J75860891020 PDF
J75860891020 PDF
J75860891020 PDF
Abstract: As an effective supplement to the centralized fossil In order to reduce these losses, DGs integrated to the
fuel based traditional generation, Distributed Generation (DG) distribution system will be a good option. DGs may be based
has become an effective alternative choice and has been rapidly on renewable energy or non-renewable energy technologies.
increasing since past few years due to growing demand for However, with the increased environmental concerns,
electricity and the new policies of governing bodies for usage of renewable energy based DGs are gaining more importance.
green energy. In overall power system, distribution systems are
Renewable energy based DGs have many techno-economical
more vulnerable to faults and reliability aspects of such systems
becomes an important issue. With higher penetration of DG into and environmental advantages. Due to increased customers
the distribution network, it will be necessary to study the impact of demand for reliable and quality power supply, evaluation of
such generation on the various aspects of distribution system. the impact of DG integration to improve performance of the
Thus, increase in rate of penetration DGs into the distribution system, especially reliability and reduction of losses is
system on one side and increased faults in distribution network on gaining more importance in the present distribution system
another side, will make the study of impact of DG integration on operating scenario. Improvement in reliability and reduction
distribution system reliability an interesting topic of research. The in losses can be achieved only by optimal selection,
present work focuses on evaluation of impacts of integration of
placement and sizing of DGs. This will in turn have added
such DGs on reliability of local distribution network, typically in
an urban scenario By using the simulation method using benefit of improved voltage profile, better power quality,
DIgSILENT PowerFactory software, the impacts of integration of optimum system loadability, enhanced system security. This
DG in terms of enhancement in distribution system reliability will also lead to reduced capital investments, repair and
indices and reduction in system losses for different scenarios are maintenance costs, fuel cost for conventional units and
studied and presented in this paper. Based on the simulation operational costs. Renewable energy based DGs will have
results obtained and after analysis of the distribution system, advantage of no-emissions, free availability and so on. With
overall results are summarized by focusing on the installation of increase in DG, the integration of such DGs into the
suitable capacity of DG and the location of DG which are
important factors affecting the system losses and system reliability
distribution networks has to be taken care and it is necessary
indices. to study the impacts of DG integration in terms of reliability
and system losses. Otherwise, if DGs are not properly
Keywords: Distributed Generation (DG), RBTS, Simulation, installed at proper locations, it may lead various problems viz.
DIgSILENT PowerFactory. Radial distribution system.
increased losses, protection co-ordination problem, power
quality issues. This problem of optimal selection, sizing and
I. INTRODUCTION siting of DGs has been dealt with in literature using several
techniques. Analytical techniques are suitable for small
The Distribution systems which were passive in nature systems and not performing well for complex systems.
earlier with uni-directional power flows are transforming into Various meta-heuristic techniques are developed for large and
active distribution systems with bidirectional power flows in complex system which provides good results. Many
the present scenario due to gradual increase in integration of simulation techniques are adopted by using different power
small-scale DGs [1]. Integration of DG into the distribution system simulation software which also provides good output
system results in increased system availability and improved indicators to arrive at suitable conclusions based on the
reliability of the system. Also, there is possibility of increased simulation results. Simulation studies are carried out using
system complexity and problem of increased losses due to Neplan software in [1], [24], [26] using ETAP in [3], [8],
improper placement, sizing of DGs in distribution networks. [12], [16], [17], [18], [19], [21] DigSILENT PowerFactory in
About 65-70% of the losses occurring in the power system [7], [14], [25], [28]. [29], using MiPower in [6],[15], using
can be attributed to distribution system losses [30]. DISREL in [30] and using MATLAB in other works. Real
time feeder data has been considered in [4], [13], [14], [17],
[24], [27] for case studies. Along with the objective of
improvement of reliability of the system, reduction in system
Revised Manuscript Received on August 05, 2020. loss and improvement in voltage profile has been considered
Mr. Ravishankar B. S., Assistant Professor, Department of Electrical & as the objective in [2], [3], [4], [6], [8], [9], [10], [11], [15],
Electronics Engineering, JSS Science & Technology University, Mysuru, [20], [25]. Concept of DSM has been considered in [7], [22].
Karnataka, India. E-mail: [email protected].
Mr. Vijayendra V K, PG-Scholar, Department of Electrical &
Solar PV has been considered as choice for DG in most of the
Electronics Engineering, JSS Science & Technology University, Mysuru, literature.
Karnataka, India. E-mail: [email protected].
Dr. K T Veeramanju, Professor, Department of Electrical & Electronics
Engineering, JSS Science & Technology University, Mysuru, Karnataka,
India. E-mail: [email protected].
Published By:
Retrieval Number: J75860891020/2020©BEIESP Blue Eyes Intelligence Engineering
DOI: 10.35940/ijitee.J7586.0891020 381 and Sciences Publication
Evaluation of Distributed Generation Impact on Reliability of a Distribution System using DIgSILENT PowerFactory
Energy storage has been considered in [1], micro hydro in B. System reliability indices
[13], Diesel generator in [26] and wind in [7], [9], [12], [13], For complete understanding of the system, system oriented
[15], [18], [22], [26]. and energy oriented reliability indices are required in addition
This present work addresses to assess the reliability of to basic indices. These system oriented indices, namely
distribution system in presence of DGs for RBTS test System Average Interruption Frequency Index (SAIFI),
distribution system and practical system of 11kV feeders
System Average Interruption Duration Index (SAIDI),
emanating from 66/11 kV Hebbal sub-station coming under
Customer Average Interruption Duration Index (CAIDI),
Karnataka Power Transmission Corporation Limited
Average System Availability Index (ASAI), Average System
(KPTCL), Mysuru and distribution feeders coming under the
jurisdiction of Chamundeshwari Electricity Supply Company Unavailability Index (ASUI) considered in the present work
(CESC), Mysuru. Both test system and practical system are represented by (4)-(8) and energy oriented indices namely
feeders are modeled using DIgSILENT PowerFactory. Average System Interruption Frequency Index (ASIFI),
Failure rates are taken as per the test system values. Average System Interruption Duration Index (ASIDI) and
Reliability indices of the test system and practical system are Energy Not Supplied (ENS) are represented by the (9)-(11).
determined for different cases of DG integration. Simulation Sum of no. of cust interrutpions i Ni
results are summarized by focusing on the installation of SAIFI f/Ca…... (4)
suitable capacity of DGs and the location of DGs which are Total no. of cust served Ni
important factors affecting the system losses and system
reliability indices Sum of cust interrutpion duration U i Ni
SAIDI h/Ca.. (5)
This paper has been organized into IV sections. This Total no. of cust served Ni
introduction section is followed by section-II which provides
overview of Reliability analysis of a distribution system; Sum of cust interrutpion duration U i Ni
CAIDI hrs….…….. (6)
section-III provides the problem formulation for DG Sum of no. of cust interrutpions i Ni
integration, section-IV provides both test system and practical
system data, simulation and analysis for difference cases, Customer hours of available service Ni x8760 Ui Ni
ASAI .. (7)
section-V deals with results and discussion and section-VI Customer hours demanded Ni x8760
provides conclusions based on case study results.
ASUI = 1-ASAI………………………………………… (8)
Sum of connectedkVA of load interrupted
II. RELIABILITY ANALYSIS OF A DISTRIBUTION
SYSTEM
ASIFI …….….. (9)
TotalonnectedkVA served
This work mainly concentrates on radial distribution Sum of connectedkVA durationsof load interrupted
system. IEEE standard 1366 provides a set of indices for ASIDI (10)
determining reliability of power distribution system. Data TotalonnectedkVA served
related to reliability for set of power system components, load ENS La xUi ………..……………………………. (11)
points and customers are statistically interpreted using
Where, λi is the failure rate of the components i =
reliability indices. These indices are classified into load point
1,2,3……N Where Ni is the number of customers at the load
indices and system indices [18].
point i = 1,2,3…….N. Ui is the annual unavailability at the
A. Basic load point reliability indices load point i = 1,2,3…….N.
Average failure rate (λs), average outage time (rs) and Total energy demand in the period of interest
average annual unavailability (Us) are the basic elementary La
indices called load point indices [5]. These indices denote the Period of interest
average values. Average failure rate provide information
regarding the number of failures happening at load point for III. PROBLEM FORMULATION
the specific time interval. Average failure time interval at the With higher penetration of DGs, distribution system are
load point is expressed by average outage time. Average becoming similar to transmission systems where load and
supply outage at the load point for a period of one year is generation node points are mixed and reliability of such
termed as average annual outage time. systems are becoming important. Evaluation of the DG
Depending on failure rates for each system components, integration impact on reliability of distribution system is
repair times and feeder configurations, these basic indices are important from both utility and consumer point of view.
expressed using the following equations: This present paper addresses to evaluate the reliability of
s i f/yr ………….…..(1) distribution system in presence of DGs by simulation method
using DIgSILENT PowerFactory. RBTS test distribution
U s i i hrs/yr…………(2) system and practical system pertaining to Hebbal sub-station
is modeled using DIgSILENT PowerFactory. Reliability
Us
s
i i
hrs….….(3) indices of the test system are determined for different cases of
s i DG integration.
Where, λi and ri are the failure rate and the average repair
time of component-i, and Ui is the annual unavailability at the
load point i.
Published By:
Retrieval Number: J75860891020/2020©BEIESP Blue Eyes Intelligence Engineering
DOI: 10.35940/ijitee.J7586.0891020 382 and Sciences Publication
International Journal of Innovative Technology and Exploring Engineering (IJITEE)
ISSN: 2278-3075, Volume-9 Issue-10, August 2020
The cases considered are: i) Without DGs (Base Case), ii) points and loads are shown lumped at 415V level. For
With one DG (Synchronous / PV) to determine optimal size, industrial bulk consumers, loads are shown lumped at 11kV
iii) With two DGs (PV / Synchronous DG) to determine level itself. Overall system peak load is 20MW and average
optimal size, iv) DGs at different distance from the source to load is 12.29MW with total of 1908 customers at 22 load
determine optimal location. points Feeder-wise peak and average loads considered for
The objective in all the case studies above is to reduce the RBTS is show in the table-I. The defined average load is
system losses and to improve the reliability indices of the based on the fact that this will be value at the load point due to
given system. The impacts of DG integration on reliability are diversity factor between customers and normal load variations
throughout the day and through the year [35].
analyzed through simulation method using DIgSILENT
Power Factory software. The system losses and the reliability Table- I: Feeder-wise data for RBTS Bus2 system
indices obtained from the above case studies are used to Line Avg No. of
Feede Load Peak load
illustrate the impact of DG integration and in improving the r No.
length
Points (in MW)
load (in customer
reliability of the distribution system. Step by step in km MW) s
methodology adopted for the carrying out the work is: i) F1 2.85 LP1-7 5.934 3.645 652
Modeling of RBTS test distribution system and practical F2 2.35 LP8-9 3.5 2.15 2
Hebbal system using DIgSILENT PowerFactory software, ii) F3 2.9 LP10-15 5.046 3.106 632
F4 2.9 LP16-22 5.521 3.39 622
Determination of the real power loss in the system without
DG integration, iii) Determination of the reliability indices of Total 22 20.001 12.291 1908
the test system using reliability analysis tool without DG
integration, iv) Carrying out case studies with one DG and Line lengths, transformer capacities, load data are considered
two DGs and determine the power losses and reliability as per the RBTS data in [35]. The reliability data considered
indices, v) Carrying out case studies by placing the DGs at for 33kV and 11kV system components are shown in the
different distances from the source to determine the optimal table-II.
location, vi) Carrying out case studies to determine optimal
size of the DG for individual feeders of test system.vii) Table- II: Reliability relate data for 33kV and 11kV
comparison of results for test and practical system. Flow chart system components
showing the proposed methodology is shown in the fig.1. 33/11 kV Transformers
Start Active Failure Rate in f/yr.km 0.015
Repair time in hrs 15
Modeling of test system using
DIgSILENT PowerFactory 11 / 0.433 kV Distribution transformer
Active Failure Rate in f/yr.km
Load flow using modified NR method 0.015
without considering DG integration
Repair time in hrs 200
Ploss (without DG) = P(Gen) – P(Load) 11 kV lines
Active Failure Rate in f/yr.km 0.065
Determine the reliability Indices (SAIDI, SAIFI, ASAI, ASUI,
ENS, ASIFI & ASIDI) using Reliability analysis tool Repair time in hrs 5
Published By:
Retrieval Number: J75860891020/2020©BEIESP Blue Eyes Intelligence Engineering
DOI: 10.35940/ijitee.J7586.0891020 383 and Sciences Publication
Evaluation of Distributed Generation Impact on Reliability of a Distribution System using DIgSILENT PowerFactory
The 66/11 kV Hebbal SS is fed from 66 kV transmission condition, DG is connected to distribution network with a
line emanating from upstream 220 kV Hootagally Receiving circuit breaker iii) It is assumed that, the operation of the
Station (RS). The upstream network has been modeled as grid breaker is 100% reliable and it operates in case of any fault in
for analysis purpose Modeling and Simulation 3 Nos. of 11 the system and isolates the faulty portion so that power supply
kV Feeders viz. F1-HPCL, F2-Hebbal and F4-Birla which is available for the other customers of the healthy portion of
connected to 11kV Bank-1 at 66/11 kV Hebbal SS has been the system, iv) Either a synchronous DG (for 1-DG studies) or
considered for practical system study. 11kV Bank-1 and PV-DG with synchronous-DG (for 2-DG studies) is
above 11 kV feeders are connected to 66/11 kV, 12.5 MVA considered for case studies.
Transformer-1 at the SS.Line lengths, transformer capacities, The RBTS system and Hebbal feeder-1 system modeled
load data are considered as per the actual field data collected. using the DIgSILENT PowerFactory is as shown in the fig.2
The line parameters are as per table-3 and transformer and fig.3 respectively.
parameters considered are as per table-V.
Table- V: Transformer parameters for Hebbal System
Parameters Values
Published By:
Retrieval Number: J75860891020/2020©BEIESP Blue Eyes Intelligence Engineering
DOI: 10.35940/ijitee.J7586.0891020 384 and Sciences Publication
International Journal of Innovative Technology and Exploring Engineering (IJITEE)
ISSN: 2278-3075, Volume-9 Issue-10, August 2020
MW Losses in MW 0.09
Published By:
Retrieval Number: J75860891020/2020©BEIESP Blue Eyes Intelligence Engineering
DOI: 10.35940/ijitee.J7586.0891020 385 and Sciences Publication
Evaluation of Distributed Generation Impact on Reliability of a Distribution System using DIgSILENT PowerFactory
Published By:
Retrieval Number: J75860891020/2020©BEIESP Blue Eyes Intelligence Engineering
DOI: 10.35940/ijitee.J7586.0891020 386 and Sciences Publication
International Journal of Innovative Technology and Exploring Engineering (IJITEE)
ISSN: 2278-3075, Volume-9 Issue-10, August 2020
Also, the case studies are carried out for all the feeders of for RBTS and Hebbal system feeders for two DG case are
practical Hebbal system. presented in the table-XI and the bar chart in the fig.7.
The percentage loss reduction, optimal capacity of DG
Table- XI: Comparison of %age loss reduction,
than can be connected, percentage improvement in reliability optimal DG capacity and %age improvement in
in terms of SAIFI, SAIDI, ENS, ASIFI and ASIDI for RBTS reliability for RBTS Bus2 feeders & Hebbal system
bus2 system feeders and Hebbal feeders with single DG are feeders with 2-DGs.
presented in the table-X. Paramet RBTS Bus2 system Hebbal System
ers /
Table- X: Comparison of %age loss reduction, optimal Feeders F1 F3 F4 F2 F1 F2 F4
DG capacity and %age improvement in reliability for Optimal 70.0
72.00 80.00
90.0 60.0
50.00 77.00
RBTS Bus2 feeders & Hebbal system feeders with 1-DG. capacity 0 0 0
Paramet Loss
RBTS Bus2 system Hebbal System 33.3 50.0 60.0
ers / reductio 37.50 44.44 20.00 66.67
3 0 0
Feeders F1 F3 F4 F2 F1 F2 F4 n
Optimal 25.3 62.7 55.5
65.0 66.0 74.0 80.0 55.0 50 74 SAIFI 29.87 52.81 24.05 79.00
capacity 7 6 9
Loss 66. 62.7 16.4
33.3 37.5 44.4 50.0 40.0 20 SAIDI 4.61 5.94 10.47 10.65 31.55
reduction 6 0 7
24. 76. 11.6 65.0 35.0
SAIFI 16.6 23.4 47.8 57.8 60.7 ENS 12.24 14.51 5.41 38.34
0 3 1 5 8
10. 30. 52.6 65.0 56.1
SAIDI 3.0 4.6 9.4 57.9 18.0 ASIFI 58.41 60.43 12.59 82.86
6 5 3 4 5
5.4 37. 11.6 65.0 35.1
ENS 10.9 11.5 14.1 60.3 32.6 ASIDI 12.24 14.51 5.41 38.33
1 7 1 4 0
12. 81.
ASIFI 49.4 55.2 58.8 60.4 52.2
6 5
5.4 37.
ASIDI 10.9 11.5 14.1 60.4 32.6
1 7
Published By:
Retrieval Number: J75860891020/2020©BEIESP Blue Eyes Intelligence Engineering
DOI: 10.35940/ijitee.J7586.0891020 387 and Sciences Publication
Evaluation of Distributed Generation Impact on Reliability of a Distribution System using DIgSILENT PowerFactory
VI. CONCLUSIONS 6. Rudresh B.Magadum and D.B Kulkarni, “Optimal Location and
Sizing of Multiple DG for Efficient Operation of Power System”,
The DG integration impact on distribution system in terms IEEE, 2018.
of improvement in reliability indices and reduction in system 7. Mohamed Mostafa, Mostafa Elshahed, Mohamed S.Esobki, “The
Impact of Distributed Energy Resources on the Reliability of Smart
losses for different scenarios are determined by simulation Distribution System”, Majlesi Journal of Electrical Engineering,
method using DIgSILENT PowerFactory Software. Vol.12, No.4, December 2018.
Simulations have been performed for individual feeders of 8. Muhammad Zahid Kamaruzaman, Noor Izzri Abdul Wahab and
Mohammad Nasrun Mohd Nasir, “Reliability Assessment of Power
RBTS test system and practical Hebbal system feeders. Based system with Renewable Source using ETAP”, Proceedings of the
on the study results obtained from simulations and analysis of SMART-2018, IEEE conference ID: 44078, International conference
the distribution system, overall results are summarized by on system modeling & advancement in research trends,
November-2018.
focusing on the installation of suitable capacity of DG and the 9. J.Senthil kumar, P.Venkatesh, S.Charles Raja, J.Jeslin Drusila
location of DG which are important factors affecting the Nesamlar, C.Palanichamy, “Reliability Enhancement of Small and
system losses and system reliability indices Medium Distribution System with Renewable Genertions and
Summary of results for individual feeder studies are as Reclosers”, IEEE, 2018.
10. Vikas Singh Bhadoria, Nidhi Singal Pal, Vivek Shrivastava and Shiva
follows, i) the optimal capacity for maximum loss reduction Pujan Jaiswal, “Reliability Improvement of Distribution system by
with single DG would be 50-74% of the loading of the line. Optimal Sitting and Sizing of Disperse Generation”, International
This is in line with 2/3 rule for the radial feeders. This can be Journal of Reliability, Quality and Safety Engineering, Vol.2, No.6
(2017) 1740006.
improved up to 70-84% in case of 2 DGs, ii) Loss reduction 11. Juan Li, Honglian Zhou, Erbiao Zhou, Jingjie Xue, Zifa Liu and
with 2-DG interconnection will be less than that of 1-DG case, Xuyang Wang, “Comprehensive Evaluation of Impacts of High
iii) Reliability will further improve with 2-DGs when Penetration of Distributed Generation Integration in Distribution
Network, IEEE, 2017.
compared to 1-DG placement, iv). For maximum loss 12. Sanaullaha Ahmad, Azzam Ul Asar, Sana Sardar and Babar Noor,
reduction and reliability improvement, it is optimal to place “Impact of Distributed Generation on the Reliability of Local
DG between 75% of line length towards the tail end for lower Distribution System”, International Journal of Advanced Computer
Science and Applications, Vol.8, No.6, 2017.
DG capacities below optimal, v) For higher DG capacity, loss
13. Hadi Suyono, Wiono, Rini Nur Hasanah and Syamsu Dhuba, “Power
reduction is much better in case of placing DG at 50% line Distribution System Reliability Improvement due to Injection of
length. Hence, it is best feasible to place the DG between 50% Distributed Generation”, IEEE, 2017.
to 75% of the line length for better reliability improvement, 14. A.Ngaopitakkul, C.Jettanasen, “The Effects of Multi-Distributed
Generator on Distribution System Reliability”, IEEE, 2017.
vi) It is not feasible to place the DG nearer to the source in 15. M.R.Siddappaji, Dr.K.Thippeswamy, “Reliability Indices Evaluation
view of both higher losses and poor reliability compared to and Optimal Placement of Distributed Generation for Loss Reduction
placing DGs away from the source. These simulation results in Distribution System by using Fast Decoupled Method”,
International Conference on Energy, Communication, Data Analytics
will provide the network operators a good tool to anticipate and Soft Computing (ICECDS-2017).
the system performance in presence of DGs and to evaluate 16. K. Prakash, F. R. Islam, K. A. Mamun, A. Lallu and M. Cirrincione,
the reliability of the system before allowing for “Reliability of Power Distribution Networks With Renewable Energy
Sources”, IEEE, 2017.
interconnections. Simulation results have demonstrated that
17. Fabian C.Oreke, D.C Idoniboyeobu, “Reliability Assessment of
the proposed method can be an effective means for Electrical Energy Distribution System – A cas study of Port Harcourt
considering DG placement in the distribution system. The Distribution Network”, IJRASET, Vol-5, Issue VI, June 2017.
decision regarding the DG placement and sizing can be taken 18. Sanaullaha Ahmad, Sana Sardar, Babar Noor and Azzam Ul Asar,
“Analyzing Distributed Generation Impact on the Reliability of
based on the study results. The advantage of the present Electric Distribution Network”, International Journal of Advanced
method is that it takes into account both the system losses and Computer Science and Applications, Vol.7, No.10, 2016.
the reliability of the system in presence of DGs. 19. Ulas Eminoglu, Ridvan Uyan, “Reliability Analyses of Electrical
Distribution System: A case study”, International Refereed Journal of
Engineering and Science (IRJES), Vol.5, Issue 12, December-2016,
ACKNOWLEDGMENT PP.94-102.
20. Prabhjot Kaur, Sandeep Kaur and Rintu Khanna, “Optimal Placement
The authors thank Dr. M S Shashikala, Professor & Head, and Sizing of DG Comparison of Different Techniques of DG
Department of E&EE, JSS Science & Technology University, Placement”, 1st IEEE International Conference on Power Electronics,
Mysuru for her valuable inputs and support. Intelligent Control and Energy Systems (ICPEICES-2016).
21. V.S.S.Sailaja, Dr.P.V.N.Prasad, “Determination of Optimal
Distributed Generation Size for Losses, Protection Co-Ordination and
REFERENCES Reliability Evaluation Using ETAP”, Biennial International
Conference on Power and Energy Systems:Towards Sustainable
1. A.T.Mohamed, A.A.Helal, S.M.El safty, “Distribution System
Energy (PESTSE), 2016.
Reliability Evaluation in Presence of DG”, IEEE, 2019.
22. Maad Al Owaifeer, Mohammad AlMuhaini, “Reliability Analysis of
2. Ashutosh Barik, Srinivasalu G and Balakrishna P, “An effective
Distribution Systems with Hybrid Renewable Energy and Demand
Method of optimal DG location, Type and Size to Deal with Power
Side Management”, 13th International Multi-Conference on Systems,
System Constraints”, ICSETS, IEEE, 2019.
Signals & Devices, 2016.
3. Sreevidya.L, S.U.Prabha and S.Sathiya, “Evaluation of the Reliability
23. P.Chandhra Sekhar, R.A.Deshpande, V.Sankar, “Evaluation and
of Distribution System with Distributed Generation using ETAP”,
Improvement of Reliability Indices of Electrical Power Distribution
International Journal of Soft Computing and Engineering (IJSCE),
System”, IEEE, 2016.
ISSN: 2231-2307, Volue-8 Issue-5, January 2019.
24. Noppatee Sabpayakon, Somporn Sirisumrannukul, “Power losses
4. Mingze Zhang et al, “Reliability Evaluation of Distribution Power Unit
reduction and reliability improvement in distribution system with Very
Based on DG Power Contribution”, IEEE PES Innovative Smart Gird
Small Power Producers”, Elsevier, 2016.
Technologies Asia, 2019.
5. K.Kirubarani, APeer Fathima, “Distribution System Reliability
Assessment for Improved Feeder Configurations”, IEEE PES
Innovative Smart Gird Technologies Asia, 2019.
Published By:
Retrieval Number: J75860891020/2020©BEIESP Blue Eyes Intelligence Engineering
DOI: 10.35940/ijitee.J7586.0891020 388 and Sciences Publication
International Journal of Innovative Technology and Exploring Engineering (IJITEE)
ISSN: 2278-3075, Volume-9 Issue-10, August 2020
AUTHORS PROFILE
Mr. Ravishankar B. S. is working as Assistant
Professor in the Department of Electrical &
Electronics Engineering. He obtained his B.E. and
M.Tech. Degrees from Visveswaraiah Technology
University. His research interests are in the field of
Applications in Power Systems, Distributed
generation and reliability of Distribution systems.
Published By:
Retrieval Number: J75860891020/2020©BEIESP Blue Eyes Intelligence Engineering
DOI: 10.35940/ijitee.J7586.0891020 389 and Sciences Publication