1 SEPCO3 EPC Contractor 91 71 73 91 218 167 160 218

2 Steady Lift(BD)PVT.LIMITED Logistics company for EPCC 5 5 5 5 30 30 30 30

3 Zhong Ji Jian kan Bangladesh Co.Ltd PG piles construction 0 0 0 0 0 0 0 0


Pipe construction,civil construction,coal transport,
3 3 3 3 130 130 130 130
4 Sinohydro corporation limited booster Station
SS installation of BOP area 0 0 0 0 0 0 0 0

Foundation work of 2# boiler area & 2# main power


5 Tianyuan Construction Group Co.,Ltd 6 6 6 6 90 90 90 90
house area etc.

Foundation work for Chimney area & 1# boiler area &


8 8 8 8 105 105 105 105
1# main power house area, etc.
6 Zhongjijianye construction engineering LTD
Painting in MPH and BOP area 12 12 12 12 103 103 103 103

Steel structure lifting of #1 &#2 MPH, etc. 2 2 2 2 30 30 30 30

China State Construction Port Engineering Group


7 Jetty construction and south breakwater 2 2 2 2 30 30 30 30
Corp., Ltd

CRCC Harbour & Channel Engineering Bureau


8 North breakwater(including the fabrication area) 2 2 2 2 5 5 5 5
Group Co., LTD

Chimney Consultants & Construction (Bangladesh) Chimney construction and construction of ash storage
9 3 3 3 3 30 30 30 30
PVT.LTD & desulfurization absorption tower
SS installation of #1&2 Boiler,boiler proper such as
10 Shandong Futai Construction Engineering Co., Ltd 0 0 0 0 0 0 0 0
waterwall etc. of #2 boiler
installation of #1ESP,air and flue duct and auxiliary
11 Laiwu Shengjian Construction Co., Ltd 0 0 0 0 0 0 0 0
machinery installation

water tank installation 0 0 0 0 0 0 0 0


The First Construction of China Mechanical Industry Turbine BOP area installation 0 0 0 0 0 0 0 0
12
Co.Ltd
Production and installation of oil tanks & installation o
3 3 3 3 10 10 10 10
f oil pipelines
turbine 10 10 10 10 32 32 32 32
13 China Petroleum Pipeline Engineering Co., Ltd
HDPE -Civil 15 15 15 15 35 35 35 35

WTS Boiler Energy Saving Science &Technology Co.,


14 anticorrosion of CW 3 3 3 3 17 17 17 17
Ltd

Temporary building work 5 5 5 5 15 15 15 15

All electric work expect for #1 turbine and FGD 5 5 5 5 15 15 15 15


15 Laiwu Shaohua Construction Co., Ltd I&C construction of #1and #2 MPH, water tratement
5 5 5 5 15 15 15 15
area,HVAC and FAS
Anticorrosion of boiler SS 5 5 5 5 30 30 30 30
Unit 2 steam turbine installation project, steam turbine
5 5 5 5 40 40 40 40
auxiliary equipment and pipelines
Northwestern Third Electricity Power Construction
16 Whole plant heat treatment engineering contrac 0 0 0 0 10 10 10 10
Co., Ltd
Four major Critical pipeline processing and
0 0 0 0 10 10 10 10
preparation
Binhai Water Conservancy Construction Engineering
17 Ground treatment of CW pipe 0 0 0 0 0 0 0 0
Company
Chinese Bangladeshi
SI No. Agency Name Description of Work
Now January February March Now January February March
18 Henan Biaohui Construction Engineering Co., Ltd. Painting of all equipments and pipe at site 3 3 3 3 21 21 21 21
Auxiliary equipment and pipe installation of #1MPH
19 Shandong Xiantong Equipment Installation Co., Ltd. 0 0 0 0 0 0 0 0
and BOP area
Zhengzhou Longhua Electromechanical Engineering
20 Electrical installation work of unit 1 10 10 10 10 50 50 50 50
Co., Ltd.
Installation of #1ESP,electric dedusting, boiler
Shandong Lvchuang power equipment installation auxiliary equipment 3 3 3 3 20 20 20 20
21 Installation of #2ESP,electric dedusting, boiler
Co., Ltd 0 0 0 0 0 0 0 0
auxiliary equipment
22 Changyuan construction installation Co.Ltd Drain construction 1 1 1 1 15 15 15 15

23 WESTERN Cement bag shifting & loading 0 0 0 0 4 4 4 4

24 FALCON® SECURITY LIMITED Security 0 0 0 0 128 128 128 128

25 Shengqiang Engineering Company Electrical work for BOP and CHP Area 10 10 10 10 40 40 40 40
Installation of desulphurization and ash removal
26 Yitong construction installation Co.Ltd 12 12 12 12 91 91 91 91
pipeline,oil and start-up boiler
27 Living water supply pipeline 3 3 3 3 50 50 50 50
Tiankun fire protection Co.Ltd Fire fighting, ventilation and air conditioning
28 6 6 6 6 100 100 100 100
construction
29 M/S green construction Co.Ltd Drainage ditch 0 0 0 0 15 15 15 15

30 BIX All testing work at site 0 0 0 0 0 0 0 0

31 IITS All testing work at site 0 0 0 0 10 10 10 10

32 S.K.Corporation Anti-corrosion of BOP 0 0 0 0 20 20 20 20

33 Shandong DeJian Co.Ltd Service building 8 8 8 8 50 50 50 50

34 Tai Yang Company Pier prefabrication 3 3 3 3 20 20 20 20

35 SuTong construction Co.Ltd Seawater inatke pump house 10 10 10 10 90 90 90 90

36 Shandong Yaohua Co.Ltd Pipe anti-corrosion in MPH 5 5 5 5 40 40 40 40

37 Henan Huaye Co.Ltd Insulation work of boiler 10 10 10 10 70 70 70 70

38 Manufacturer representative Technical communication 23 23 23 23 0 0 0 0

39 Hua Feng Wei Ye Testing boiler and quipment 6 6 6 6 2 2 2 2

40 Xin Ya Harbor dredging 0 0 0 0 3 3 3 3

41 Hua Cheng Electrical work 5 5 5 5 2 2 2 2

42 Tajrian Drainage ditch 0 0 0 0 42 42 42 42

43 Afser Fencing wall 0 0 0 0 40 40 40 40

total 308 288 290 308 1923 1872 1865 1923