Matecconf Mse2019 10003
Matecconf Mse2019 10003
Matecconf Mse2019 10003
1051/matecconf /201929010003
MSE 2019
1 Introduction
Considering the information provided by the International Energy Agency [1], the global
natural gas demand increased continuously since 2009, reaching 3757 billion m 3, with the
perspective of an increase up to 23% to 25% share of the global energy consumption in
2040.
The global natural gas demand increase is related, mainly, with a lower environment
impact of this fuel as compared to other fossil fuels, especially in relation to air quality, as
well as to greenhouse gas, as natural gas is the main substitute of coal in electricity
generation industry, despite the higher risks implied by the explosive character of the
natural gases [2].
Thus, “natural gas comprised 22% of electricity supply globally in 2014. By 2060 this could
change to anything between 17-32% - an absolute increase of between 300-1500 bcm” [3].
In order to satisfy such demand, the gas producers plan drilling programs for exploration
– in order to discover new gas reservoirs, and for production - in order to increase the gas
production rate for reservoirs in production. To achieve such investment programs,
considerable amounts are often allocated, amounts which are often spent before completing
the program, due to complications and technical accidents occurred during drilling which
might increase the final cost of the wells.
*
Corresponding author: [email protected]
© The Authors, published by EDP Sciences. This is an open access article distributed under the terms of the Creative
Commons Attribution License 4.0 (http://creativecommons.org/licenses/by/4.0/).
MATEC Web of Conferences 290, 10003 (2019) https://doi.org/10.1051/matecconf /201929010003
MSE 2019
To reduce such unforeseen costs of the well drilling operations, more and more companies
experiment and implement new drilling techniques and technologies which reduce the down-
time, mitigate the risk and technical accidents while drilling.
Casing while drilling - CwD is one of the alternatives of controlled pressure drilling like
Constant Bottomhole Pressure, Pressurized Mud Cap Drilling or Dual Gradient Drilling.
Casing while drilling is an alternative to conventional drilling using the casing as drilling
string, drilling and casing the well simultaneously.
Although the casing while drilling technology was tested in the 1920s, extensive use was
possible only during the last decade, following the technical advancements [4]. The method
was therefore proven as effective in reducing the overall drilling cost by reducing drilling
time and the problems associated to the drilling string.
2
MATEC Web of Conferences 290, 10003 (2019) https://doi.org/10.1051/matecconf /201929010003
MSE 2019
Fig. 1. Casing drive System [4]. Fig. 2. Milling the drilling bit used for CwD.
To maintain the well’s track, to manage casing wear and lining-up casing during
cementing the casing is fit with centralizers. It is recommended to use centralizers with rough
surface and hard blades, non-rotating, made of zinc alloy, that are extremely durable during
directional drilling with casing - Figure 5.
Casing threads are different from those used for conventional drilling to meet the different
working conditions in the well. Therefore, the casing manufacturers developed a range of
casings that satisfy the challenges and severe well conditions manifested during casing while
drilling. These connections have to ensure torque resistance, adequate sealing capacity and
fatigue strength.
In certain situations, casing while drilling calls for using a recoverable/retractable drilling
system due to the need to replace the damaged equipment before reaching the casing depth.
Operators have to reach rapidly and efficiently the formations beneath the casing shoe
and to recover the expensive tools used for a directional casing while drilling.
Casing while drilling uses a bottom hole assembly (BHA) that can be run in and retrieved
by a wireline; its main elements are a bit and an under reamer at the bottom of casing string
to drill a hole of adequate size to allow the casing to pass freely.
The BHA is attached to Drill-Lock Assembly (DLA) engaging axial lock and torsional
lock, fixed in a nipple at the lower part of the casing string that can be retrieved by wireline
without removing the casing from the well. The retrievable DLA rotates both the casing string
and the drilling string and transfers compression and torque loading. It is recommended to
use centralizers on the casing and to prevent wear of sleeves.
BHA may include other equipment necessary for performing almost any operation as a
conventional drilling string. Conventional directional drilling tools (positive displacement
motor, MWD) and LWD may be suspended below the casing shoe for directional drilling.
3
MATEC Web of Conferences 290, 10003 (2019) https://doi.org/10.1051/matecconf /201929010003
MSE 2019
Fig. 3. Float collar [4]. Fig. 4. Wiper Plugs [4]. Fig. 5. Centralizer Sub [4].
3 CwD Advantages
Using CwD a lot of problems associated to conventional drilling are eliminated or reduced.
Among these problems, an important category is caused by the drilling string that may
induce the following risks:
− twist off of the drill collar, kelly, drill pipe;
− drilling string sub-assemblies pull out of threads or unscrewing;
− drilling string getting stuck;
− drill pipe breaking or bending.
Other problems that can be avoided by casing while drilling are those associated to
inserting casing in wells with bended or collapsed holes. Moreover, one can avoid problems
caused by crossing formations that deteriorate due to long exposure to drilling fluids,
problems associated to crossing unstable formations (borehole collapsing and overpull) or
crossing formations with loss of circulation.
These issues are overcome by the so-called plastering effect generated by rotating the
casing string in a small annular space causing detritus to enter the borehole wall, sealing the
formation pores and strengthening the borehole walls [4].
As shown in figure 6, while drilling with a conventional drilling string the annular space
is larger, casing while drilling reduces to minimum the annular space resulting in a more
stable and sealed wellbore. Additionally, the annular ascending velocity of the drilling fluid
through this annular space is high, improving detritus cleaning from the wellbore, and the
rigidity of the casing string make a less tortuous hole, reducing the risk of key seats or
mechanical sticking.
Another CwD advantage is total drilling time reduction by eliminating time and efforts
implied by tripping casing string. Therefore, after reaching the depth for setting the casing,
the drilling fluid is replaced by cement, the float collar being installed before drilling start.
Therefore, the operations performed before conventional casing and cementing are
avoided, operations involving control tripping of the borehole to correct the overpulling
areas, circulating for removing solids from the fluid from, performing electrometric
operations, retrieval the bit by decomposing strings, inserting casing by filling the casing
string at each casing section.
4
MATEC Web of Conferences 290, 10003 (2019) https://doi.org/10.1051/matecconf /201929010003
MSE 2019
5
MATEC Web of Conferences 290, 10003 (2019) https://doi.org/10.1051/matecconf /201929010003
MSE 2019
The outer pressure that reaches on the inner casing wall the minimum yield point is given
by the ratio (thick wall casing) [5]:
𝐷⁄ −1
𝑡
𝑃𝑒 = 2𝜎𝑐 ⌊ 2⌋ (1)
(𝐷⁄𝑡 )
where c is yield point;
D – outside diameter;
t – wall thickness.
Inner pressure is the casing fluid pressure, that can be the drilling fluid or the fluid from
a layer opened while drilling. The strength to inner pressure can be calculated by using
Barlow’s formula [5]:
𝜎 𝑡
𝑃𝑖 = 2 𝑐 (2)
𝐷
Torque at the drill bit at the bottom of the hole is the consequence of the cutting process
and of the friction of the casing against the wall of the borehole and/or of the previously cased
hole. Having the drill bit above the bottom hole, the torque resides only from friction of the
casing. Casing while drilling torque is usually higher than at conventional drilling due to the
friction forces acting on the contact point between the borehole walls and the casing, creating
a strength moment with a vector direction opposite to the casing rotation. Thus, when the
casing is rotating in the borehole placing a certain weight on the bit, the moment at the bit is
much lower than the rotating moment at the surface. Therefore, the maximum torque at the
surface sets the casing rotation limit and the increase of the drilling rate.
Fatigue results from the cyclic load at different stress levels considerably lower than the
yield point of the casing material. Under continuous load, a small crack starts to spread from
the high stress point along the casing breaking it.
Buckling results from the bending moments created by the casing-borehole geometry and
the compressive load, thus making it unstable. If the compressive stress acting on the casing
exceeds a certain value, the casing buckles into a helical or sinusoidal shape.
6
MATEC Web of Conferences 290, 10003 (2019) https://doi.org/10.1051/matecconf /201929010003
MSE 2019
After buckling, the casing leans against the borehole walls, thus the lateral stress from the
contact point may cause wear and may lead to an increase of the moment required for rotation.
Taking into account the above-mentioned elements, following stages are necessary for
sizing the casing string [5]:
- preliminary sizing for cracking and crushing;
- correct the profile set in the first stage by reducing the casing collapsing pressure
under tensile forces;
- to check the casing and joints tensile resistance.
Other loadings have to be also considered [4]:
- bending with tongs during make-up;
- pull-out of the joint and slip crushing;
- corrosion and fatigue failure;
- pipe wear from running wireline tools and drill string.
To perform casing while drilling in safety conditions it is mandatory to apply during the
design phase safety coefficients. The highest safety coefficients should be considered for
tensile forces, in order to consider additional stress such as friction with the borehole wall,
sticking trends, dynamic forces or buckling. With respect to tension a safety factor of 1.6 –
1.8 is applied for the upper joint of casing [4].
In case of breaking and crushing, the coefficient can be lower, for breaking 1.1 and 1.0 and
for crushing 0.9; the calculation hypotheses for such stress are less probable to be fulfilled [5].
7
MATEC Web of Conferences 290, 10003 (2019) https://doi.org/10.1051/matecconf /201929010003
MSE 2019
Drill string Drill pipes break off. Non-productive String control while run in
failure Threaded connections pull times. Additional hole and pull out.
out or break off. consumption of Using drill pipes in
Lost string. materials and accordance with well
services. requirements of wear and
Compromised well. tear.
Control of elevator, links,
rams, drilling cable.
Casing Casing pull out from a Non-productive Proper tightening of
failure connection. times. Additional connection.
Casing collapse. consumption of Drilling fluid pumping at
Break of casing. materials and each or every second
services. casing(s) run in hole.
Well construction Casing testing at surface
compromised. before RIH.
8
MATEC Web of Conferences 290, 10003 (2019) https://doi.org/10.1051/matecconf /201929010003
MSE 2019
6 Conclusions
In the context of ever rising costs of well drilling, many of them performed in new geological
structures, deep wells, implying a series of geological and technical risks, more and more
companies are experimenting and implementing new drilling techniques and technologies
with the aim of reducing non-productive times, technical accidents while drilling, and risk
mitigation.
Casing while drilling, constantly improving over time, has proven an efficient method to
reduce risks, especially those related to the presence of a conventional drill string in the
borehole, maintenance of borehole stability or loss of circulation. Moreover, by reducing
non-productive times and additional costs to overcome difficulties and technical accidents
while drilling, implementation of casing while drilling results in significant cost savings.
References
1. International Energy Agency, Natural Gas Information: 2018 Overview (IEA, 2018)
2. A. Gligor, Petroleum - Gas University of Ploiesti Bulletin, Technical Series, 68, 3 (2015)
3. C. Frei, World Energy Focus (2017)
4. Weatherford Atlas GIP, Drilling-while-casing (DwC) system. (Bucharest, 2015)
5. N. Macovei, Tubarea si cimentarea sondelor (Editura Universității din Ploiești, 1998)
6. ISO, ISO/Guide 73:2009 - Risk management – Vocabulary (ISO, 2010)
7. ISO, ISO 31010, Risk Management – Risk assessment techniques (ISO, 2010).