3999 Dgen 1 19 0021 Afc
3999 Dgen 1 19 0021 Afc
3999 Dgen 1 19 0021 Afc
SHEET [ CRS ]
CONTRACT NUMBER GC16109100 QP PROJECT NUMBER 3999
CONTRACT TITLE EPIC FOR REPLACEMENT OF CRUDE OIL TRANSFER LINES AT DUKHAN
Page 1 of 1
METHOD STATEMENT FOR
CONCRETE DEMOLITION
Contents
1. SCOPE ........................................................................................................................................................... 3
2. REFERENCE ................................................................................................................................................... 3
3. DEFINITIONS ................................................................................................................................................. 3
4. RESPONSIBILITY ............................................................................................................................................ 3
4.1 The Civil Engineer ....................................................................................................................................... 3
4.2 The Construction Supervisor ...................................................................................................................... 3
4.3 The Civil QC Inspector (QCIC) ..................................................................................................................... 4
4.4 The Safety Officer....................................................................................................................................... 4
4.5 The Surveyor .............................................................................................................................................. 4
4.6 The Banks Man ........................................................................................................................................... 4
4.7 The Equipment Driver/Operator ................................................................................................................ 4
5. RESOURSE .................................................................................................................................................... 5
5.1 Manpower .................................................................................................................................................. 5
5.2 Equipment. ................................................................................................................................................. 5
6. HSE REQUIREMENT ...................................................................................................................................... 5
7. WORK PROCEDURE ...................................................................................................................................... 5
7.1 Concrete Demolition .............................................................................................................................. 5
7.2 MATERIAL SHIFTING .............................................................................................................................. 6
8. ATTACHMENT............................................................................................................................................... 6
1.Job Hazard Analysis .................................................................................................................................... 6
1. SCOPE
The scope of this method statement is to describe in detail a construction
methodology for civil works associated with pre-cast installation and concrete
demolition. Identification of associated hazards and mitigation methods to be
taken in order to execute all works safely as per project requirements and
specification.
2. REFERENCE
➢ QP Specification for Onshore Pipeline Construction - QP-SPC-L-018
➢ Qatar construction specification (QCS) - 2014
➢ Project HSE Plan - 3999-DGEN-3-24-
0001
➢ Contract Quality Plan - QP-STD-Q-004
➢ Inspection & Testing Plan - 3999-DGEN-
1-25-0003
➢ QP safety regulations for contractors - QP-REG-S-001
➢ QP Corporate Philosophy for Fire and Safety - QP-PHL-S-001
3. DEFINITIONS
➢ PROJECT : EPIC for Replacement of crude oil
Transfer lines at Dukhan
➢ COMPANY : Qatar Petroleum
➢ CONTRACTOR : Al-Balagh Trad &Contra Co W.L.L
➢ CONST. SUPERVISOR : Authorized Permit Receiver
➢ QCIC : Quality Control Inspector(Civil)
➢ HSE : Health, Safety & Environment.
➢ CAR : Corrective Action Request
➢ AFC : Approved for Construction
➢ ITP : Inspection and Test Plan
4. RESPONSIBILITY
4.1 The Civil Engineer
• Civil engineer will supervise all activities on the area based on project scope
of work and as per relevant standards and project specification.
4.2 The Construction Supervisor
• Construction Supervisor is required to ensure that all works are carried out as
per approved drawings, project specifications & requirements.
• Construction Supervisor will ensure that the work is covered with valid work
permits from QP, wherever applicable, and all permit/safety requirements are
strictly followed.
• Conduct tool box talks explaining the hazards associated with the work and
the mitigation measures.
5. RESOURSE
5.1 Manpower
AL-BALAGH shall adequately resource the foundations construction works with
staff, which are well versed and experienced, crafts to be utilized be are outlined
are as follows:
5.2 Equipment.
AL-BALAGH has allocated licensed, authorized and certificated equipment which
will be available and can be deployed to any section of work as when required
bases. The types of equipment are enumerated as follows:
8. ATTACHMENT
1. Job Hazard Analysis