒆𝒓𝒊𝒐𝒓 𝒇𝒂𝒄𝒆 𝒐𝒇 𝒇𝒊𝒓𝒔𝒕 𝑰𝒏𝒕𝒆𝒓𝒊𝒐𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕) =
𝟐

𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑭𝒂𝒄𝒆 𝒐𝒇 𝒐𝒕𝒉𝒆𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕𝒔) =
𝟐

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(74 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 178.71 𝑘𝑁
2 2

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(75 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 181.125 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (65 𝑚 )(3 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 96 𝑘𝑁
2 2

MAXIMUM SHEAR 181.125 𝒌𝑵


(GRID J)

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (7 − 8) = 36.37362857 + 17.604 = 53.97762857 ≈ 54
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (8 − 9) = 30.794904 + 17.604 = 48.398904 ≈ 49
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (9 − 10) = 27.43387347 + 17.604 = 45.03787347 ≈ 46
𝑚 𝑚 𝑚 𝑚
DESIGN SHEAR:

APPROXIMATE METHOD

𝟏. 𝟏𝟓𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑬𝒙𝒕𝒆𝒓𝒊𝒐𝒓 𝒇𝒂𝒄𝒆 𝒐𝒇 𝒇𝒊𝒓𝒔𝒕 𝑰𝒏𝒕𝒆𝒓𝒊𝒐𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕) =
𝟐

𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑭𝒂𝒄𝒆 𝒐𝒇 𝒐𝒕𝒉𝒆𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕𝒔) =
𝟐

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(54 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 130.41 𝑘𝑁
2 2

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(46 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 111.09 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (49 𝑚 )(3 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 73.5 𝑘𝑁
2 2

MAXIMUM SHEAR 130.41 𝒌𝑵


ROOF

(GRID A)
𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (1 − 2) = 0.3132 + 5.184 = 5.4972 ≈6
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (2 − 3) = 0.4176 + 5.184 = 5.6016 ≈6
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (3 − 4) = 0.4176 + 5.184 = 5.6016 ≈6
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (4 − 5) = 0.4176 + 5.184 = 5.6016 ≈6
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (5 − 6) = 0.4176 + 5.184 = 5.6016 ≈6
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (6 − 7) = 0.4176 + 5.184 = 5.6016 ≈6
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (7 − 8) = 0.4872 + 5.184 = 5.6712 ≈6
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (8 − 9) = 0.348 + 5.184 = 5.532 ≈6
𝑚 𝑚 𝑚 𝑚

DESIGN SHEAR:

APPROXIMATE METHOD

𝟏. 𝟏𝟓𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑬𝒙𝒕𝒆𝒓𝒊𝒐𝒓 𝒇𝒂𝒄𝒆 𝒐𝒇 𝒇𝒊𝒓𝒔𝒕 𝑰𝒏𝒕𝒆𝒓𝒊𝒐𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕) =
𝟐

𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑭𝒂𝒄𝒆 𝒐𝒇 𝒐𝒕𝒉𝒆𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕𝒔) =
𝟐
𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(6 𝑚 )(2.7 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 9.315 𝑘𝑁
2 2

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(6 𝑚 )(3 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 10.35 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (6 𝑚 )(3.6 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 10.8 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (6 𝑚 )(3.6 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 10.8 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (6 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 12.6 𝑘𝑁
2 2

MAXIMUM SHEAR 𝟏𝟐. 𝟔 𝒌𝑵


(GRID B)
𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (1 − 2) = 0.3132 + 0.348 + 5.184 = 5.8452 ≈6
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (2 − 3) = 0.4176 + 0.8023333333 + 5.184 = 6.4039333333 ≈7
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (3 − 4) = 0.4176 + 0.8023333333 + 5.184 = 6.4039333333 ≈7
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (4 − 5) = 0.4176 + 0.8023333333 + 5.184 = 6.4039333333 ≈7
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (5 − 6) = 0.4176 + 0.8023333333 + 5.184 = 6.4039333333 ≈7
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (6 − 7) = 0.4176 + 0.8023333333 + 5.184 = 6.4039333333 ≈7
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (7 − 8) = 0.4872 + 0.8664489796 + 5.184 = 6.53764898 ≈7
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (8 − 9) = 0.348 + 0.348 + 5.184 = 5.88 ≈6
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (9 − 10) = 0.4872 + 0.8664489796 + 5.184 = 6.53764898 ≈7
𝑚 𝑚 𝑚 𝑚 𝑚

DESIGN SHEAR:

APPROXIMATE METHOD

𝟏. 𝟏𝟓𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑬𝒙𝒕𝒆𝒓𝒊𝒐𝒓 𝒇𝒂𝒄𝒆 𝒐𝒇 𝒇𝒊𝒓𝒔𝒕 𝑰𝒏𝒕𝒆𝒓𝒊𝒐𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕) =
𝟐
𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑭𝒂𝒄𝒆 𝒐𝒇 𝒐𝒕𝒉𝒆𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕𝒔) =
𝟐

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(6 𝑚 )(2.7 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 9.315 𝑘𝑁
2 2

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(7 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 16.905 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (7 𝑚 )(3.6 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 12.6 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (7 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 14.7 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (6 𝑚 )(3 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 9 𝑘𝑁
2 2

MAXIMUM SHEAR 𝟏𝟔. 𝟗𝟎𝟓 𝒌𝑵


(GRID C)
𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (1 − 2) = 0.3132 + 0.348 + 5.184 = 5.8452 ≈6
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (2 − 3) = 0.4176 + 0.8023333333 + 5.184 = 6.4039333333 ≈7
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (3 − 4) = 0.4176 + 0.8023333333 + 5.184 = 6.4039333333 ≈7
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (4 − 5) = 0.4176 + 0.8023333333 + 5.184 = 6.4039333333 ≈7
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (5 − 6) = 0.4176 + 0.8023333333 + 5.184 = 6.4039333333 ≈7
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (6 − 7) = 0.4176 + 0.8023333333 + 5.184 = 6.4039333333 ≈7
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (7 − 8) = 0.4872 + 0.8664489796 + 5.184 = 6.53764898 ≈7
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (8 − 9) = 0.348 + 0.348 + 5.184 = 5.88 ≈6
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (9 − 10) = 0.4872 + 0.8664489796 + 5.184 = 6.53764898 ≈7
𝑚 𝑚 𝑚 𝑚 𝑚

DESIGN SHEAR:

APPROXIMATE METHOD

𝟏. 𝟏𝟓𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑬𝒙𝒕𝒆𝒓𝒊𝒐𝒓 𝒇𝒂𝒄𝒆 𝒐𝒇 𝒇𝒊𝒓𝒔𝒕 𝑰𝒏𝒕𝒆𝒓𝒊𝒐𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕) =
𝟐
𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑭𝒂𝒄𝒆 𝒐𝒇 𝒐𝒕𝒉𝒆𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕𝒔) =
𝟐

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(6 𝑚 )(2.7 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 9.315 𝑘𝑁
2 2

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(7 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 16.905 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (7 𝑚 )(3.6 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 12.6 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (7 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 14.7 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (6 𝑚 )(3 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 9 𝑘𝑁
2 2

MAXIMUM SHEAR 𝟏𝟔. 𝟗𝟎𝟓 𝒌𝑵


(GRID D)
𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (1 − 2) = 0.3132 + 5.184 = 5.4972 ≈6
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (2 − 3) = 0.4176 + 5.184 = 5.6016 ≈6
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (3 − 4) = 0.4176 + 5.184 = 5.6016 ≈6
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (4 − 5) = 0.4176 + 5.184 = 5.6016 ≈6
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (5 − 6) = 0.4176 + 5.184 = 5.6016 ≈6
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (6 − 7) = 0.4872 + 5.184 = 5.6016 ≈6
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (7 − 8) = 0.4872 + 0.9459918367 + 5.184 = 6.617191837 ≈7
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (8 − 9) = 0.348 + 0.348 + 5.184 = 5.88 ≈6
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (9 − 10) = 0.4872 + 0.9459918367 + 5.184 = 6.617191837 ≈7
𝑚 𝑚 𝑚 𝑚 𝑚

DESIGN SHEAR:

APPROXIMATE METHOD

𝟏. 𝟏𝟓𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑬𝒙𝒕𝒆𝒓𝒊𝒐𝒓 𝒇𝒂𝒄𝒆 𝒐𝒇 𝒇𝒊𝒓𝒔𝒕 𝑰𝒏𝒕𝒆𝒓𝒊𝒐𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕) =
𝟐
𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑭𝒂𝒄𝒆 𝒐𝒇 𝒐𝒕𝒉𝒆𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕𝒔) =
𝟐

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(6 𝑚 )(2.7 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 9.315 𝑘𝑁
2 2

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(7 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 16.905 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (6 𝑚 )(3.6 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 10.8 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (7 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 14.7 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (6 𝑚 )(3 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 9 𝑘𝑁
2 2

MAXIMUM SHEAR 𝟏𝟔. 𝟗𝟎𝟓 𝒌𝑵


(GRID E)

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (7 − 8) = 0.9459918367 + 0.9459918367 + 5.184 = 7.075983673 ≈8
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (8 − 9) = 0.348 + 0.348 + 5.184 = 5.88 ≈6
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (9 − 10) = 0.9459918367 + 0.9459918367 + 5.184 = 7.075983673 ≈8
𝑚 𝑚 𝑚 𝑚 𝑚
DESIGN SHEAR:

APPROXIMATE METHOD

𝟏. 𝟏𝟓𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑬𝒙𝒕𝒆𝒓𝒊𝒐𝒓 𝒇𝒂𝒄𝒆 𝒐𝒇 𝒇𝒊𝒓𝒔𝒕 𝑰𝒏𝒕𝒆𝒓𝒊𝒐𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕) =
𝟐

𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑭𝒂𝒄𝒆 𝒐𝒇 𝒐𝒕𝒉𝒆𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕𝒔) =
𝟐

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(8 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 19.32 𝑘𝑁
2 2

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(8 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 19.32 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (6 𝑚 )(3 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 9 𝑘𝑁
2 2

MAXIMUM SHEAR 𝟏𝟗. 𝟑𝟐 𝒌𝑵


(GRID F)

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (7 − 8) = 0.9459918367 + 0.9459918367 + 5.184 = 7.075983673 ≈8
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (8 − 9) = 0.348 + 0.348 + 5.184 = 5.88 ≈6
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (9 − 10) = 0.9459918367 + 0.9459918367 + 5.184 = 7.075983673 ≈8
𝑚 𝑚 𝑚 𝑚 𝑚
DESIGN SHEAR:

APPROXIMATE METHOD

𝟏. 𝟏𝟓𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑬𝒙𝒕𝒆𝒓𝒊𝒐𝒓 𝒇𝒂𝒄𝒆 𝒐𝒇 𝒇𝒊𝒓𝒔𝒕 𝑰𝒏𝒕𝒆𝒓𝒊𝒐𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕) =
𝟐

𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑭𝒂𝒄𝒆 𝒐𝒇 𝒐𝒕𝒉𝒆𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕𝒔) =
𝟐

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(8 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 19.32 𝑘𝑁
2 2

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(8 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 19.32 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (6 𝑚 )(3 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 9 𝑘𝑁
2 2

MAXIMUM SHEAR 𝟏𝟗. 𝟑𝟐 𝒌𝑵


(GRID G)

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (7 − 8) = 0.9459918367 + 0.9459918367 + 5.184 = 7.075983673 ≈8
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (8 − 9) = 0.348 + 0.348 + 5.184 = 5.88 ≈6
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (9 − 10) = 0.9459918367 + 0.9459918367 + 5.184 = 7.075983673 ≈8
𝑚 𝑚 𝑚 𝑚 𝑚
DESIGN SHEAR:

APPROXIMATE METHOD

𝟏. 𝟏𝟓𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑬𝒙𝒕𝒆𝒓𝒊𝒐𝒓 𝒇𝒂𝒄𝒆 𝒐𝒇 𝒇𝒊𝒓𝒔𝒕 𝑰𝒏𝒕𝒆𝒓𝒊𝒐𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕) =
𝟐

𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑭𝒂𝒄𝒆 𝒐𝒇 𝒐𝒕𝒉𝒆𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕𝒔) =
𝟐

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(8 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 19.32 𝑘𝑁
2 2

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(8 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 19.32 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (6 𝑚 )(3 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 9 𝑘𝑁
2 2

MAXIMUM SHEAR 𝟏𝟗. 𝟑𝟐 𝒌𝑵


(GRID H)

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (7 − 8) = 0.9459918367 + 0.9459918367 + 5.184 = 7.075983673 ≈8
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (8 − 9) = 0.348 + 0.348 + 5.184 = 5.88 ≈6
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (9 − 10) = 0.9459918367 + 0.9459918367 + 5.184 = 7.075983673 ≈8
𝑚 𝑚 𝑚 𝑚 𝑚
DESIGN SHEAR:

APPROXIMATE METHOD

𝟏. 𝟏𝟓𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑬𝒙𝒕𝒆𝒓𝒊𝒐𝒓 𝒇𝒂𝒄𝒆 𝒐𝒇 𝒇𝒊𝒓𝒔𝒕 𝑰𝒏𝒕𝒆𝒓𝒊𝒐𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕) =
𝟐

𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑭𝒂𝒄𝒆 𝒐𝒇 𝒐𝒕𝒉𝒆𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕𝒔) =
𝟐

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(8 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 19.32 𝑘𝑁
2 2

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(8 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 19.32 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (6 𝑚 )(3 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 9 𝑘𝑁
2 2

MAXIMUM SHEAR 𝟏𝟗. 𝟑𝟐 𝒌𝑵


(GRID I)

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (7 − 8) = 0.9459918367 + 0.8101653061 + 5.184 = 6.940157143 ≈7
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (8 − 9) = 0.348 + 0.685908 + 5.184 = 6.217908 ≈7
𝑚 𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (9 − 10) = 0.9459918367 + 0.8101653061 + 5.184 = 6.940157143 ≈7
𝑚 𝑚 𝑚 𝑚 𝑚
DESIGN SHEAR:

APPROXIMATE METHOD

𝟏. 𝟏𝟓𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑬𝒙𝒕𝒆𝒓𝒊𝒐𝒓 𝒇𝒂𝒄𝒆 𝒐𝒇 𝒇𝒊𝒓𝒔𝒕 𝑰𝒏𝒕𝒆𝒓𝒊𝒐𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕) =
𝟐

𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑭𝒂𝒄𝒆 𝒐𝒇 𝒐𝒕𝒉𝒆𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕𝒔) =
𝟐

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(7 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 16.905 𝑘𝑁
2 2

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(7 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 16.905 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (7 𝑚 )(3 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 10.5 𝑘𝑁
2 2

MAXIMUM SHEAR 𝟏𝟔. 𝟗𝟎𝟓 𝒌𝑵


(GRID J)

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (7 − 8) = 0.8101653061 + 5.184 = 5.994165306 ≈6
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (8 − 9) = 0.685908 + 5.184 = 5.869908 ≈6
𝑚 𝑚 𝑚 𝑚

𝑘𝑁 𝑘𝑁 𝑘𝑁 𝑘𝑁
𝑊𝑢−𝑡𝑜𝑡𝑎𝑙 (9 − 10) = 0.8101653061 + 5.184 = 5.994165306 ≈6
𝑚 𝑚 𝑚 𝑚
DESIGN SHEAR:

APPROXIMATE METHOD

𝟏. 𝟏𝟓𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑬𝒙𝒕𝒆𝒓𝒊𝒐𝒓 𝒇𝒂𝒄𝒆 𝒐𝒇 𝒇𝒊𝒓𝒔𝒕 𝑰𝒏𝒕𝒆𝒓𝒊𝒐𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕) =
𝟐

𝒘𝒖 𝒍𝒏
𝑽𝒖 (𝑭𝒂𝒄𝒆 𝒐𝒇 𝒐𝒕𝒉𝒆𝒓 𝑺𝒖𝒑𝒑𝒐𝒓𝒕𝒔) =
𝟐

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(6 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 18.9 𝑘𝑁
2 2

𝑘𝑁
1.15𝑤𝑢 𝑙𝑛 1.15(6 𝑚 )(4.2 𝑚)
𝑉𝑢 (𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑓𝑖𝑟𝑠𝑡 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡) = = = 18.9 𝑘𝑁
2 2

𝑘𝑁
𝑤𝑢 𝑙𝑛 (6 𝑚 )(3 𝑚)
𝑉𝑢 (𝐹𝑎𝑐𝑒 𝑜𝑓 𝑜𝑡ℎ𝑒𝑟 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑠) = = = 9 𝑘𝑁
2 2

MAXIMUM SHEAR 𝟏𝟖. 𝟗 𝒌𝑵


Shear Design
Beam 1

(Ground Floor)

DESIGN PARAMETERS:

b = 300 mm

h = 600 mm

d = 540 mm

f’c = 28 MPa

fy = 276 MPa (for Ø 10 mm and smaller)

Main bar diameter = 20 mm

Stirrups diameter = 10 mm

Concrete cover = 40 mm
Vu = 248.745 kN

L = 4.2 m L/2 = 2.1 m

h = 600 mm = 0.60 m 2h = 1200 mm = 1.2 m

d = 540 mm = 0.54 m

1. Computation of Critical Shear

248.745 𝑘𝑁 𝑉𝑢𝑑
=
2.1 𝑚 2.1 𝑚 − 0.54 𝑚

𝑉𝑢𝑑 = 184.782 𝑘𝑁

2. Computation of Factored Shear Load


(at 2H)

248.745 𝑘𝑁 𝑉𝑢2𝐻
=
2.1 𝑚 2.1 𝑚 − 1.2 m

𝑉𝑢2𝐻 = 106.605 𝑘𝑁
3. Computation of Shear at Concrete

𝑉𝐶 = 0.17𝜆√𝑓𝑐́ 𝑏𝑤 𝑑

= 0.17(1.0)(√28 𝑀𝑃𝑎)(300 𝑚𝑚)(540 𝑚𝑚)


= 145727.9822 𝑁

0.33√𝑓𝑐́ 𝑏𝑤 𝑑 = 0.33(√28 𝑀𝑃𝑎)(300 𝑚𝑚)(540 𝑚𝑚)


= 282883.7302 𝑁

0.67√𝑓𝑐́ 𝑏𝑤 𝑑 = 0.67(√28 𝑀𝑃𝑎)(300 𝑚𝑚)(540 𝑚𝑚)


= 574339.6946 𝑁

Finding x’:

∅𝑉𝐶 = (0.75)(145727.9822 𝑁) = 109295.9867 𝑁 = 109.2959867 𝑘𝑁

248.745 𝑘𝑁 109.2959867 𝑘𝑁
=
2.1 𝑚 𝑥

x = c = 0.9227183343 m = 922.7183343 mm

x’ = 2100 – 922.7183343 = 1177.281666 mm

Note: The location (x’) of ∅𝑉𝐶 is between the location of 𝑉𝑢𝑑 and 𝑉𝑢2𝐻 . Thus, no need to compute for spacing at ∅𝑉𝐶 .
4. Computation of Spacing and number of stirrups at base (a)

By default:

Provide first 2 @ 50 mm.

For 2 @ 50 mm, there will be 100 mm length of stirrups

a = 2H – 100 mm = 1200 mm – 100 mm = 1100 mm

𝑉𝑢𝑑 = ∅(𝑉𝐶 + 𝑉𝑆 )

184782 𝑁 = (0.75)(145727.9822 𝑁 + 𝑉𝑆 )

𝑉𝑆 = 100648.0178 𝑁

∴ 𝑉𝑆 < 0.33√𝑓𝑐́ 𝑏𝑤 𝑑 𝑎𝑛𝑑 𝑉𝑆 < 0.67√𝑓𝑐́ 𝑏𝑤 𝑑 (𝐶ℎ𝑒𝑐𝑘 𝑎𝑙𝑙 𝑟𝑒𝑞𝑢𝑖𝑟𝑒𝑚𝑒𝑛𝑡𝑠)

Stirrup Area (𝐴𝑣 ) = (2)(π × 𝑟2 ) = (2)(π × (5 𝑚𝑚)2 ) = 50𝜋 𝑚𝑚2

𝐴𝑣 𝑓𝑦𝑡 𝑑 (50𝜋 𝑚𝑚2 )(276 MPa )(540 mm)


𝑆𝑠𝑡𝑟 = = = 232.6041681 𝑚𝑚
𝑉𝑠 100648.0178 𝑁

𝐴𝑣𝑚𝑖𝑛 𝑓𝑦𝑡 (50𝜋 𝑚𝑚2 )(276 MPa )


𝑆𝑚𝑖𝑛1 = = = 440.4909592 𝑚𝑚
0.062√𝑓𝑐́ 𝑏𝑤 0.062√28 MPa (300 𝑚𝑚)

𝐴𝑣𝑚𝑖𝑛 𝑓𝑦𝑡 (50𝜋 𝑚𝑚2 )(276 MPa )


𝑆𝑚𝑖𝑛2 = = = 412.8950345 𝑚𝑚
0.35𝑏𝑤 0.35(300 𝑚𝑚)

𝑑 540 mm
𝑆𝑚𝑎𝑥1 = = = 270 𝑚𝑚
2 2
𝑆𝑚𝑎𝑥2 = 600 𝑚𝑚

𝑈𝑠𝑒 𝑆 = 232.6041681 𝑚𝑚 ≈ 230 𝑚𝑚

𝑎 1100 mm
𝑛= = = 4.782608696 ≈ 5 𝑏𝑎𝑟𝑠
𝑠 230 𝑚𝑚

∴ 𝑼𝒔𝒆 𝟓 − 𝟏𝟎 𝒎𝒎 𝒅𝒊𝒂𝒎𝒆𝒕𝒆𝒓 𝒔𝒕𝒊𝒓𝒓𝒖𝒑𝒔 𝒔𝒑𝒂𝒄𝒆𝒅 𝒂𝒕 𝟐𝟑𝟎 𝒎𝒎 (𝟓 @ 𝟐𝟑𝟎 𝒎𝒎)

5. Computation of Spacing and number of stirrups at base (b)

Occupied spacing: 2 @ 50 mm and 5 @ 230 mm

= 2(50 mm) + 5(230 mm)

= 1250 mm

Available spacing = 2100 mm - 1250 mm = 850 mm

𝑉𝑢2𝐻 = 106605 𝑁

∴ 𝑉𝑢2𝐻 < ∅𝑉𝐶 𝑎𝑛𝑑 𝑉𝑢2𝐻 > 0.5∅𝑉𝐶 (𝐶ℎ𝑒𝑐𝑘 𝑎𝑙𝑙 𝑟𝑒𝑞𝑢𝑖𝑟𝑒𝑚𝑒𝑛𝑡𝑠 𝑎𝑠𝑖𝑑𝑒 𝑓𝑟𝑜𝑚 𝑆𝑠𝑡𝑟 )

Stirrup Area (𝐴𝑣 ) = (2)(π × 𝑟2 ) = (2)(π × (5 𝑚𝑚)2 ) = 50𝜋 𝑚𝑚2

𝐴𝑣𝑚𝑖𝑛 𝑓𝑦𝑡 (50𝜋 𝑚𝑚2 )(276 MPa )


𝑆𝑚𝑖𝑛1 = = = 440.4909592 𝑚𝑚
0.062√𝑓𝑐́ 𝑏𝑤 0.062√28 MPa (300 𝑚𝑚)

𝐴𝑣𝑚𝑖𝑛 𝑓𝑦𝑡 (50𝜋 𝑚𝑚2 )(276 MPa )


𝑆𝑚𝑖𝑛2 = = = 412.8950345 𝑚𝑚
0.35𝑏𝑤 0.35(300 𝑚𝑚)
𝑑 540 mm
𝑆𝑚𝑎𝑥1 = = = 270 𝑚𝑚
2 2

𝑆𝑚𝑎𝑥2 = 600 𝑚𝑚

𝑈𝑠𝑒 𝑆 = 270 𝑚𝑚

∴ 𝑼𝒔𝒆 𝟏𝟎 𝒎𝒎 𝒅𝒊𝒂𝒎𝒆𝒕𝒆𝒓 𝒔𝒕𝒊𝒓𝒓𝒖𝒑𝒔 𝒔𝒑𝒂𝒄𝒆𝒅 𝒂𝒕 𝟐𝟕𝟎 𝒎𝒎 𝒇𝒐𝒓 𝒕𝒉𝒆 𝒓𝒆𝒔𝒕 𝒐𝒇 𝒕𝒉𝒆 𝒃𝒆𝒂𝒎

Final Spacing Details:

Use 10-mm diameter stirrups spaced at 2 @ 50 mm, 5 @ 230 mm, and the rest at @ 270 mm.
Beam 2

(2nd floor = 3rd floor = 4th floor)

DESIGN PARAMETERS:

b = 300 mm

h = 600 mm

d = 540 mm

f’c = 28 MPa

fy = 276 MPa (for Ø 10 mm and smaller)

Main bar diameter = 20 mm

Stirrups diameter = 10 mm

Concrete cover = 40 mm
Vu = 217.35 kN

L = 4.2 m L/2 = 2.1 m

h = 600 mm = 0.60 m 2h = 1200 mm = 1.2 m

d = 540 mm = 0.54 m

1. Computation of Critical Shear

217.35 𝑘𝑁 𝑉𝑢𝑑
=
2.1 𝑚 2.1 𝑚 − 0.54 𝑚

𝑉𝑢𝑑 = 161.46 𝑘𝑁

2. Computation of Factored Shear Load


(at 2H)

217.35 𝑘𝑁 𝑉𝑢2𝐻
=
2.1 𝑚 2.1 𝑚 − 1.2 m

𝑉𝑢2𝐻 = 93.15 𝑘𝑁
3. Computation of Shear at Concrete

𝑉𝐶 = 0.17𝜆√𝑓𝑐́ 𝑏𝑤 𝑑

= 0.17(1.0)(√28 𝑀𝑃𝑎)(300 𝑚𝑚)(540 𝑚𝑚)


= 145727.9822 𝑁

0.33√𝑓𝑐́ 𝑏𝑤 𝑑 = 0.33(√28 𝑀𝑃𝑎)(300 𝑚𝑚)(540 𝑚𝑚)


= 282883.7302 𝑁

0.67√𝑓𝑐́ 𝑏𝑤 𝑑 = 0.67(√28 𝑀𝑃𝑎)(300 𝑚𝑚)(540 𝑚𝑚)


= 574339.6946 𝑁

Finding x’:

∅𝑉𝐶 = (0.75)(145727.9822 𝑁) = 109295.9867 𝑁 = 109.2959867 𝑘𝑁

217.35 𝑘𝑁 109.2959867 𝑘𝑁
=
2.1 𝑚 𝑥

x = c = 1.055999871 m = 1055.999871 mm

x’ = 2100 – 1055.999871 = 1044.000129 mm

Note: The location (x’) of ∅𝑉𝐶 is between the location of 𝑉𝑢𝑑 and 𝑉𝑢2𝐻 . Thus, no need to compute for spacing at ∅𝑉𝐶 .
4. Computation of Spacing and number of stirrups at base (a)

By default:

Provide first 2 @ 50 mm.

For 2 @ 50 mm, there will be 100 mm length of stirrups

a = 2H – 100 mm = 1200 mm – 100 mm = 1100 mm

𝑉𝑢𝑑 = ∅(𝑉𝐶 + 𝑉𝑆 )

161460 𝑁 = (0.75)(145727.9822 𝑁 + 𝑉𝑆 )

𝑉𝑆 = 69552.0178 𝑁

∴ 𝑉𝑆 < 0.33√𝑓𝑐́ 𝑏𝑤 𝑑 𝑎𝑛𝑑 𝑉𝑆 < 0.67√𝑓𝑐́ 𝑏𝑤 𝑑 (𝐶ℎ𝑒𝑐𝑘 𝑎𝑙𝑙 𝑟𝑒𝑞𝑢𝑖𝑟𝑒𝑚𝑒𝑛𝑡𝑠)

Stirrup Area (𝐴𝑣 ) = (2)(π × 𝑟2 ) = (2)(π × (5 𝑚𝑚)2 ) = 50𝜋 𝑚𝑚2

𝐴𝑣 𝑓𝑦𝑡 𝑑 (50𝜋 𝑚𝑚2 )(276 MPa )(540 mm)


𝑆𝑠𝑡𝑟 = = = 336.991267 𝑚𝑚
𝑉𝑠 69552.0178 𝑁

𝐴𝑣𝑚𝑖𝑛 𝑓𝑦𝑡 (50𝜋 𝑚𝑚2 )(276 MPa )


𝑆𝑚𝑖𝑛1 = = = 440.4909592 𝑚𝑚
0.062√𝑓𝑐́ 𝑏𝑤 0.062√28 MPa (300 𝑚𝑚)

𝐴𝑣𝑚𝑖𝑛 𝑓𝑦𝑡 (50𝜋 𝑚𝑚2 )(276 MPa )


𝑆𝑚𝑖𝑛2 = = = 412.8950345 𝑚𝑚
0.35𝑏𝑤 0.35(300 𝑚𝑚)

𝑑 540 mm
𝑆𝑚𝑎𝑥1 = = = 270 𝑚𝑚
2 2
𝑆𝑚𝑎𝑥2 = 600 𝑚𝑚

𝑈𝑠𝑒 𝑆 = 270 𝑚𝑚 ≈ 270 𝑚𝑚

𝑎 1100 mm
𝑛= = = 4.07407407407 ≈ 5 𝑏𝑎𝑟𝑠
𝑠 270 𝑚𝑚

∴ 𝑼𝒔𝒆 𝟓 − 𝟏𝟎 𝒎𝒎 𝒅𝒊𝒂𝒎𝒆𝒕𝒆𝒓 𝒔𝒕𝒊𝒓𝒓𝒖𝒑𝒔 𝒔𝒑𝒂𝒄𝒆𝒅 𝒂𝒕 𝟐𝟕𝟎 𝒎𝒎 (𝟓 @ 𝟐𝟕𝟎 𝒎𝒎)

5. Computation of Spacing and number of stirrups at base (b)

Occupied spacing: 2 @ 50 mm and 5 @ 270 mm

= 2(50 mm) + 5(270 mm) = 1450 mm

Available spacing = 2100 mm - 1450 mm = 650 mm

𝑉𝑢2𝐻 = 93150 𝑁

∴ 𝑉𝑢2𝐻 < ∅𝑉𝐶 𝑎𝑛𝑑 𝑉𝑢2𝐻 > 0.5∅𝑉𝐶 (𝐶ℎ𝑒𝑐𝑘 𝑎𝑙𝑙 𝑟𝑒𝑞𝑢𝑖𝑟𝑒𝑚𝑒𝑛𝑡𝑠 𝑎𝑠𝑖𝑑𝑒 𝑓𝑟𝑜𝑚 𝑆𝑠𝑡𝑟 )

Stirrup Area (𝐴𝑣 ) = (2)(π × 𝑟2 ) = (2)(π × (5 𝑚𝑚)2 ) = 50𝜋 𝑚𝑚2

𝐴𝑣𝑚𝑖𝑛 𝑓𝑦𝑡 (50𝜋 𝑚𝑚2 )(276 MPa )


𝑆𝑚𝑖𝑛1 = = = 440.4909592 𝑚𝑚
0.062√𝑓𝑐́ 𝑏𝑤 0.062√28 MPa (300 𝑚𝑚)

𝐴𝑣𝑚𝑖𝑛 𝑓𝑦𝑡 (50𝜋 𝑚𝑚2 )(276 MPa )


𝑆𝑚𝑖𝑛2 = = = 412.8950345 𝑚𝑚
0.35𝑏𝑤 0.35(300 𝑚𝑚)

𝑑 540 mm
𝑆𝑚𝑎𝑥1 = = = 270 𝑚𝑚
2 2
𝑆𝑚𝑎𝑥2 = 600 𝑚𝑚

𝑈𝑠𝑒 𝑆 = 270 𝑚𝑚 ≈ 270 𝑚𝑚

∴ 𝑼𝒔𝒆 𝟏𝟎 𝒎𝒎 𝒅𝒊𝒂𝒎𝒆𝒕𝒆𝒓 𝒔𝒕𝒊𝒓𝒓𝒖𝒑𝒔 𝒔𝒑𝒂𝒄𝒆𝒅 𝒂𝒕 𝟐𝟕𝟎 𝒎𝒎 𝒇𝒐𝒓 𝒕𝒉𝒆 𝒓𝒆𝒔𝒕 𝒐𝒇 𝒕𝒉𝒆 𝒃𝒆𝒂𝒎

Final Spacing Details:

Use 10-mm diameter stirrups spaced at 2 @ 50 mm, 5 @ 270 mm, and the rest @ 270 mm. Alternatively, use 10-mm
diameter stirrups spaced at 2 @ 50 mm, the rest @ 270 mm.
Beam 3

(Roof)

DESIGN PARAMETERS:

b = 300 mm

h = 600 mm

d = 540 mm

f’c = 28 MPa

fy = 276 MPa (for Ø 10 mm and smaller)

Main bar diameter = 20 mm

Stirrups diameter = 10 mm

Concrete cover = 40 mm
Vu = 19.32 kN

L = 4.2 m L/2 = 2.1 m

h = 600 mm = 0.60 m 2h = 1200 mm = 1.2 m

d = 540 mm = 0.54 m

1. Computation of Critical Shear

19.32 𝑘𝑁 𝑉𝑢𝑑
=
2.1 𝑚 2.1 𝑚 − 0.54 𝑚

𝑉𝑢𝑑 = 14.352 𝑘𝑁

2. Computation of Factored Shear Load


(at 2H)

19.32 𝑘𝑁 𝑉𝑢2𝐻
=
2.1 𝑚 2.1 𝑚 − 1.2 m

𝑉𝑢2𝐻 = 8.28 𝑘𝑁
3. Computation of Shear at Concrete

𝑉𝐶 = 0.17𝜆√𝑓𝑐́ 𝑏𝑤 𝑑 = 0.17(1.0)(√28 𝑀𝑃𝑎)(300 𝑚𝑚)(540 𝑚𝑚) = 145727.9822 𝑁

0.33√𝑓𝑐́ 𝑏𝑤 𝑑 = 0.33(√28 𝑀𝑃𝑎)(300 𝑚𝑚)(540 𝑚𝑚) = 282883.7302 𝑁

0.67√𝑓𝑐́ 𝑏𝑤 𝑑 = 0.67(√28 𝑀𝑃𝑎)(300 𝑚𝑚)(540 𝑚𝑚) = 574339.6946 𝑁

Finding x’:

∅𝑉𝐶 = (0.75)(145727.9822 𝑁) = 109295.9867 𝑁 = 109.2959867 𝑘𝑁

19.32 kN 109.2959867 𝑘𝑁
=
2.1 𝑚 𝑥
x = c = 11.87999855 = 11879.99855 mm

x’ = 11879.99855 – 2100 = 9779.998554 mm

Note: The location (x’) of ∅𝑉𝐶 is beyond the location of 𝑉𝑢𝑑 and 𝑉𝑢2𝐻 . Thus, no need to compute for spacing at ∅𝑉𝐶 .

4. Computation of Spacing and number of stirrups at base (a)

By default:

Provide first 2 @ 50 mm.

For 2 @ 50 mm, there will be 100 mm length of stirrups

a = 2H – 100 mm = 1200 mm – 100 mm = 1100 mm

𝑉𝑢𝑑 = 14352 𝑁

∅𝑉𝐶 = (0.75)(145727.9822 𝑁)
= 109295.9867 𝑁 = 109.2959867 𝑘𝑁

0.5∅𝑉𝐶 = (0.50)(0.75)(145727.9822 𝑁) = 54647.99333 𝑁 = 54.64799333 𝑘𝑁

∴ 𝑉𝑢𝑑 < ∅𝑉𝐶 𝑎𝑛𝑑 𝑉𝑢𝑑 < 0.5∅𝑉𝐶 (𝐶ℎ𝑒𝑐𝑘 𝑜𝑛𝑙𝑦 𝑡ℎ𝑒 𝑆𝑚𝑎𝑥1 𝑎𝑛𝑑 𝑆𝑚𝑎𝑥2 )

Stirrup Area (𝐴𝑣 ) = (2)(π × 𝑟2 ) = (2)(π × (5 𝑚𝑚)2 ) = 50𝜋 𝑚𝑚2

𝑑 540 mm
𝑆𝑚𝑎𝑥1 = = = 270 𝑚𝑚
2 2
𝑆𝑚𝑎𝑥2 = 600 𝑚𝑚

𝑈𝑠𝑒 𝑆 = 270 𝑚𝑚

𝑎 1100 mm
𝑛= = = 4.074074074 ≈ 5 𝑏𝑎𝑟𝑠
𝑠 270 𝑚𝑚

∴ 𝑼𝒔𝒆 𝟓 − 𝟏𝟎 𝒎𝒎 𝒅𝒊𝒂𝒎𝒆𝒕𝒆𝒓 𝒔𝒕𝒊𝒓𝒓𝒖𝒑𝒔 𝒔𝒑𝒂𝒄𝒆𝒅 𝒂𝒕 𝟐𝟕𝟎 𝒎𝒎 (𝟓 @ 𝟐𝟕𝟎 𝒎𝒎)

5. Computation of Spacing and number of stirrups at base (b)

Occupied spacing: 2 @ 50 mm and 5 @ 270 mm

= 2(50 mm) + 5(270 mm)

= 1450 mm

Available spacing = 2100 mm - 1450 mm = 650 mm

𝑉𝑢2𝐻 = 8280 𝑁

∅𝑉𝐶 = (0.75)(145727.9822 𝑁) = 109295.9867 𝑁 = 109.2959867 𝑘𝑁

0.5∅𝑉𝐶 = (0.50)(0.75)(145727.9822 𝑁) = 54647.99333 𝑁 = 54.64799333 𝑘𝑁

∴ 𝑉𝑢𝑑 < ∅𝑉𝐶 𝑎𝑛𝑑 𝑉𝑢𝑑 < 0.5∅𝑉𝐶 (𝐶ℎ𝑒𝑐𝑘 𝑜𝑛𝑙𝑦 𝑡ℎ𝑒 𝑆𝑚𝑎𝑥1 𝑎𝑛𝑑 𝑆𝑚𝑎𝑥2 )

Stirrup Area (𝐴𝑣 ) = (2)(π × 𝑟2 ) = (2)(π × (5 𝑚𝑚)2 ) = 50𝜋 𝑚𝑚2

𝑑 540 mm
𝑆𝑚𝑎𝑥1 = = = 270 𝑚𝑚
2 2
𝑆𝑚𝑎𝑥2 = 600 𝑚𝑚

𝑈𝑠𝑒 𝑆 = 270 𝑚𝑚

∴ 𝑼𝒔𝒆 𝟏𝟎 𝒎𝒎 𝒅𝒊𝒂𝒎𝒆𝒕𝒆𝒓 𝒔𝒕𝒊𝒓𝒓𝒖𝒑𝒔 𝒔𝒑𝒂𝒄𝒆𝒅 𝒂𝒕 𝟐𝟕𝟎 𝒎𝒎 𝒇𝒐𝒓 𝒕𝒉𝒆 𝒓𝒆𝒔𝒕 𝒐𝒇 𝒕𝒉𝒆 𝒃𝒆𝒂𝒎

Final Spacing Details:

Use 10-mm diameter stirrups spaced at 2 @ 50 mm, 5 @ 270 mm, and the rest @ 270 mm. Alternatively, use 10-mm
diameter stirrups spaced at 2 @ 50 mm, the rest @ 270 mm.