17 Degree Of Protection IP 65
18 Cable Entry ½” NPT Brass double compression cable gland to be provided with unit
Terminal block to be provided suitable for a terminating a wire up to 2.5
19 Electrical Connection
sq.mm conductor
20 Gasket Heat resist moisture proof
21 Conversion 3 Wire
22 Type 3 Wire DUPLEX
23 Material Platinum - 100 (PT-100)
24 Calibration To DIN Standards
25 Ice Point Resistance 100 Ohms at 0 Deg.C
26 Leads Hermatically sealed
PROBE / ELEMENT DETAILS
40 Material SS 316
41 Construction Straight & closed end tube
42 Wall Thickness 4 mm
43 Outer Diameter 16 mm
44 Inner Connection ½” NPT (F)
1 1/2" ANSI, 150#, CS flange with suitable adapter to adjust immersion length
45 Process Connection / Mounting Details along with counter flange, suitable nuts, bolts and spring washers etc. should
be included in the supply
(i). PT-100 RTD probe with adjustable screw
(ii). Flange type Thermowell
46 Accessories (iii). Counter flange, suitable nuts, bolts,spring washers and gasket
OTHER DETAILS
Sr. No. Service Immersion Length Input Range Tag-No. Quantity Model No. Remark
HGG NATURAL GAS LINE
1 300 mm 0 - 450 °C 3TE01 0216 1 (*)
TEMPERATURE
DYNAMIC CLASSIFIER INLET
2 300 mm 0 - 150 °C 3TE01 0207 1 (*)
TEMPERATURE
DYNAMIC CLASSIFIER INLET
3 300 mm 0 - 150 °C 3TE01 0203 1 (*)
TEMPERATURE
DYNAMIC CLASSIFIER INLET
4 300 mm 0 - 150 °C 3TE01 0206 1 (*)
TEMPERATURE
GENERAL NOTES
1 This is preliminary specification. Order to be placed on supplier only after technical clarification from engineering.
2 Supplier to confirm specifications as mentioned above. Deviation/discrepancy if any should be informed before supplying the material.
4 Schenck data sheet number should be mentioned on all inspection reports & Drawings /Documents to be submitted for approval / records.
7 The serial number should be mentioned on the unit and also on all inspection reports.
8 The equipment should be packed with adequately rigid packing with adequate bracing and waterproof packing to avoid any damage during transportation handling & storage.
9 The supplier is responsible for design, supply and operational guarantee of the unit for committed period from the date of commissioning.
10 Supplier should provide guarantee on utility & consumption parameters provided by them.
For specified input conditions and required output parameters, supplier to specify and supply all required components, accessories & mounting even if the same is not mentioned in
11
this datasheet.
12 Supplier need to be consider relevant points under General Notes as applicable.