Storage and Settling Tanks (SSTR) Revamp: ES/NCDMB/MPN-TITT/07032023/UPD
Storage and Settling Tanks (SSTR) Revamp: ES/NCDMB/MPN-TITT/07032023/UPD
Storage and Settling Tanks (SSTR) Revamp: ES/NCDMB/MPN-TITT/07032023/UPD
This document is the Job Specification which forms the technical basis for the
proposed contract. It details what work the contractor is requested to perform,
the schedule for that work and how the contractor will communicate and interact
with the Project Team during the life of the contract.
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
Table of Contents
JOB SPECIFICATION.................................................................................................................0
SECTION B: DEFINITIONS.........................................................................................................3
A. OVERVIEW............................................................................................................................9
2. CLIMATIC CONDITIONS.....................................................................................................9
A. INTRODUCTION.......................................................................................................................22
B. REFERENCES............................................................................................................................23
D. JOB PROCESS...........................................................................................................................25
ATTENDANT.....................................................................................................................................32
ENTRANTS........................................................................................................................................32
RESCUER...........................................................................................................................................32
7 COMPANY’S RESPONSIBILITIES:....................................................................................40
A COMPENSATION.................................................................................................................43
A. SCOPE OF WORK:..............................................................................................................50
B. DETAILED WORKSCOPE:...........................................................................................................53
1. PREPARATORY WORKS....................................................................................................53
1.1 MOBILIZATION:..................................................................................................................53
1.2 MOBILIZATION FROM ONE TANK SITE TO ANOTHER WITHIN SAME TERMINAL:.................53
1.3 DEMOBILIZATION:..............................................................................................................53
1.4 INSTALL FENCING:..............................................................................................................53
1.5 INSTALL FIRE SCREEN:.......................................................................................................53
1.6 LEAK TESTING:...................................................................................................................54
1.7 CLEAN AND GAS FREE FLOATING ROOF PONTOONS:..........................................................54
1.8 FLOATING ROOF STABILIZATION:.......................................................................................54
1.9 TANK INSPECTION:.............................................................................................................54
1.10 VACUUM BOX TESTING:....................................................................................................55
2 ROOF WORKS.......................................................................................................................56
2.3.2 REMOVAL OF ROOF PENETRATIONS (WHEN ENTIRE ROOF IS NOT BEING DEMOLISHED)
INCLUDING ALL REINFORCING PAD PLATES ETC...................................................................................56
2.4 ROOF PLATE AND ROOF STRUCTURE INSTALLATION..........................................................56
2.4.1 SUPPLY, FABRICATE AND INSTALL NEW ROOF PLATES/STRUCTURAL SECTIONS PER API
650/653................................................................................................................................................56
2.4.2 ROOF APPURTENANCES, ACCESSORIES & STRUCTURES..........................................................57
2.5 BLASTING AND COATING OF ROOF......................................................................................58
2.6 FLOATING ROOF SEAL:.......................................................................................................59
3 SHELL WORKS.....................................................................................................................60
3.1 REMOVE AND REPLACE SHELL PLATES, INSERT PLATES, DOOR SHEETS OR WIND GIRDER
60
3.1.1 REMOVE AND REPLACE SHELL PLATES...................................................................................60
3.1.2 REMOVE AND REPLACE WIND GIRDER...................................................................................60
3.1.3 REMOVE AND REPLACE COMPLETE SHELL COURSE................................................................60
3.1.4 REMOVE SHELL ATTACHMENT:...............................................................................................60
3.2 BLASTING AND COATING OF SHELL (EXTERNAL)................................................................60
3.3 BLASTING AND COATING OF SHELL (INTERNAL) TOP 1 METER BAND.................................61
3.4 MANWAYS AND NOZZLES....................................................................................................61
4 BOTTOM WORKS.................................................................................................................62
5 PIPE WORKS.........................................................................................................................63
7 ANCILLARY WORK.............................................................................................................67
SUPPLY AND INSTALL FIBER OPTIC CABLE, SINGLE MODE, 8 STRANDS MINIMUM,
INCLUDING PATCH PANELS...................................................................................................69
8 WELD REPAIR:.....................................................................................................................69
9 TESTING:...............................................................................................................................70
10 TANKS RECALIBRATION.................................................................................................71
12 TANK JACKING
UP………………………………………………………………………...72
13 DESCALING OF INSTALLED
PIPING……………………………………………………...72
14 APPENDICES.......................................................................................................................73
A. PURPOSE...............................................................................................................................75
B. DEFINITIONS.........................................................................................................................75
C. COMPANY PLAN...................................................................................................................76
D. SCHEDULE MILESTONES.......................................................................................................76
E. CONTRACT CONTROL SCHEDULE..........................................................................................76
F. SCHEDULE CONTROL.............................................................................................................77
APPENDIX 1.................................................................................................................................79
COMPANY PLAN........................................................................................................................79
APPENDIX 1.................................................................................................................................80
APPENDIX 2.................................................................................................................................81
SCHEDULE MILESTONES.........................................................................................................81
APPENDIX 3.................................................................................................................................84
PREFACE......................................................................................................................................87
1. INTRODUCTION......................................................................................................................88
1.1 COMPANY DUTIES...................................................................................................................88
1.2 CONTRACTOR DUTIES............................................................................................................88
1.3 SYSTEMS, PROCEDURES, AND PLANS..........................................................................................89
1.4 REPORTS.....................................................................................................................................97
2. ORGANIZATION AND STAFFING.............................................................................................98
2.1 COMPANY DUTIES...................................................................................................................98
2.2 CONTRACTOR DUTIES............................................................................................................98
2.3 SYSTEMS, PROCEDURES, AND PLANS..........................................................................................99
2.4 REPORTS...................................................................................................................................100
3. ADMINISTRATION................................................................................................................101
3.1 COMPANY DUTIES.................................................................................................................101
3.2 CONTRACTOR DUTIES..........................................................................................................101
3.3 REPORTS...................................................................................................................................108
4. INFORMATION MANAGEMENT.............................................................................................112
4.1 COMPANY DUTIES.................................................................................................................112
4.2 CONTRACTOR DUTIES..........................................................................................................112
4.3 SYSTEMS, PROCEDURES, AND PLANS........................................................................................116
4.4 REPORTS...................................................................................................................................117
5. INTERFACE MANAGEMENT..................................................................................................118
5.1 COMPANY DUTIES.................................................................................................................118
5.2 CONTRACTOR DUTIES..........................................................................................................118
5.3 SYSTEMS, PROCEDURES, AND PLANS........................................................................................120
5.4 REPORTS...................................................................................................................................120
6. ENGINEERING AND TECHNICAL DOCUMENTATION..............................................................121
6.1 COMPANY DUTIES.................................................................................................................121
6.2 CONTRACTOR’S DUTIES.......................................................................................................121
6.3 SYSTEMS, PROCEDURES, AND PLANS........................................................................................125
6.4 REPORTS...................................................................................................................................135
7. PROCUREMENT....................................................................................................................139
7.1 COMPANY DUTIES.................................................................................................................139
7.2 CONTRACTOR DUTIES..........................................................................................................139
7.3 SYSTEMS, PROCEDURES, AND PLANS........................................................................................148
7.4 REPORTS...................................................................................................................................158
8. CONSTRUCTION, FABRICATION, AND WORK SITE OPERATIONS.......................................161
8.1 COMPANY DUTIES.................................................................................................................161
8.2 CONTRACTOR DUTIES..........................................................................................................161
8.3 FABRICATION............................................................................................................................163
8.4 SYSTEMS, PROCEDURES, AND PLANS........................................................................................164
8.5 ABANDONMENTS, DISMANTLING AND DEMOLITION................................................170
8.6 REPORTS...................................................................................................................................170
9. SYSTEMS COMPLETION.......................................................................................................173
9.1 COMPANY DUTIES.................................................................................................................173
9.2 CONTRACTOR DUTIES..........................................................................................................173
9.3. SYSTEMS, PROCEDURES, AND PLANS....................................................................................177
9.3.1. SYSTEMS COMPLETION PLAN...............................................................................................177
9.4 REPORTS...........................................................................................................................182
9.4.1 CLOSEOUT REPORT...............................................................................................................182
10. LOGISTICS.......................................................................................................................183
SECTION G....................................................................................................................................404
COMPANY-PROVIDED ITEMS...........................................................................................................416
1. GENERAL............................................................................................................................418
2. CONTRACTOR'S RESPONSIBILITIES.................................................................................419
3. QUALIFIED SUPPLIERS AND SUBCONTRACTORS...................................................................419
4. NOMINATING SUPPLIERS OF MATERIALS AND EQUIPMENT AND SUBCONTRACTORS...........419
APPENDICES...................................................................................................................................422
[Contract Number – A]
Revision 1
September 2022
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
2) Section B, Definitions
This Section defines common terms used throughout the JOB SPECIFICATION.
[Contract Number – A]
SECTION B: DEFINITIONS
Revision 1
September 2022
Table B 0 -1 lists terms and associated definitions for specific words and phrases used in the JOB
SPECIFICATION. These terms are identified by use of initial capitalization (e.g., Project, Plan,
System, Procedure, etc.).
Term Definition
[Interface] Supplier Organization responsible for producing and providing interface deliverable/activity
information to another organization (Interface Receiver).
Key Personnel Personnel as defined in accordance with the PRINCIPAL DOCUMENT and
Attachment 1 of the COORDINATION PROCEDURE
Key Positions Positions as defined in accordance with the PRINCIPAL DOCUMENT and
Attachment 1 of the COORDINATION PROCEDURE
National /Local National or Local company or registered agent qualified to supply goods or services in
Supplier/Contractor the COUNTRY OF OPERATION.
Loss Prevention The application of engineering principles to the design of oil and gas facilities for the
purpose of preventing injury, loss of life, and property damage by identifying process
and facility hazards, and minimizing the likelihood of the occurrence and/or
consequences of these hazards. This entails risk identification and management
throughout the lifecycle of the project.
National Content As defined in Attachment 1 of the COORDINATION PROCEDURE (e.g.
Stakeholder federal/provincial, territorial, municipal host government, non-government
organizations, local suppliers, local community and other parties impacted by the
Project activities)
National/Local Content An overall value created to support the COMPANY’s operations and to contribute to
the economic development at the host-country and local levels through:
Workforce Development – Recruitment and development of qualified national / local
employees;
Supplier Development – Development and use of qualified local vendors for the supply
of goods and services; and
Strategic Community Investments – Investments in health, education and infrastructure
that assist in the development of local capabilities (capacity building) and improve
the socio-economic environment of host communities.
Nationalization – Total number of host country personnel as a percentage of the total
personnel employed by CONTRACTOR in the country.
National/Local Workforce comprised of qualified National and Local employees, and citizens of the
Workforce COUNTRY OF OPERATION.
Nonconformities Non-fulfillment of a requirement
Off Sites Sites where parts of the WORK are performed and are not defined as a WORK SITE.
COMPANY personnel may or may not be present at such sites.
Procedures A specific methodology or process to accomplish a discrete activity or set of activities
Project As defined in the JOB SPECIFICATION
Project Plans CONTRACTOR's written scheme or approach to manage, organize, coordinate, and
execute the WORK. Plans include documentation of how CONTRACTOR will apply
CONTRACTOR's Systems and Procedures in performing the WORK.
Quality Issues Planning and execution areas with sufficient risk or known impact to Project and
require increased PT Quality and Management attention. Quality issues include known
as well as potential nonconformities.
Quality Management Coordinated quality related activities based on risk using the Criticality Rating process
to direct and control an organization to meet established requirements
Re-Baseline Reestablish new control schedule for remaining work scope to be completed from
current project position.
Revision Any modification to a deliverable after it has been approved
Risk Management The identification of hazards; assessment of uncertainty, likelihood, and consequence
associated with hazards; characterization of inherent risks; and prioritization of tasks to
eliminate, reduce, or control these risks. Risk management is a structured process in
the execution of the WORK.
Term Definition
Source Inspection Activities performed on behalf of the purchaser to ensure that purchased product meets
specified purchase requirements.
Source Inspector Qualified individual who performs source inspection.
Specification Deviation Waivers to specific technical requirements of the JOB SPECIFICATION that do not
meet the criteria of a CHANGE ORDER, such as minor wavers for specific pieces of
equipment, material component, or material substitutions.
Stakeholders All parties with vested interests, including interfacing parties
Subcontractor A member of CONTRACTOR GROUP providing services directly to
CONTRACTOR's.
Sub-Critical Path In a schedule it is an additional or parallel path through the network with a total
duration just longer than the Critical Path. A delay of a terminal element of the
Critical Path could raise a Sub-critical Path to the Critical Path of a recovery schedule.
Supplier/Vendor The recipient of a "direct" or "indirect" purchase order for materials and/or equipment.
In this context, a "direct" order is one issued to a Vendor/Supplier by a Contractor or
the Company Representative. An "indirect" order is one issued by a Vendor/Supplier
(recipient of a "direct" order) to another Vendor/Supplier for mill materials, fabricated
components, or subassemblies.
Systems Groups of related procedures.
Systems Completion The systematic process facilitating flawless transition from construction to continuous
operations utilizing an integrated plan. Systems Completion spans the entire life cycle
of a project, from engineering to stable operations. It is a multi-discipline, multi-team,
and multi-organization activity with multiple interfaces requiring careful management.
Turnover The act of transferring care, custody, and control of the FACILITY or parts of the
FACILITY to COMPANY.
[Contract Number – A]
Revision 1
September 2022
A. Overview
The WORKs are located in Qua Iboe Terminal (QIT)and Bonny River Terminal (BRT) in
Nigeria. The primary purpose of these facilities are to receive and export all crude oil and
Pentane Plus production from offshore production platforms. In QIT, the crude oil is
received and processed from offshore through three 24" submarine pipelines. Once received,
the crude goes through a low pressure degassing and dewatering process, and is then routed
to storage. Currently, there are nine 500kbbls (labelled 5001 through 5009) and three
670kbbls (labelled 6704 through 6706) crude storage tanks, while the condensate is routed to
the three 670kbbls of condensate storage tanks, all located within the QIT operating plant.
During upset conditions, additional separation/settling is performed in the storage tanks
before the export grade oil is subsequently transferred to the Berth Operations Platform
(BOP) through a 42" submarine pipeline. Three single point moorings (SPM's) are connected
to the BOP for final loading of the oil onto the export oil tankers. In BRT, ther are two
Pentane Plus storage tanks of floating roof type, each 300KBBL capacity and one Fixed roof
process tank of 20 KBBL capacity.
2. Climatic Conditions
The equatorial climate of the coastal regions of Nigeria is characterized by an annual weather
cycle. The weather cycle comprises a dry season, from December through February,
followed by a wet season for the remainder of the year.
During the dry season, rainfall amounts are low but the humidity remains greater than 85%
for about half of the time. At the beginning and end of the wet season thunderstorms are
frequent. During the remainder of the wet season the weather is dominated by monsoons
characterized by steady winds from the Southwest which bring persistent rain, high humidity
(100%), and somewhat lower temperatures.
The 670,000 bbls series tanks are double deck floating roof tanks
The storage tank dimensions, geometry and general data are as described beneath.
GENERAL:
TANK NUMBER: 5003
OWNER: Mobil Producing Nigeria, Utd.
DESIGN STD: API 650 Appendix G & K
TANK LOCATION: Ibeno, Nigeria
MANUFACTURER: Whessoe, UK
PRODUCT: Crude Oil
CATHODIC Yes
PROTECTION:
NAME PLATE PRESENT: No
DIMENSIONS:
DIAMETER: 260.00 ft
HEIGHT: 56.00 ft
NOMINAL CAPACITY: 500,000 bbls
GEOMETRY:
FOUNDATION: Concrete Ringwall
BOTTOM: ---
SHELL: Butt Welded
FLOATING ROOF: Single Deck w/ Annular Pontoons
PRIMARY SEAL: Mechanical Shoe seal
SECONDARY SEAL: Yes
WEATHERSHIELD: Metallic/Fabric
DATES:
YEAR BUILT: 1975
LAST COATED: Data not available
LAST INSPECTION: Data not available
ACCESS:
FLOATING ROOF: Spiral Stairway w/ Rolling Ladder &
Vertical Ladder
COATINGS:
BOTTOM: Yes
SHELL: External - White paint
FLOATING ROOF: External - White paint
GENERAL:
TANK NUMBER: 6705
OWNER: Mobil Producing Nigeria, Utd.
DESIGN STD: API 650
TANK LOCATION: Ibeno, Nigeria
MANUFACTURER: Chicago Bridge & Iron under Daewoo
PRODUCT: Crude Oil/Condensate
CATHODIC Yes
PROTECTION:
NAME PLATE PRESENT: Yes
DIMENSIONS:
DIAMETER: 300.00 ft
HEIGHT: 56.00 ft
GENERAL:
TANK NUMBER: 673
OWNER: Mobil Producing Nigeria, Utd.
DESIGN STD: Data Not Available
TANK LOCATION: Ibeno, Nigeria
MANUFACTURER: Koyo Iron Works, Japan
PRODUCT: Crude Oil/Produced Water
CATHODIC Yes
PROTECTION:
NAME PLATE PRESENT: Yes
DIMENSIONS:
DIAMETER: 100.00 ft
HEIGHT: 48.00 ft
NOMINAL CAPACITY: 67,000 bbls
GEOMETRY:
FOUNDATION: Concrete Ringwall
BOTTOM: Asymmetric cone-down
SHELL: Butt Welded
DATES:
YEAR BUILT: 1971
LAST COATED: Unknown
LAST INSPECTION: 2000 - External, Unknown - Internal
ACCESS:
FIXED ROOF: Spiral Stairway & Vertical Ladder
COATINGS:
BOTTOM: Tank Lining Epoxy (assumed Valspar)
SHELL & FIXED ROOF: 3-coat system, white (assumed Valspar)
GENERAL:
TANK NUMBER: 406
OWNER: Mobil Producing Nigeria, Utd.
DESIGN STD: API 650
TANK LOCATION: BRT, Nigeria
MANUFACTURER: JGC, Japan
PRODUCT: Pentane Plus
CATHODIC Data not available
PROTECTION:
NAME PLATE PRESENT: Data not available
DIMENSIONS:
DIAMETER: 60 ft
HEIGHT: 42 ft
NOMINAL CAPACITY: 20,000 bbls
GEOMETRY:
FOUNDATION: Data not available
BOTTOM: Data not available
SHELL: Butt Welded
DATES:
YEAR BUILT: 2000
LAST COATED: 2000
LAST INSPECTION: Data not available
ACCESS:
FIXED ROOF: Spiral Stairway & Vertical Ladder
COATINGS:
BOTTOM: Unknown
SHELL & FIXED ROOF: Unknown
Oil Recovery
API Inspection
EPC CONTRACTOR (Tank Cleaning, Waste
Disposal, Oil Recovery, API 653 Inspection, Design
Detailed Engineering
Engineering, Material Procurement, Construction
Management, Fabrication and Construction, NDT &
Material Procurement
Hydro testing / Calibration/ Commissioning)
3 Tank Revamp
Construction Management,
Fabrication & Construction
NDT
Hydrotesting /
Calibration/Commissioning
[Contract Number – A]
Revision 1
September 2022
Page 16 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
Introduction
The Scope of WORK describes Project specific, obligations, and / or requirements with
respect to the WORK. It should be noted that, as defined in the PRINCIPAL
DOCUMENT, the Scope of WORK is part of the JOB SPECIFICATION. As such, it is not
a standalone document and must be read in conjunction with the PRINCIPAL
DOCUMENT and the other Sections of the JOB SPECIFICATION (e.g. the Section F -
COORDINATION PROCEDURE and Section G - Design Basis Documents etc.) to fully
understand the, obligations, and / or the requirements of the CONTRACT. Therefore,
references are made throughout the Scope of WORK to specific Articles in the PRINCIPAL
DOCUMENT and / or Sections of the JOB SPECIFICATION.
The Scope of WORK also defines the boundaries of the WORK to be performed under the
CONTRACT and describes responsibilities at specific interfaces with COMPANY and
COMPANY's other contractors. In this regard, the Scope of WORK includes the following
Appendix DB - External Interface Responsibility Matrix.
It should be noted that there are two (2) sets of definitions. The first one –
“DEFINITIONS” in upper case is located in the PRINCIPAL DOCUMENT and the second
one – “Definitions” in title case is in Section B – Definitions which must be read in
conjunction with the rest of the JOB SPECIFICATION to give a complete understanding of
what the CONTRACTOR is required to do / provide.
Acronyms used throughout the JOB SPECIFICATION are contained in Appendix DA
hereto.
This CONTRACT work scope is captured in two main categories - Tank Cleaning & Tank
Revamp.
Page 17 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
Page 18 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
Job Specification
Revision 1
September 2022
Page 19 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
A. Introduction
This section D1 specifies all the requirements regarding safety and work process for
executing the Tank De-sludging and cleaning job at Qua Iboe Terminal of COMPANY.
Page 20 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
B. References
CONTRACTOR MUST execute ALL the work in line with associated MPN Procedures and
API References (unless otherwise specified herein, use the latest edition), including but not
limited to the following:
American Petroleum Institute (API) Standard 2015; “Requirements for Safe
Entry and Cleaning of Petroleum Storage Tanks"
American Petroleum Institute (API) Recommended Practice 2016;
“Guidelines and Procedures for Entering and Cleaning Petroleum Storage
Tanks"
API Bulletin 2015 & 2016 “Recommended Practice for Cleaning Petroleum
Storage Tanks”
Upstream Nigeria Safety Manual
MPN Tank and Storage Cleaning Maintenance Procedure
MPN Work Management System
MPN Atmospheric Gas Testing Procedure
MPN Job Safety Analysis Procedure
MPN Control of Hazardous Energy Procedure (LOTO – Lock-out/Tag-out)
MPN Hot Work Procedure
MPN Temporary Bypass of Safety System Procedure
MPN Lifting and Cargo Management Guide
Page 21 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
CONTRACTOR will weigh (COMPANY to witness) the debris and solids after loading
into skips and this will be the basis of compensation for the CONTRACTOR
Note: Cleaning Height for Crude/Condensate includes the seals; Cleaning area for the
Settling Tanks includes the sloped roof and floor areas
Page 22 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
D. Job Process
It is the COMPANY’s desire to have its tanks cleaned of hydrocarbons, sludge and made Gas
Free by using an integrated automated process that will allow for continuous operation until a
given tank is clean.
Please note that this SOW cannot be altered without permission from MPN
SSTR Project Representative (TBD) and QIT/BRT Operations Representative
(TBD) once approved except in writing. This SOW must be at the site at all
times and must be reviewed with each person onsite. MPN TANK AND
STORAGE CLEANING MAINTENANCE PROCEDURE MUST BE
FOLLOWED AT ALL TIMES. ALL WORK MUST BE CARRIED OUT
WITH REFERENCE TO ALL RELEVANT API/OTHER APPLICABLE
STANDARDS (INCLUDING REVISIONS/UPDATES) PUBLISHED TILL 31 ST
DECEMBER 2015.
CLEANING SPECIFICATIONS:
SERVICE: to be indicated
Page 23 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
The intent is to clean tank and provide a gas free certificate for an API 653 Internal
inspection/Hot Work
Recovery of residual oil shall be done using the following equipment and
procedure – CONTRACTOR TO INDICATE IN Technical Tender Form
Removal of sludge/wax and cleaning of tank shall be done using the following
equipment and procedure – CONTRACTOR TO INDICATE IN Technical
Tender Form
De-oiling and cleaning/gas freeing of Pontoons shall be done using the
following equipment and procedure – CONTRACTOR TO INDICATE IN
Technical Tender Form
Recovery of Oil from the sludge shall be done using the following equipment
and procedure – CONTRACTOR TO INDICATE IN Technical Tender
Form
The oil recovery process will separate sludge into oil, water and solid phases.
All recovered oil shall be pump to Emulsion Pit or as directed by COMPANY
The solids will have a maximum moisture content of wt% CONTRACTOR
TO INDICATE IN Technical Tender Form and placed into skips
Skips shall be transported by certified road trucks after weighing by
CONTRACTOR (COMPANY to witness) to a DPR approved agency for
waste disposal. COMPANY shall issue Duty of Care documents rendering the
solids loaded truck the sole responsibility of the CONTRACTOR
(CONTRACTOR to provide all equipment, cranes, skips, load cells,
trucks for loading).
Final water washing of tank internal surface. Wash water to be transported to
designated tank by QIT/BRT operations. Contractor Supervisor to enter the
tank to perform the API 2016 checklist and finds the inside of the tank in safe
condition, CONTRACTOR will enter the tank with a minimum of two tank
cleaners and remove the remaining water/oil mixture by washing material to
per CONTRACTOR residual cleaning procedure. Contractor will continue in
this manner until tank is cleaned. Tank will be continuously monitored while
personnel are inside of tank.
Page 24 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
Page 25 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
vii) Review plans for transferring residual product, (e.g. connection points
on tank, valve for water draw-off, vacuum truck placement, product
receipt point)
Page 26 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
Page 27 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
Contractor shall liaise with the responsible MPN personnel to know the type
of gas detector (s) recommended for sniffing storage tanks
Contractor shall ensure that the gas detectors are regularly calibrated (as per
manufacturer’s specifications). MPN SHE coordinator shall verify that
instruments have been calibrated according to manufacturer’s specifications,
before Contractor uses such equipment for sniffing.
Contractor shall provide qualified personnel trained to use these MPN
approved gas detectors.
Contractor shall ensure that storage tanks environment comply with the
requirements of Table 3-4 below taken from Section 3.4.1 of the UN Work
Management System Manaul (pg 3-36) for allowing personnel entry.
Contractor shall ensure that all equipment and lighting devices, used within
the work environment that has not been certified gas free (either inside the
storage tanks or within the immediate vicinity), shall be explosion-proof.
Contractor shall provide all respiratory equipment/breathing apparatus
appropriate to the instructions/requirements of the MSDS (Materials & Safety
Data Sheets) and as approved by MPN for entry into storage tanks.
Contractor shall ensure that a work specific Job Safety Analysis (JSA) is
conducted, documented and communicated to all persons prior to
Page 28 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
ATTENDANT
The attendant must know the hazards, including the signs or symptoms and
consequences of exposure to materials normally contained in entered storages.
-Is aware of the possible behavioral effects of exposure to the hazards by
entrants
-Maintains count of entrants & monitors activities of entrants.
-Remains outside the space and communicates with entrants.
-Continuously monitors conditions inside the storage tanks.
-Activate emergency rescue plan as needed and have no other duties while the
entrants are in the storage tanks.
-During any break, end of shift, completion of the job, comfort break, or any
time the space is not occupied, the attendant will ensure that the point of
entry is closed off and ‘no entry’ signs are posted. All equipment used in the
entry must be left in a safe condition, removed or stowed away properly.
ENTRANTS
The entrants into the storage tanks must know the hazards, including signs or
symptoms and consequences of exposure to materials normally contained in
Page 29 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
RESCUER
-The rescuer must know the hazards, including signs or symptoms and
consequences of exposure to materials normally contained in entered
storages.
-Trained to use properly the personnel protective equipment, procedures and
tools necessary for making rescues from Confined Spaces.
-Practice rescue drill at least once every 12 months.
-Trained in First Aid and CPR with at least one member holding a current
certification in both.
-If a third party provides rescue services, all previously mentioned
requirements should be checked by Contractor’s responsible personnel to
ensure compliance by the third party.
Contractor shall note that the Confined Space Entry Permit is valid for a
maximum time of 12 hours. All permits will expire at the end of each 12-hour
shift. If the job is not completed, a new permit must be issued before work
continues.
If work is suspended for one hour, the permit must be revalidated by the
Contractor’s responsible personnel (after all checklist conditions have
been satisfied – see Figure 2). If work is suspended for more than one
hour the permit becomes invalid and a new permit must be issued.
Contractor shall ensure that all personnel involved in this job take the
following actions, in the event of an emergency:
Stop work, all entrants must vacate the storage tanks.
Make the work site safe.
Isolate all sources of power and heat.
Stop all engines and secure static equipment.
Walk briskly to muster area.
Follow facility / emergency procedures.
Contractor shall ensure that the Permit Preparer performs a check to confirm
that all locks and tags, blinds and skillets are removed, leak test performed and
work site is left in a safe manner before the permit is closed out.
Contractor shall adhere strictly to the following conditions that warrant or are
associated with the monitoring of gas in and around the storage tanks:
A total hydrocarbon (THC) and gas monitoring is required for entries into Confined
Spaces that contain or have contained hydrocarbons.
Page 30 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
A benzene monitoring test is required for all entries into Confined Spaces that have
been exposed to a hydrocarbon stream with benzene > 0.1% by weight unless
respiratory protection is utilized.
Additional gas level monitoring beyond the initial testing is required and must be
documented on the permit.
Mechanical ventilation must be shut off at least 30 minutes prior to gas testing in
confined spaces. Continuous monitoring of the space must be performed using
monitoring equipment set to alarm the presence of LEL, H2S, and low and high
oxygen levels.
The table below serves as a guide to describe the minimum conditions under which
entry may be allowed or prohibited. MPN may review these requirements
periodically and specify actual requirements before or during the course of the
project. Table 3-4 is from Section 3.4.1 of the UN Work Management System Manaul
(pg 3-36) and reference should be made to Section 3.4 of this document for further
detail of the requirements for obtaining a ConfinedSpace Entry Permit.
Contractor shall barricade and label the work at all times: “Danger- Entry Permit
Required – Do Not Enter”
Contractor shall ensure that all confined spaces are sufficiently cleaned of all
materials, solids, liquids or gases which may present a hazard to personnel before
entry permit is approved
Page 31 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
Contractor shall ensure that all personnel who issue or use the permit must be trained
in the application of the work permit procedures, including but not to: lock-out/tag-
out requirements, by-pass of safety systems, confined space entry, etc.
Contractor shall, at the end of each day’s work during the cleaning operation or
whenever work is suspended, cover all manways and clean out doors with
wooden blind.
CONTRACTOR shall provide all necessary permits and operating licenses for
Delegated Supervisory Decontamination units and adhere strictly to all relevant
environmental, health and safety procedures and regulations pertaining to operation
of the plant.
CONTRACTOR shall submit proper inventories of all solid waste and debris
recovered, transported and treated with sign-off from COMPANY.
CONTRACTOR shall submit Completion/Disposal certificates to COMPANY.
CONTRACTOR shall insure that COMPANY has access to the Delegated
Supervisory Decontamination units during the disposal of COMPANY waste and can
audit associated records.
Page 32 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
Figure 1 serves as a guide to the minimum requirements expected for this type. MPN may
review these requirements prior to, or during the course of the project.
Page 33 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
Page 34 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
NOTE: PIC stands for the most senior Contractor personnel at the location
Anything mentioned in COMPANY’S SCOPE OF WORK and not shown on
CONTRACTOR’S METHOD STATEMENT or shown on the METHOD STATEMENT and
not mentioned in the SCOPE OF WORK shall be of like effect as if shown or mentioned in
both. In case of any conflict or inconsistency among any of the incorporated documents,
CONTRACTOR shall bring this to the attention of COMPANY, which shall resolve the
conflict in writing. In most cases, the more stringent of the two cases shall suffice.
CONTRACTOR should note that COMPANY shall exercise zero tolerance to issues
pertaining to non-compliance with procedures (particularly Confined Space Entry
procedures/guidelines as earlier outlined). COMPANY expects strict adherence to these
Page 35 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
Page 36 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
7 COMPANY’S Responsibilities:
COMPANY shall provide or assist CONTRACTOR in providing any existing technical
data and equipment location diagram as may be necessary to execute the project.
COMPANY shall ensure that the tank is ready for the CONTRACTOR by landing
floating roof on legs for crude/condensate storage tanks (draining to minimum level) and
draining settling tanks to a minimum level.
COMPANY shall provide crude oil as cutting stock if required by CONTRACTOR (If
light gravity stock is required, CONTRACTOR to reimburse company for the cost).
Page 37 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
Upon satisfactorily cleaning of the tank, CONTRACTOR shall complete each activity
shown in Appendix A & B, respectively, to obtain a Gas Free Certified clean tank (Class I
entry requirements)., A Project Completion Certificate shall be signed by the COMPANY
Project Manager or his delegated authority upon receipt of the signed off form by
QIT/BRT operations. If not cleaned to the Class I requirement, CONTRACTOR shall be
required to repeat whatever tasks are needed to meet the Class I requirement at his
expense. Approved Project Completion Certificate will be required with submitted
invoice (except in the case where a milestone completion certificate is approved, if
applicable).
Page 38 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
Page 39 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
A Compensation
The entire tank de-sludging and cleaning scope as described in sections 1 thru 9 of this document will
be compensated through the following unit rate items based on relevance/applicability. (e.g. items A.3
and A.4 are not applicable for De-sludging and cleaning of Fixed Roof settling Tank). All contractor
costs including but not limited to Project management, overhead, manpower, materials, consumables,
fuel, power, water, SHES compliance, community development, lodging, boarding, emergency
response, profit, etc for Tank de-sludging and cleaning of tank shall be included in the relevant unit
rate items below.
A.1 Mobilization
CONTRACTOR shall mobilize to site all personnel workforce, equipment, materials and
consumables necessary to progress the work without interruption.
COMPANY and CONTRACTOR shall jointly carry out Pre-Mobilization inspection on all
CONTRACTOR’s equipment; materials and consumables required for the work and certify
them satisfactory prior to mobilization to site.
The mobilization scope includes providing the following Job Specific Procedures and Job
Safety Analysis (JSA) but not limited to:
Mobilization will be deemed to be completed when all listed procedures are reviewed and
approved by COMPANY.
CONTRACTOR shall remove the residual oil after COMPANY operations has handed over
the tank and transfer the oil to the Emulsion sump or any other location within QIT/BRT as
per COMPANY direction.
CONTRACTOR shall drain oil from pontoons of single deck or double deck floating roof, if
found containing oil, and wash/clean with detergent if necessary and make the pontoon gas
free. (Unit rate quoted shall be for each pontoon).
Page 40 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
CONTRACTOR shall drain oil from top deck of single deck or double deck floating roof, if
found containing oil, and wash/clean with detergent if necessary. (Unit rate quoted shall be
for entire roof deck).
CONTRACTOR shall recover oil from sludge/solids/wax content of the tank using a non-
entry integrated system that receives sludge from the tank and produces Oil, Water and
Solids/Debris. The CONTRACTOR would provide all equipment, temporary storage,
vacuum trucks (if required), and metering to recover maximum oil from the sludge.
Recovered oil shall be transferred to the QIT/BRT emulsion sump by CONTRACTOR or as
directed by MPN.
CONTRACTOR shall dispose all solid and debris generated during entire tank cleaning
operation. The solids and debris removed from the tank shall be weighed by the
CONTRACTOR and witnessed by COMPANY and a document of Duty of Care issued for
onward transportation by roadworthy certified truck to DPR approved Waste disposal
agency/site . The crane, forklifts, load cells and any other equipment for weighing/handling
shall be provided by CONTRACTOR. Duty of Care documents for transporting the solid
waste and debris renders the loaded waste truck the sole responsibility of the
CONTRACTOR.
CONTRACTOR shall wash and clean the tank internal surface with water/detergent if
necessary and wipe clean with rags/absorbents. Wash water to be transported to designated
tank with in QIT/BRT by COMPANY operations. Contractor Supervisor to enter the tank to
performed the API 2016 checklist and finds the inside of the tank in safe condition,
CONTRACTOR will enter the tank with a minimum of two tank cleaners and remove the
remaining water/oil mixture by washing material to per CONTRACTOR residual cleaning
procedure. Contractor will continue in this manner until tank is cleaned. Tank will be
continuously monitored while personnel are inside of tank.
Page 41 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
Page 42 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
Upon completion of the work, all tools and equipment will be properly cleaned and
decontaminated to remove residual process products.
Mobilize from one tank site to another tank site within the QIT/BRT and perform all activities
specified in A.1 (Rate for A.1 will not be applicable when A.9 is applicable)
Page 43 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
Note: Items excluded for cleaning for Gas Free Certification are Gauging Platform and Wind Girder.
Date Assigned Supervisor Gas Tests Results (O2, H2S, LEL, THC, CO, BZ)
Page 44 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
Date Assigned Supervisor Gas Tests Results (O2, H2S, LEL, THC, CO, BZ)
Page 45 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
Job Specification
Revision 1
September 2022
Page 46 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
A. Scope of Work:
Until tank cleaning, API 653 inspection and joint inspection between MPN and
CONTRACTOR is concluded, the specific scope may not be fully known. The Work Order
for one tank project will be issued with the base estimate by COMPANY. CONTRACTOR
will carry out tank cleaning, API 653 Inspection on the tank and other preparatory works.
Subsequent to the Inspection Report, the Work Order will be supplemented by other repair
items specified in the Inspection Report and accepted by COMPANY. However, the detailed
general scope of work activities that are expected for repair of any tank (Floating Roof Tanks
and Cone Roof Tanks) are as follows:
i. Execute repair and replacement work in compliance with API 650, 653 and the MPN
Standard Specifications (Global Practices). In case of conflicts between API and
MPN Standard specifications, MPN standard specifications (Global Practices) shall
take precedence. All other applicable references are listed in Table 1.
ii. Replacement of corroded sections of floating roof and the pontoons (pontoon plates
top/bottom, inner/outer rims, bulkheads, manholes, roof dam, roof vents and roof
drains etc.). The replacement is based on the notable plate defects, excessive metal
loss, and patches.
iii. Replace/repair tank shell plates/bottom plates
iv. Replace primary and secondary seals with new
v. Replace old fire foam ring main and foam nozzles and install new fixed foam system
vi. Repair wind girder and supports
vii. Repair shell stiffeners and supports
viii. Repair emergency escape ladder and rolling ladder
ix. Upgrade roof drainage system (replace existing drain lines with new coflexip hoses)
x. Upgrade tank level gauging system with Enraf Gauging system
xi. Maintenance of external coating, internal lining, and tank base seals
Other findings noted in the incident investigations and the out-of-service inspection reports
will also be addressed. Replacement in-kind of worn or defective material and components is
the preferred approach. Steel plates and structural members will be replaced in line with API
653 and API 650 specifications.
i. Removal and replacement of existing columns, rafters and girders with new ones.
ii. Design, fabrication and installation of a new cone roof; design shall include
replacement of all the existing appurtenances including personnel access provisions
with handrails.
iii. Replace/repair shell plates/bottom plates
iv. Remove existing inlet diffuser, and install newly designed and fabricated spreader
bar.
Page 47 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
Replacement in-kind of worn or defective material and components is the preferred approach.
Page 48 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
Page 49 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
A. DETAILED WORKSCOPE:
The entire tank revamp scope as described below shall be compensated through the following unit rate
items based on relevance/applicability.
1. Preparatory Works
1.1
Mobilization of all facilities, equipment, machinery, vehicles and personnel for executing work in
QIT/BRT tank farm for one tank, including Site preparation for equipment access into the tank bund
area while protecting any MPN pipeline/equipment as directed by MPN. CONTRACTOR shall
supply CAD drawings of access ramps or crossover etc. that may be required for equipment access to
COMPANY for approval prior to installation. Also included are careful dismantling of all light poles
with fixtures, cable & cable trays within bund area and collapsing the cable and burying it
temporarily with appropriate protection to facilitate crew/equipment movement (if required).
1.2 Mobilization from One Tank Site to Another within same terminal:
Mobilize from one tank site to another tank site within the QIT/BRT and perform all activities
specified in 1.1 (Rate for 1.1 will not be applicable when 1.2 is applicable)
1.3 Demobilization:
Demobilization of all contractor equipment, machinery, vehicles, kiosks, caravans, scraps etc. and
restoring bund area grade level and handing over clear possession of company provided laydown area
(if any). Restore the removed cable trays, cables, light poles with fixtures etc. to original state and
COMPANY specification after the project work is over Barrier gate, access ramps/cross overs or
grading material in dyke area shall be removed and bund wall/area restored by CONTRACTOR when
project work inside bund area is completed.
Page 50 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
c. 200' dia double deck Floating Roof with 56 pontoons (unit rate shall be for entire roof
covering all pontoons)-BRT
Provide hardwood cribbing supports and/or structural steel supports below the roof. Allow minimum
of 25% of existing roof support legs as per support plan to be approved by COMPANY. Rate to
include removal/shifting as per job requirement and final removal at the end of construction.
a. For Tanks 260 ft. dia. single/double deck roof-QIT
b. For Tanks 300 ft. dia. double deck roof-QIT
c. For tanks 200 ft. dia double deck roof-BRT
Carry out API 653 inspection of following tanks as per scope detailed in Appendix C to be conducted
by an authorized inspection agency (having certified API 653 inspector) as defined in API 653 and
approved by COMPANY including making all arrangements, providing necessary equipment, crew,
tools, illumination, access for working in confined space or working at height and submitting report
with drawings and photographs.
a. Tanks 100 ft. dia. cone roof tank-QIT
b. Tanks 260 ft. dia. single deck roof-QIT
c. Tanks 260 ft. dia. double deck roof-QIT
d. Tanks 300 ft. dia. double deck roof-QIT
e. Tanks 200 ft. dia. Double deck roof-BRT
f. Tank 60 ft dia cone roof tank-BRT
Page 51 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
2 ROOF WORKS
2.2 Demolition of Existing Single Deck Floating Roof and Installation of New Double
Deck Roof
Remove complete single deck floating roof of 260' dia tank and design, supply,
fabricate, install a new double deck floating roof including providing necessary
temporary supports, doorsheets as required, if doorsheets are removed, the same will
be re-installed at no extra cost. Any damage made to tank shell or bottom has to be
made good at no extra cost to COMPANY. For detailed scope refer Appendix E.
2.3.1 Removal of Roof Plates/Rafters and other structural members in Cone and
Floating Roof Tanks as directed by COMPANY
a. from 3/16" up to and including 1/4" plate for roof, lower deck, upper deck, pontoon
rims, pontoon partition plates, foam dam, sub pontoons
b. from 1/4" up to and including 3/8" plate for roof, lower deck, upper deck, pontoon
rims, pontoon partition plates, foam dam, sub pontoons
c. Rafter beams with clips, angle, channel and any other structural sections associated
with roof
2.3.2 Removal of Roof Penetrations (when entire roof is not being demolished)
including all reinforcing pad plates etc.
a. 3" to 6" roof penetrations
b. 20" to 30" roof penetrations
2.4.1 Supply, Fabricate and Install New Roof Plates/Structural Sections Per API
650/653.
a. from 5 mm up to and including 6 mm plate for roof, lower deck, upper deck, pontoon
rims, pontoon partition plates, foam dam, sub pontoons
b. above 6 mm up to and including 10 mm plate for roof, lower deck, upper deck,
pontoon rims, pontoon partition plates, foam dam, sub pontoons
c. Rafter beams with clips, angle, channel and any other structural sections associated
with roof
Page 52 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
2.4.2.1 Supply, Fabricate and Install New Roof Manways, Hatches, and
Nozzles per API 650 Complete with Flanges, Gaskets, Hinges, Bolts,
Reinforcement Plate, Cover Plate etc.
a. 6" Roof Nozzles
b. 8" Roof Nozzles
c. 10" Roof Nozzles
d. 12" Roof Nozzles
e. 20" Pontoon Manways
f. 24 " Roof manways
g. 30 " Roof manways
Page 53 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
b. Supply, fabricate and install new collection sump and connect to existing roof drain
centre sump along with below deck piping (4" dia.) up to 15 m long including pipe
braces/supports etc.
Page 54 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
Page 55 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
3 SHELL WORKS
3.1 Remove and Replace Shell Plates, Insert Plates, Door Sheets or Wind Girder
3.1.1 Remove and Replace Shell Plates
Remove existing and supply, fabricate and install new shell plates, insert plate, door sheet in
identified shell courses at any height per API 653 and COMPANY standards. Plates shall conform to
ASTM A36 or original spec. Door sheet for construction access shall have necessary supports to
prevent shell deformation.
a. Up to and including 3/8" thick plates
b. Above 3/8" and up to and including 7/8" thick plates
c. Greater than 7/8" thick plates
Page 56 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
blast SSPC SP10, primer, intermediate coat and top coat with paints of approved vendors of
ExxonMobil. DFT of the coats shall be as per manufacturer's recommendation. Refer Appendix G.
a. Floating roof tanks 260' in diameter-QIT
b. Floating roof tanks 300' in diameter-QIT
c. Floating roof tank 200' in diameter -BRT
Page 57 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
4 BOTTOM WORKS
Page 58 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
5 PIPE WORKS
Remove of large bore carbon steel pipework over 2" diameter (excluding steam coils) where hot work
is permissible and stack the removed pipes at a designated place within company terminal as directed.
a. Remove 3" piping
b. Remove 4" piping
c. Remove 6" piping
d. Remove 8" piping
e. Remove 30" piping
f. Remove 10”NPS to 24” NPS piping
Page 59 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
a. 6" SS piping
b. 8" SS piping
c. 6" - 90 deg. SS elbows
Page 60 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
d. 6" - SS Tee
Page 61 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
Page 62 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
7 ANCILLARY WORK
Page 63 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
a. Floating roof Tanks 200’, 260' or 300' in diameter and upto 58' in height
b. Settling Tanks 100' in diameter x 48' in height
overall Jkt-BLK sunlight PVC low acid gas jkt,An AL interloked armor with
UL1569, ICEA &CSA, 600V, 90 deg C)
e. OKONITE OR NORTEK MAKE 3C x 12 AWG Class B stranded, bare, annealed CU
ASTM B-3 B-8, XLP, BLK sunlight resistant PVC (inner & outer JKT) to ICEA, AL
interlocked armor UL1569 ICEA& CSA, 600V, 90 deg C.
f. NORTEK OR OKONITE MAKE 14C X 14AWG Type 2 (Class B, stranded, bare,
annealed copper, XLP insulation Type UL-XHHW2 & CSA RW90, insulated
conductors cabled with single UL grnd uninsulated grnd wire and fillers,Inner &
overall Jkt-BLK sunlight PVC low acid gas jkt,An AL interloked armor with
UL1569, ICEA &CSA, 600V, 90 deg C)
g. 2P x 18AWG, Type 1 (MC-HL BC PVC/NYL 600V BLK/WHT/#S FOIL SHLD
ARMOR-X PVC JKT IEEE 1202)
h. 16AWG-2P MC-HL BC PVC/NYL 600V ARMOR – X BLK/WHT/# EA PR
IND+OA SHD PVC JKT IEEE1202
i. 10AWG – 11C MC – HL BC XLP 600V 90C CC: E2 1X#10 GRDS ARMOR – X –
40 PVC JKT 1EEE1202
j. 18AWG-25P OKONITE BC 600V 30 XLP INS W/GRD PVC JKT AIA BLK PVC
JKT UL CSA
k. 10C X 10AWG MC – HL BC XLP 600V 90C CC: E2 1X#10 GRDS ARMOR – X –
40 PVC JKT IEEE1202
Supply and install Fiber Optic cable, single mode, 8 strands minimum, including patch panels.
8 WELD REPAIR:
Remove defective butt, fillet or lap weld, prepare and re-weld and carry out appropriate NDT on the
new weld. (applicable for max plate thickness of 10 mm and 5 mm fillet weld) (rate shall be for unit
length in meter).
Page 65 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
9 TESTING:
9.1 Hydrostatic Test:
Hydrostatic testing of tanks as per API 650 including all necessary
connections, equipment/pump set, labour, corrosion inhibitor, access,
disconnection, removal at the end of testing complete.
Page 66 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
10 TANKS RECALIBRATION
Page 67 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
CONTRACTOR shall carry out detailed engineering for the works to be executed and shall manage
design engineering, procurement, construction and completions documentation in accordance with the
requirements defined in the JOB SPECIFICATION Contract Coordination Procedure Section F
CONTRACTOR shall produce a “List of Deliverables”, as required and identified in various sections
of the JOB SPECIFICATION, which shall be submitted to COMPANY for review and acceptance.
The “List of Deliverables” shall include a schedule of delivery for the documentation which shall be
linked to Work Scope delivery Milestones. Submission dates of documents for COMPANY review,
as recorded in the “List of Deliverables“, shall be tracked and progress reported within Contractor’s
monthly reports.
12 Tank Jacking Up
Install hydraulic synchronous jacking system including design and construct necessary foundation,
necessary steel work to jack up the tank shell up to a height of 3.2m from top of tank foundation and
maintaining it in jacked up condition till the revamp work is completed by CONTRACTOR. Unit rate
quoted shall be lumpsum all inclusive cost for each type of tank.
14 Appendices
Appendix A Scaffolding
Page 68 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
Page 69 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
Revision 1
September 2022
Page 70 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
A. Purpose
The information in this Section E defines timing and scheduling requirements relevant to the
performance of the WORK. The Company Plan is an integrated execution plan that reflects not
only CONTRACTOR's WORK but also the activities of COMPANY’s other contractors. It
defines the overall timing and scheduling of activities and site access windows that are available
to the various Contractors working on the Project. It also contains key activities where interfaces
among the COMPANY's various contractors are critical. Cooperation, interface management,
and timely communication among the various Contractors on the project will be critical to the
success of the overall Project.
B.Definitions
Throughout this document, words and expressions established as defined terms in the Principal
Document - Article 1 shall apply. Other words, expressions, and abbreviations used in this
section are defined below.
Company Plan is an integrated execution plan prepared by COMPANY that reflects not only
CONTRACTOR's WORK but also the activities of COMPANY’s other contractors.
Milestone Completion for each Milestone shall be deemed to occur on the date COMPANY
issues the appropriate Milestone Completion Certificate.
Scheduled Milestone Completion Date(s) are the date(s) by which CONTRACTOR has agreed
to achieve Milestone Completion for each Schedule Milestone.
Schedule Control: is an activity which continuously predicts final schedule outcomes based on
project experience to date (forecast) and applying corrective actions where necessary to help
control the forecast within the approved schedule.
Cost Control: is an activity which continuously predicts final cost outcomes based on project
experience to date (forecast) and applying corrective actions where necessary to help control the
forecast within the approved budget.
Page 71 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
C. Company Plan
The Company Plan specifies the overall schedule for the Project. The Company Plan is an integrated
execution plan that reflects not only CONTRACTOR's WORK but also the activities of COMPANY
and other COMPANY’s contractors. The Company Plan is included as Appendix 1.
CONTRACTOR’s planning and scheduling of the WORK shall be based on, and consistent with, the
Company Plan.
The Company Plan contains an execution sequence that depicts the overall schedule and Appendix 2
describes key Schedule Milestones to achieve the overall project objectives and for those activities
where interfaces among the various COMPANY contractors are critical. These key Schedule
Milestones, and the associated interfaces, are particularly important for proper planning and execution
of activities where several contractor activities are dependent on each other or may be occurring
simultaneously.
D. Schedule Milestones
For schedule control purposes, the completion of certain parts of the WORK is referred to as
Schedule Milestones and have been described in Appendix 2. The Schedule Milestones are key
events that form the basis of planning and scheduling the project and reflect completion of significant
parts of the WORK. Any slippage of these Schedule Milestones may impact the activities of other
contractors working on the Project and the overall Project completion date.
The Coordination Procedure sets forth detailed requirements for the preparation, management, and
control of the Contract Control Schedule. The Contract Control Schedule shall include Contractor's
Plan to complete each Schedule Milestone on or before the Scheduled Milestone Completion Dates
stipulated in Appendix 2. Completion of each Milestone includes, but is not limited to, submittal of
all required documentation to COMPANY, completion of repairs, inspections, and non-destructive
examinations to COMPANY's satisfaction. Milestones shall only be considered complete when all
portions of the WORK included in the appropriate Milestone description and the Contract Control
Schedule, including all prior WORK activities (defined in the Contract Control Schedule), are
complete to COMPANY's satisfaction as evidenced by a Milestone Completion Certificate.
No adjustments to Scheduled Milestone Completion Dates or the SCHEDULED COMPLETION
DATE may be made except by the use of CHANGE ORDERS as described in Article 7 of the
Principal Document.
E. Contract Control Schedule
The Contract Control Schedule sets forth CONTRACTOR's definitive plans for performing the
WORK, including the Schedule Milestones, and defines the order, estimated duration and dates in
which key parts of the WORK are planned to be completed including histograms of direct manpower
(by craft), subcontract, indirect, and total manpower for each major construction related work
breakdown structure area. The Contract Control Schedule is included as Appendix 3.
F. Schedule Control
CONTRACTOR-PMT shall include a dedicated full time planning engineer with experience in
Tank cleaning and revamp to steward development of work packs and detailed execution
schedule (level IV - resource loaded) for all aspects of the WORK.
The planning engineer shall maintain, monitor, control and report progress throughout the
duration of the project.
Page 72 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
CONTRACTOR shall provide COMPANY access, without restriction, to all information inputted
to and generated under CONTRACTOR's Schedule Control Systems, including, but not limited to
the following;
» Planning and scheduling
» Progress measurement
» Resource loading and man-hours
» Benchmark data and productivity data etc.
This access shall be for data at any level, including interface data and data prepared by
CONTRACTOR.
CONTRACTOR shall develop schedule in a hierarchical manner, and shall maintain the
ability to roll up individual activity assessments into an overall schedule assessment for
the WORK.
CONTRACTOR's schedule shall reflect the entire WORK and provide sufficient details
in all areas of project execution
» Development of plans and procedures
» Final documentation, as-builting
» Project close-out etc.
Schedule shall incorporate the SCHEDULE MILESTONES.
CONTRACTOR shall include plan versus actual histograms and forecast histograms of direct
resources (by discipline/craft) and total resources for the WORK. These histograms shall include
the following:
» Man-power adjustments and productivity
» Productivity forecasts through completion
» Work-hours per percent complete
CONTRACTOR shall provide time-resource (TR) sheets during execution phase to include the
following:
i. A description of each activity and descriptions of the resources including man-hours, materials
and equipment to be utilized in completing each activity and the duration of time for which the
resources will be employed.
ii. Construction work-hours broken down by discipline/craft.
iii. Material and equipment descriptions including type and quantity to be used for the execution of
the WORK.
CONTRACTOR shall provide COMPANY with CONTRACTOR's schedule both in print and
electronic copy (PDF and native Primavera backup file PRX or .XER file and/or Microsoft
Project back up file MPP), which shall include all information necessary to duplicate
CONTRACTOR's schedule, progress measurement, and resource requirements.
As requested by COMPANY or when schedule slips up to 5% of the baseline agreed at project
kick off, CONTRACTOR shall immediately provide a schedule recovery plan.
Page 73 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
CONTRACTOR shall develop a progress measurement system that incorporates all activities
consistent with the milestone payment schedule for COMPANY review and approval prior to
project kick off meeting.
CONTRACTOR shall submit weekly updated S-curves tracking baseline versus actual work
progress throughout the duration of the project.
G. COST CONTROL
CONTRACTOR shall track and report project cost performance on plan, actual and forecast basis
throughout the duration of the project on a weekly and monthly basis.
Appendix 1
COMPANY PLAN
Page 74 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
Page 75 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
Tender Number – 00000144 JOB SPECIFICATION
Section E
Schedule Basis
Appendix 1
COMPANY PLAN
To Be Inserted
Page 76 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
Appendix 2
SCHEDULE MILESTONES
Page 77 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
Item
Milestone # Week
#
Work Order Award 0
Page 78 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
Item
Milestone Title Intent of Milestone Deliverables/Specific Actions
No.
1 Work Order Award To initiate WORK Contract execution and WORK initiation
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
Page 79 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
Appendix 3
Page 80 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
Page 81 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
Job Specification
Revision 1
September 2022
Page 82 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
Preface
The COORDINATION PROCEDURE sets forth administrative and procedural requirements to be
met by COMPANY and CONTRACTOR in performing the WORK.
Page 83 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
1. Introduction
This Coordination Procedure provides detail regarding administrative responsibilities of and
interfaces between COMPANY and CONTRACTOR. This Coordination Procedure also serves to
describe the following:
1) Minimum requirements for the execution of specified elements of the WORK.
2) Guidelines that facilitate alignment between COMPANY and CONTRACTOR.
3) Involvement by COMPANY in monitoring and appraising the WORK and results thereof.
Terms that are fully capitalized are defined in the Principal Document (e.g. CONTRACTOR,
COMPANY, and WORK), and those terms defined elsewhere in this CONTRACT and in this
Coordination Procedure, begin with a capital letter (e.g. Project).
Page 84 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
Page 85 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
As part of the tendering process, CONTRACTOR submitted a proposed Execution Plan and parts
thereof may have been incorporated into CONTRACTOR's Execution Basis (in Section K –
CONTRACTOR’s Execution Basis of the JOB SPECIFICATION). CONTRACTOR shall update the
tendered Execution Plan incorporating any COMPANY-approved changes made after tender
submission and submit to COMPANY for review and approval in accordance with the due date
specified in Table F1-2.
Page 86 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
Page 87 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
For the CSTR II Contract effective date (CED) refers to Work Order effective date
1) CONTRACTOR shall develop its Execution Plan in a format and structure that is consistent with
its existing systems. CONTRACTOR shall provide a list of cross-references from its Execution
Plan topics and sections to the relevant section in the COORDINATION PROCEDURE and the
required Project Plans (see Table F1-2).
2) The Project Plans—as listed in Table F1-2 and detailed in each section of the COORDINATION
PROCEDURE—will serve to supplement CONTRACTOR's Execution Plan with more specific
Page 88 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
plans, systems, and procedures describing how CONTRACTOR will execute the WORK. Project
Plans shall build upon the overall strategies, guidance, and milestones contained in the Execution
Plan. If the Project Plans deviate from current Execution Plan, CONTRACTOR shall update the
Execution Plan.
3) CONTRACTOR shall update the Execution Plan and review changes with COMPANY on a
monthly basis. CONTRACTOR shall maintain a record of changes made to the Execution Plan.
CONTRACTOR shall inform COMPANY, at weekly meetings, of any major changes to the
Execution Plan
Page 89 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
Page 90 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
International Codes & Standards: As referenced within the Upstream Nigeria (UN) Global Practices
MPN Global Practice Version to be per current Upstream Nigeria(UN) Global Practices index
GP 00-00-02 Explanation and Use of Upstream Global Practices
GP 00-00-02S Explanation and Use of Upstream Global Practices
GP 01-01-03 & GP 01-01-03S Upstream CAD Requirements - Drawings, Data, and System
GP 02-01-01 GP 02-01-01S Facility Noise Design Criteria
GP 03-01-01 & GP 03-01-01S Upstream piping general design
GP 03-05-01 Fill and Discharge Lines and Auxiliary Piping for Storage Tanks and
Vessels
GP-03-06-01 GP 03-06-01S Piping for Instruments
GP 03-06-04 Vents and Drains, Flushing and Cleaning Connections
GP-03-12-09 General Requirement for Valves
GP-03-19-02 Piping Fabrication Shop or Field
GP-03-20-02 Upstream Piping Classification - Line Classes Atmospheric and 125
GP-03-20-03 Upstream Piping Classification - Line Class 150
GP-03-20-10 Upstream Piping Classifications - Valve Indices and Descriptions
GP-04-01-01 Concrete Design and Construction
GP-04-01-02 Structural Steel Design
GP-04-01-03 Design Load for Structures
GP-04-02-01 & GP-04-02-01S Auxiliary Structures for Operation and Maintenance
GP-04-02-02 Pipe Supports
GP-04-06-01 Reinforced Concrete Foundations Anchor Bolts and Grout
GP-04-08-01 Tank Foundations
GP-04-14-01 Equipment Lifts by Cranes
GP-09-04-01 & GP-09-04-01S Atmospheric Storage Tanks
GP-09-07-01 Accessories for Atmospheric Storage Tanks
GP 09-07-03 Vents for Fixed Roofs Atmospheric Storage Tanks
GP-09-07-04 Internal Floating Roofs for Atmospheric Storage Tanks
GP-12-01-01 & GP-12-01-01S Upstream Numbering System for Project Technical Documents
GP-12-01-02 Upstream Identification of Equipment Components and Devices Lines and
Valves
GP-15-01-03GP 15-01-03S Instruments for Storage Tanks and Vessels
GP-15-02-01 Temperature Instruments
GP-15-03-01 Pressure Instruments
GP-15-04-01 Flow Instruments
GP-15-05-01 Level Instruments
GP-15-06-01 Electronic & Pneumatic Instruments
GP-15-06-03 Programmable Logic Controllers
GP-15-06-04 Instrumentation Inspection, Testing, Calibration, Pre-commissioning
GP-15-07-07 Upstream Protective System
GP-15-09-01 Control Valves
GP-15-09-03 Actuators for on / off Valves
Page 91 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
1.4 Reports
Page 92 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
5) CONTRACTOR's Key Positions and Key Personnel shall be as identified in the Table F2-1 and
Table F2-2 below. CONTRACTOR shall perform background checks on CONTACTOR’s
personnel in security-sensitive positions.
Page 93 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
6) CONTRACTOR shall develop, and maintain throughout the duration of the Project, an electronic
directory containing names, position titles, and contact and other relevant information for all of
CONTRACTOR's Project personnel and select COMPANY Project personnel.
7) CONTRACTOR shall submit, upon COMPANY's request, job descriptions for positions shown
on CONTRACTOR's Organization Chart. COMPANY may require CONTRACTOR to facilitate
COMPANY interviews of CONTRACTOR Key Personnel candidates (including major
Subcontractors' Key Personnel) prior to granting approval of personnel assignment or changes.
8) CONTRACTOR shall submit to COMPANY for approval any mobilization or demobilization of
personnel, or any other personnel changes.
Page 94 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
2.4 Reports
On a monthly basis, CONTRACTOR shall perform the following:
1) Submit the current Organization Chart(s) and Staffing Plan to COMPANY highlighting updates
and changes from the previous month.
2) Report any significant personnel or staffing issues
3) Report staffing and organization status, open positions, and fulltime equivalents (FTEs).
3. Administration
Page 95 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
6) COMPANY will advise CONTRACTOR on requirements for the fixed asset record.
3.2.1 General
In accordance with Section 1, CONTRACTOR shall submit the following for COMPANY review and
approval:
1) CONTRACTOR’s Correspondence Procedure
2) CONTRACTOR's Business Standards Procedure
3) Foreign Corrupt Practices Act Compliance Procedure
4) Workplace Harassment Communication and Reporting Procedure
5) Human Rights Policy Communication and Reporting Procedure
3.2.2 Meetings
Page 96 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
5) The minutes of meetings form shall contain, as a minimum, the following attributes:
a) Project name
CONTRACT number (or purchase order number)
Minutes of meeting number
Subject of meeting
Date of meeting
Meeting called by (or N/A)
Meeting location
Meeting participants (name and company)
Agreed action item list and concerns noting
i. Responsible person and target completion or resolution date for each item
ii. Previously identified actions, status, and explanation if not completed
COMPANY Representative and CONTRACTOR Representative signature blocks
6) COMPANY may expand the minutes of meetings numbering system or attributes to include the
following:
a) Discipline
a) Meeting type (e.g., interface, cost and schedule, Project management, steering, other)
a) Meeting frequency (e.g., single, weekly, monthly, quarterly, annual)
3.2.4 Communications
Page 97 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
7) Letters are the appropriate means for transferring the monthly reports, invoices, and CHANGE
ORDERS. Each letter shall deal with one subject only. Attachments shall be uniquely
identifiable in the body of the main document.
8) Formal communication shall include the following information:
a) Project name
a) CONTRACT number
Letter number
Date of letter
Sender's company, person, and address
Recipient's company, person, and address
To attention
Subject
Reference letter number (if letter is a reply)
Body of letter
List of attachments
Authorizing signature
9) Hard copy international correspondence shall be by airmail, except that CONTRACTOR shall
operate a courier service between its main site and any foreign site(s). COMPANY may use the
courier service at COMPANY's discretion. National mailing shall be by first class mail or by
other quicker means of mailing. Large mailings shall be split into small packages to facilitate
handling and delivery. Split packages are to be numbered per the following format: package
[sequence number of package] of [total number of packages]
10) Confirmation of receipt is required for all letters. Email confirmation of receipt with the letter
number in the subject line is acceptable.
11) Formal communication shall be date stamped on receipt. The date stamp shall include provision
for a distribution list for both COMPANY and CONTRACTOR.
12) Correspondence between COMPANY and CONTRACTOR shall be addressed as follows in
Table F3-1 below.
13) Letters and transmittals shall be designated with a unique identification number as given in Figure
F3-1.
Figure F3-1: Format for Letter and Transmittal Unique Identification Number
Page 98 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
Page 99 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
14) Minutes of Meetings shall be designated with a unique identification number per the format
specified in Figure F3-2.
16) Individual Purchasing Plans are required for each purchase order with a value greater than [Insert
Value Here].
17) Individual Subcontracting Plans are required for each subcontract with a value greater than [Insert
Value Here].
3.3 Reports
CONTRACTOR's monthly summary report shall include an executive summary with the following as
a minimum:
1) Narrative highlights of major activities by discipline and phase (engineering, operations readiness,
procurement, construction, commissioning)
2) Critical issues list including delays, standby activities, causes, responsible parties, timing to
resolve
3) Schedule outlook for activities to be started or finished during the upcoming 30 to 90 days
4) Progress versus planned performance, with particular emphasis on those activities on the Critical
and Sub-Critical Paths
5) A cataloged, digital photographic report that illustrates the progress of the WORK.
6) A safety narrative describing safety performance during the prior month for both leading and
lagging safety indicators in appropriate detail, including the following:
a) A detailed description of each safety incident: injuries, illnesses, and safety near misses.
b) Root causal factors, assessment learnings, and corrective actions shall be listed.
c) Comprehensive safety statistics and leading and lagging safety indicators for the prior
month and Project to-date. Leading and lagging safety indicators for the prior month and
Project to-date shall include the following, as indicated for each:
4. Information Management
Category Examples
Category III Utility sizing calculations
Utility equipment arrangement plans, elevations, isometrics, and special support
drawings
Utility piping special item data sheets, material takeoffs, material requisitions
Utility equipment and engineered package requests for quotations (RFQs)
Secondary process piping stress reports
HVAC design calculations, equipment data sheets, arrangement plans, and
elevations
Quarters equipment list, architectural layout, arrangement plans, and piping and
cable routing
Instrumentation calculations, logic diagrams, loop drawings, data sheets, and
installation drawings
Instrumentation panel layouts (utilities)
Electrical, instrumentation, and control equipment building layout plans and
elevations, installation details, and bulk takeoffs
Electrical and instrumentation global drawings, sheet index, symbols, legend,
and general notes
Secondary structural steel drawings, model, steel specifications, shop drawings
Utility system boundary diagrams and commissioning and operating procedures
Turnover and completion packages (ancillary process systems and utilities)
Low-criticality spare parts lists
4.4 Reports
5. Interface Management
b) Providing for the creation of an IDR for managing, tracking, forecasting, and reporting
interface activity for which CONTRACTOR is responsible. The IDR template shall be in a
format approved by COMPANY and shall be updated on a regular basis.
c) Identifying and tracking any Critical Interfaces in the IDR.
2) All interface-related correspondence, referenced documents, and exchanged deliverables between
CONTRACTOR and other entities will be compiled to and tracked in a document register.
5.4 Reports
CONTRACTOR shall provide interface management status reports accompanied with associated
back-up data (such as the IDR) in formats and frequencies as agreed by COMPANY.
Contractor shall update the 3D CADD model to reflect As-Built conditions and submit to
Company
2) The 3D CADD model shall be the latest static version and shall be updated periodically based on
design progression from the latest dynamic model.
3) CONTRACTOR's planning and execution of the 3D CADD models shall be in accordance with
GP 01-01-03, GP 01-01-03S and other GP supplements. Additionally, CONTRACTOR shall
comply with the following:
a) Assign an overall Design Drafting Coordinator, whose function is to manage inter-discipline
design conflicts and ensure consistent 3D CADD implementation across all disciplines.
a) Ensure 3D CADD model design is led by experienced designers with prior experience in 3D
CADD modeling. The designers shall interface with an experienced core team of 3D
CADD designers (per discipline) who will input design data into the system.
Ensure onsite technical support is available on a day-to-day basis to troubleshoot hardware and
software issues that may arise.
Early during the WORK, develop a computerized line list so that 3D CADD models can be monitored
on a line-by-line basis. The line list shall include status information such as the following:
i. Routing of lines in model
ii. Generation of isometrics
iii. Checking of isometrics
iv. Release of isometrics to construction
v. Revision levels
Link the 3D CADD Model to CONTRACTOR's Materials Management System (MMS) so that
material takeoffs (MTOs) can be directly downloaded from the 3D CADD Model to the MMS.
Verify the accuracy of MTOs.
Ensure that all disciplines use the 3D CADD system and the same database.
4) COMPANY's model review and CONTRACTOR's implementation of comments into the 3D
CADD model shall be scheduled milestone activities that are part of the progress measurement
system utilized for measuring and controlling progress of the electronic model.
5) To maximize the clash-checking capability of the electronic model, CONTRACTOR shall draft
and design appropriate disciplines (e.g., piping; structural; electrical; instrumentation; heating,
ventilation, and air conditioning [HVAC]; insulation and fire-proofing envelopes; operations and
maintenance envelopes) within the 3D CADD environment.
6) CONTRACTOR shall schedule clash-check dates as key milestones in the development of the 3D
CADD model. CONTRACTOR shall perform simultaneous clash-checks for all disciplines.
7) CONTRACTOR shall perform clash-checking for junction boxes and cable trays and shall review
junction boxes for adequacy and interference with passageways and equipment.
2) For the detailed design phase, the Design Verification Plan shall also include the following:
a) Key milestones for the execution of the design verification, including the following:
i) Submittal of Design Verification Plan
ii) Review of the Plan by COMPANY
iii) Timing window for queries to COMPANY
iv) Submittal of draft verification report
v) Issue of final report
vi) Target closeout of identified design verification deficiencies
b) Summary of verification philosophy, extent of review, and key activities for each discipline.
c) Process for submittal and finalization of verification queries.
d) Plans and timing for status reviews with COMPANY.
e) Clear definition of metrics that will be used to track deliverables throughout the design phase
(e.g., deliverable initiated, issued for internal review, issued for COMPANY review, issued
for design [IFD], issued for construction [IFC], etc.)
f) Plan for how cost and schedule impacts identified from the verification process will be
addressed, if applicable.
g) Identification of party responsible for 3D CADD model verification against engineering
deliverables.
h) Identification of party responsible for ensuring the 3D CADD designers are utilizing the
Project 3D CADD specifications.
i) Identification of the checking and verification activities for CONTRACTOR engineering,
Subcontractor engineering, and procurement and Supplier data. Checking and verification of
Supplier Data shall include confirmation that the manufacturer’s Installation, Operation and
Maintenance recommendations are being followed.
j) Engineering software control and verification.
k) Identification of party responsible for the verification activities including third-party
Verification and Certifying Agents.
d) Listing of CONTRACTOR work processes and copies of those processes, with clear
identification as to which processes are unique to the WORK and which processes are
CONTRACTOR standards.
e) Description of the work processes, management, and oversight to be used if CONTRACTOR
uses multiple offices for the WORK, including how activities between various offices will be
transferred, monitored, reviewed, etc., as well as who has overall responsibility for the
finished deliverable
f) Description of how engineering quality processes will be conducted, including the following:
i. Checking and verification activities for CONTRACTOR engineering, Subcontractor
engineering, and procurement and Supplier data
ii. Checking and verification activities for interfaces with other COMPANY entities (e.g.,
Construction, Drilling, and Operations)
iii. Checking and verification of Supplier Data shall include confirmation that the
manufacturer’s Installation, Operation and Maintenance recommendations are being
followed
iv. Design change control, revision control, and management of change process including
performing risk assessments on CONTRACT Changes, design changes, CHANGE
ORDERS, and Specification Deviations
v. Engineering software control and verification
vi. Identification of third-party Verification and Certifying Agents
vii. How CONTRACTOR will track key quality metrics and report to COMPANY
g) A constructability plan that provides, as a minimum, for early input by key construction
stakeholders into the design to establish guidance and direction as it relates to construction,
including execution steps, sequence, productivity enhancements, standardization, etc., as well
as the following:
i. Risk reduction
Incorporate mitigations from construction hazards review identified in early
construction execution planning strategy
Design erection attachment points and vessel shells to minimize work at heights –
fully dress equipment prior to erection
Incorporate attachment points for construction access platforms into permanent
facilities and equipment
Minimized tie-ins to energized facilities e.g. hot taps as last resort, shutdowns for
tie-ins, etc.
ii. Productivity considerations
Suitability of approach for major equipment entry (maintenance considerations are
also to be accommodated)
Suitability of adjacent areas for use as work areas (maintenance considerations are
also to be accommodated)
Scheduling design deliverables based on sequences of installation and delivery of
major equipment
Three-dimensional accessibility
Industrialized construction – modularization, factory built vs. stick built
iii. Construction philosophy, including design basis drivers, such as the following:
Location conditions – weather, labor supply, social and economic
Schedule constraints
Quality objectives
National content
Construction equipment limitations
As applicable, CONTRACTOR shall include constructability requirements as stated in the
Offshore Installation and Transportation section of the COORDINATION PROCEDURE.
h) An operability plan that provides, as a minimum, for early input by key operations
stakeholders into the design to establish guidance and direction as it relates to Operations
including accessibility, maintenance, ergonomics, etc.
i. Description of the following:
Engineering software and its application in the design process, including
descriptions of capabilities and quality control documentation for all
noncommercial programs
Processes for ensuring quality and integrity of the databases and program inputs to
be used in the design process and the databases for the design results.
2) CONTRACTOR shall indicate if any of the design offices propose to use any database software
for the first time during the course of the Project.
3) Description of the process used to capture design input from the Risk Assessment activities during
design evolution as outlined in Section 15. of Section F – COORDINATION PROCEDURES.
4) A 3D CADD implementation plan outlining the various procedures to ensure systematic
development, maintenance, and control of the 3D CADD Model. The 3D CADD implementation
plan shall address the following:
a) The early studies required prior to start of 3D CADD inputs
b) Milestone schedule, including model freeze milestones such as hold points, reviews, freeze
points, etc.
c) Management of change process
d) The timing of model reviews
e) Review and verification process including how review comments will be tracked and
implemented
f) The quality and content of electronic-model-generated general arrangement drawings, plans,
and sections (i.e., the extent of annotation to assure adequacy to support construction)
g) How pipe supports will be accounted for in 3D CADD model and clash checks
h) How clash-checking will be done
i) How isometric drawings will be extracted from the model, including the timing and number
of extractions before the IFC extraction
j) Process for developing IFC drawings from the model
k) How MTOs will be performed, including MTO release and its interface with
CONTRACTOR's MMS
l) How early (pre-IFC) purchase orders for bulk materials (e.g., valves, piping, etc.) and
overages will be reconciled with future MTOs extracted from the model
m) How the 3D CADD model will be electronically linked to CONTRACTOR’s MMS
n) How the 3D CADD database will be controlled and managed
o) How progress on the 3D CADD model status will be measured and controlled
p) Management of the disciplines and respective management of the interfaces
q) The organizational aspects of 3D CADD, including how flow of WORK between disciplines
will be managed
r) An organization chart identifying personnel and positions and their reporting hierarchy with
respect to managing and executing the 3D CADD model and engineering design
s) How progress of the 3D CADD model will be monitored, tracked, and reported
5) Clear definition of who is responsible (CONTRACTOR or Supplier) for identification, inclusion
into the model (if at all) of, and the procurement of the following:
a) Non-process vents and drains (those used by Systems Completions for hydro-testing and
high- and low-point vents and drains)
b) Items required for pipe spooling for construction efforts (e.g., extra flanges, valves, gaskets,
etc.)
6) Clear definition of the following:
a) Procedures for adding multi-discipline supports in the model (piping, electrical, instrument,
etc.)
b) Who has the responsibility for multi-discipline support input and the timing in which they are
to be added
7) If the model is to be turned over to fabricator at various stages of completion, then a description
of how transitions will be handled, including the following:
a) Model turned over one deck at a time, sections and blocks of a deck at a time, etc.
b) How will material-handling (no touch) areas that spreads across decks be handled
c) Procedures for handling changes once a section of the model has been turned over to the
fabricator
d) Penetrations between decks and walls that will be shared between the areas turned over at
various stages in the design.
a) A plan to document and control Specification Deviation requests
Site-specific document control plans that include the following:
i. Technical documentation controls
ii. Plans for complying with CONTRACT Information Management requirements
iii. Turnaround cycles for deliverables listed in the Master Document Register (MDR)
8) Description of how CONTRACTOR's engineering and project controls groups will interface to
develop and maintain a detail design schedule, work-hour estimates, and inputs to measure and
report physical progress, and to provide development and status of key engineering milestones.
To the extent possible, the physical progress measurement for detailed engineering shall be
based on deliverables completed.
2) Requirements for engineering completed at offices away from CONTRACTOR’s home office,
including but not limited to offices that may be referred to as Remote Engineering Offices,
Satellite Engineering Offices, and subcontracted or Integration Engineering offices.
3) All requirements as set forth in Section 1. as they apply to HVEC WORK.
4) HVEC qualifications to complete the assigned portions of the WORK with specific reference to
how critical processes will be managed by the home office, including the following:
a) Clearly define WORK scope assignments and how they match HVEC capabilities
Define roles and responsibilities of the HVEC team and the reporting structure in relation to
CONTRACTOR’s home office
Define specific plans and procedures to be used to maintain security and protection of proprietary
information at each HVEC
5) Definition of the process by which the HVEC knowledge base will be validated to meet the
requirements of the WORK, with specific reference to the following:
a) How the WORK-sharing relationship between HVEC Lead Discipline Engineers and their
home office counterparts will be leveraged to enhance WORK efficiency and productivity
a) Provisions for home office oversight, including timing of regular meetings, frequency of
visits by home office management, the need for home office personnel to be located in the
HVEC, and provisions for visits from COMPANY representatives to the HVEC
The process by which HVEC Lead Discipline Engineers are aligned with the home office work
processes and CONTRACTOR's Quality system
How the JOB SPECIFICATION requirements are shared with HVECs and how CONTRACTOR will
ensure that discipline engineers are familiar with their use
Processes to align the HVEC 3D Model with the 3D CADD implementation requirements, including
the procedure for sharing model results between the HVECs and the home office on a “real time
basis”
6) Identification of CONTRACTOR's interface management process for the HVEC, including
specific references to the following:
a) Definition of positions in the HVEC that are duplicates of those on the home office team
(e.g., Project Manager [or Engineering Manager], Project Engineers, Lead Discipline
Engineers, Controls Engineers)
a) The procedures and practices to be used to manage the interface between the home office
and HVEC
7) An HVEC coordination procedure that includes the following:
a) Clear definition of the areas of WORK, and the division of responsibilities between the
home office and HVECs
a) Methodology for transferring information and WORK from and to the HVEC for all
disciplines
The process by which concurrent engineering in multiple offices will be kept consistent to avoid
recycle and rework
Definition of persons responsible for detailed activities by discipline
Definition of the WORK share system and division of responsibility between the home office and
HVECs
Definition of how the HVEC progress and productivity measurement system will be compatible with
the home office systems and how it will integrate into the overall Project progress system to meet
reporting needs
Process to ensure the effectiveness and completeness of HVEC quality assurance and quality control
processes and ensure that the Quality Plan addresses Project needs
Procedure for conducting face-to-face alignment meetings between the home office Lead Engineers
and the HVEC Lead Engineers prior to starting WORK at the HVEC offices.
8) Description of how CONTRACTOR will provide for and perform the following:
a) Define practices for establishing progress and productivity measurements and assessment of
physical progress that specifically relate to the HVEC team
a) Review procedures and processes of integrating HVEC progress into overall progress
Obtain a clear list of deliverables that are populated into the MDR that will ensure tracking of WORK
completed by the HVECs
Develop a Level 3 schedule for the HVECs as part of the overall Project schedule.
Develop an integrated planning protocol between home office and HVECs
Ensure that the HVEC mobilization plan is consistent with the schedule, work hour budget, available
work, and deliverables sequencing and priorities per the Execution Plan
Develop surveillance plans that specifically address HVEC WORK and that are consistent with
COMPANY's ESP requirements
Develop a quantity assessment plan for HVEC WORK that is consistent with the quantity assessment
and tracking requirements of Section 6.2.5 and Section 6.3.4 of Section F – COORDINATION
PROCEDURES.
Ensure a system is in place for HVEC personnel assignments, overtime, and travel authorization
consistent with home office established procedure
6.4 Reports
CONTRACTOR shall submit regular reports as described below. The engineering reports' content
may be incorporated into the Weekly and Monthly Summary Report described in Section 3.4 and
Section 1.4.1 of Section F – COORDINATION PROCEDURES.
7. Procurement
Procurement means all Purchasing, Subcontracting, and Materials Management activities required for
the WORK. Purchasing means activities related to the acquisition and delivery of materials, whereas
Subcontracting means activities related to the acquisition of services or portions of the FACILITY
having significant labor content. Materials Management means activities related to inspection,
expediting, FATs, logistics, customs, and custody transfer issues, Spare Parts, warehousing, etc.
In executing its procurement activities, CONTRACTOR shall keep COMPANY informed of
CONTRACTOR's ongoing procurement activities to maintain alignment with COMPANY via
meetings with COMPANY and the issuance of procurement reports on an agreed schedule, but not
less frequently than monthly. CONTRACTOR shall ensure meetings and reports highlight all
problem areas related to procurement and describe actions being taken to resolve these issues.
CONTRACTOR shall also invite appropriate COMPANY representative(s) to all bid clarification,
technical bid evaluation, pre-production, and other procurement-related meeting between
CONTRACTOR and Suppliers in sufficient time for the Representative(s) to attend, if COMPANY
desires. For the purposes of coordination, COMPANY will assign a procurement advisor as a focal
point with CONTRACTOR in matters of communication, meetings, approvals, and related
procurement matters.
7.2.1 General
In accordance with Section 1, table F1-2 of Section F – COORDINATION PROCEDURES,
CONTRACTOR shall submit the following for COMPANY review and approval:
1) Materials Management System (MMS)
2) Overall Procurement Management Plan
3) Overall Purchasing Plan
4) Overall Subcontracting Plan
5) Materials Management Plan
6) Expediting and Logistics Plan
7) Individual Purchasing Plans
8) Individual Subcontracting Plans
9) Spare Parts Management Plan
1) Maximize practical use of National and/or Local Content Subcontractors and Suppliers to meet
Project objectives.
2) Use, as appropriate or as required by the JOB SPECIFICATION, COMPANY’s and
CONTRACTOR's existing procurement agreements to meet cost and schedule objectives.
3) Develop bid lists subject to the following:
a) Use only Subcontractors and Suppliers listed in Section J of the JOB SPECIFICATION for
the categories of goods and services listed therein as may be later modified with
COMPANY’s approval.
Use instructions provided in Section J of the JOB SPECIFICATION for evaluating and nominating
additional Suppliers and Subcontractors for performance of the WORK.
CONTRACTOR's non-compliance with nomination procedures prescribed in Section J of the JOB
SPECIFICATION may be considered sole grounds for disapproval or rejection of Supplier and/or
Subcontractor nominations.
COMPANY shall have no obligation to approve nominations for such Suppliers or Subcontractors.
4) For Criticality I and II equipment and materials, develop a list of proposed Supplier purchase
orders and identify sub-suppliers and sub-orders comprising the entire supply chain for review by
COMPANY.
Execution milestones (e.g., dates of inquiries, awards, and deliveries, including target and actual dates
of COMPANY approvals where applicable)
Latest revisions, change orders, or amendments
Export control and classification numbers (ECCNs)
4) Manage principal procurement interfaces between CONTRACTOR and its Suppliers and
Subcontractors, as well as interfaces with COMPANY's other Contractors, as set forth in the JOB
SPECIFICATION or as directed by COMPANY.
5) Assume responsibility for POs and subcontracts assigned to CONTRACTOR by COMPANY
including, but not limited to, the following:
a) Remaining engineering
a) Expediting
Related Supplier documentation
Invoice payment
Quality management activities
Logistics
Material traceability
WORK SITE material control
Factory acceptance testing (FAT), commissioning, if applicable, and warranty
6) Ensure that CONTRACTOR’s Suppliers and Subcontractors meet their contractual obligations in
connection with the WORK.
7) Immediately notify COMPANY of any claims received.
8) Process and handle claims in accordance with CONTRACTOR’s claims handling Procedures
approved by COMPANY for the Project
9) Ensure the following items have been resolved prior to final payment and closeout of the POs and
subcontracts:
a) Revisions
b) Claims and liens
c) Back-charges
d) Liquidated damages
e) Overages, shortages, and damages (OS&Ds)
f) Insurance claims
g) Disputed invoices or payments
10) Provide such assistance as required to support COMPANY's task of setting up equipment or
materials codes in COMPANY's fixed asset accounting system prior to COMPLETION of the
WORK.
11) Maintain and provide to COMPANY a copy of CONTRACTOR's master procurement file, paper
and/or electronic, which shall include copies of incoming and outgoing correspondence (including
mail, facsimile, etc.) sent to or received from Subcontractors, Suppliers, agents, or the like,
dealing with procurement matters.
12) Perform administrative activities through completion of the subcontracted or purchased WORK.
7.2.3 Purchasing
With respect to the purchasing of equipment and materials, CONTRACTOR shall perform the
following:
1) Identify equipment and material criticalities for each PO in accordance with GP 20-01-04 and
other GP supplements, and adjust purchasing and materials management efforts accordingly.
2) Prepare Individual Purchasing Plans for Critical Items and for POs valued above the amount
stated in the Section 3.2.4 - 16) and 17) of Section F – COORDINATION PROCEDURES.
3) Monitor engineering design schedule to ensure that drawings, specifications, and requisitions are
produced and received in time to meet the schedule for issuing inquiries and placing POs.
4) Purchase only new materials, equipment, and spare parts for the WORK (the meaning of "new" in
this context is defined as unused and originating from a non-secondary market).
5) Issue POs in accordance with COMPANY-approved format and content requirements, including
POs for spare parts and technical support services, etc., as required in the JOB SPECIFICATION.
6) Be responsible to negotiate the terms and conditions and obtain COMPANY's approval for any
deviations if Supplier takes exception to the standard terms and conditions approved by
COMPANY. Unless otherwise agreed in writing by COMPANY, COMPANY’s approval of such
deviations shall not relieve CONTRACTOR of its obligations under the CONTRACT for
CONTRACTOR GROUP.
7) Ensure that Suppliers and sub-suppliers permit timely access for CONTRACTOR and
COMPANY personnel to facilitate expediting and inspection.
8) Ensure that COMPANY receives full benefit of all allowable exemptions, discounts, and refunds.
9) Provide information and assistance to COMPANY in the event that COMPANY is required to
apply for refunds or waivers of sales tax, duties, or similar items.
10) Prepare Individual Purchasing Plans for Critical Items and for POs valued amount stated in the
Special Conditions Article of Section F of the Coordination Procedures.
7.2.6 Subcontracting
With respect to the subcontracting of the WORK, CONTRACTOR shall perform the following:
1) Identify subcontracts that contain services related to Critical Items and adjust subcontracting
management efforts accordingly.
2) Monitor engineering design schedule to ensure that drawings, specifications, and requisitions are
produced and received in time to meet the schedule for issuing inquiries and placing subcontracts.
3) Prepare Individual Subcontracting Plans for subcontracts valued above the amount stated in the
Special Conditions Article of Section F of the Coordination Procedures.
4)
Negotiate the terms and conditions and obtain COMPANY's approval for any deviations if
Subcontractor takes exception to the standard terms and conditions approved by COMPANY.
Unless otherwise agreed in writing by COMPANY, COMPANY’s approval of such deviations
shall not relieve CONTRACTOR of obligations for CONTRACTOR GROUP under the
CONTRACT.
5) Issue subcontracts in accordance with COMPANY-approved format and content requirements.
6) Unless directed otherwise by COMPANY, CONTRACTOR shall submit the documents listed in
Table F7-1 to COMPANY for review and approval within the targeted lead times specified.
9) Initial PO register with content consistent with Section 7.2.2.3 of Section F – COORDINATION
PROCEDURES.
10) A list of planned equipment purchases where technical support agreements or long-term service
agreements are required and a description of CONTRACTOR's plans for obtaining these services,
either for CONTRACTOR or on behalf of COMPANY. The list shall include Supplier services
required for installation, commissioning, start-up, or operator training.
11) List of inquiries and POs initiated by COMPANY prior to EFFECTIVE DATE, as may be
specified in the JOB SPECIFICATION, and a process to transition them into CONTRACTOR's
system where necessary for CONTRACTOR to complete the purchasing activities.
12) List of materials and equipment that will potentially be purchased at the WORK SITE. The value
of items purchased at the WORK SITE shall be limited to levels approved by COMPANY.
13) A list of Critical Items as well as equipment and material at or near the Critical Path. COMPANY
will review and include additional items on the list as required. In addition to reviews required
per Table F7-1, where applicable COMPANY’s review shall include proposed sources of key
materials and critical components, including sub-suppliers, sources of billets, and fabrication
locations (see GP 20-01-04 and other GP supplements).
14) A list of the major purchasing issues anticipated for the WORK (with emphasis on interface
management and priority based on Project risk (e.g., work scope, schedule, value, etc.), and
recommended actions to successfully address these issues.
15) CONTRACTOR's procedures for export compliance.
16) CONTRACTOR's plans for materials surplus mitigation and strategy with Suppliers on restocking
rates or buy back to be included in equipment and material POs.
2) The level of detail for each Individual Purchasing Plan shall be commensurate with its criticality
and the PO value. Each Individual Purchasing Plan shall include, as a minimum, the following:
a) Scope of supply, by tag numbers, if applicable.
b) Recommended procurement method (e.g., single source, call-off from enabling agreement,
competitive bid, etc.) and bidders list.
c) Lead time estimates for major purchasing milestones developed by CONTRACTOR for
scheduling purposes.
d) Target dates for principal events, such as requisition receipt, bid list finalization, inquiry issue
and proposal due dates, bid evaluation, award recommendation, target date for execution of
order, and required-onsite (ROS) date. These times shall be compatible with the schedule for
the WORK.
e) Description of relevant quality control and testing requirements.
f) General technical requirements and specifications.
g) If applicable, relevant post-order delivery dates for design and interface information,
materials and/or services, and special interface management issues resulting from placement
of the order such as interfaces with COMPANY's other Contractors.
h) General discussion of proposed technical and commercial evaluation criteria, which may
include but is not limited to the following:
i) Schedule (equipment and spares delivery)
ii) Execution considerations
iii) Delivery terms
iv) Quality considerations
v) Anticipated technical aspects of the competing proposals
vi) Anticipated commercial aspects of the competing proposals (including estimated cost of
spare parts and technical services, as appropriate)
vii) Licensing requirements
viii) Confidentiality requirements
ix) Other such terms to be requested from bidders, including payment terms, damages for
delay, warranties and buy-back of surplus materials
Releases against CONTRACTOR's or COMPANY's existing pre-priced enabling agreements and POs
placed on a single-source basis do not require detailed bid evaluation plans if the original agreement
has already been approved by COMPANY (e.g., agreement covering bulk materials).
2) Description of portions of the WORK that CONTRACTOR proposes to subcontract, including the
following:
a) The general division of responsibility between CONTRACTOR and its Subcontractors for
providing engineering documents, materials, equipment, services, etc., and definition of
each party's roles and responsibilities
The number and proposed compensation basis of subcontracts, including the scope of WORK and
estimated value for each
3) CONTRACTOR’s plan to identify and use local Subcontractors in executing the WORK.
4) Subcontracts that CONTRACTOR proposes to manage from the WORK SITE, including a
description of any portion of oversight or assistance to be provided by the home office.
5) CONTRACTOR’s subcontracting-related templates, including but not limited to, pro forma
subcontract (with criteria for use of the various forms).
6) Description of details of CONTRACTOR's prequalification process used to evaluate any
additional Subcontractors prior to nominating them for COMPANY approval, including
guidelines, checklists, and related document templates. The qualification process shall focus on
the following qualifications:
a) Technical performance qualification including technical capabilities, capacities, safety,
quality, and schedule.
a) Commercial qualification compliance screening, including methods to ensure the following:
i. The prospective Subcontractor is not restricted by LAW (e.g., restricted parties
screening
ii. Financial strength and stability of the prospective Subcontractor based on a
subcontract value or other criteria as determined by COMPANY
7) Initial subcontract register consistent with Section 7.2.2.3 of Section F – COORDINATION
PROCEDURES, with schedule for managing all subcontracting activities (e.g., issuance of
inquiries, bid evaluations, execution of subcontracts, etc.) through subcontract closeout, ensuring
that the key dates shown are compatible with the CONTRACT SCHEDULE. The register shall
include pertinent data such as requisition and subcontract numbers, scope, execution milestones
(target and actual dates, including for required COMPANY approvals), and amendments.
8) List of inquiries and contracts initiated by COMPANY prior to EFFECTIVE DATE, as may be
specified in the JOB SPECIFICATION, and a process to transition them into CONTRACTOR’s
system where necessary for CONTRACTOR to complete the subcontracting activities.
9) A list of the major subcontracting issues anticipated for the WORK with emphasis on interface
management and priority based on Project risk (e.g., work scope, schedule, value, etc.), and
recommended actions to successfully address these issues.
10) A summary of subcontracting activities already completed by CONTRACTOR.
11) Subcontract administration processes and procedures, including the following:
a) A description of how CONTRACTOR will ensure that Subcontractors comply with all
requirements of the subcontract
a) CONTRACTOR's allocation of roles and responsibilities for oversight of subcontract
activities, including change management and document control
The level of detail for each Individual Subcontracting Plan shall be commensurate with its value and
potential impact on the Project. Each Individual Subcontracting Plan shall include, as a minimum, the
following:
1) Scope of WORK to be subcontracted.
2) The detail division of responsibility between CONTRACTOR and Subcontractors for providing
engineering documents, materials, equipment, WORK SITE services, etc., and definition of each
party's roles and responsibilities.
3) Recommended procurement method (e.g., single source, call-off from enabling agreement,
competitive bid, etc.), proposed compensation basis, and bidders list.
4) Lead-time estimates for major milestones developed by CONTRACTOR for scheduling purposes.
5) Subcontracting process milestones such as inquiry issue and proposal due dates, proposal
evaluation, award recommendation, and target dates for subcontract award and execution.
6) General technical and execution requirements and specifications.
7) If applicable, relevant post-award delivery dates for interface information, materials and/or
services, and a special interface management issues with COMPANY's other Contractors.
8) General discussion of proposed bid review program including technical, execution, and
commercial evaluation criteria addressing the following:
a) Pricing and other commercial considerations
Schedule
Interface and execution considerations
Quality considerations
Confidentiality requirements
7.4 Reports
CONTRACTOR shall regularly inform COMPANY of CONTRACTOR's ongoing procurement
activities via meetings with COMPANY and issuance of procurement reports on an agreed schedule
not less frequently than monthly. Format and content for the reports will be agreed upon between
COMPANY and CONTRACTOR prior to first issuance and shall include the following as a
minimum:
1) A six-week look-ahead on procurement-related activities.
2) Customs reports including full detailed and itemized reports of import duties, TAXES, or any
other required payments made by CONTRACTOR or CONTRACTOR's agents necessary for the
clearance of items through customs. These reports shall be submitted to COMPANY at least once
a month or more frequently as requested by COMPANY.
3) Procurement status reports showing the overall progress of the following:
a) Preparation of requisitions
Issuance of inquiries
Receipt of bids
Issuance of POs and subcontracts
Cost comparison of actual PO and subcontract value versus CONTRACT PRICE BUDGET
PO and subcontract change orders, claims, and potential or actual impacts
4) Materials delivery status report, in Microsoft Excel format, that includes the following
information for each PO or suborder:
a) PO number
a) Brief description of the equipment or materials
a) ECCN of any controlled materials
Supplier and manufacturing location for each part of the PO
Date required (i.e., construction ROS dates or equivalent), with updates as engineering and
construction of the WORK progresses
Original and current promised delivery dates
Date of last expediting contact and type of contact
Estimated time of departure (ETD), actual time of departure (ATD), estimated time of arrival (ETA),
and actual time of arrival (ATA)
5) Materials delivery exception reports listing all items (including, if applicable, fabricated piping
spools) that are required to meet construction schedules but which have not yet been delivered to
the WORK SITE. These reports shall show for each listed item the forecasted and promised
delivery dates, PO number, name of Supplier, and date of last expediting visit.
6) Ad hoc purchasing reports such as the following:
a) Field material requisition, procurement, and expediting reports
a) Construction, commissioning, and remote site material shortage reports
a) Supplier technical support reports
Closeout status reports
Surplus material disposal reports
7) For field materials management and warehousing, weekly reports showing receipt date, storage
location, preservation status, date issued to field, and key issues that will negatively impact
materials management activities. CONTRACTOR shall send the weekly report electronically to
COMPANY in a format to be agreed upon between COMPANY and CONTRACTOR.
8.3 Fabrication
CONTRACTOR will advise COMPANY on CONTRACTOR's fabrication strategy at its own WORK
SITE(s) and those of its subcontractors. CONTRACTOR will obtain COMPANY agreement on the
following, as a minimum:
1) Plans for mobilizing and demobilizing equipment, material, personnel, and subcontractors to/from
the WORK SITE.
2) Erection plan, including size of components built in shops or outside areas; erection of major
sections/blocks for outside yard and assembly; erection sequence; placement and selection of
construction equipment, such as cranes, jacking towers, transporters, and their degree of
utilization.
3) Detail for workflow through the yard, beginning with delivery of steel and continuing to each
phase of each work element to the completed component.
4) Plan for protection of equipment and materials from the time CONTRACTOR takes custody until
the item is turned over to COMPANY at the installation site. The Plan shall include provisions
for preventive maintenance per vendor requirements.
5) Ensure that all steel plates provided are nested in the most efficient manner prior to cutting and
rolling. CONTRACTOR shall ensure that all steel pipe, tubulars, sections, etc., are measured and
cut with the minimum scrap as is practical.
6) Plan and procedures for material traceability from the time CONTRACTOR receives materials
that are to be provided by CONTRACTOR.
7) Requirements for major construction tools and equipment and for their maintenance.
8) Requirements for temporary offices, warehousing, and other facilities.
9) Requirements for electrical power, water, sewage disposal, and all other utilities. Mitigation
measures to ensure adequate drainage at WORK SITE(s).
10) Plans for hiring craft personnel, identifying employment criteria, orientation, and training
requirements.
11) Plans for measuring, monitoring and reporting field labor productivity at the individual or craft
level weekly and plans continuously to improve productivity during the work
12) Details regarding the use of vendors' technical representatives during construction, systems
completion, installation, commissioning, and start-up.
13) Procedures for managing subcontracted work.
14) Consideration of Critical lifts with sufficiently detailed plans to demonstrate all aspects of the lift
(e.g., size and capacity of rigging equipment, crane and/or load movements, radii, and capacities
and ground conditions).
15) Dimensional control, including, but not limited to, adherence with tolerance, documentation,
certification, personnel qualifications, etc.
16) Weight control, including weight certification for equipment, modules, etc., and development of a
database to steward the weight budget.
17) Plans and procedures for load out and tie down of all components four (4) weeks prior to load out.
c) Sequences of installation
d) Maintenance of three-dimensional accessibility
e) Erection and assembly safety – cordoning, sequencing work, fall protection, and etc.
f) Coordinated usage of major construction equipment
g) Minimized work at heights – i.e., dressing of equipment prior to erection
h) Coordinated scaffolding and minimized support from ground – i.e., incorporate attachments
into permanent facilities and equipment for hanging scaffold
i) Brownfield tie-ins – i.e., utilize replacement spools instead of hot taps as philosophy
j) Conflict identification
6) Temporary facilities requirements
a) Infrastructure development – materials offloading and receiving facilities, access roads, onsite
roads, parking, staging, storage, laydown areas, etc.
b) Life support facilities, including accommodations, medical care, recreation, food handling
and serving, housekeeping, laundry services, security, and all other facilities to render a
physically and mentally healthful environment
c) Temporary utilities generation and distribution, and wastes collection, treatment and disposal
for the life support facilities, temporary facilities, and construction work areas
d) Temporary facilities maintenance and operations
e) Construction fuels, lubricants, and equipment servicing
f) Layouts should consider the following:
i. Cross-wind locations from hydrocarbon areas (before and after start-up)
ii. Location of temporary facilities should consider potential expansion areas for future
work
iii. Preservation of emergency and delivery accessibility with a minimum of two routes
iv. Allowance for large equipment turning radius and not creating blind intersections
v. Separation of travel paths for personnel from equipment
vi. Drainage
vii. Proximities so as to minimize utilities distribution costs
7) Construction equipment
a) Sources of equipment and spare parts
b) Pre-inspection of equipment at origin prior to mobilizing
c) Customs and import duties, and duration limitations for recovery of duties
d) Export requirements
e) Validation of any temporary construction equipment
8) Simultaneous operations (SIMOPS)
a) Identification of SIMOPS activities and interfaces
b) Constraints such as not affecting operating company production
c) Hazards analysis and mitigations
vi. Maintenance, inspection, and tests plans for cranes and associated lifting aids or
equipment lifts as per GP 04-14-01 and other GP supplements.
16) Heavy haul plans
a) Load parameters – weight, center of gravity, and eccentricity confirmation
b) Route attributes – interfaces, obstructions, facilities crossings, bearing capacities confirmed
for all bridges, culverts and road sections, and required enhancements
c) Transport equipment selection
d) Notifications and permits
17) Materials receiving, storage, preservation, traceability, and issue
a) Materials storage and preservation in accordance with CONTRACT and provider
requirements
b) Full retention of Supplier records and traceability
18) Compressed gas cylinder control procedure addressing the following as a minimum:
a) Isolated storage area, shaded and incorporating blast directional control provisions
b) Segregated areas for full, partial, and empty cylinder storage
c) Segregation of differing gasses
d) Specialist cylinder handling team that delivers, moves, and recovers cylinders
19) Pressure testing plans for each system or system component to be tested, defining the following:
a) Test medium – source, treatment, disposal
b) Test specimen structural stability
c) Stored energy release study and mitigations
d) Controlled entry test areas – cordoning, notices, enforcement
e) Positive isolation – removed sections, full rated blinding, double block and bleed, etc.
f) Physical disconnection from equipment and non-included components
g) Thermal input variation
20) Waste management and construction site cleanliness
a) Waste collection and receptacle schedule
b) Reuse / repurpose / recycle / dispose waste collection plan
c) Temporary detention areas
d) Clean site policy, plan, and procedures
e) Additional procedures as needed
21) Demobilization plan
a) Plan for disposal of all useable surplus bulk materials
b) Demobilization plans for the following:
i. Materials
ii. Construction equipment
iii. Construction workforces
iv. Management
8.6 Reports
2) Weekly expediting status report: less than 90 days from required-onsite (ROS) date and any
known issues
3) Three-week look-ahead report: status of actual vs. planned work completion tracked on a three-
week look ahead and one-week arrears bar chart schedule format with vertical delineation status
lines with arrow-indexing to identify current status by craft disciplines and by area
4) Weekly production report: actual vs. planned construction activities, labor productivity by crew,
craft or gang vs. USGC norms, changes in productivity from previous reports
5) Weekly quality report (Audit schedule and results of audits conducted, Corrective Action Request
and Nonconformity Report status showing (open, closed, past agree closure date),, inspection
witness and hold point requests including FAT/SAT’s with a one month look ahead and weekly
look ahead schedules, rejections, and reschedules)
6) Summary of notable events (achievements, milestones, work stoppages)
7) List of work permits planned within the following two weeks
8) Record of work packages completed versus total with one-month projection
9) Materials receiving, storage, preservation, traceability, and issue, including the following:
a) Update of expected delivery dates of tagged items, bulk materials, and prefabricated items
versus ROS schedule requirements
Shipping dimensions, packing protection, and bracing details
Receiving; over, short, and damaged verification; Positive Material Identification; storage;
preservation; and issue accountability
Construction consumables control
10) Site instruction status
9. Systems Completion
Systems Completion spans the entire life cycle of a project, from engineering to stable operations. It
is a multi-discipline, multi-team, and multi-organization activity with multiple interfaces requiring
careful management.
This section provides detail regarding administrative responsibilities of, and interfaces between,
COMPANY and CONTRACTOR in the execution of Systems Completion. Effective planning,
communication, and coordination must start early after CONTRACT award.
9.2.6 Commissioning
CONTRACTOR shall refer to GP 21-01-01 and other GP supplements for definitions of Static and
Dynamic Commissioning.
9.2.7 Handovers
CONTRACTOR's teams shall execute defined handovers of each system (e.g., from the Mechanical
Completion team to Static Commissioning team at Mechanical Completion, and from Static
Commissioning team to Dynamic Commissioning team after Static Commissioning).
1) Handovers shall occur as follows:
a) Each handover can proceed only with COMPANY approval
Each handover must be documented and certified by issuing the appropriate certificate and/or notice
ensuring the following:
i. All requirements have been met
ii. A minimal number of outstanding punchlist items remain
iii. None of the outstanding punchlist items are of a nature that could compromise
personnel safety or equipment integrity
iv. For a list of Systems Completion certificates and notices, refer to Appendix FI of
Section F – COORDINATION PROCEDURES.
9.2.12 Acceptance
Upon successful conclusion of the FACILITIES Performance and Acceptance Testing, data and
documentation transfer, CONTRACTOR-purchased spare parts stocked in Operations warehouse, and
CONTRACTOR-supplied logistics and infrastructure material transferred to Operations, COMPANY
will issue to CONTRACTOR an ACCEPTANCE NOTICE, certifying its agreement that the specified
criteria and any performance guarantees have been satisfied. This signifies the commencement of the
Warranty Period
28) Plans for providing dedicated radio communication channels for commissioning activities and an
adequate quantity of radios for CONTRACTOR's, COMPANY's, and Suppliers' representatives
and staff for support of commissioning activities.
9.4 Reports
CONTRACTOR shall provide regular progress reports to COMPANY as requested by COMPANY.
Progress reports shall include, as a minimum, current Systems Completion status with a one-month
projection.
On a monthly basis, CONTRACTOR shall report to COMPANY the following:
1) Status and discussion of punchlist items
2) Systems completed for handover, Turnover, and ACCEPTANCE, with a list of systems in service
10. Logistics
This section describes CONTRACTOR’s logistics responsibilities related to CONTRACTOR’s
procured materials and equipment, and CONTRACTOR's equipment and personnel for the WORK.
10.4 Reports
CONTRACTOR shall submit to COMPANY weekly and monthly reports that provide detailed
information with respect to all of the following:
1) Plan versus actual logistics schedule for procurement, transport, and supply chain management of
all materials and supplies, specifying associated cost
2) Status and location of all materials, supplies, and equipment
3) CONTRACTOR shall deliver these weekly and monthly reports in an electronic format that can
be submitted to a third-party data management company based on CONTRACTOR's system
capabilities and COMPANY request.
11) CONTRACTOR's Project Manager shall hold regular meetings with members of
CONTRACTOR's Project Organization to discuss, as a minimum, the following topics:
a) Cost control and forecasting
b) Trends and corrective actions
c) Effectiveness of corrective actions
d) CONTRACTOR's staff and organizational changes
e) Change control
12) The frequency and schedule for such meetings shall be agreed by CONTRACTOR and
COMPANY.
2) CONTRACTOR shall review the Cost Control Estimate with COMPANY prior to submittal for
the purpose of timely finalization of the CONTRACT PRICE BUDGET.
3) Prior to CONTRACTOR beginning WORK on the assigned portions of the detailed Cost Control
Estimate, CONTRACTOR shall meet with COMPANY to discuss and agree upon the following
items:
a) Design Basis – CONTRACTOR shall base the estimate on the JOB SPECIFICATION. The
estimate shall not reflect any anticipated design or execution changes.
b) Cost Basis – CONTRACTOR shall use the same cost basis for the entire Cost Control
Estimate. Factors that must be agreed by COMPANY and CONTRACTOR shall include the
following:
i. Wage rates and productivity factors
ii. Unit costs for common commodities
iii. Data sources for equipment costs
iv. Source of bulk material quantities and cost
v. Escalation based upon Project timing
vi. Foreign Exchange ("Forex")
Allowances – CONTRACTOR shall identify any and all allowances, takeoff factors, or
contingencies that CONTRACTOR normally uses as part of its estimating methods, together
with a description of the costs that these are intended to cover. CONTRACTOR must submit
all allowance to COMPANY for review and approval before incorporation into the Cost
Control Estimate.
Exclusions – CONTRACTOR shall review with COMPANY estimate content exclusions and
inclusions to define estimating responsibilities.
Code of Accounts – CONTRACTOR shall prepare the Cost Control Estimate using the same
code of accounts and area breakdown that CONTRACTOR will use to report and control the
costs and progress of the WORK. This code of accounts shall apply to CONTRACTOR's
accounting system. CONTRACTOR's code of accounts shall meet COMPANY's
requirements for the Project cost breakdown structure.
Supporting Documentation – CONTRACTOR shall provide supporting documentation and
information, as defined by COMPANY, for the Cost Control Estimate. Prior examples of
CONTRACTOR's control estimates and documentation will be used to gain agreement on the
information to be included in supporting documentation.
i. Material takeoff (MTO) data
ii. Equipment and materials quotes
iii. Historical performance information
iv. Direct and indirect labor costs
Review – In accordance with the timing prescribed by COMPANY, CONTRACTOR shall review
with COMPANY the Cost Control Estimate, or portions of the Cost Control Estimate.
Timing – Relevant details of the cost estimate must be available before any cost commitment is made.
These will include quantity estimates, as well as costs.
Release of Cost Control Estimate details – The detailed cost estimate, whether developed by
COMPANY or CONTRACTOR, shall be released incrementally if necessary.
CONTRACTOR shall grant COMPANY access to historical data and benchmarks that may have
been used by CONTRACTOR.
11.3 Reports
12.2.1 General
1) In accordance with Section 1 of Section F – COORDINATION PROCEDURES,
CONTRACTOR shall submit the following for COMPANY review and approval:
a) CONTRACTOR Schedule Basis Memorandum
CONTRACT Control Schedule
Schedule Control System
Schedule Development and Control Plan
90-Day Plan
2) Upon issuance of a CHANGE ORDER, CONTRACTOR shall incorporate approved changes into
the Current Control Schedule.
3) CONTRACTOR shall impose the same schedule and progress requirements in the CONTRACT
on Subcontractors and Suppliers.
4) CONTRACTOR shall submit to COMPANY CONTRACTOR's intended schedule control,
progress measurement, and data reporting procedure(s) for CONTRACTOR GROUP.
12.2.2 Access
1) CONTRACTOR shall provide COMPANY access, without restriction, to all information input to
and generated under CONTRACTOR's Schedule Control Systems, including, but not limited to,
planning, scheduling, progress measurement, work-hours, resources analysis, productivity data,
and benchmark data used to develop project schedules. CONTRACTOR may remove from
benchmark data any project names or other project-specific information. This access shall be for
data at any level, including interface data and data prepared by CONTRACTOR GROUP.
2) CONTRACTOR shall provide COMPANY with CONTRACTOR's schedule both in hard copy
and Microsoft Project file which shall include all information necessary to duplicate
CONTRACTOR's schedule, progress measurement, and resource requirements.
4) Permitting
5) COMPANY, partner, or government requirements
6) Management of interfaces
7) Local content activities
8) Equipment and bulk material delivery, including vendor data information
9) Resource availability
10) Workweek basis
11) Construction equipment and marine asset utilization
12) Weather assumptions and other schedule assumptions or allowances
13) Logistics
14) Brownfield activities
3) CONTRACTOR's schedule shall reflect the entire scope of WORK, including the WORK of
CONTRACTOR GROUP. Schedules shall provide sufficient detail in all areas of Project
execution (engineering, procurement, fabrication, construction, commissioning, transportation,
and installation) to enable monitoring and control of those execution areas impacted by key
Project issues.
4) CONTRACTOR shall identify Critical and Sub-Critical Paths.
5) Schedules shall be presented as time-scaled bar charts with an associated logic network, which
set forth the planned order and estimated dates for activities. Schedule networks shall be
thorough and complete and shall sequence all activities using schedule logic rules. Logic rules
include, but are not limited to, the following examples:
a) All activities shall have predecessors and successors (with the exception of the first and last
activity, milestones, etc.).
b) Schedules shall have one logical start and one logical finish.
c) For each activity, schedules shall identify activity type, calendar, and constraints.
d) Activity constraints, float constraints, and negative lags for establishing logic relationships
shall be minimized as agreed with COMPANY.
e) The use of expected finish dates shall be avoided for the purpose of the network update.
6) For each WORK SITE and Off Site, CONTRACTOR shall indicate the daily work-hours, work
week, shift schedule, scheduled facility shutdowns (if any), and holidays used to develop
schedules.
7) CONTRACTOR's schedules shall be structured to provide three activity code fields for
COMPANY's use, titled EM1, EM2, and EM3, and each of these fields shall be four characters in
length. COMPANY will provide the applicable activity coding to CONTRACTOR for inclusion
within these COMPANY code fields.
8) Schedules shall incorporate the SCHEDULE MILESTONES and payment milestones.
9) CONTRACTOR shall identify and provide a description of those activities associated with
material sources, Subcontractors, Suppliers, and offsite fabrication. The schedule shall show, as a
minimum, the following subcontracting and purchasing activities:
a) Preparation of the tender package, tendering period, tender evaluation and subcontract
award, engineering duration, field mobilization, and duration of field construction
Preparation of Request for Quotation (RFQ), bid review and clarification period, Purchase Order (PO)
issue date, receipt of vendor data, and delivery span for major equipment and materials including
sequential deliveries from a Supplier and required-onsite (ROS) dates.
10) Schedules shall include the following:
a) Identify potential constraints on execution
b) Facilitate monitoring and control of scheduled activities and timely identification of potential
problem areas
c) Show interfaces within the WORK, and between the WORK and all other key external
Project participants.
11) Schedule control activities will interface effectively with CONTRACTOR's Progress
Measurement System. Progress measurements shall be made in such a manner that the physical
progress of the WORK can be related easily to established SCHEDULE MILESTONES and
CONTRACTOR's Detail Schedule.
12) Schedules shall be resource-loaded to reflect distribution and resource leveling for the following:
a) External interfaces
b) CONTRACTOR-imposed and COMPANY-imposed limits used to develop the schedule
activity durations
c) CONTRACTOR shall periodically update resource loading and leveling.
13) To support CONTRACTOR's schedule, CONTRACTOR shall include time-resource (TR) sheets
for each activity, including the following:
a) A description of each activity and descriptions of the resources including work-hours,
materials, and equipment to be employed in completing each activity and the duration of time
for which the resources will be employed
b) Construction work-hours broken down by directs (by craft) and indirects, and by subcontract
c) Material and equipment descriptions including type and quantity of bulk materials to be
procured and installed by CONTRACTOR
14) CONTRACTOR shall include plan versus actual histograms and forecast histograms of
engineering resources (by discipline), project management resources, direct resources (by craft),
subcontracts, indirects, and total resources for each major WBS area. These histograms shall
include the following:
a) Early and late loading
b) Staffing adjusted for productivity
c) Productivity forecasts through completions
d) Work-hours per percent complete
d) Construction durations based upon estimated design quantities shall be updated by replacing
the estimated design quantities with actual quantities installed each period and
CONTRACTOR's material takeoffs.
e) Construction activities shall be resource loaded with work-hours and updated with spent-to-
date and forecasted-to-complete hours.
f) As actual fabrication or construction progress and productivity data becomes available, it
shall be reflected in activity durations. This analysis will incorporate such items as
considerations of resource availability, remaining overtime/shifting flexibility as agreed with
COMPANY, and work face availability (by craft).
g) Latest status of major CONTRACTOR Internal and External Interfaces shall be included.
h) Latest status of installation vessels (for offshore projects) shall be included.
3) CONTRACTOR shall progress the WORK and forecast the remaining duration of each activity
on CONTRACTOR's Detail Schedule and compare the forecasted COMPLETION DATE to the
SCHEDULED COMPLETION DATE.
4) CONTRACTOR's Detail Schedule shall be updated to include as a minimum, resources, progress,
quantities, and remaining durations for all activities, including data from peripheral databases.
The activities must be updated with a minimum of the following five fields:
a) The activity actual start date
b) The activity actual finish date
c) Physical percentage progress earned
d) Remaining duration to complete the activity in progress (a discipline engineer's or craft
supervisor's estimate of the required working time for completion of the task. determined by
remaining work, and availability of resources, materials, drawings, etc.)
e) Earned man-hours (cumulative)
f) Progress measurement shall use established budgeted work-hours for each activity or
deliverable.
g) Rules of credit shall allow for rework when measuring progress. No progress-measurable
deliverable should be given full credit until rework for that deliverable has been completed.
h) Progress shall be calculated by measuring the proportion of actual WORK accomplished
towards completion of given Project deliverables or activities, and shall not be calculated by
spent versus budgeted work-hours.
i) Physical progress measurements shall exclude home office and field support functions such as
project management, administration, project controls, engineering office follow-up during
construction, and site management, supervision, and indirect support.
j) The method of earning progress and activity progress milestones/rules of credit shall be
subject to COMPANY's review and approval, and shall not be changed without COMPANY's
approval.
2) CONTRACTOR shall monitor and notify COMPANY of the following:
a) Significant changes during the reporting period, special actions being implemented or
recommended, and the outlook for activities that will be started or finished during the next six
to eight weeks.
b) Schedule delays and deviations, as well as impacts to the Current Control Schedule.
c) Changes to Critical Path and Sub-Critical Paths
d) Activities on standby or hold
3) CONTRACTOR shall develop progress "S" curves showing planned, actual, and forecasted
progress (cumulative and by period) for each of the major elements of measurable items. The
forecast element of the "S" curves is derived from the updated CONTRACTOR's Detail Schedule.
4) CONTRACTOR shall provide units of measure, actual quantities installed overall, quantities
installed in the current period, forecasted quantities at COMPLETION, and percent of physical
progress (defined as actual quantities completed divided by forecasted quantities at completion).
5) When the WORK is 85 to 95 percent complete, CONTRACTOR shall provide run-down curves
that reflect the remaining quantities to be liquidated. Sufficient backup information shall also be
available to show location of actual quantities installed.
6) For Mechanical Completion and commissioning, CONTRACTOR shall report progress based on
prioritized systems. CONTRACTOR's Detail Schedule shall reflect prioritized Systems
Completion consistent with COMPANY's system priorities, including Mechanical Completion,
Static Commissioning, and Dynamic Commissioning to Systems. Skyline charts reflecting
System handover status shall be used for reporting.
7) CONTRACTOR shall develop histograms indicating actual-to-date, planned, and forecasted
resources by month. The resource projections shall include production engineering by discipline
and principal construction requirements by craft or by Subcontractor resources. Histograms
should show equivalent resources adjusted for work-week differences
8) CONTRACTOR shall develop tracking profiles that show actual-versus-planned productivity and
forecasted productivity for production engineering (by discipline) and construction activities (by
craft or subcontract).
11) How CONTRACTOR's schedule control activities interface with progress measurement, cost
control activities, and organizations.
12) How resource analysis will consider the performance to date versus the plan, including planned
productivity patterns throughout engineering, fabrication and construction, use of overtime and
multiple shifting to allow better use of available resources or the adding additional resources, and
other corrective actions to meet Project schedule requirements.
13) The frequency of updates (and responsibility for updates), and level of detail for each of the
various Project schedules CONTRACTOR shall develop to control the execution of the Project.
14) Details of CONTRACTOR's Progress Measurement System to be applied to the WORK, and how
planned progress curves will be developed.
15) The method of earning progress and developing activity progress milestones/rules of credit.
16) How CONTRACTOR will measure, verify, and report physical progress of each of the various
activities or groups of activities in engineering (specifically addressing use of 3D CADD models),
procurement, logistics, fabrication, construction, Systems Completion, operations readiness and
other major activities related to the WORK (e.g., permitting / regulatory).
17) The method for weighting and combining individual craft/discipline progress measurements to
arrive at the overall progress assessments for engineering, procurement, fabrication, construction,
and other major activities related to the WORK. Progress weightings shall be subject to
COMPANY's review and approval and shall not be changed without COMPANY's prior written
approval.
18) Procedures within CONTRACTOR's organization for review and verification of progress
measurement information prepared at each WORK SITE.
19) The method for recognizing the impact of rework on apparent progress during engineering,
procurement, fabrication, and construction, and the method for specifically progressing and
tracking the rework.
20) The methods and procedures for incorporating the effects of CHANGE ORDERS on the
assessment of progress.
12.4 Reports
COMPANY and CONTRACTOR will agree on a reporting calendar, which will include the reporting
cutoff dates for CONTRACTOR GROUP and report issue dates
iv. Report units of measure, actual quantities installed overall, quantities installed current
period, forecasted quantities at COMPLETION, and percent physical progress
(defined as actual quantities/forecasted quantities to complete)
v. Report run-down curves, which reflect the remaining quantities to be liquidated.
Sufficient backup information shall also be available to show location of actual
quantities installed
Report Mechanical Completion and commissioning on prioritized systems based methodology, and
curves/tables of the liquidation of punchlist items, e.g., total and number completed by unit checking,
pressure testing, function testing, and commissioning of the installed WORK. Skyline charts
reflecting System handover status shall be used for reporting.
Report readiness for operations activities associated with development of readiness for operations
documentation including training manuals, operations and maintenance procedures, and other
maintenance, reliability, and surveillance data.
6) Histograms indicating actual to date, planned, and forecasted resources by month. Histogram or
table with comparison of direct, indirect, and total personnel by discipline or craft, between the
number of personnel actually engaged on the WORK and the number planned.
7) Graphs showing actual-versus-planned and forecasted productivity for production engineering by
discipline and construction activities by craft or Subcontractor.
8) Monthly analysis of the progress of the WORK as compared to the Current Control Schedule with
particular emphasis on those activities on the Critical and Sub-Critical Paths.
Term Definition
Change Any Revision or Contract Change.
Contract Change A revision to JOB SPECIFICATION, a revision to elements of
WORK already completed or being performed, a deletion of WORK
already authorized additional goods or services requested by
COMPANY of CONTRACTOR, revisions to Payment Milestones or
Schedule Milestone requirements or dates. All Contract Changes
require COMPANY approval.
Change Inquiry A request by COMPANY for CONTRACTOR to evaluate cost and
schedule implications of a potential Contract Change.
Change Proposal CONTRACTOR's proposal for a Contract Change, including cost and
schedule impacts and assessment of risk including health, safety,
environmental, regulatory, and technical implications.
Change Order Company's formal authorization to Contractor for execution of a
Contract Change. It represents full and complete compensation for the
change and any cumulative effect that the Contract change may have
on the overall WORK.
Change Notice CONTRACTOR's written notice to COMPANY to indicate in their
opinion that a part or parts of the WORK is entitled to Contract
Change in accordance with the Principal Document, Article 7.2.
Deviation Future developments to the JOB SPECIFICATION. These generally
result from detailed design progress, data from vendors or
subcontractors. The Principal Document outlines the criteria to
determine if a contract change is necessary.
Revision Any modification to a deliverable after it has been approved.
Waiver Acceptance of an existing nonconformance to the JOB
SPECIFICATION. The Principal Document outlines the criteria to
determine if a contract change is necessary.
2) Change Proposals shall be numbered sequentially and shall include the following:
a) A detailed description of the requested revision to the JOB SPECIFICATION and the services
required, including supporting documentation and references (e.g., previously approved
Change Request).
b) The estimated adjustment, if any, to the CONTRACT PRICE BUDGET, including a detailed
estimate of the quantities of materials, equipment, and resources related to the change. These
items shall be defined on new or revised cost, time, resource (CTR) sheets. The detailed
estimate will include quantity takeoffs and shall be broken down into categories aligned with
the CONTRACT PRICE BUDGET.
c) The proposed adjustment to any FEE and supporting calculations.
d) The estimated adjustment, if any, to the SCHEDULE MILESTONES, SCHEDULED
COMPLETION DATE or forecasted COMPLETION DATE, with appropriate accompanying
backup data.
e) At COMPANY's discretion, CONTRACTOR shall provide a proposed schedule and
associated logic network, which demonstrates new tasks, modifications to existing tasks, and
the estimated work hours associated with the Change Proposal.
f) A risk assessment in accordance with Section 16., including impact on any completed risk
assessments.
g) The latest date that authorization can be given without affecting the SCHEDULED
COMPLETION DATE or impacting the SCHEDULED COMPLETION DATE in the
Change Proposal. CONTRACTOR shall target timely completion of its proposal so as to
allow COMPANY 21 calendar days for review and approval before impacting the above
latest date of authorization.
13.2 Reports
1) CONTRACTOR shall issue the Change Order Log(s) to COMPANY at least monthly and as may
otherwise be requested by COMPANY.
2) CONTRACTOR shall report to COMPANY on a monthly basis the status of potential changes for
which CONTRACTOR has not yet issued a Change Request to COMPANY, along with
CONTRACTOR's estimate of the effects to any activities involved and impact on the Critical
Path schedule.
14. Quality
14.2.3 Execution
14.2.3.1Control of WORK
1) CONTRACTOR shall ensure that required documents related to quality—such as drawings,
specifications, Inspection and Test Plans (ITPs), and procedures—are of latest issue, complete,
and available, with all required comments resolved and/or with required approvals, prior to start
of the corresponding WORK.
2) CONTRACTOR shall ensure appropriate controls are implemented in accordance with approved
procedures and plans.
14.2.3.3Purchasing Documentation
1) CONTRACTOR shall ensure a Quality representative verifies that documentation used for
purchasing materials, equipment, and fabricated items includes all quality requirements, in
accordance with GP 20-01-04 and other GP supplements.
2) CONTRACTOR shall obtain from COMPANY or prepare Criticality Ratings for systems and
their subcomponents, purchased materials, equipment, and fabricated items in accordance with
GP 20-01-04 and other GP supplements. In the event CONTRACTOR prepares Criticality
Ratings, CONTRACTOR shall obtain COMPANY approval of the assigned Criticality Ratings,
including approval for any addition or revisions, prior to the start of related WORK.
14.2.3.4Source Inspection
1) CONTRACTOR shall be responsible for Source Inspection of purchased equipment, materials,
and fabricated items in accordance with GP 20-01-04 and other GP supplements.
2) CONTRACTOR shall determine inspection levels and obtain written COMPANY approval of
inspection levels prior to placement of purchase order. Source Inspection assignment packages
and Source Inspector selection are subject to COMPANY approval prior to start of Source
Inspection activities. CONTRACTOR shall not change the nominated Source Inspector unless
agreed in writing by COMPANY.
3) CONTRACTOR shall perform Source Inspections of purchased equipment, materials, and
fabricated items in accordance with the approved ITPs.
2) CONTRACTOR shall support COMPANY and any COMPANY third parties, including
providing access, notification, and CONTRACTOR resources necessary to perform quality
activities.
3) CONTRACTOR shall provide for unrestricted safe access for COMPANY's Quality Organization
and any COMPANY third parties to any WORK facility, personnel, WORK areas, elevated
access ways (such as scaffolding or man lifts), and Project documentation, as required to facilitate
physical cross checking, audit, assessment, and verification activities.
4) CONTRACTOR shall provide sufficient notification (as a minimum, 24 business hours of notice)
via a Request for Inspection (RFI) to COMPANY and any COMPANY third parties to enable
participation in inspections and tests at fabrication and construction sites.
5) CONTRACTOR shall provide sufficient notification (as a minimum, five days of notice) to
COMPANY and any COMPANY third parties to participate in inspections and tests at Supplier
facilities. CONTRACTOR shall provide notification within one business day of receiving
inspection notification from Supplier.
6) CONTRACTOR shall immediately upon COMPANY's request re-perform inspections and tests
solely at CONTRACTOR expense, regardless of findings, in cases where CONTRACTOR fails to
provide required notice of inspection or fails to provide safe access to WORK and proceeds
independently with inspections and testing and/or subsequent WORK.
14.2.3.8Quality Audits
1) CONTRACTOR shall perform quality audits of WORK. CONTRACTOR shall ensure Quality
audits are conducted by qualified personnel independent of those who perform or directly
supervise the activity being audited.
2) CONTRACTOR shall include COMPANY, at COMPANY's discretion, in CONTRACTOR's
audit planning and execution.
14.3.7 Procedures
1) CONTRACTOR shall establish and provide to COMPANY, directly or via Subcontractors and
Suppliers, quality procedures that comply with the JOB SPECIFICATION, GP 20-01-04 and
other GP supplements, and that are sufficient for monitoring all aspects of Quality Management
for the WORK.
2) CONTRACTOR shall identify and notify COMPANY of procedures that require COMPANY
approval, using standard industry documents such as distribution matrices, weld procedure
matrices, etc. CONTRACTOR shall manage the development and approval process such that
procedures are approved and available prior to the start of related WORK.
3) As a minimum, procedures shall cover the following:
a) Design change control
b) Qualification of Subcontractors and Suppliers
c) Management of Source Inspection, including the following:
I. Determining the level of Source Inspection
II. Assigning, managing, coordinating, and reporting Source Inspection activities,
including the tools, databases, and reporting for Source Inspection management,
status, planning, and coordination
III. Monitoring the effectiveness of the Source Inspection program and of individual
Source Inspectors
d) Notification to COMPANY for COMPANY to participate in inspections and tests at Supplier
facilities and at fabrication and construction sites.
e) Management of Positive Material Identification (PMI) for materials subject to PMI controls
in GP 29-01-01 and GP 20-01-04.
f) Management of Material Traceability for compliance with GP 29-01-34 & GP 29-01-34S
g) Oversight of Subcontractors, including review and approval of Subcontractor documents,
assessing Subcontractor work processes, inspecting and testing WORK performed by
Subcontractors, and review and acceptance of Subcontractor records.
h) Management and assessment of material and equipment handling, storage, shipping,
receiving inspection, material control including segregation, markings and tracking, and
preservation, including COMPANY-supplied material and equipment.
i) Where the ability of the work process to conform to requirements is proven through process
qualification, validation and control of special processes, such as the following:
i. Welding
14.4 Reports
1) CONTRACTOR shall determine, collect, and analyze Quality Management data. On a monthly
basis as a minimum, CONTRACTOR shall prepare and submit a status report—for each site and
for the overall Project—specific to Quality Management, in accordance with GP 20-01-04 and
other GP supplements. CONTRACTOR's monthly report shall include quality activities
performed and those planned for the next month, as well as a list of all nonconformities and
metrics per discipline.
2) CONTRACTOR shall submit to COMPANY report frequency, format, and type of report content
to be used 30 days in advance of initiation of site activities.
3) CONTRACTOR shall report, as a minimum, quality issues requiring management attention,
status of activities required to manage quality of WORK, status of nonconformities, quality audit
status and results, quality metrics and trends (e.g., rework rates by discipline, etc.), inspection and
test status, Mechanical Completion check sheet status, and planned Quality Management
activities.
4) Reports shall include relevant information from Subcontractors and Suppliers.
5) COMPANY will review for approval the final Risk Assessment report for distribution and
implementation.
6) COMPANY will audit CONTRACTOR's risk register periodically to ensure documentation
required for action item closure is adequate and complies with COMPANY Project Risk
Management Plan.
7) Risk reduction actions shall be followed to COMPLETION with the use of an action tracking
System that is acceptable to COMPANY. The action tracking report shall show priority,
responsibility, and timing for completion of each action. COMPANY may choose to provide the
tracking System or provide a specific format for the tracking System. Deviations from agreed-
upon actions and timings shall be approved and endorsed by the levels of CONTRACTOR and
COMPANY management that approved and endorsed the original actions and timings.
8) Action tracking reports shall be submitted to COMPANY monthly. At the completion of each
risk assessment and its associated response actions, the results of the risk assessment and response
actions shall be communicated in a closeout report to those affected
those incidents, identifying additional potential mitigation measures, and assessing the risk of
each scenario with potential mitigation measures in place)
g) Agenda overview
h) Deliverables
i) Roles and responsibilities of sponsor, risk coordinator, and team members
5) CONTRACTOR shall comply with the following risk assessment requirements:
a) The members of risk assessment teams shall be qualified for ensuring risks are correctly
identified and assessed.
b) Risk assessments shall include the identification of potential risk scenarios associated with
Project execution and operation, including, but not limited to, risks related to the following:
i. Safety, health, and environment (SHE)
ii. Labor relations
iii. Community relations
iv. Financial impact on COMPANY
a) Risk assessments shall include the identification of environmental hazards and the completion
of approved risk reduction plans for the WORK, incorporating, as necessary, control
measures into CONTRACTOR's Plans.
All risk assessments shall include consideration of human and health factors.
Risk assessments shall be conducted at least 35 calendar days prior to their related Project milestones
or activities to allow resolution of risks without schedule disruption.
Charters, pre-read information (including procedures for the activities being assessed), and all
required drawings shall be issued at least 15 calendar days prior to the risk assessment commencing.
6) For the evaluation, resolution, tracking, and incorporation into execution of the Project findings or
any risk reduction actions resulting from COMPANY's risk, Loss Prevention, or technical safety
studies, CONTRACTOR shall use the following:
a) COMPANY's Risk Matrix (). The use of numbering in the Risk Matrix is internal to
COMPANY and indicates the requirements for endorsement by COMPANY management of
specific hazard consequence and probability combinations.
b) COMPANY's Risk Management Plan.
7) Before any risk reduction action commences, CONTRACTOR shall submit risk scenarios,
evaluations, and proposed risk reduction actions to CONTRACTOR's management for approval
and then to COMPANY for endorsement. COMPANY's Risk Management Plan outlines the
approval and endorsement process.
8) CONTRACTOR shall assess all credible risk scenarios for possible risk reduction by the
following (in order of preference):
a) Elimination of the hazard source
b) Reduction of the likelihood or mitigation of the consequences
c) Control of the resultant impact or damage
d) Emergency response and recovery systems
9) Immediately after design freeze and preceding construction and fabrication, CONTRACTOR
shall conduct HAZOPs based on the detailed design and Supplier data.
10) CONTRACTOR shall submit for COMPANY approval CONTRACTOR's risk assessment
facilitator. COMPANY may elect to provide a facilitator for risk assessments, HAZOPs, and
safety integrity level (SIL) studies.
3) presents the minimum risk assessment activities with supporting Loss Prevention
activities/studies planned for this Project. The full list of risk assessments and Loss Prevention
studies is included in COMPANY's Risk Management Plan. CONTRACTOR shall use
COMPANY Guidance Documents as required.
Table F0-5: Risk Assessments, Loss Prevention Activities, and Human Factors Activities
Activity Description When Responsible
Risk Detailed Design Focuses on detailed piping and instrumentation After design freeze, CONTRACTOR
Assessments HAZOP diagrams (P&IDs) / plot plans to ensure equipment can prior to Construction
be operated in a safe and efficient manner. Emergency
shutdown (ESD), safe control, and alarm strategies are
essential aspects.
Detailed Design Focuses on detailed P&IDs / plot plans to ensure After design freeze, CONTRACTOR
HAZOP – Supplier equipment can be operated in a safe and efficient prior to Construction
Packages manner. ESD, safe control, and alarm strategies are
essential aspects.
Construction Risk Addresses the major hazards associated with Prior to Construction CONTRACTOR
Assessment construction and fabrication activities, including major and Fabrication
lifts and modifications of the FACILITY.
Hookup & Addresses the major hazards associated with hookup & Prior to Hookup CONTRACTOR
Commissioning Risk commissioning for the Project.
Assessment
Transportation and Addresses the risks associated with transportation of After completion of CONTRACTOR
Installation Risk equipment and facilities to the field location and execution plan and
Assessment installation. installation procedures;
Prior to transportation
and installation
SIMOPS Risk To assess the risk associated with concurrent activities Prior to SIMOPS CONTRACTOR
Assessment on the site activities
15.4 Reports
1) CONTRACTOR shall submit the following reports, as a minimum, to COMPANY:
a) CONTRACTOR shall update on a monthly basis forecasted dates of existing and newly
proposed risk assessment activities/studies as well as the activities that have been completed
monthly.
b) CONTRACTOR shall use the COMPANY-provided standard templates (in Appendix FG of
Section F – COORDINATION PROCEDURES) to report and document risk assessments
and risk action item status.
c) Using the standard templates for roll-up reporting, CONTRACTOR shall submit the
following information, as a minimum, to COMPANY on a monthly basis:
i. Assessments and studies planned vs. completed
ii. Approval and completion status of action plans
iii. The number of risk assessments formally closed out
iv. The number of unresolved Action Plans
d) CONTRACTOR shall submit as part of its monthly report a list of assessments with proposed
dates.
e) CONTRACTOR shall include progress and description of risk management activities and
issues in the summary monthly report.
16. Safety
CONTRACTOR is responsible for managing safety aspects of the WORK and COMPANY's
oversight and coaching role shall not create an obligation on COMPANY and shall in no way relieve
CONTRACTOR or its subcontractors of their responsibilities for managing safety aspects of the
WORK.
Figure F17-1 provides an overview of the high level safety roles between COMPANY,
CONTRACTOR, and it subcontractors.
Figure F0-2: High-Level Safety Roles and Relationships among COMPANY, CONTRACTOR,
and Subcontractors
subcontractors. CONTRACTOR shall update the document to address COMPANY’s feedback before
issuing for use.
Sections 17.2 through 17.3.7 of Section F – COORDINATION PROCEDURES describe the
minimum Project-level safety requirements that CONTRACTOR shall address during the planning
and execution phases of the WORK. CONTRACTOR shall incorporate these requirements into its
Project Safety Management Plan.
Safety requirements for major WORK SITES are described in Section 17.3.2. of Section F –
COORDINATION PROCEDURES. Safety requirements for other WORK SITES are described in
Section 17.3.5. of Section F – COORDINATION PROCEDURES.
1) Safety Leadership
CONTRACTOR shall work with COMPANY to mutually develop and implement an integrated
collection of safety leadership processes on the Project. The objective is to collaborate early and often
to achieve world class safety performance, which may require CONTRACTOR and its subcontractors
to implement safety improvement initiatives with support from COMPANY. The overall approach is
to create and maintain a high level of alignment between CONTRACTOR and COMPANY senior
and project management personnel through the systematic application of the safety leadership
processes described in this Section 17.3.1. For clarity, robust safety leadership from Project level
management is intended to supplement, but not replace, robust safety leadership from WORK SITE
management.
2) Safety Leadership Roadmap
CONTRACTOR shall develop and update quarterly a Safety Leadership Roadmap to describe how
CONTRACTOR and COMPANY will implement the various safety leadership processes, as well as
any Project-specific improvement initiatives resulting from the implementation of such processes.
The Safety Leadership Roadmap supplements, but does not replace, the Project Safety Management
Plan.
CONTRACTOR shall initially submit a draft Safety Leadership Roadmap to COMPANY with its
Technical Proposal.
The draft Safety Leadership Roadmap shall reflect any alternative proposals that CONTRACTOR
would like COMPANY to consider regarding scope or sequencing. CONTRACTOR shall describe
the rationale for any alternative proposals. COMPANY shall review and approve the draft Safety
Leadership Roadmap after CONTRACT AWARD.
The approved Safety Leadership Roadmap shall be stewarded by the COMPANY-sponsored Safety
and Health Leadership Team utilized on the Project.
3) Safety and Health Leadership Team
CONTRACTOR shall actively participate in a Project-level Safety and Health Leadership Team
comprising senior project management and senior project safety personnel from COMPANY,
CONTRACTOR, and selected major subcontractors.
CONTRACTOR shall work together with COMPANY to develop a charter for the team. The Safety
and Health Leadership Team meetings will serve as a forum to further define, implement, and steward
many of the safety leadership processes described in this section.
Refer to Section 4.8 of NGER-ED-BSPDS-000001 to review specific requirements for Safety and
Health Teams.
CONTRACTOR shall plan on attending such meetings on a monthly basis.
4) Gap Analysis
COMPANY shall perform a Gap Analysis on CONTRACTOR’s (and selected major subcontractors’)
existing safety management system(s), which shall be submitted to COMPANY immediately
following CONTRACT AWARD.
The focus will be verification of the existence of written policies, procedures, processes, and work
practices deemed critical to success.
During the Safety Leadership Kickoff Workshop (described in Section 17.3.1, #6 of Section F –
COORDINATION PROCEDURES), CONTRACTOR and COMPANY shall use the results of the
Gap Analysis to identify mutually agreed upon safety improvement initiatives to be implemented.
5) Cold Eyes Review
To supplement the Gap Analysis, COMPANY may decide to perform a Cold Eyes Review (CER) of
CONTRACTOR’s (and selected major subcontractors’) existing safety management system(s) in
order to determine the effectiveness of implementation of the various policies, processes, procedures,
and work practices. A CER is a comprehensive, week-long safety assessment that utilizes personal
interviews, field observations, and documentation reviews to evaluate aspects related to culture,
management systems, and performance. COMPANY may request CONTRACTOR to nominate
personnel to participate in the CERs.
If performed immediately after CONTRACT award, the CER results will be evaluated at the Safety
Leadership Kickoff Workshop (in conjunction with the Gap Analysis) and any resulting safety
improvement initiatives shall be incorporated into the Safety Leadership Roadmap.
If performed during execution of the WORK, the CER results will be evaluated by the following
teams, and any resulting safety improvement initiatives shall be incorporated into the Safety
Leadership Roadmap:
a) Safety and Health Leadership Team
b) Project level Safety and Health Team
c) WORK SITE Safety and Health Team
6) Safety Leadership Kickoff Workshop
After CONTRACT award and performance of the Gap Analysis and CER (if performed),
COMPANY and CONTRACTOR shall mutually conduct a two-day Safety Leadership Kickoff
Workshop attended by COMPANY and CONTRACTOR project sponsors, senior project
management, senior safety personnel, and key personnel from selected major subcontractors. The
objectives of the workshop include:
a) Review leadership principles and the safety leadership processes included in the draft Safety
Leadership Roadmap
b) Define the Project safety vision, mission, and guiding principles
c) Review results of the Gap Analyses and (if performed) CERs
d) Agree upon Project safety improvement initiatives
e) Discuss success criteria for safety and how progress will be monitored
f) Discuss communication of expectations to others
g) Finalize the draft Safety Leadership Roadmap
When feasible, COMPANY and CONTRACTOR senior management shall solicit input on
improvement initiatives from COMPANY and CONTRACTOR WORK SITE management before
finalization to ensure buy-in and alignment.
7) Safety Leadership and Cultural Diagnostic Surveys
CONTRACTOR shall describe the structured means utilized to communicate and frequently reinforce
COMPANY's and CONTRACTOR's safety expectations, including but not limited to:
a) Participating in Safety Meetings
b) Participating in Safety and Health Teams
c) Performing Safety Walkthroughs
d) Communicating expectations during Safety and Health Orientations
e) Participating in Safety and Health Kickoff Meetings
CONTRACTOR shall implement Safety and Health Kickoff Meetings in accordance with the
requirements of Section 4.9 of NGER-ED-BSPDS-000001.
CONTRACTOR shall participate in COMPANY facilitated Safety and Health Kickoff Meetings.
No later than 60 calendar days after CONTRACT award, CONTRACTOR shall facilitate a Project
Safety and Health Kickoff Meeting to communicate safety expectations to its entire Project level
team.
12) Safety and Health Teams
CONTRACTOR shall implement Safety and Health Teams in accordance with the requirements of
Section 4.8 of NGER-ED-BSPDS-000001.
CONTRACTOR shall work collaboratively with COMPANY to develop a Safety and Health
Governance Model using Figure F17-2 as a guide that identifies the various types of multi-tier Safety
and Health Teams that will be utilized on the Project and how such teams will interface with each
other. The Safety and Health Governance Model shall consider the size, complexity, duration,
organizational structure, region, and contracting strategy of the WORK, as well as the maturity level
of CONTRACTOR and its subcontractors.
Requirements for WORK SITE Safety and Health Teams and Worker Safety and Health Teams are
included in Section 17.5.1.3 of Section F – COORDINATION PROCEDURES.
13) Safety Staffing
CONTRACTOR shall provide one qualified, full-time, and dedicated Project-level Safety Manager to
provide oversight for Project-level safety considerations throughout the planning and execution
phases of the WORK. In accordance with Article 4 of the Principal Document, CONTRACTOR’s
Safety Manager is a key position and shall be staffed immediately upon CONTRACT award with a
COMPANY-approved candidate.
Upon request of CONTRACTOR and with COMPANY approval, the scope of CONTRACTOR
Safety Manager’s responsibilities may be broadened to cover related disciplines (e.g. health,
environmental, security) if:
a) As a minimum, the nominated candidate shall possess a good first degree in Engineering OR the
Sciences in addition to NEBOSH International Diploma Certificate or its equivalent (Certified
Safety Professional) with not less than 15 years relevant experience.
b) The candidate has the knowledge, skills, and experience to effectively manage such disciplines
c) Iii) Specialist staff are sourced either full-time or part-time (as appropriate) to provide the
nominated candidate with technical support and the required levels of manpower to provide
adequate management of the related disciplines
d) CONTRACTOR shall provide and describe the following in its Project Safety Management Plan:
e) Project-level safety organization chart
f) Project-specific roles and responsibilities for CONTRACTOR Project-level staff (e.g. managers,
supervisors, safety advisors)
14) Safety and Health Training
CONTRACTOR shall implement a Safety and Health Training process in accordance with the
requirements of Section 4.1 of NGER-ED-BSPDS-000001.
CONTRACTOR shall provide a Project-level Safety and Health Training Plan to COMPANY for
review and endorsement no later than 60 calendar days after CONTRACT award. This plan shall
broadly describe any Project-specific training courses that will be required or otherwise provided to
CONTRACTOR and subcontractor personnel (including expatriates, home country nationals, and
other-country nationals) to assure they have the knowledge and skills to perform their jobs safely.
CONTRACTOR's Project-level Safety and Health Training Plan shall specifically include Safety
Leadership Training for managers and supervisors as described in Section 17.4.1.7 of Section F –
COORDINATION PROCEDURES.
15) Safety and Health Orientation
CONTRACTOR shall implement a Safety and Health Orientation process in accordance with the
requirements of Section 4.2 of NGER-ED-BSPDS-000001.
CONTRACTOR shall perform Project level Safety and Health Orientations to ensure that all
personnel supporting planning and execution of the WORK are adequately familiarized with
COMPANY and CONTRACTOR safety and health requirements and expectations when they
mobilize.
CONTRACTOR shall perform several types of Project-level Safety and Health Orientations
specifically customized for different audiences including the following:
a. Management, coordinators, and supervisors
b. Workers
At its sole discretion COMPANY reserves the right to provide Project-level personnel (e.g., line
managers, safety advisors, technical specialists) to support the WORK SITE Incident Management
process.
CONTRACTOR shall communicate the status of corrective actions to COMPANY Project-level
personnel on a weekly basis until closure.
CONTRACTOR shall share learnings with COMPANY Project-level personnel through the use of an
SSHE Alert system.
19) SSHE Performance Measurement and Reporting
CONTRACTOR shall measure and report leading and trailing SSHE performance indicators in
accordance with the requirements of Section 4.6 of NGER-ED-BSPDS-000001.
CONTRACTOR shall utilize Safety and Health Teams as the primary forums for stewarding SSHE
performance indicators. The Project-level Safety and Health Team shall develop their own safety and
health leading performance indicators to support the leadership activities and desired behaviors
required to adequately support the WORK SITES. These leading performance indicators shall be
developed in alignment with the Project Safety and Health Team’s charter objectives.
In addition to the trailing SSHE performance indicators described in Section 4.6 of NGER-ED-
BSPDS-000001, CONTRACTOR shall work with COMPANY to develop and steward Project-level
leading SSHE performance indicators. Such indicators should supplement, but not replace, the
leading SSHE performance indicators utilized at the WORK SITES. CONTRACTOR shall measure,
consolidate, and report Project-level leading SSHE performance indicators to COMPANY not later
than three calendar days after the close of the month.
In addition to the SSHE performance indicators described in Section 4.6 of NGER-ED-BSPDS-
000001, CONTRACTOR shall implement the following leading and trailing SSHE performance
indicators:
a) Safety Leadership (Training and Workshops)
b) Hazard Management (Job Safety Analysis and Personal Risk Assessment)
c) O&I
d) Near Miss and Hazard Reporting
e) Additional leading indicators for consideration include:
f) Number of Management Safety Walkthroughs Performed
g) Average Housekeeping Assessment Score
h) Average Quality of Job Safety Analyses (JSAs) Performed
i) Number of Tool Box Talks Performed
j) Average turn-around time to address Reported Unsafe Conditions
Additional considerations for leading indicators are as follow:
a) Will be WORK SITE specific.
b) May focus on qualitative and/or quantitative measures.
c) Should evolve over time as cultures, Systems, and Processes mature.
d) Provide measurement on key focus areas requiring improvement.
e) Attempting to steward too many leading indicators may be ineffective.
CONTRACTOR shall set aggressive yet attainable targets for Project-level leading SSHE
performance indicators. CONTRACTOR shall evaluate Project-level leading SSHE performance
indicator trends against the established targets on a monthly basis as a minimum.
CONTRACTOR shall develop and steward structured action plans to address Project-level leading
SSHE performance indicator trends that are not meeting established targets. CONTRACTOR shall
communicate Project-level leading SSHE performance indicator trends to Project-level personnel on a
monthly basis at minimum.
20) Safety and Health Assessments and Audits
CONTRACTOR shall implement Safety and Health Assessments and Audits in accordance with the
requirements of Section 4.7 of NGER-ED-BSPDS-000001.
CONTRACTOR shall provide a Project-level Safety and Health Assessment and Audit Plan to
COMPANY for review and endorsement no later than 90 calendar days after CONTRACT award.
CONTRACTOR shall provide a Charter for each Safety and Health Assessment and Audit to
COMPANY for review and endorsement.
21) Lessons Learned and Best Practices
CONTRACTOR shall facilitate a Project-level workshop after CONTRACT award in order to capture
and evaluate lessons learned and best practices from previous projects and apply them into the safety
planning process. COMPANY shall participate at its sole discretion.
CONTRACTOR shall capture, evaluate, and apply as appropriate those Project-level lessons learned
and best practices that are identified throughout execution of the WORK.
CONTRACTOR shall facilitate a Project-level workshop no later than sixty days after completion of
the WORK in order to capture lessons learned and best practices associated with the Project.
COMPANY shall participate at its sole discretion. CONTRACTOR shall include the lessons learned
and best practices in the Project-level Final Safety Report described in Section 17.4.13 of Section F –
COORDINATION PROCEDURES.
22) Final Report
CONTRACTOR shall develop a Final Safety Report in accordance with the requirements of Section
4.37 of NGER-ED-BSPDS-000001.
CONTRACTOR shall forward a Project-level Final Safety Report to COMPANY no later than 90
calendar days after the COMPLETION of the WORK.
CONTRACTOR shall plan and execute WORK performed at major WORK SITES as well as other
major work scopes and in accordance with the safety requirements described in Section 16.3.2 of
Section F – COORDINATION PROCEDURES.
CONTRACTOR shall implement Safety and Health Teams in accordance with the requirements of
Section 4.8 of NGER-ED-BSPDS-000001.
CONTRACTOR shall implement a WORK SITE Safety and Health Team comprised of WORK SITE
line management and safety and health advisors at each WORK SITE. CONTRACTOR shall
facilitate such meetings on a monthly basis as a minimum during the execution phase of the WORK.
CONTRACTOR shall implement a Worker Safety and Health Team at each WORK SITE to
maximize worker participation and gain valuable worker insight. CONTRACTOR shall facilitate
such meetings on a monthly basis as a minimum during the execution phase of the WORK. Workers
representing a cross-section of the workforce shall be selected based on being recognized as a safety
role model, having a positive attitude, being a leader, their experience level, and their dedication to
safety and health.
v. Safety Staffing
CONTRACTOR shall provide one qualified, full-time, and dedicated WORK SITE Safety Manager
for each major WORK SITE. Unless approved by COMPANY, such positions are required even if a
subcontractor provides a similar position at a WORK SITE managed by the subcontractor. Positions
will be filled no later than 60 calendar days prior to commencement of the WORK and will remain in
place until completion of the WORK.
Upon request of CONTRACTOR and with COMPANY approval, the scope of CONTRACTOR
WORK SITE Safety Manager’s responsibilities may be broadened to cover related disciplines (e.g.,
health, environmental, security) if:
a) As a minimum, the nominated candidate shall possess a good first degree in Engineering OR the
Sciences in addition to NEBOSH International Diploma Certificate or its equivalent (Certified
Safety Professional) with not less than 15 years relevant experience
b) The candidate has the knowledge, skills, and experience to effectively manage such disciplines
c) Specialist staff are sourced either full-time or part-time (as appropriate) to provide the nominated
candidate with technical support and the required levels of manpower to provide adequate
management of the related disciplines
CONTRACTOR shall provide an adequate number of qualified, full-time, and dedicated WORK
SITE Safety Advisors during execution of the WORK. Unless approved by COMPANY,
CONTRACTOR will provide at least one WORK SITE Safety Advisor for a maximum of 70
workers.
CONTRACTOR shall describe its WORK SITE Safety Management organization in its WORK SITE
Safety Plan, including the following:
a) A WORK SITE level safety organization chart
b) Project-specific roles and responsibilities for CONTRACTOR WORK SITE staff (e.g. managers,
supervisors, safety advisors).
vi. Safety and Health Training
CONTRACTOR shall implement a Safety and Health Training process in accordance with the
requirements of Section 4.1 of NGER-ED-BSPDS-000001.
CONTRACTOR shall provide a WORK SITE Safety and Health Training Plan to COMPANY for
review and endorsement no later than 90 calendar days prior to the commencement of WORK. This
plan shall describe in detail any Project-specific training courses that will be required or otherwise
provided to CONTRACTOR and subcontractor personnel (including expatriates, home country
nationals, and other-country nationals) to assure they have the knowledge and skills to perform their
jobs safely.
CONTRACTOR's WORK SITE Safety and Health Training Plan shall specifically include Safety
Leadership Training for managers and supervisors as described in Section 17.3.1.(8) of Section F –
COORDINATION PROCEDURES.
vii. Safety and Health Orientation
CONTRACTOR shall implement a Safety and Health Orientation process in accordance with the
requirements of Section 4.2 of NGER-ED-BSPDS-000001.
CONTRACTOR shall perform WORK SITE Safety and Health Orientations to ensure that all
personnel supporting planning and execution of the WORK are adequately familiarized with the
COMPANY and CONTRACTOR safety and health requirements and expectations when they
mobilize.
CONTRACTOR shall perform several types of WORK SITE Safety and Health Orientations
specifically customized for different audiences including the following:
a) Management, coordinators, and supervisors
b) Workers
c) Safety and Health Advisors
d) Visitors
CONTRACTOR management is encouraged to attend WORK SITE Safety and Health Orientations in
order to demonstrate their leadership and commitment.
viii. Subcontractor Management
CONTRACTOR shall implement a Subcontractor Management process in accordance with the
requirements of Section 4.3 of NGER-ED-BSPDS-000001.
Where CONTRACTOR utilizes lower tier subcontractors at the WORK SITE, CONTRACTOR shall
develop and implement a written subcontractor safety mitigation plan endorsed by COMPANY when:
a) CONTRACTOR identifies substantial opportunities for improvement during the subcontractor
evaluation phase that could impact a proposed subcontractor’s ability to satisfy CONTRACTOR
and COMPANY requirements and expectations
b) A subcontractor is not satisfying CONTRACTOR and/or COMPANY safety expectations and
requirements during execution of the WORK
ix. Emergency Preparedness and Response
As required by COMPANY, CONTRACTOR shall develop an Emergency Preparedness and
Response Plan for each WORK SITE for which it is responsible for managing in accordance with the
requirements of Section 4.4 of NGER-ED-BSPDS-000001.
CONTRACTOR shall submit WORK SITE Emergency Preparedness and Response Plan(s) to
COMPANY for review and endorsement not later than 90 calendar days prior to commencement of
the WORK.
Where COMPANY or its production affiliate has a regional Emergency Preparedness and Response
Plan in place that will cover activities associated with the WORK, CONTRACTOR shall develop a
WORK SITE level Emergency Preparedness and Response Bridging Document upon request by
COMPANY.
CONTRACTOR shall provide for COMPANY review and endorsement a structured program of
WORK SITE level simulations, drills, and exercises to be performed for each WORK SITE.
x. Incident Management Requirements
CONTRACTOR shall work collaboratively with COMPANY to identify any additional WORK SITE
leading SSHE performance indicators to be monitored. CONTRACTOR shall set aggressive yet
attainable targets for WORK SITE leading SSHE performance indicators. CONTRACTOR shall
measure, consolidate, and report WORK SITE level leading SSHE performance indicators to
COMPANY no later than three calendar days after the close of the month. CONTRACTOR shall
evaluate leading SSHE performance indicator trends against the established targets on a monthly basis
at minimum. CONTRACTOR shall develop and steward structured action plans to address leading
SSHE performance indicator trends that are not meeting established targets. CONTRACTOR shall
communicate leading SSHE performance indicator trends to the workforce on a monthly basis at
minimum.
xxii. Safety and Health Assessments and Audits
CONTRACTOR shall implement Safety and Health Assessments and Audits in accordance with the
requirements of Section 4.7 of NGER-ED-BSPDS-000001.
CONTRACTOR shall provide a WORK SITE Safety and Health Assessment and Audit Plan to
COMPANY for review and endorsement not later than 30 calendar days prior to commencement of
the WORK at each WORK SITE.
CONTRACTOR shall perform a structured safety and health readiness review at each WORK SITE
to confirm that all WORK SITE safety and health deliverables have been developed and that all safety
and health planning activities have been completed prior to commencement of the WORK (or prior to
asset handover or transition to another project phase). CONTRACTOR shall immediately inform
COMPANY and take corrective action when deviations from established requirements and
expectations are identified. COMPANY reserves the right to refuse commencement of the WORK
until the major deviations are resolved.
xxiii. Alcohol and Drug Policy Requirements
CONTRACTOR shall comply with COMPANY’s Alcohol and Drug Policy requirements described in
Section 16.3.7 of Section F – COORDINATION PROCEDURES.
xxiv. Lessons Learned and Best Practices
CONTRACTOR shall facilitate a WORK SITE-level workshop no later than 90 calendar days from
commencement of the WORK to capture and evaluate lessons learned and best practices from
previous projects and apply them into the safety planning process. COMPANY shall participate at its
sole discretion.
CONTRACTOR shall capture, evaluate, and apply as appropriate those WORK SITE lessons learned
and best practices that are identified throughout execution of the WORK.
CONTRACTOR shall facilitate a WORK SITE-level workshop no later than 30 days after completion
of the WORK in order to capture lessons learned and best practices. COMPANY shall participate at
its sole discretion. CONTRACTOR shall include the lessons learned and best practices in the WORK
SITE Final Safety Report described in Section 16.3.4 of Section F – COORDINATION
PROCEDURES.
Additional Requirements
Basic Requirements (see section (see Section 17.3.3 of Section
Topic
of NGER-ED-BSPDS-000001) F – COORDINATION
PROCEDURES
Pre-Shift Safety Meeting 4.10
Task Based Hazard Analysis 4.11
Personal Risk Assessment 4.12
Observation and Intervention 4.13
Safety Walkthrough 4.14
Safety Inspections 4.15 ---
Near Miss and Hazard 4.16
Reporting
Short Service Employee 4.17
Safety Recognition 4.18
Permit to Work 4.19
Hot Work 4.20 ---
Energy Control 4.21
Confined Space Entry 4.22 ---
Excavation 4.23 ---
Personal Protective 4.24
Equipment
Housekeeping 4.25 ---
Working at Heights 4.26 ---
Scaffolding 4.27 ---
Mechanized Lifting and 4.28 ---
Rigging Apparatus
Tools and Equipment 4.29 ---
Manual Lifting 4.30 ---
Electrical 4.31 ---
Fire Prevention 4.32 ---
Pressure 4.33 ---
Journey Management 4.34
Safety Walkthroughs
CONTRACTOR shall work collaboratively with COMPANY to integrate the use of Safety
Walkthroughs into the various Safety and Health Teams utilized on the Project.
The COMPANY-sponsored Safety and Health Leadership Team shall perform at least one Safety
Walkthrough at a WORK SITE each quarter.
The Project Safety and Health Team shall perform at least two Safety Walkthroughs at a WORK
SITE each month.
The WORK SITE Safety and Health Team shall perform at least one Safety Walkthrough each week.
The Worker Safety and Health Team shall perform at least four Safety Walkthroughs each week.
Safety Recognition
CONTRACTOR shall collaborate with COMPANY to define specific criteria to serve as the basis for
recognizing workers.
Permit to Work
When serving as the dominant WORK SITE organization, CONTRACTOR shall implement a Permit
to Work (PTW) system. When not serving as the dominant WORK SITE organization,
CONTRACTOR shall perform its WORK under the PTW system implemented by the dominant
WORK SITE organization.
a) For Greenfield WORK areas, CONTRACTOR shall implement CONTRACTOR’s PTW
system.
b) For Facilities Startup, CONTRACTOR shall work collaboratively with COMPANY to
determine the most appropriate milestone for transition from CONTRACTOR’s PTW system
to COMPANY’s PTW system prior to start-up of a facility. As a minimum, the transition
milestone shall not be later than two to three weeks prior to introduction of process
hydrocarbons into the facility. CONTRACTOR should recognize (and plan accordingly) that
WORK performed under COMPANY’s PTW system shall be performed under more stringent
administrative and technical controls relative to WORK performed under CONTRACTOR’s
PTW system utilized in a greenfield WORK area.
c) For brownfield WORK areas, CONTRACTOR shall perform its WORK under COMPANY’s
or COMPANY co-venture partner’s PTW system.
d) For active drilling locations, CONTRACTOR shall perform its WORK under drilling
contractor’s PTW system.
Energy Control
CONTRACTOR shall implement CONTRACTOR’s Energy Control procedure for WORK performed
on plant and equipment which are owned or controlled by CONTRACTOR. CONTRACTOR shall
implement COMPANY’s Energy Control procedure for WORK performed on plant and equipment
owned or controlled by COMPANY.
Upon request of COMPANY, report WORK SITE trailing SHE&S performance indicators to
COMPANY
Comply with the established minimum requirements of the applicable sections of NGER-ED-BSPDS-
000001 as identified in Table F17-2
Table F16-2: Sections of NGER-ED-BSPDS-000001 Applicable to WORK Performed at Other
WORK SITES
Topic Section
Safety and Health Training 4.1
Safety and Health Orientation 4.2
Emergency Preparedness and Response 4.4
Incident Management 4.5
SSHE Performance Measurement and Reporting 4.6
Safety and Health Assessments and Audits 4.7
Safety Inspection 4.15
Permit to Work 4.19
Hot Work 4.20
Energy Control 4.21
Confined Space Entry 4.22
Excavation 4.23
Personal Protective Equipment 4.24
Housekeeping 4.25
Working at Heights 4.26
Scaffolding 4.27
Mechanized Lifting and Rigging Apparatus 4.28
Tools and Equipment 4.29
Manual Lifting 4.30
Electrical 4.31
Fire Prevention 4.32
Pressure 4.33
Journey Management 4.34
Marine Transportation and Personnel Transfer 4.35
Helicopter Transportation 4.36
CONTRACTOR, subcontractors, and COMPANY will work together to classify incidents in the most
appropriate manner. In some cases, CONTRACTOR, subcontractors, and COMPANY may classify
incidents differently.
Table F16-3: COMPANY Incident Classification Guidelines
Term Definition
Injury or An injury or illness is an abnormal condition or disorder of an individual.
Illness Injuries include cases such as, but not limited to, a cut, fracture, sprain, or
amputation. Illnesses include both acute and chronic illnesses, such as, but not
limited to, a skin disease, respiratory disorder, or poisoning.
Work-Related An injury or illness is considered work-related if an event or exposure in the
work environment either caused or contributed to the resulting condition or
significantly aggravated a pre-existing injury or illness. Injuries or illnesses that
are not work-related are not recordable.
Recordability Work-related injuries or illnesses are recordable if they involve one or more of
Criteria the following:
a) Death
b) Day(s) away from work
c) Restricted work or transfer to another job
d) Medical treatment beyond First Aid
e) Loss of consciousness
f) A significant diagnosed injury or illness
Near Miss A Near Miss Incident is an unintended or unwanted event that, under slightly
Incident different conditions, would have had a negative effect on safety, health of people,
property, or the environment. Does not include Clinic Visits Without Treatment.
Clinic Visit A Clinic Visit Without Treatment is an incident which has actual consequences,
Without but the injured person does not require any type of medical treatment. Typically
Treatment considered a “soft hit”. Is not considered a Near Miss Incident.
First Aid Case First Aid Cases are generally defined as any one-time treatment, and any follow-
up visit for the purpose of observation, of minor scratches, cuts, burns, splinters,
and so forth, which do not ordinarily require medical care. Such treatment and
follow-up is considered first aid even though provided by physician or registered
professional personnel. First Aid Cases are not recordable. The First Aid Case
classification is appropriate when any of the following treatments are provided:
a) Using a non-prescription medication at nonprescription strength (for
medications available in prescription and non-prescription form, a
recommendation by a physician to use a non-prescription medication at
prescription strength warrants classification as a Medical Treatment
Incident).
b) Administering tetanus immunizations. (Other immunizations, such as
Hepatitis B vaccine or rabies vaccine, warrant classification as a Medical
Treatment Incident.)
c) Cleaning, flushing, or soaking wounds on the surface of the skin.
Term Definition
d) Using wound coverings such as bandages, Band-Aids™, gauze pads, etc.;
or using butterfly bandages or Steri-Strips™ (other wound closing devices
such as sutures, staples, tapes/glues, etc. warrant classification as a Medical
Treatment Incident).
e) Using hot or cold therapy (e.g., compresses, soaking, whirlpools).
f) Using any non-rigid means of support, such as elastic bandages, wraps,
non-rigid back belts, etc. (devices with rigid stays or other systems
designed to immobilize parts of the body warrant classification as a
Medical Treatment Incident).
g) Using temporary immobilization devices while transporting a victim (e.g.,
splints, slings, neck collars, backboards, etc.).
h) Drilling of a fingernail or toenail to relieve pressure, or draining fluid from
a blister.
i) Using eye patches.
j) Removing foreign bodies from eye using only irrigation or cotton swab.
k) Removing splinters or foreign material from areas other than the eye by
irrigation, tweezers, cotton swabs or other simple means (procedures
involving the excision of the outer layer of skin warrant classification as a
Medical Treatment Incident).
l) Using finger guards.
m) Using massages (physical therapy or chiropractic treatment warrants
classification as a Medical Treatment Incident).
n) Drinking fluids for relief of heat stress.
That the preventive use of Oxygen in absence of symptoms is not considered
medical treatment.
Medical A work-related injury or illness that requires the management and care of a
Treatment patient to combat disease or disorder. Medical Treatment Incidents are
Incident recordable. Medical treatment does not include the following: 1.) visits to a
physician solely for observation or counseling, 2.) the conducting of diagnostic
procedures, such as x-rays and blood tests, including the administration of
prescription medications used solely for diagnostic purposes (e.g., eye drops to
dilate pupils.), or 3.) application of First Aid.
Term Definition
Restricted Duty A work-related injury or illness that results in a person being unable to perform
Incident one or more of the routine functions of the person's job, or from working the full
workday that the person would otherwise have been scheduled to work on any
calendar day after the day of the illness or injury. Restricted Duty Incidents are
recordable. [Routine functions are those work activities that the person regularly
performs at least once per week. Do not record as a Restricted Duty Injury
where persons produce fewer goods or services than they would have produced
prior to the injury or illness but otherwise perform all of the routine functions of
their work. If follow-up with the persons making the restriction indicates that the
restriction does not prevent the persons from either their routine job functions or
from working all of their normally assigned work shift, then the case should not
be recorded as a Restricted Duty Incident. Work restrictions recommended by a
physician result in a Restricted Duty Incident classification even if the person
does not follow the restrictions. In cases where recommendations are received
by two (2) or more physicians, COMPANY may decide which recommendation
is the most authoritative and determine recordability based on that
recommendation.]
Lost Time Also known as a Days Away from Work Case (DAFWC). Any work-related
Incident injury or illness (including fatalities) that results in at least one (1) lost workday
after the day of the incident. If a condition resulting from an injury or illness
causes a person to be unable to return to work on the calendar day following the
day on which the incident occurred, the case is recordable and should be
classified as a Lost Time Incident. [It does not matter whether the next calendar
day is a scheduled work day or not, only whether the person was able to work on
that day. If the injury or illness occurs on the last day a person is scheduled to
work (e.g., last day of the work week) and the person reports to work on the next
scheduled work day, record the case as a Lost Time Incident only if information
is received from a physician indicating the person should not have worked. An
injury or illness in which the person is unable to work is classified as a Lost
Time Incident even if the individual takes unscheduled vacation on the day
following the day of the injury or illness. Exclude classification as a Lost Time
Incident in situations where an individual is capable of working, but unable to
return to work solely due to circumstances such as 1.) a seaman missing a ship
sailing, 2.) a person unable to return to a location due to bad weather or lack of
reasonably available transportation, 3.) a lack of local medical facilities needed
for observation or treatment provided there was no unnecessary delay in
traveling to seek such medical treatment, or 4.) the person refuses to work.]
Fatality A recordable incident which results in the death from a work-related injury or
illness, regardless of the time intervening between the incident and death.
Regional Regional illnesses are illnesses that could result in a debilitating condition or
Illness death, or a health-related situation that could disrupt ongoing operations. Vector
borne examples include Malaria, Dengue, and Yellow Fever.
Person-to-person spread examples include Meningitis, TB, and Ebola. Food or
water borne examples includes Typhoid, Cholera, and Salmonella.
2) Prohibitions
Unless specifically authorized in writing by COMPANY, CONTRACTOR's policy and its
implementation shall prohibit CONTRACTOR and Contractor Personnel from the following:
i. Prescription drugs have been prescribed by a licensed physician for the person in
possession of the drugs.
ii. The prescription was filled by a licensed pharmacist for the person possessing the drugs.
iii. The individual notifies their supervisor that they will be in possession of or using,
impairment-causing prescription drugs or over-the-counter medication and appropriate
steps are taken to accommodate the possibility of impairment, including but not limited
to, removal from work for the period of possible impairment.
C. Being Under the Influence of Prohibited Substances while performing any WORK for
COMPANY.
D. Switching or adulterating any urine, blood or other sample used for testing.
E. Performing WORK for COMPANY if that person has tested positive, or refused testing, in
any employment-related test except that Contractor Personnel seeking access to ExxonMobil
Property may be considered if the positive employment-related test in question was an initial
pre-employment test administered more than twelve months before and the employee will not
perform in a designated-like position. The prohibition in part 3(E) will not apply to
Contractor Personnel seeking access to ExxonMobil Property for low-exposure positions
whose employment-related positive test did not occur during employment on ExxonMobil
Property or WORK.
F. Upon request CONTRACTOR will certify in writing that it has enforced all provisions of
Paragraph 3.
G. Contractor Personnel are not eligible to be assigned to WORK for COMPANY, or to access
ExxonMobil Property, while they are prescribed, or are otherwise taking, any medication or
controlled substance (prescribed or over the counter) that is known to cause impairment. An
exception to this prohibition may be granted based on CONTRACTOR's written certification
to COMPANY that a fitness for duty evaluation has been conducted by a licensed health care
professional, to assess the individual's ability to work in a safety sensitive environment (i.e.
offshore platform or other operating, mechanical or construction area) while under the
influence of such medication. CONTRACTOR's certification must confirm that the health
care professional expressly cleared the individual to work in a safety sensitive environment.
The certification must also set forth any restrictions or accommodations that are necessary in
relation to the use of such medications in a safety sensitive environment.
Similarly, CONTRACTOR must determine, and report to COMPANY any individual (s) who
are prescribed a controlled substance or impairment causing medication during the course of a
COMPANY WORK assignment. Personnel so identified are not eligible to continue working
for COMPANY and will be immediately removed from COMPANY WORK and
ExxonMobil Property. When personnel are no longer prescribed any controlled substance or
impairment causing medication, they will be allowed to return to COMPANY and have
access to ExxonMobil Property provided he or she is in compliance with all current
contractual requirements as outlined in the contract. The only exception is when
CONTRACTOR certifies in writing to COMPANY that a fitness for duty evaluation has been
conducted by a licensed health care professional on any individual who is taking an
impairment causing prescription or medication, and that fitness for duty evaluation gives
clearance that allows the individual to work in a safety sensitive environment (i.e offshore
platform or other operating, mechanical or construction area) and what restrictions, if any,
must be in place, to accommodate the use of the prescription medication.
CONTRACTOR should, at a minimum, take the following steps to determine if any drug or
medication (over the counter or controlled) is potentially impairment causing:
Refer to the product label (s), insert (s,) and any information or instructions available
from the physician or pharmacist to identify any physiological restrictions associated with
the use of the prescription drug or medication, and
Consult with CONTRACTOR's licensed health care professional.
3) Searches and Inspections
On COMPANY property COMPANY may, at any time, have COMPANY supervisors,
CONTRACTOR supervisors and/or authorized search and inspection specialists, including scent-
trained animals, conduct unannounced searches, and inspections of CONTRACTOR and/or
CONTRACTOR Personnel and their property; that property may include, but is not limited to, the
following: wallets, purses, lockers, baggage, offices, desks, tool boxes, clothing, and vehicles.
4) Testing
a) Categories
All CONTRACTOR personnel shall be assigned to one of the following categories based on the
individual's job function or WORK SITE assignment:
i. Comparable-to-Designated
Has a high exposure to a catastrophic operational incident; has a direct role in operations
where failure could result in serious harm to public or employee well-being, company
assets, or the environment; and has no direct or very limited supervision available to
provide operational checks.
ii. Safety-Sensitive
Has a high exposure to catastrophic operational incident and has access to operations where
failure could result in serious harm to public or employee well-being, company assets, or
the environment.
iii. Low-Exposure
Has an indirect role and no access to operations where failure could result in serious harm
to public or employee well-being, company assets or the environment.
the WORK SITE, property damage of more than $1000, or an incident that carried the
potential for serious personal injury or significant property damage.
An individual so removed shall be allowed to return to work on COMPANY property
only after CONTRACTOR conducts alcohol and drug testing on the individual as soon as
possible following the individual's removal from the WORK SITE, and CONTRACTOR
certifies in writing the test identification number, the individual's government work
identification number (i.e., U.S. Social Security, or equivalent), the test date and time, and
a negative test result. On that written certification CONTRACTOR shall include a
consent signed by the individual permitting disclosure to COMPANY of the test result.
See Table F17-7 of Section F – COORDINATION PROCEDURES.
iv. Reasonable Suspicion Testing :
Upon Reasonable Suspicion of CONTRACTOR or COMPANY that a CONTRACTOR
Personnel is Under the Influence of a Prohibited Substance while on COMPANY
property, CONTRACTOR shall remove the individual(s) from COMPANY property and
surrender their WORK SITE credentials to COMPANY.
An individual removed from COMPANY property for Reasonable Suspicion shall be
allowed to return to work on COMPANY property only after CONTRACTOR conducts
alcohol and drug testing on the individual as soon as possible following the individual's
removal from the WORK SITE, and CONTRACTOR certifies in writing the test
identification number, the individual's social security number, the test date and time, and
a negative test result. On that written certification CONTRACTOR shall include a
consent signed by the individual permitting disclosure to COMPANY of the test result.
See Table F17-7.
CONTRACTOR's Policy shall specify substances and threshold levels that comply, as a
minimum, with the USDOT alcohol and drug testing regulations. CONTRACTOR shall
adopt collection, chain-of-custody, and other related procedures consistent with USDOT
testing procedures or sound industry practice. CONTRACTOR shall include alcohol in
any test panel regardless of any lesser USDOT requirement. CONTRACTORs that do
not have an existing program are strongly encouraged to adopt COMPANY's alcohol and
drug testing standards.
CONTRACTORs in the U.S. shall use only testing laboratories that are certified by
SAMHSA. CONTRACTORs outside the US, should only use testing laboratories that are
certified by a government agency with equivalent standards to SAMHSA.
At International (Non-US) locations CONTRACTOR may choose to use a COMPANY
approved field screen device. COMPANY has approved the Quest Diagnostics’ 10 Drug
“Express Results Integrated Multi-Drug Screen Cup”. This device was approved by
COMPANY after being scientifically validated in a significant field validation study. This
approved device may be used for any type of drug test (i.e. pre-access, post-incident,
reasonable suspicion and random). Only those field screens resulting in a non-negative
result must be forwarded immediately to a SAMHSA approved (or government agency
with equivalent standards to SAMHSA) laboratory for confirmation of the field screen
result. Prior to adoption of the COMPANY field screen device, CONTRACTOR must
certify, in writing, to COMPANY that appropriate controls are in place, and collectors
have been trained in the proper use of the field screen device. The approved field screen
device may be purchased from Quest Diagnostics at COMPANY contracted rates.
Contractors may contact the COMPANY Account Representative at Quest at 913-895-
2549 or [email protected] to purchase the approved field screen
device.
c) Non-Compliance
information on each alcohol and drug test conducted for each Contractor Personnel
identified by COMPANY from those lists:
1) Date of and type of test (e.g. random, pre-access); and
2) Laboratory chain-of-custody identification number and/or test number.
D. CONTRACTOR will obtain an agreement from any consortium, specimen collection
service, laboratory and/or Medical Review Officer providing drug/alcohol testing
services under this agreement that upon submission by COMPANY of a list, or lists,
of Government Work Identification Numbers, chain-of-custody ID numbers and test
dates:
1) The laboratory will verify that the tests were conducted as represented; and
2) The laboratory and/or Contractor Medical Review Officer will provide a
sworn statement that each of the tests identified by COMPANY was
confirmed as negative or that it/he/she cannot so swear.
j-2) For CONTRACTOR’s services provided to COMPANY at a “Category-2 WORK SITE” under
this CONTRACT, the following provisions of j-2 shall apply:
A. CONTRACTOR shall keep records required by this section, available for inspection
by COMPANY during the term of this CONTRACT, and for a period of three (3)
years after its termination.
B. CONTRACTOR will immediately notify COMPANY of all Contractor Personnel
who are suspected of being under the influence of a prohibited substance while on
duty, as well as all Contractor Personnel who are required to submit to a post-incident
alcohol and drug test as a result of an incident that occurred while performing
services for COMPANY under this CONTRACT.
C. Upon written request by COMPANY, CONTRACTOR will provide to COMPANY
the following information for every reasonable suspicion or post incident test
conducted on Contractor Personnel during the period defined COMPANY in such
request:
1) Government work identification number,
2) Date of and type of test (e.g. for cause, post-incident)
3) Laboratory chain-of-custody identification number and/or test number.
D. CONTRACTOR will obtain an agreement from any consortium, specimen collection
service, laboratory, and/or Medical Review Officer providing drug/alcohol testing
services under this agreement, that upon submission by Company of a list, or lists, of
Government work identification numbers, chain-of-custody ID numbers, and test
dates:
1) The laboratory will verify that the tests were conducted as represented;
2) The laboratory and/or Contractor Medical Review Officer will provide a
sworn statement that each of the tests identified by Company were confirmed
as negative, or that it/he/she cannot so swear.
Consent and Authorization for Disclosure to COMPANY of Drug Test Result and Related Information
I hereby consent to disclosure by CONTRACTOR and its agents, including, but not limited to, any
collecting and testing agencies, of the test result identified above and any related information to
COMPANY and/or COMPANY authorized agents, assigns or representatives.
______________________________ __________________________
CONTRACTOR Personnel Signature Date
______________________________ _____________________________
Authorized CONTRACTOR Representative Signature
_____________________Title ____________________Date
_____________________ certifies that the individual shown above was tested on _____________ at __________
(CONTRACTOR) (date) (time)
and that the result of the required laboratory alcohol and drug test was negative.
______________________________ _____________________________
Authorized CONTRACTOR Representative Signature
_____________________Title ____________________Date
Instructions to the CONTRACTOR: Fax or send a copy of this form to COMPANY at the work site when the disclosure consent
and Section 1 of the certification have been completed. Deliver the completed original to COMPANY when Section 2 of the
certification is completed.
16.6 Reports
CONTRACTOR shall provide to COMPANY weekly and monthly safety reports in accordance with
the Minimum Safety Requirements for Executing Major Projects.
d) Interfaces with the Project, government agencies, third party emergency responders,
Subcontractors, and external agencies as appropriate
e) Identification of personnel qualified to respond to emergencies, noting their associated
training
f) Identification of critical emergency response equipment and associated maintenance,
inspection, and testing procedures
g) Plans for conducting and assessing training, exercises, drills, and simulations at prescribed
frequencies that are based on realistic emergency scenarios and involve external emergency
response organizations, local authorities and the community as appropriate
h) Procedures for reporting training and drill activity to COMPANY as required
3) CONTRACTOR shall include EP&R Interface Management in the EP&R Plan as directed by
COMPANY, addressing Project and WORK SITE interfaces as appropriate. EP&R Interface
Management shall align COMPANY's and CONTRACTOR's roles and responsibilities with
regard to EP&R. CONTRACTOR shall verify that Subcontractors have developed and
implemented effective tactical (i.e., WORK SITE) EP&R Plans. CONTRACTOR shall also
verify that Subcontractors have developed and implemented effective emergency response
interfaces as appropriate.
18.4 Reports
1) CONTRACTOR shall notify COMPANY of WORK SITE performance metrics, security
incidents, threats, and corrective actions as directed by the onsite COMPANY representative.
CONTRACTOR shall provide COMPANY a monthly summary of security incidents and threat
conditions including, but not limited to, the following:
a) Theft involving property greater than or equal to $200 US
b) Any security-related incident that may cause adverse media coverage of COMPANY
c) Threats and assaults against all personnel, assets, or facilities
d) Security incidents affecting property, such as arson, sabotage, trespassing, or vandalism
e) Violations of polices on alcohol, drugs, and weapons
f) Any known incidents where inappropriate physical force is used by assigned Host
Government security or private security providers at the WORK SITE
g) Unauthorized access to computer systems or computer programs
h) Action to close identified gaps
i) Events that impact the Project (labor disputes, public disturbances)
j) Other incidents as directed by COMPANY
2) CONTRACTOR shall report to COMPANY as required, records of drills, exercises, and
responses.
11) CONTRACTOR and its Subcontractors shall meet all local and country regulations for health and
health-related aspects of the Project.
12) CONTRACTOR shall participate in COMPANY-sponsored lessons learned workshops as
requested by COMPANY.
13) Contractor shall include specific control measures according to COMPANY’s Malaria Control
Program if malaria is identified as a risk, minimum requirements of which are summarized in
appendix FL
18.4 Reports
Regulatory filings
Formal public hearings
d) Support COMPANY's efforts to develop regulatory license, permit, and approval
applications.
e) Identify and obtain all necessary permits, notifications, authorizations, approvals, licenses,
agreements, etc. that are required by LAW to progress the WORK according to the Detail
Schedule and as agreed to in CONTRACTOR's RCP and meet all conditions of such permits,
notifications, authorizations, approvals, licenses, agreements, etc. This includes rectification
of inconsistencies between conditions of different permits, notifications, authorizations,
approvals, licenses, agreements, etc.
f) Develop and conduct regulatory, environmental, socioeconomic, and health training programs
for CONTRACTOR's and Subcontractors' personnel, as agreed to in CONTRACTOR's Plans.
CONTRACTOR shall keep training records for each member of CONTRACTOR's,
Subcontractors', and Suppliers' personnel.
g) Develop and implement the following for regulatory compliance and environmental,
socioeconomic, and community health management:
i. Monitoring and inspection programs for the WORK and WORK SITES, including the
following:
Keep required monitoring and performance records and make these records available
to COMPANY upon request
Conduct regular inspections of the WORK SITES to ensure WORK SITES are being
maintained in an environmentally and socioeconomically sound and healthful manner
and that environmental, socioeconomic, and community health risks are being
identified and appropriately managed
ii. Compliance assessments program including the following:
Assessment of compliance with LAWS and regulations and other requirements listed
in Item c) (above)
Identification of compliance metrics
Frequency of assessment
Action tracking system and reporting to CONTRACTOR's management
h) Promptly resolve, to COMPANY's satisfaction, assessment findings from regulatory agencies
or COMPANY.
i) Facilitate interfaces with governmental contacts in the COUNTRY OF OPERATION only as
directed by COMPANY. CONTRACTOR shall perform the following:
i. Develop and agree upon general procedures for CONTRACTOR interfaces with
governmental authorities and ensure that any persons in CONTRACTOR's organization
who may need to meet with governmental authorities are fully aware of the agreed
procedures.
ii. Provide COMPANY's Representative reasonable advance notice of all known and/or
scheduled meetings between CONTRACTOR and governmental authorities or agencies
concerning the WORK.
iii. Maintain records and files relating to governmental agency permits, notifications,
authorizations, approvals, licenses, agreements, etc., required for the WORK, including
original copies of all pertinent correspondence.
j) Report spills related to the WORK at Off Sites to governmental authorities pursuant to LAW
and other agreements. Within 48 hours of spill report submission, CONTRACTOR shall
provide to COMPANY documentation of the report.
k) Related to waste management practices, provide the following:
i. As a minimum, provide secondary containment for liquid restricted (i.e., hazardous or
toxic) wastes that are stored
ii. At CONTRACTOR's operating waste management sites, maintain a computer database
with records of all wastes received at the WORK SITE and final destinations within the
waste management site (e.g., which landfill cell)
l) Ensure CONTRACT Changes and revisions to LAW are appropriately addressed to maintain
compliance.
m) Promptly resolve, to COMPANY'S satisfaction, any deficiencies identified by COMPANY in
CONTRACTOR's waste management activities.
n) CONTRACTOR shall promptly report major spills to COMPANY and keep a log of all spills
and the response actions taken.
c) Describe how CONTRACTOR's RCP is bridged to COMPANY's RCP and to other relevant
CONTRACTOR Plans and documents (e.g., CONTRACTOR's EMP and its associated plans)
3) Organization
a) Describe CONTRACTOR's regulatory compliance organization and demonstrate that this
organization will include adequate staffing for planning and implementing the RCP
b) Identify CONTRACTOR's personnel with appropriate skills, expertise, and training who are
responsible for ensuring that CONTRACTOR's activities related to the WORK are in
compliance with all applicable LAW, regulations and other regulatory documents
c) Define and document roles and responsibilities for WORK SITE management, supervisory
personnel, and the workforce involved in regulatory compliance activities
d) Describe how these roles and responsibilities will be communicated to CONTRACTOR's and
Subcontractors' personnel involved in the WORK
4) Processes and Procedures
a) Identification Process
Describe CONTRACTOR's process to ensure that LAW, regulations, and other regulatory
documents (including treaties, permits, notifications, authorizations, approvals, licenses,
agreements, etc.) that are applicable to the WORK are identified.
5) List
List all the LAW, regulations, and other regulatory documents including permits, notifications,
authorizations, approvals, licenses, agreements, etc., that are applicable to or required for all aspects
of the WORK. This list will include the Project phase and the lead agencies that will provide the
required permits, notifications, authorizations, approvals, licenses, agreements, etc. The list of LAW,
regulations, and other regulatory documents will include, but not be limited to, the following:
a) Communication
b) Engineering and Construction
c) Customs
d) Environment
e) General business
f) Health and safety
g) Labor/visas
h) Land/real property tax
i) Damages compensation
j) United States Export Controls and similar export controls of other countries
k) Transportation (where applicable)
l) Security
6) Approvals Management
Define CONTRACTOR's process to support timely receipt of required permits, licenses, and
approvals. For each required permit, license, or approval listed in the Plan, the following information
is required:
a) CONTRACTOR's Plan for obtaining any required permit, authorizations, approvals, licenses,
etc., along with owner (i.e., CONTRACTOR or COMPANY) and forecasted/actual
submission and approval dates
b) Based on the time line, a demonstration that CONTRACTOR's Plan for fulfilling the
requirements of the LAW, regulation, or other regulatory document is consistent with the
Detail Schedule
7) Regulatory Compliance Instruction
For each applicable regulatory requirement that has been identified for the WORK, include a
description of the processes that CONTRACTOR will use to accomplish the following:
a) Identify the end user
b) Develop end-user compliance instructions and communicate these instructions to appropriate
CONTRACTOR and Subcontractor personnel
c) Develop, document, and implement a procedure to perform a final check, prior to beginning a
task associated with the WORK, to ensure regulatory compliance
8) Communication Process
Define CONTRACTOR's Processes to identify and communicate new LAW, regulations, and other
regulatory documents that are deemed to be applicable to the WORK. The RCP shall describe how
CONTRACTOR shall perform the following:
a) Monitor, on an ongoing basis, legislation or potential legislation associated with all WORK
SITES so that CONTRACTOR is able to obtain timely knowledge of new and/or emerging
LAW, regulations, and other regulatory documents that could affect the WORK.
b) Communicate new and emerging LAW, regulations, and other regulatory documents to
CONTRACTOR's organization and to COMPANY.
c) Follow up with appropriate CONTRACTOR and Subcontractor personnel to ensure that new
LAW, regulations, and other regulatory documents have been added to the processes that are
in place to confirm compliance.
9) Assessment and Evaluation
Describe the processes that CONTRACTOR will use, in accordance with Item 2)g) of Section
19.2 of Section F – COORDINATION PROCEDURES, to perform the following:
a) Monitor and assess the various aspects of the WORK for regulatory compliance
b) Assess and evaluate CONTRACTOR's activities to ensure compliance with all LAW
10) Lessons Learned
Describe CONTRACTOR's process for capturing and implementing lessons learned from
assessments and evaluations to improve overall compliance performance
11) Training Requirements
Describe the qualifications and training required for CONTRACTOR personnel who are
responsible for ensuring regulatory compliance
d) Document how environmental, socioeconomic, and health aspects of the Project will be
managed by CONTRACTOR
e) Communicate the implementation and execution of the issues/impacts avoidance and
mitigation measures identified in COMPANY's ESHIA and/or EMP
2) CONTRACTOR's EMP shall also include the Waste Management Plan and the Spill Prevention
and Response Plan.
d) The process for resolving conflicts between the objectives of CONTRACTOR Environmental
Management Group and other CONTRACTOR personnel
5) CONTRACTOR's processes for performing the following:
a) Evaluating the effectiveness of CONTRACTOR's environmental, socioeconomic, and
community health mitigation measures
b) Monitoring (inspections) and enforcing compliance with the EMP
c) Using results of assessments and evaluations to implement remedial actions and improve
CONTRACTOR's environmental, socioeconomic, and community health performance
d) Documenting, reporting, and investigating incidents of noncompliance
e) Capturing lessons learned from such incidents
CONTRACTOR shall include a list of environmental, socioeconomic, and community health
compliance indicators (e.g., quality of treated effluent before discharge, local hiring, local
business utilization statistics, key health and disease statistics) to be measured and the frequency
of measurement
6) Training
A description of CONTRACTOR's environmental, socioeconomic, and community health
awareness training and training schedule
7) Expectations
a) Define CONTRACTOR's specific environmental, socioeconomic, and community health
expectations related to policies, performance indicators, and targets and other desired results
b) Identify how these expectations are communicated to personnel
c) Define the elements that are essential to the success of the environmental, socioeconomic, and
community health effort
d) Define performance indicators, which will include tracking COMPANY-stipulated
environmental, socioeconomic, and community health performance indicators
8) Procedures
a) Site-specific data gathering that CONTRACTOR may undertake, as directed by COMPANY,
at WORK SITES associated with COMPANY's ESHIA and/or EMP
b) Mechanism for obtaining endorsement from COMPANY for changes or deviations from the
Project environmental and/or socioeconomic and/or community health specifications
c) Provisions for incorporating improvements to the environmental, socioeconomic and
community health management program
d) WORK SITE specific programs or actions to control and/or mitigate the identified
environmental, socioeconomic, and community health impacts, taking into consideration
COMPANY's ESHIA
e) CONTRACTOR's endorsement process and environmental, socioeconomic, and community
health milestones for deliverables during each phase of the Project (detailed design and
engineering, construction, operations, etc.) as applicable
4) Nature of medical situations that will be handled by the Project versus those requiring medical
evacuation
5) Disease prevention programs including awareness and training programs
19.4 Reports
7) Waste Reporting
a) CONTRACTOR shall report to COMPANY all waste quantities generated on COMPANY-
provided WORK SITES during performance of the WORK and transferred to COMPANY.
The waste quantity measurement and/or calculation methodologies utilized shall be specified
and data for generated waste quantities shall be submitted to COMPANY on a monthly basis.
Subcontractor data must be included in CONTRACTOR's submitted data. Restricted or other
regulation-defined waste quantities and construction waste quantities must be reported
separately.
b) CONTRACTOR-reported waste quantities must include all COMPANY-specified wastes
leaving the WORK SITE as well as those sent to storage.
8) Socioeconomic Reporting
On a periodic basis, but no less frequent than monthly, CONTRACTOR shall report
socioeconomic metrics, including but not limited to the following:
a) Grievances
b) Work stoppage
c) Land use
d) Community engagement
e) Evaluation of human rights and transparency initiatives
f) Other information as required by the EMP
9) Other Reporting
Any other reporting and notification requirements as defined in COMPANY's EMP
2) Keep a check list of all export and permit requirements pertaining to the WORK and maintain up-
to-date records and documentation of all Nigerian Export/Import Permits for the WORK.
3) List and describe all equipment and materials purchased or imported into Nigeria that will become
a permanent part of the WORK and/or FACILITIES.
liaison to the host communities as may be determined by the project manager. The Liaison
Officer shall also liaise with COMPANY Public Affairs department in the facilitation of the
resolution of all labour disputes.
2) The Community Interface Coordinator should preferably come from any of the host communities
but must be experienced in handling community issues. The liaison officer shall not be involved
or be responsible for any local/community labour hiring.
3) The resume of Community Interface Coordinator to be considered for this job, shall be as
recommended by the Government Joint Industrial Labour Relations and Development Committee
(GJILRDC) and approved by the Public & Government Affairs.
Environmental Issues
Relevant SHE and Waste disposal guidelines shall be issued to CONTRACTOR to ensure that the
CONTRACTOR makes effort to protect the environment where the project is located. The
CONTRACTOR shall conduct all its activities in a manner by which the health and safety of its
employees, its sub-contractors and communities is enhanced. The CONTRACTOR is expected to
adhere strictly to COMPANY SHE guidelines and meet all relevant government requirements. Effort
shall be made to avoid destruction of aquatic life and/or jeopardize fishing activities of the local
fishing folks. Cases of non-compliance to COMPANY SHE standard by CONTRACTOR will not be
tolerated.
2) Skilled labour is defined as all those trades that require a lot of skill as a result of long practice to
perform. These include trades such as welders, electricians, mechanics, pipe fitters, scaffolders,
sandblasters, riggers, divers, carpenters, safety officers and others in like category.
3) Professionals are defined as those groups of workers that require formal training and university
education. These include engineers, Administrator, secretaries, etc.
The CONTRACTOR will engage those that are suitable for recruitment after passing the various
selection and medical tests, as determined.
Any Sub-Contractor(s) to be employed shall similarly be directed to use local labour as specified
above.
The ratio for immediate communities shall be in accordance with existing practice of Ibeno (30%),
Eket (26%), Esit Eket (24%) and Onna (20%), out of the share of 30 percent.
Use of Subcontractors
1) Efforts shall be made to identify non-skilled work that will be sub-contracted to competent
CONTRACTORS from the host communities. COMPANY shall be notified prior to the award.
The work may include the following:
a) Manual digging and excavation
b) Supply of sand/food items/stationeries
c) Cleaning and clearing of site wastes
d) Fumigation offsite/site office etc.
e) Supply of sundry items
2) Host communities’ sub-contractors with proficiency and track records in technical areas will also
be considered in provision of skilled and technical services.
3) All Sub-Contractors and their personnel shall be required to maintain stipulated COMPANY
standard and guidelines, same as expected of CONTRACTOR.
Gift
1) The CONTRACTOR shall recognize and respect local customs and tradition but shall not give
donation to any individual beyond nominal value of $50 or N6, 000.
2) Customary items presented to Paramount Rulers in-council during courtesy calls as well as any
gift to groups/persons shall not exceed a nominal value of $200 or N26,000 per sizeable group of
not less than 5 persons or $50 per individual.
Liability
CONTRACTOR shall be liable for disruptions by the communities if established that such resulted
from their failure to comply with above guidelines. The COMPANY will continue to liaise with the
community to promote enabling environment for CONTRACTOR / Subcontractor to operate.
1) Special Condition or, subject to COMPANY's written approval, such other bank account as
CONTRACTOR may specify from time to time.
2) Any changes in CONTRACTOR's banking information or payment instructions shall be
submitted (prior to approval of invoices) in writing to COMPANY's Representative with a copy
to the Project Controller.
3) CONTRACTOR shall be solely responsible for any and all bank charges, fees, and overdrafts
relating to CONTRACTOR's bank account due from authorized banking activity or due to fault of
CONTRACTOR or COMPANY.
4) COMPANY shall be deemed discharged of payment obligations upon issuance of electronic
orders to CONTRACTOR bank. CONTRACTOR assumes all risks of transfer of funds from that
point forward.
22.4 Reports
c) PSSR
7) CONTRACTOR's plans to support COMPANY's activities to prepare the FACILITY for Start-up.
CONTRACTOR's plans shall provide details on CONTRACTOR's pre-Start-up support of the
following minimum elements:
a) Supporting COMPANY during COMPANY development of Operational Safety Procedures,
in place prior to the introduction of hydrocarbons
b) Development of and approval by COMPANY of all Start-up procedures
c) Full function testing of the FACILITY safety systems
d) Supporting COMPANY during Pre-Start-up IPR
e) Supporting COMPANY during ORR
f) Supporting COMPANY during PSSR
g) Development and generation of punch-list and stewardship to closure plan
h) Issuance of Ready for Start-up Certificates (RFSU) and approval by COMPANY
23.4 Reports
1) As directed by COMPANY, CONTRACTOR shall provide readiness for operations progress
reports for the following:
a) Program development
b) Plan development
c) Procedure development
Appendices
Section F
COORDINATION PROCEDURES
Location
Notes: 1. The following list is provided for guidance. The SDRL Originator should complete column 3 and...
2. The SDRL Originator should select & verify suitability of Document / Data sumission requirements against component items of the Technical Requisition.
SUBMISSION REQUIREMENTS
LEGEND SUBMISSION TIMING: EXAMPLE
Requirements
= Purchase Order
Manuals
Document Format: Hard Copy (HC) ...or
T = Inspection / Testing +2P / +4P / +6p / +8P = document to be submitted
D = Dispatch 2 / 4 / 6 / 8weeks after receipt of Purchase Order
W = Periodic Issue
2W = document to be submitted every 2 weeks
( I ) Information ( R ) Review
- = Before
Submit "Certified"
X = With Quotation Submission Timing
PTS = Prior to issue of Purchasers Inspection
HC = Hard Copy Release Note and Prior to Release of items for
M = MRB
V = VMC
pdf = Portable Document Format Shipment
Submit
SUBMISSION REQUIREMENTS
Manuals Requirements
LEGEND SUBMISSION TIMING: EXAMPLE
P = Purchase Order
+ = After
WI = When Issued
Submit "Certified"
Submission Timing
Release Note and Prior to Release of items for
HC = Hard Copy Shipment
applicable
M = MRB
pdf = Portable Document Format
V = VMC
NFF = Native File Format
D01 OUTLINE DRAWINGS, LAYOUT DRAWINGS, PIPELINE ALIGNMENT SHEETS - +4P R - C pdf V -
D02 SHOP DETAIL DRAWINGS - +4P - R - pdf - M
D03 GENERAL ARRANGEMENT DRAWINGS - +4P R - C pdf V -
D04 ASSEMBLY AND DISASSEMBLY DRAWINGS - +4P R - C pdf V -
D05 CROSS-SECTION DRAWINGS / EXPLODED VIEW DIAGRAM WITH PARTS LIST - +4P R - C pdf V -
D06 SUPPORT LOADING DIAGRAM - +4P R - C pdf V -
D07 ANCHOR BOLT LOCATION DRAWINGS - +4P R - C pdf V -
D08 INSTRUMENT SCHEMATICS AND CONTROL DIAGRAMS - +4P R - C pdf V -
D09 FLOOR PLAN DRAWINGS - +4P R - C pdf V -
D10 PIPING AND INSTRUMENT DIAGRAM (P&IDs) - +4P R - C NFF V -
D11 CAUSE AND EFFECT (C&E) CHARTS - +4P R - C pdf V -
D12 ELECTRICAL / ELECTRONIC SCHEMATICS - +4P R - C pdf V -
D13 SINGLE LINE ELECTRICAL DIAGRAMS / DRAWINGS - +4P R - C NFF V -
D14 ELECTRICAL CONNECTION DIAGRAM - +4P R - C pdf V -
D15 ELECTRICAL INTERNAL CONNECTION DIAGRAM - +4P R - C pdf V -
D16 ELECTRICAL SCHEMATIC AND WIRING DIAGRAMS - +4P R - C pdf V -
D17 PIPING SCHEMATICS AND ARRANGEMENT DRAWINGS - +4P R - C pdf V -
D18 LEGENDS AND SYMBOLS - +4P R - C pdf V -
D20 DETAILED FABRICATION DRAWINGS - +4P - R - pdf - M
D21 MECHANICAL SEAL DRAWINGS (including dry gas seals) - +4P R - C pdf V -
D22 PIPING ISOMETRICS - +4P R - C pdf V -
D23 COUPLING DRAWINGS - +4P R - C pdf V -
D24 SUPPLIER INTERFACE AND CONNECTION REQUIREMENTS - +4P R - C pdf V -
D25 SYSTEM NETWORK ARRANGEMENT DIAGRAM - +4P R - C pdf V -
D26 ELECTRONIC EQUIPMENT OUTLINE DRAWING - +4P R - C pdf V -
D27 ELECTRONIC CABLE DETAILS - +4P R - C pdf V -
Manuals Requirements
P = Purchase Order
T = Inspection / Testing
Submit "Certified"
Submission Timing
HC = Hard Copy Shipment
applicable
pdf = Portable Document Format
M = MRB
V = VMC
NFF = Native File Format
L Lists
SUBMISSION REQUIREMENTS
Manuals Requirements
P = Purchase Order
T = Inspection / Testing
+ = After
WI = When Issued
# = Number of Weeks
Submit "Certified"
Submission Timing
HC = Hard Copy Shipment
applicable
pdf = Portable Document Format
M = MRB
V = VMC
NFF = Native File Format
M Maintenance, Operation
P Procedures
P01 QUALITY ASSURANCE PLAN - INCLUDING COMPANY ORG CHART & INDEX OF QUALITY PROCEDURES X +2P R - - pdf - M
P02 HYDROSTATIC/PNEUMATIC TEST PROCEDURES - +6P R - - pdf - M
P03 NON-DESTRUCTIVE EXAMINATION (NDE) PROCEDURES - +6P R - - pdf - M
P04 WELD PROCEDURE SPECIFICATION (WPS) - +6P R - - pdf - M
P05 PERFORMANCE TESTING & FACTORY/FIELD ACCEPTANCE TEST PROCEDURES - +6P R - - pdf - M
P06 ENVIRONMETAL TEST PROCEDURES - +6P R - - pdf - M
Manuals Requirements
P = Purchase Order
T = Inspection / Testing
+ = After
WI = When Issued
# = Number of Weeks
Submit "Certified"
Submission Timing
HC = Hard Copy Shipment
applicable
pdf
M = MRB
V = VMC
NFF = Native File Format
Requirements
+2P / +4P / +6p / +8P = document to be submitted
Manuals
Submit for ( I ) Information or ( R ) Review
T = Inspection / Testing
2 / 4 / 6 / 8weeks after receipt of Purchase Order
D = Dispatch
Submit "Certified"
Submission Timing
X = With Quotation PTS = Prior to issue of Purchasers Inspection
HC = Hard Copy
Release Note and Prior to Release of items for
M= MRB
V = VMC
pdf = Portable Document Format
Shipment
...or
NFF = Native File Format
Q27 MATERIAL TEST CERTIFICATE - PTS - R - pdf - M
Q28 VIBRATION REPORT - PTS - R - pdf - M
Q29 LIFTING EQUIPMENT TEST CERTIFICATES - PTS - R - pdf - M
Q30 POSITIVE MATERIAL IDENTIFICATION (PMI) REPORT - PTS - R - pdf - M
Q31 VALVE FIRE TEST REPORTS / CERTIFICATES X PTS R R - pdf V -
Q32 WELD PROCEDURE QUALIFICATION RECORDS (PQRs) - +4P R - - pdf - M
Q33 FIREPROOF INSULATION AND LAGGING APPLICATION RECORDS - PTS R - - pdf - M
Q34 EQUIPMENT HAZARDOUS AREA CERTIFICATES - +4P R - - pdf - M
Q35 PRODUCTION TEST RESULTS - PTS R - - pdf V -
Q38 EMISSIONS CERTIFICATES - PTS R - - pdf V -
Q45 ROUTINE TEST CERTIFICATES - ELECTRICAL EQUIPMENT - PTS - R - pdf - M
Q46 SURFACE PREPARATION / PAINTING / COATINGS INSPECTION REPORT - PTS - R - pdf - M
Q47 INSTALLATION DOSSIER - PTS R - - pdf V -
Q48 MANUFACTURING RECORDS BOOK - PTS R - C pdf - M
Q49 MATERIAL TRACEABILITY MAPS / RECORDS - PTS - R - pdf - M
Q50 WELD MAP - PTS - R - pdf - M
Q51 MOTOR TEST REPORTS - PTS R R - pdf - M
Q52 MANUFACTURING RECORDS BOOK - TABLE OF CONTENTS - +8P R - - pdf - M
Q53 CERTIFICATES OF COMPLIANCE - PTS R R - pdf - M
Q54 FACTORY ACCEPTANCE CERTIFICATES / REPORTS - PTS R R - pdf - M
Q55 HARDNESS TEST RESULTS AND NACE CERTIFICATION - PTS R R - pdf - M
Q56 PROOF LOAD TEST RESULTS - PTS R R - pdf - M
Q57 REDUCED SECTION TENSILE RESULTS - PTS R R - pdf - M
Q58 IN-PROCESS MATERIAL TEST RESULTS - PTS R R - pdf - M
Q59 INSPECTION RELEASE NOTICES - PTS R - - pdf - M
Q60 SUPPLIER CLARIFICATIONS / TQ / DEVIATION REQUESTS AND RECORDS X WI / PTS R - - pdf - M
Q61 RADIOGRAPHIC INSPECTOR'S QUALIFICATION CERTIFICATE - PTS - R - pdf - M
Q62 RADIOGRAPHIC TEST RECORDS PTS - R - pdf - M
Q63 NOT USED
Q64 DESTRUCTIVE TEST RESUTLS/CERTIFICATES (SPECIFY - 0THER THAN Q27 ABOVE) - PTS R - - pdf - M
Q00 CERTIFICATION AND WARRANTIES - Others (Not Listed Above)
R Technical Reports and Studies
R01 HAZOP REPORTS - PTS R - - pdf V -
R22 PROGRESS REPORTS - 2W R - - pdf - -
R23 POWER SYSTEM ANALYSIS DATA - +4P R - - pdf V -
R38 NOISE CALCUALTIONS AND REPORT - +4P R - - pdf V -
R39 WEIGHT REPORT - PTS R - - pdf V -
R39 WEIGHT REPORT - PTS R - - pdf V -
R00 TECHNICAL REPORTS AND STUDIES - Others (Not Listed Above)
T Technical Data Sheets
T01 TECHNICAL DATA SHEETS - +4P R - C pdf V -
T00 TECHNICAL DATA SHEETS - Others (Not Listed Above)
X Procurement
X09 EXPERIENCE LIST (Supplier) X - R - - pdf - -
X10 ACKNOWLEDGEMENT OF PURCHASE ORDER - +2P I - - pdf - -
X11 UNPRICED COPIES OF SUB-PURCHASE ORDERS (MAJOR-ITEMS) - WI R - - pdf - M
X18 RATE SCHEDULE X - I - - pdf - M
X19 PERFORMANCE GUARANTEE X +4P I - - pdf - -
X20 EXPORT LICENSES OR CLASSIFICATION DETERMINATIONS
X21 LICENSE APPLICATIONS – BIS-748P, BIS-711
X22 LICENSE APPLICATION SUPPORT DOCUMENTS – EAR REQMTS INCL. EUS.
X23 ECCNs - (included in Mechanical Catalog)
X24 SHIPPER EXPORT CONTROL DOCUMENTS (USPPI – EXXONMOBIL)
X25 SPARE PARTS LIST including ECCNs - +8P R - - pdf V -
X00 PROCUREMENT - Others (Not Listed Above)
The following are standard MPN/NPO Information Management Requirements for inclusion into Technical Requisitions for NPO placed
Purchase Orders. Requirements are unique to each Technical Requisition.
Owner of this Document Format is the NPO Business Services IMG Supervisor.
Notes for Use:
1. Project Requisitioning Engineers are to complete information required where shown as (ADD)
2. Amendments to these requirements during Bid Evaluation stage require written endorsement by NPO Project Quality
3. This Cover Page is required to be completed Endorsed and Approved prior to issue of the IRIS and its inclusion into the Technical
Requisition.
INFORMATION REQUIREMENTS:
INSTRUCTION TO SUPPLIERS
(IRIS)
Note to Procurement:
Do not include this Cover Page into the RFQ Packages
2.0 Contents:
This Information Requirements; Instructions to Suppliers document contains the following:
- 3.0 Supplier Information - Definition
- 4.0 General Instructions
- 5.0 Purchasers SDRL Requirements
- 6.0 Supplier Data Requirements (SDRL) – Notes for Use
- 7.0 SDRL Codes
- 8.0 Supplier Document Register (SDR)
- 9.0 Manufacturing Record Book (MRB) & Vendor Mechanical Catalogues (VMC)
- 10.0 Supplier Certified Documents
- 11.0 Numbering of Supplier Documents
- 12.0 Document Transmittal Notes
- 13.0 Purchaser’s process for review of Supplier Documents
- 14.0 Quantities and Document Format Requirements
- 15.0 VMC Dossier Hard Copy Binding Details
Appendices of Appendix D of the Coordination Procedures (Exhibit C):
- Appendix A: Transmittal Note
- Appendix B: Company SDR Form
- Appendix C: Supplier Review Sheet
- Appendix D: Supplier Review Sheet – PDF Decal
- Appendix E: Company Response Sheet
In the case where a Supplier wishes to utilize their own secure ftp site, prior approval must be
obtained from Company. The secure ftp site to be used shall be agreed at the post award kick-off
meeting.
In all cases when the agreed secure ftp site is used for document transmittals, the transmittal shall
be notified by email from the specified sender to the specified recipient.
5) Purchaser’s review and approval of Supplier's documents shall not relieve Supplier from
responsibility for compliance with specified requirements of the Purchase Order.
Purchaser’s review and approval of Supplier's documents shall not relieve Supplier from
responsibility for correctness, safe working and quality of engineering design, materials,
workmanship standards, testing and inspection and all other matters pertaining to the supply of the
purchased items.
6) Information Requirements specified in this document as being applicable to the SUPPLIER are equally applicable to
all sub-Suppliers.
pdf
NFF
1
9.0 Manufacturing Record Book (MRB) & Vendor Mechanical Catalogues (VMC)
Dossiers
1) Supplier shall prepare and submit for Purchaser’s review and acceptance a MRB (SDRL Code Q48) and
VMC (SDRL Code M01) Dossiers as required by the PO SDRL. Each MRB & VMC Dossier shall be
structured, organized and indexed for ease of document retrieval.
2) MRB and VMC Dossiers shall be delivered to Purchaser in electronic and Hard Copy format as
required within Section 14.0 of these Instructions to Suppliers.
3) As required by the SDRL, Supplier shall submit for Purchaser’s review a proposed and detailed Index
for each MRB and VMC Dossiers.
4) “Certified” Documents (see section 10.0 below) shall be compiled into the VMC Dossiers.
5) For complex equipment packages the Supplier will be required to comply with Purchasers Global
Practice GP 21-01-02 Upstream Project Technical Documentation Requirements and Deliverables. This
will be specified in the Purchase Order.
6) Contractor shall prepare the documentation progressively and consistently in parallel with the
progress of actual work. Purchaser shall at all times be given access to Supplier’s documentation, as
related to the PO., for review and verification of status.
Supplier may have their own EDMS Electronic Transmittal which is only acceptable if approved by
Purchaser. The Supplier’s EDMS Transmittal must include all contact details and addressees. Supplier
document submissions should always be addressed to the respective Project Managers or designee and
addressed also to the respective Project DCC’s.
Method for transfer of large files shall be agreed between Purchaser and Supplier at the pre-award stage.
Transmittal numbering shall be agreed at pre-Purchase Order award.
Typically the format will be: T-MPN-XXX-ZZZZ to Supplier (ZZZZ).
Transmittal Codes, FTP transfer and overall process are to be agreed prior to Contract Award.
(See Appendix A –Purchaser’s Transmittal Note)
2) Revision numbers referred to in the table below refer to Company document numbers.
Cod
Status Basis for Code Application Document Status and Required Action
e
INFORMATION Document does not require review or was not Receipt acknowledgment only. Work associated with the
5
ONLY reviewed. document may proceed.
Order Number + Suppliers Works Reference Number + Company’s Document Number and Revision
Number + Suppliers Document Number and Revision Number.
SUBJECT:
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
Signature: Signature:
Date: Date:
Distribution:
Distribution Code:
T = Transmittal Only E = Electronic Copy
O = Original File Format
Issue Status:
[IFI] = Issued For Information [IFR] = Issued for Review [CERTIFIED] = Final
Comments:
Status Certified
SDRL Endorse Final
Supplier Document Number Project Document Number Document Title Rev. Code Planned Date Forecast Date Actual Date
Code Y/N Required
(CRC) Y/N
Appendix BC - Supplier Review Sheet (SRS) (A4 Sheet) Appendix BD - Supplier Review Sheet (SRS)
(PDF Decal)
MOBIL PRODUCING NIGERIA
SUPPLIERS REVIEW SHEET (FOR A4/A3 DOCUMENTS)
DOCUMENT
TITLE
SUPPLIERS
REV NO.
DOCUMENT No
SUPPLIERS
REFERENCE ORDER No. SUPPLIER TO COMPLETE
SUPPLIER NAME:
TOTAL No. OF PAGES
SUBMITTED FOR : Review Information Purchase Order No.:
(INCLUDING FRONT SHEET)
SDR Number:
SUPPLIER TO COMPLETE 1st Issue: Yes/No Submittal No:
Minor Work associated with document may proceed. Comments must be addressed and
2
Comments incorporated prior to re-issue. Revise and Re-submit at next applicable rev. number.
Major Work associated with document may NOT proceed. Comments must be addressed and
3
Comments incorporated prior to re-issue. Revise and Re-submit at next applicable rev. number.
Work associated with document may NOT proceed. Alignment meeting between Company
4 Not Accepted and Supplier is required to re-focus effort. Comments must be addressed and incorporated
prior to re-issue. Revise and Re-submit at next applicable rev. number.
Information
5 Receipt acknowledgment only. Work associated with the document may proceed.
Only
Electronic Files
Hard
Document Category Original;
pdf Copy
File Format
REPORTS
Progress Reports 1 - -
Planning Schedules 1 - -
Cost Estimates 1 - -
ENGINEERING & TECHNICAL
i) Documents: Specifications, Calculations, , Data Sheets, and Bills of Material, Plans, Philosophies,
Studies etc.
a) For Review 1 - -
b) Final 1 - -
c) Technical Querys & Deviations Requests to JOB SPECIFICATION 1 - -
ii) Indexes, Registers, Schedules, Lists & Matrices
a) Engineering & Technical - 1 -
b) Document Lists (MDRs, SMDRs, DDMs, SDDMs etc.) - 1 -
iii) Drawings
a) CAD Drawings - For Review 1 - -
b) CAD Drawings - Final (As-Built)) 1 1 -
c) Other Drawings 1 - -
MANUFACTURER’S INFORMATION
i) Documents:& Drawings - For Review & Final (Certified) 1 - -
ii) Indexes, Registers, Schedules, Lists & Matrices
a) Engineering & Technical - 1 -
b) Document Lists - (SDRs etc.) - 1 -
iii) Manufacturer’s Dossiers
a) Manufacturer’s Records Books (MRBs) 1 - -
b) Vendor Mechanical Catalogues (VMCs) 1 - 2
c) Operations, Installation & Maintenance Manuals 1 - -
iv) Spare Parts
a) Recommended Parts Lists - 1 -
b) Spare Parts Control Log - 1 -
MATERIALS
i) Materials Status Reports 1 - -
ii) Expediting Reports 1 - -
CONSTRUCTION & INSTALLATION
i) Documents & Drawings - For Review 1 - -
ii) Red-line As Builts 1 - -
iii) Construction Records Dossiers 1 - -
MECHANICAL COMPLETION &SYSTEMS COMPLETION
i) Documents & Drawings 1 - -
ii) Red-line As Builts 1 - -
iii) Mechanical Completion & Systems Completion Dossiers 1 - -
iv) Mechanical Completion & Systems Completion Data Base - 1 -
PROCUREMENT
a) CONTRACTOR's Proposed Source List 1 - -
b) Revisions 1 - -
Special Conditions :
Weight Impact :
CHANGE ORDER: CONTRACTOR shall be authorized to proceed with the Change as described above when this CHANGE
ORDER is signed by COMPANY. When the CHANGE ORDER is signed by both COMPANY and CONTRACTOR, then the
Parties shall be obligated to fulfill the terms and conditions of the CONTRACT as may be modified above in respect of this
CHANGE ORDER. The price adjustment and impact to schedule, if any, reflected in this CHANGE ORDER represents the full
and complete adjustment to the CONTRACT for the scope of work presented in the Change Request. NO FURTHER CHANGE
ORDER SHALL BE REQUESTED BY CONTRACTOR OR AUTHORIZED BY COMPANY TO REFLECT A SCHEDULE IMPACT
OR PRICE ADJUSTMENT ARISING FROM THIS CHANGE ORDER OR ANY PREVIOUSLY AUTHORIZED CHANGE
ORDER(S), EITHER SINGULARLY, COLLECTIVELY, AND/OR CUMULATIVELY. Nothing in this CHANGE ORDER shall be
construed as a precedent for future CHANGE ORDERS. This CHANGE ORDER is executed in duplicate originals on the date
shown below.
For CONTRACTOR: For COMPANY :
Signed by : Authorized by :
Print Name : Print Name :
Date : Date :
Attach documents with all information required to evaluate the Specification Deviation (e.g., P&IDs, ISOs, Material Selection
Worksheets, calculations).
Attachments provided? Yes (If yes, provide list here) No
Reference any associated NCR, TQ, RFI Concession Request, CAR, etc., or enter N/A if none
If this is a one-time Specification Deviation, describe affected equipment/component (including tag number, if applicable) and
location:
PT Engineering Manager or higher if required: Signature and Date (only after completion of Sect 4-8 as
required):
Have the Project Specifications been changed to reflect the Specification Deviation? Yes Not
Required
CONTRACTOR Site Lead Signature: Date:
PT Responsible Engineer Signature: Date:
Part II
(COMPANY Evaluation and Approvals)
Section 4: Impact of Change To Project
Check all that apply: None Positive Negative N/A
Safety/Health
Environmental
Regulatory
Cost (1)
Engineering/Construction
Corrosion Protection
Maintainability, Operability,
Reliability
Weight Change
Other
Positive impact is a reduction in cost or schedule. Negative impact is an increase in cost or schedule.
(1) MOC may be necessary
Section 5: Risk and SSH&E Screening
Mark boxes before change with 'X' and after change with 'O' or enter information here: ________________ _______________
Risk Before Change Risk After Change
Comments:
Risk/SHE Impact from this Change:
The PT may approve the Specification Deviation if the cost is within the PT
DOAG and if :
The change reduces risks from high to medium or medium to low, or
The Specification Deviation remains within the Low or Medium risk areas
Proceed directly with returning response if (1) Functional endorsement is not required and (2) MOC is not required.
Comments:
SSH&E_______________________________________________
Commissioning _____________________________
QA/QC
_______________________________________________
MOC Coordinator:
Other _____________________________________
______________________________________
FG3 - Loss Prevention and Other Review Recommendation / Action item Tracking Template
Hazard/Scenario
Causes
Consequences
Safeguards
Risk Before
Action Action Item
Item No.
Risk After
Action Owner Due Date
Action Plan
Comments:
*Bidder must also provide a complete Nigerian Content Compliance Certificate (NCCC)
template (fill applicable portion)
NCCC/OP/UP/Ol/IO
OPERATOR/PROJECT PROMOTER:
CONTRACT/PROJECT TITLE:
CONTRACT/PROJECT NO.:
MAIN CONTRACTOR:
SUBCONTRACTORS:
This is to certify that this Contract/Project having met all applicable provisions of the Nigerian Oil and Gas Industry Content
Development Act, 2010 as evidenced in the Agreed Nigerian Content Scope below, is hereby certified compliant for
recommendation for award.
NC
S/N DESCRIPTION VALUE NC % Comments/ Details on NC Value
($)
Number of Nigerians
CONSTRUCTION/
7. INSTALLATION Their positions
Associated man hours
NC
S/N DESCRIPTION VALUE NC % Comments/ Details on NC Value
($)
NIGERIAN
BANKS/INSURANCE Provide Names Nigerian Banks/Insurance
11.
COMPANIES/LEAGL FIRMS companies/Legal Firms to be engaged
TOTAL NC VALUE
13.
TOTAL NC %
14.
1% NIGERIAN CONTENT
BEING 1% OF THE CONTRACT SUM DEDUCTED
DEVELOPMENT
15. ENBLOC UPON CONTRACT AWARD AND PAID
FUND(NCDF) DEDUCTION
INTO NCDF
______________________________ ______________________________
Company may require Contractor to verify, and ensure that its Subcontractors verify, the use of
chemoprophylaxis by their respective non-immune employees through laboratory testing or other means
acceptable to Company on a cost reimbursable basis. Upon written request from Contractor, Company will
help facilitate Contractor's use of the same personnel and laboratories for Contractor's employee testing as
Company is using for its employees. Should Contractor choose to use these personnel, Company will pay
all fees for the services provided and test results will be provided to Contractor's designated medical
review officer (not to Company or to any non-medical personnel in Contractor's organization). Should
Contractor choose to use other means for collecting, storing, testing and reporting, Company reserves the
right to audit the processes and facilities and to determine acceptability to Company of those alternative
providers. Company further reserves the right to refuse to reimburse any amount charged by the
alternative providers which is in excess of that which would have been charged had Contractor chosen to
use the same providers as Company. Company may review Contractor's program and actual
implementation measures for acceptability to Company.
Contractor agrees to provide written notice to Company within 24 hours of learning of any stewardable
case of malaria experienced by any Contractor or Subcontractor personnel providing Services to
Company. For purposes of this notification requirement, a "stewardable case of malaria" shall include any
death as a result of malaria whether previously diagnosed or not; a diagnosed case of malaria in a semi-
immune person (i.e., a person born and raised to the age of at least 5 years in a location that has similar
intensity of transmission as the location of the current malaria exposure who has not been away from such
exposure for more than 12 months preceding the current period of exposure), which also includes any one
of the following: 1) hospitalization, 2) 5% or higher level of parasitemia, or 3) meeting the World Health
Organization (WHO) criteria for severe malaria; and any diagnosis of malaria in a non-immune person
[anyone other than a "semi-immune person"].
10 For personnel that are Applies to semi-immune (2) Permethrin can be applied to the following items:
) outside from dusk to and non-immune (3) a) Field utility uniform blouses and trousers
dawn, treat clothing with employees of b) Other working clothing such as coveralls
insecticide suited for CONTRACTOR/
c) Insect repellent ("Deet") jackets (when liquid
purpose (permethrin). Subcontractor living/working
Deet is not available)
in or traveling to a malarial
d) Canvas GP and CP tents
area (1) on COMPANY
contractual scope of work. e) Bed nets
Includes expatriates, rotators Permethrin should not be applied to the following:
and business travelers for a) Underwear
any trip duration.
b) Hats
c) Waterproof materials including vinyl coated
tents and waterproof tent flies
d) Extreme cold weather gear ("Gore-Tex"
material)
e) MOPP gear
11 Ensure that personnel Applies to semi-immune (2) Personnel should avoid unnecessary exposure
) wear long sleeve shirts and non-immune (3) (outside) to mosquitoes during dawn to dusk
and pants when working employees of hours.
outside from dusk to CONTRACTOR/
dawn; strongly Subcontractor living/working
encourage at other in or traveling to a malarial
times. area (1) on COMPANY
contractual scope of work.
Includes expatriates, rotators
and business travelers for
1) A malarial area (1) is any area of the world where the Centers for Disease Control and Prevention (CDC) has
recognized a risk of malaria and/or any location worldwide where COMPANY has implemented its own
Malaria Control Program.
2) Persons that have been repeatedly exposed over their lifetime and have acquired some partial immunity to the
malaria parasite are considered to be semi-immune (2).Typically nationals that have not spent any significant
amount of time out of the malarial area (1). If in any doubt, consult physician.
3) Persons that are not native to a particular malarial area (1) are considered to be non-immune (3) .Typically these
are considered to be any expatriate even if such persons have spent a significant amount of time in a
particular malarial area (1).
4 CONTRACTOR shall procure and ensure that adequate stock of COMPANY approved Malaria Survival
Kits(MSK) are available to concerned employees at all times.
As per EMDC guidelines Contractor shall complete the relevant MCCP enrollment with INTERNATIONAL
SOS (ISOS) of all non-immune and maintain records.
Contractor, its employees, agents, and subcontractors shall comply with the requirements set forth in this Exhibit.
Contractor shall notify its employees, agents, and subcontractors of the requirements of this Exhibit.
A. Cell-phones, whether hands-free or hand-held, may not be used during the time Contractor is driving while
performing services exclusively for Company, regardless of whether the vehicle is owned by Company.
Without limiting the generality of the foregoing, cell phones may not be used while driving during:
(i) Travel between sites or locations at which Contractor performs services for Company ("Company
Sites"), regardless of whether such sites are owned or operated by Company,
(ii) Transportation of Company personnel, regardless of whether non-Company personnel are
concurrently transported, or
(iii) Travel to a point of departure, such as an airport, train station, or port, for a trip involving business
related to Company.
B. The foregoing prohibition against cell phone use does not apply to:
(i) The daily commute between the driver's residence and Company Site,
(ii) Commutes between Company Site and non-Company businesses for which Contractor, its
employees, agents, or subcontractors may perform work,
(iii) Common carriers,
(iv) Private carriers, manufacturers, distributors, and suppliers that transport both Company and non-
Company items in their vehicles,
(v) Citizen band and/or two-way radios,
(vi) Use while the vehicle is properly parked in a rest area, designated parking area, or other safe
location, and
(vii) Use of cell phones by passengers if the use is not a distraction to the driver of a passenger vehicle.
Maintenance Workers: Both office and field maintenance personnel working under little or no
supervision and having access to sensitive or critical information, areas and personnel
NOTE: The Spreadsheet below provides additional clarity and guidance for EM Contractors’ compliance
on SBC requirements. Security Background checks for personnel occupying security sensitive position
working on EM projects will be conducted by MPN HR approved SBC Consultants.
EPC/EPCM Contractors and PT shall consult NPO Security Supervisor or Alternate for further
clarification/information.
Unless otherwise specified by Buyer, Contractor shall provide and maintain field medical care services acceptable to
Buyer, including personnel, equipment, supplies and facilities suitable to the geographical area of operations in
accordance with the standards set forth in Attachment 1 of this Exhibit. This includes a qualified Emergency
Medical Technician, Paramedic, Nurse, or Medical Doctor onsite that is appropriate for the operation. In addition,
adequate back-up medical support (24-hour coverage) with a Consultant Physician holding a current certification in
emergency medicine from USA, Canada, Western Europe, Australia, New Zealand or South Africa.
All medical service providers shall be licensed in the area they are providing services and shall provide medical
liability insurance providing coverage in the area where the personnel are licensed and in the areas where they are
practicing.
The Medical Service Provider(s) will have a minimum of one year of field care experience in a remote location
Contractor and Buyer shall mutually agree on the number and type of qualified medical personnel, equipment,
supplies, and facilities that will be available for the project.
C.V.'s and license for Field Medical Care Providers and Consultant Physician
ExxonMobil shall have the right, at its discretion, to perform unannounced audits/inspections of Contractor's on site
medical services, including medical personnel, equipment and supplies, to verify that Contractor understand and
comply with ExxonMobil's contract requirements regarding medical services.
Attachment 1
1. Contractor shall deliver field medical care services, in accordance with internationally recognized standards and
protocols and provide field medical providers with current certifications in BLS,ACLS, BTLS or the equivalent
from the USA, Canada, Western Europe, Australia, New Zealand or South Africa. Medical service field providers
shall have 24 hour access to a consultant physician, with a current certification in emergency medicine trained in the
USA, Canada, Western Europe, Australia, New Zealand or South Africa. Field medical services shall include:
General medical care, including diagnosis and therapy of common, acute medical conditions
First aid and minor trauma management, including control of bleeding, treatment of shock, treatment of hypothermia
and heat stroke/exhaustion, treatment of burns, scalds, inhalation of hot gases and fumes, suturing of lacerations,
immobilization of sprains and simple fractures, and removal of non-embedded foreign bodies
In-field stabilization of medical and surgical emergencies, including cardiovascular and trauma
Rescue, extrication and medical transportation of ill or injured parties by suitable air, water or ground transport
2. Contractor shall provide occupational health (OH) services in accordance with Buyer’s OH procedures and
protocols and consult with Buyer OH advisers, as required. OH services shall include:
Return to work examination
Health inspection of the field facilities including vector control program, drinking water sanitation and food
sanitation
Monitoring of the catering staff
Exposure monitoring (e.g. noise, as required)
Health awareness and training (e.g. first aid training)
3. Contractor shall provide appropriate and adequate quantities of equipment, medication and consumable supplies,
befitting internationally recognized protocols for the delivery of medical care, and commensurate with the training
and experience of the medical personnel. Contractor shall maintain medical equipment in good operating order at
all times. Contractor shall maintain a complete and up-to-date inventory and ensure that appropriate minimum
quantities of critical medications and consumables are available at all times. A list of critical equipment is provided
in this Attachment. Contractor will review proposed inventory with Buyer health advisors and will advise Buyer in
writing of subsequent changes.
4. Contractor shall provide qualified personnel experienced in delivery of medical and OH care in remote locations and
possess evidence of the requirements described in this Attachment. Contractor shall submit the certifications and
resume of the proposed candidates before mobilization.
5. Contractor shall provide Buyer with evidence of operating procedures, protocols and reference materials regularly
used by the field medical care providers.
6. Buyer will provide Contractor with Buyer health reporting forms, software and instructional materials where
compliance with Buyer’s Health Reporting System procedures is required.
Medical Equipment
Where appropriately trained and licensed medical personnel are required and in place to maintain and operate the
equipment listed, Contractor shall provide the field facility with the following equipment:
Cardiac monitor defibrillator (including manual operation mode and 12 lead EKG capability)
Intubation kit with Lynch scope
Suction pump
Oxygen resuscitator and manual resuscitator
Pulse oxymeter
Sterilizer/autoclave
Kendrick extrication device
Body splint (vacuum mattress) and spinal board
Splinting kit
Stretchers
Scoop stretcher
Stiff cervical collar/neck splints
Cardiac Kit with medications
IV sets
Contractor shall prepare a list of critical medications and consumables commensurate with the training and
experience of the medical personnel and in quantities appropriate for the numbers of covered staff and re-supply
intervals. The list shall be reviewed and approved by the Buyer health advisor and any subsequent changes shall be
requested in writing.
Medical Service Provider shall be able to meet ExxonMobil specifications as a minimum or all regulatory
requirements including local license requirements, whichever is more stringent.
Medical Service Provider shall provide medical liability insurance to cover medical personnel where they are
licensed or where they will work.
The Medical Service Provider(s) will have a minimum of one year of field care experience in a remote location.
Consultant Physician
Consultant physician shall possess current certification in emergency medicine or equivalent from the USA, Canada,
Western Europe, Australia, New Zealand or South Africa. Consultant physician shall be actively involved in daily
management of emergencies and be accessible by telephone 24 hours through similarly qualified backup, as
necessary.
I. APPLICATION
Projects/works/services include engineering, fabrication, marine, aviation, land transport, and drilling
activities as well as provision of specialist national and expatriate personnel within Nigeria to MPN and
EEPNL.
The Guidelines are not applicable to contractors supplying only materials and or consumables e.g. fuel
products to any of our upstream subsidiaries.
Community groups would be required to meet the expectations listed on Attachment B, to further
facilitate the application of these Guidelines by primary contractors/sub-contractors working for the
upstream subsidiaries.
II. PURPOSE
• Promote an incident free workplace in consideration of industrial safety, occupational health and welfare
of Contractors/sub-contractors and their workforce.
• Provide transparent process for effective planning, implementation and monitoring of community and
labor relations activities by
Contractors /Sub-contractors working for MPN & EEPNL.
• Ensure realistic, competitive and equitable wages, and conditions of service of workers employed by
Contractors/Sub-contractors in order to motivate them for effective utilization of manpower and man-
hours.
• Clarify roles and responsibilities of key stakeholders in the interface chain and facilitate open
communication.
• Promote community and Nigeria content in projects handled by Contractors/Sub-contractors for MPN
and EEPNL.
III. INTRODUCTION
Mobil Producing Nigeria (MPN) and Esso Exploration and Production Nigeria Limited (EEPNL) (herein
referred to as “Company”), the Upstream subsidiaries of ExxonMobil (herein referred to as
“Corporation”) in Nigeria utilize services of many Nigerian and Foreign Contractors/Sub-contractors
(herein referred to as “Contractors/Sub-contractors”), to support the company’s business activities (herein
referred to as “Service”). Depending on the scope, these Services require continual interface with
business units, government officials and members of the communities within and outside the project
locations. It is important that the interface process is understood by all key stakeholders and that
Contractors/Sub-contractors maintain harmonious relationship with the communities to ensure non-
disruption of the Service activities. It is also essential that Contractors/Sub-contractors adhere to
ExxonMobil’s Corporate Guiding Principles.
“Be a good corporate citizen in all the places we operate worldwide. We will maintain high ethical
standards, obey all applicable laws, rules, and regulations and respect local and national cultures. Above
all other objectives, we are dedicated to running safe and environmentally responsible operations”.
While we maintain flexibility to adapt to changing conditions, the nature of our business requires a
focused, long term approach. We will consistently strive to improve efficiency and productivity through
learning, sharing and implementing best practices.
We aspire to achieve our goals by flawlessly executing our business plans and by adhering to these
guiding principles.
Contact Groups: The Contract Owner (for MPN or EEPNL) is the primary contact for coordination of
all Projects/works/services activities.
However, Company’s Public Affairs and Human Resources Departments will provide necessary
guidance, assistance and advice on community and labor relations activities. These include introducing
Contractors/Subcontractors to authorized community contact persons/groups; regular review of issues and
status of compliance with stated Community Relations, Labor and Security Guidelines.
Contractors/Sub-contractors are advised to restrict all formal interfaces on community and labor related
matter with external publics to and through the collective authorized community group. Requests received
from other individuals or groups should be communicated to the authorized community group, with
notification to MPN Public Affairs personnel and Contract owner, for information and appropriate
guidance.
Contractors/Sub-contractors will be primarily responsible for their community relations, labor and
security activities, to ensure enabling environment for timely and incident-free completion of job. To this
effect, Contractors/Sub-contractors should engage staff, competent in community relations, labor and
security practices and conversant with the operational areas, to handle these activities.
Community Employment: It is the Company’s objective to ensure that communities in the immediate area
benefit in terms of employment and related activities from the projects/works/services, while also
accommodating interests of other communities.
For non-highly specialized services/job positions (e.g. those requiring less complex/professional skills),
and as otherwise justified, the following employment sharing formula shall apply for services to be done
at the respective locations:
The ratio for immediate communities will be in accordance with existing practice of Ibeno (30%),
Eket (26%), Esit Eket (24%) and Onna (20%), out of the share of 30 percent.
For projects located in Bonny, the ratio for Finima and Bonny will be 40% and 60% respectively, out of
the immediate community share of 30 percent respectively.
Deepwater Operations Coastal Nigerian states and Nigeria will be the focus for projects located within
EEPNL’s deepwater operations. Local workforce recruited from the communities would include skilled
professionals e.g. engineers, accountants etc (except where such are not available) as well as semi-skilled
and non-skilled personnel. Job positions in these categories include but not limited to the following:
welders, electricians, pipe fitters, scaffolders, sand blasters, carpenters, mason, stewards, cooks, drivers,
helpers, etc.
Staffing Plan Conditions of Service: Company will require Contractor/Subcontractor to provide its
Staffing Plan and Conditions of Services stating factual information on the following, prior to
mobilization:
Complete list of its own core staff to be utilized for the Project, stating Local Government areas of
origin, states and nationalities for each job position occupied.
Additional job positions with stated qualifications for personnel, to be recruited locally for the
project.
Work schedule and project staffing plan
Breakdown of pay structure and payment schedule for the locally recruited personnel
Duration of employment
All other conditions of employment including bonuses, special payments, and other benefits (as
applicable)
This information would be reviewed with Company contract owner designated personnel, Public Affairs
and Human Resources departments to ensure reasonable community participation and compliance with
Nigerian laws
Employment Distribution: Employment slots for the communities will be shared through the authorized
community groups based on an established formula, where available or as jointly agreed with the
communities. In all cases, the Contractor/Sub-contractor shall have responsibility for determining the
necessary qualifications and suitability of the potential workers. Contractor/Sub-contractor should plan to
provide standard requisite training as maybe required to enhance skill levels of local personnel for the job.
All recruited persons must be assigned specific job tasks. No standby positions/practice allowed. If the
project size and scope dictates, Community Liaison Officers (CLO5) would be appointed from among the
already recruited staff that has other assigned duties. Such person(s) may earn additional stipend as an
incentive. Solely designated CLO position will not exist. The CLOs will not be involved in recruitment
processes.
Wages: Contractors/sub-contractors are expected to pay realistic, competitive and equitable wages in line
with standard competitive practices in the Nigerian Oil and Gas Industry and commensurate with other
companies offering similar services within the environs. Conditions of service, specifying salary and
other benefits including contract duration and terminal benefits, should be stated and duly executed as
agreed by all parties (Company, Contractor/Sub-contractor and workers, prior to commencement of
work).
Guidelines of expected compensation rates will be issued from time to time.
Labor Contractors: Depending on the size of the workforce (e.g. above 20) and project duration,
Contractor may engage the services of a Labor Contractor to coordinate and manage its recruited
workforce. Such appointees should be reputable companies owned or managed by indigenes of the
immediate project communities, having requisite experience, strong organizational and financial
background or any other relevant criteria as determined by Contractor. The labor contractors will be
responsible for managing the labor requirement of the community workforce after their recruitment.
Contact Offices: All contractors sub-contractors, including those involved in providing services for the
deepwater operations are advised to have functional contact office/address in an accessible on-shore
location outside Company’s facilities and within/around the project vicinity/state. The contact offices
would serve to facilitate interface activities, including dissemination of relevant information to members
Page 340 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
Tender Number – 00000144 JOB SPECIFICATION Section F
Coordination Procedure
In addition, the company encourages contractors handling such relevant contracts to endeavor to execute
as much of the project and fabrication activities involved locally and consistent with the Nigerian Content
Development Short Term Directives issued by the Nigerian National Petroleum Corporation (NNPC),
Local ContractinglContract Awards: Contractors/ Sub-contractors are encouraged to give priority to
companies within the communities for their supplies and support requirements. Contractors/sub-
contractors should ensure proper documentation and prompt payment for these activities.
Suggested assistance areas with sustainable and wide utility impact, include but not limited to training
schemes, scholarship awards, construction/equipping of educational and health facilities, sundry
donations, program sponsorship, etc. Recommended activity and execution plan would be as determined
by Contractor but endorsed by the Company Public Affairs Department in conjunction with the
communities. Contractors/sub-contractors should not give cash for this purpose to any member of the
community or its representatives.
Gifts: Contractors/ Sub-contractors are advised to recognize and respect local customs and traditions.
However, gifts and donations to groups/persons shall not exceed a nominal value of $200 or N26000 per
sizeable group of not less than 5 persons or $50 per individual. Gifts are discouraged and should not be
given in exchange for favorable treatment or to facilitate approvals.
Local Taxes and Levies: Contractors/Sub-contractors are required to pay relevant local taxes and levies
which are within bounds of the law.
Monitoring and Reporting — Contractors/Sub-contractors are to submit quarterly status report of
compliance with the above items to the Companys contract owner and Public Affairs designated
personnel.
Liability — Contractor/sub-contractor will be liable for disruptions by the communities if established that
such resulted from their failure to comply with above guidelines. The Company will continue to liaise
with community to promote enabling environment for contractors/sub-contractors to operate.
Community and Labor Relations Plan - Details of the above stated items should be included in the
Contractor’s Community and Labor Relations Plan to be submitted as part of the tender documents.
Following the contract award, the overall Plan will be reviewed and endorsed by Company Public Affairs
Department, prior to their mobilizing for the Project.
For the purpose of these Principles and Guidelines (including the Recitals), the following words and
phrases shall have the meaning stated below:
Primary Contractor - Contractor having direct contractual agreement with either Mobil Producing
Nigeria (MPN) or Esso Exploration and Production Nigeria Limited (EEPNL) herein after ref erred to as
Communities - Geographical areas located around Company operations to the Nigerian State in general
Immediate community” - Geographical communities and or Local Government Areas within or around
Company’s operations and/or where specific Service activities are carried out. For Qua lboe Terminal
(QIT)/Offshore, Akwa Ibom State located Services these are the four (4) Local Governments of Ibeno,
Eket, Esit Eket and ONNA. For Bonny River Terminal (BRT)/Onne Shorebase, Rivers State located
Services; they are the three (3) Local Govemments of Bonny, Onne and lkpokiri.
Coastal Community - Geographical communities identified and so designated by the Akwa thom State.
These include the five (5) Local Governments of Eastern Obolo, Ikot Abasi, Mbo, Nsit Ubium and Mkpat
Enin.
Outer Community - Local Governments within Akwa Ibom and Rivers States outside the listed
immediate and coastal communities, as applicable.
Service - Contractors/Sub Contractors Company contracted activity
Contract Owner - Specific Business unit within MPN or EEPNL stewarding the contracted Service
Authorized Community Group - Group having the mandate of recognized and accepted
Community/Government authority to coordinate labor related activities
• Collate and maintain database of employable candidates as well as professional groups, within their
respective localities.
• Ensure that information on Job Vacancies, short listed and successful candidates are duly posted at
designated locations accessible to the community publics. The group will maintain comprehensive
database of all employments/programs offered by each Contractor and provide periodic updates of these
to respective constituting authority, community leadership and its general public
• Adjudicate on labor disputes that may arise between the communities, workers, labor contractor,
contractor and/or company.
• Play active role in ensuring a conducive operating environment and non disruption of the Service
activities by the contractor community staff or members of the community.
• Provide periodic status reports of its activities including the community participation in the service by
the various Contractors/sub contractors to the respective constituting authority, the State Government,
Company and as well as members of their respective communities
• Participate in periodic (quarterly) review meetings with Contract Owners, Public Affairs, Human
Resources, Security and Contractors representatives to review status and address issues/concerns.
• Constitute and/or continue to provide oversight function to the Authorized Community Group.
• Along with the Authorized Community Group steward communication of periodic status reports of
community participation in the service activities to the respective community publics.
• Assist, as necessary in adjudicating on community and labor issues that may arise between the
Authorized Community Group, Contractors Community Staff, Contractors and/or Company.
• Help facilitate a conducive operating environment to ensure non disruption of project activities
• Comply with the terms of their employment agreements as duly executed. Any request for amendment
shall be in line with stated procedure
• Support and promote the business objective of the project for which they have been hired, to ensure safe
and timely execution of the project
• Comply with stipulated Nigerian labor guidelines for resolution of conflicts and will utilize structured
approach in presenting their requests and resolving conflicts. The following channels are recommended:
(i) Contractors’ Community Staff initiates dialogue with designated Contractor personnel on issue of
concern/request
(ii) Where issues are not resolved, Contractor Community Staff shall formally notify the Authorized
Community Group or their labor contractor as applicable, for their intervention
(iii) Authorized Community Group or labor contractor or Contractor or Business Unit will promptly
notify Public Affairs for information and necessary action towards resolving the issues
(iv) Contractor Community Staff shall always respect agreement reached with their employer
• Defer to the Authorized Community Group on all community and labor relations issues.
• Not unduly interfere in the relationship between Contractor and Contractor Community Staff.
• Notify the Constituting Authority and Company Public Affairs of any issues of concern with respect to
the conduct of Authorized Community Group or the Contractor.
• Provide a conducive operating environment to ensure incident free, safely and timely execution of
project activities.
ATTACHMENT C:
ATTACHMENT D:
a. Pledge to abide by the rules and regulations governing my contract with _______ (my
employer) throughout the duration of the project.
b. Pledge to be totally committed to the Safety, Health, Environment and Security values of
MPN
c. I commit to strictly adhere to all lawful instructions issued to me in the course of discharging
my duties for the success of the project.
d. I shall discharge my responsibilities to the best of my ability and in accordance with the
expectations of my assigned roles.
e. I will not in any way, consciously or unconsciously, instigate, incite, promote, partake or
encourage other workers to embark on any form of strike action or cause the breach of peace
throughout the duration of the project without following the specified Grievances Procedure
and as authorized by law.
f. I further affirm that any form of grievances shall be channeled through my employer,
following the specified grievance procedure and via the authorized workers representative for
resolution.
g. I will contribute to the overall success of the project and undertake that any disciplinary
action, legal or otherwise be taken against me, if I run foul of the aforestated.
h. I fully understand and accept the terms and conditions as stated in my contract.
This undertaking is made in good faith and without any form of coercion whatsoever.
Page 346 of 407
Onshore Program Construction & Installation Contract (OPCIC) Enabling Agreement
Tender Number – 00000144 JOB SPECIFICATION Section F
Coordination Procedure
Attestation
I confirm that the above person is known to me. For the purpose of his involvement in this project and the
intent this document serves to protect, I therefore attest to his good conduct throughout the duration of the
project.
Signed by Me: …………………………….. Name:…………………………..
Date:……………………………. Address:………………………..
1. Contractor shall act in accordance with Company’s Statement of Principles on Security and Human Rights
(refer to page 2 attached) and applicable provisions of the Universal Declaration of Human Rights, the
Fundamental Principles and Rights at Work of the 1998 ILO Declaration, the UN Code of Conduct for Law
Enforcement Officials and the UN Principles on the Use of Force and Firearms by Law Enforcement
Officials and communicate such expectations to Government Security Forces (“GSF”).
2 Contractor shall maintain policies regarding appropriate standards of conduct, including respect for human
rights, for its employees and contract workers (“Personnel”) assigned to provide services for Company.
3 Contractor shall provide training to its Personnel assigned to provide services for Company on applicable
laws, Company's Statement of Principles on Security and Human Rights, Contractor's policies regarding
appropriate standards of conduct, and applicable provisions of the Universal Declaration of Human Rights,
the Fundamental Principles and Rights at Work of the 1998 ILO Declaration, the UN Code of Conduct for
Law Enforcement Officials and the UN Principles on the Use of Force and Firearms by Law Enforcement
Officials.
4 Contractor shall only provide defensive security services to protect Company personnel, facilities and/or
operations. Contractor shall not engage in activities related to general maintenance of law and order which
is the exclusive responsibility of the host government.
5 Contractor shall monitor the conduct of its Personnel and GSF assigned to provide services to Company
and provide Company with notice of any allegations of human rights abuses committed by Contractor's
Personnel or GSF at Company facilities or directly related to Contractor's protection of Company
personnel, GSF, facilities and/or operations. Contractor shall also provide Company with notice of any use
of force, even if such use of force is appropriate, committed by Contractor's Personnel or GSF at Company
facilities and/or directly related to the Contractor's protection of Company personnel, facilities and/or
operations.
6 Contractor shall report in writing all credible allegation of human rights abuse (in any form) committed by
Contractor's Personnel or GSF at Company’s operational facilities or directly related to Contractor's
facilities or personnel protection to NPO Security via the Project Manager/Project SSHE Manager for
appropriate Company notification.
7 Consequent upon above #6, Contractor shall investigate any credible allegation of human rights abuses
committed by Contractor's Personnel or GSF at Company facilities or directly related to Contractor's
protection of Company personnel, facilities and/or operations and shall report the results of the
investigation to Company for appropriate notifications and guidance.
8 Contractor shall ensure that GFS under investigations for alleged involvement in human right abuses are
deployed to provide security services for Company project or business.
9 Contractor shall not assign any individual credibly alleged to have committed a human rights abuse to
provide services for Company. Contractor shall immediately remove any of its Personnel credibly alleged
to have committed a human rights abuse from providing services to Company.
10 Company shall have the right to terminate this Agreement, and Company shall have the right to terminate
an Order hereunder, if Contractor or any Personnel of Contractor is credibly alleged to have violated
applicable laws or to have committed a human rights abuse. Such right of termination is in addition to any
other termination rights under this Agreement or an Order.
11 This Agreement and any Order hereunder is between the parties thereto and shall confer no rights on nor
inure to the benefit of any third party. However, if the Agreement contains language
Affording third party beneficiary rights to an ExxonMobil Affiliate or joint venture operated by an ExxonMobil
Affiliate, such language will prevail over the previous sentence.
ExxonMobil is committed to conducting business in a way that protects the security of its personnel, facilities and
operations and respects human rights. The Company’s practices and operations reflect the spirit and intent of the
Universal Declaration of Human Rights, the Fundamental Principles and Rights at Work of the 1998 ILO
Declaration, the UN Code of Conduct for Law Enforcement Officials and the UN Principles on the Use of Force and
Firearms by Law Enforcement Officials.
While recognizing that host governments have the responsibility of maintaining law and order, security and respect
for human rights, ExxonMobil believes that:
Pursuant to Article 26 of the principal document Contractor shall maintain and preserve, and shall cause
its Subcontractors to maintain and preserve, in accordance with generally accepted accounting practices,
accurate documentation and data (including, but not limited to written and electronic records, books of
account, correspondence, Project Executive Plans, Regulatory permits, licenses, drawings, payroll
records, memoranda, receipts, and documentation of related security data systems and general access to
controls processes and procedures ) or any of the following documentation :
1) Access to original invoices billed to MPN under the Contract/or any Order
7) Receivables report showing payments outstanding from MPN for over 30 days
15) Access to all change orders, with supporting back-up and signatures
16) Access to pending change orders, change order requests, requests for information etc.
17) Access to all payroll/labour distribution reports, certified payroll and/or equivalent
payroll records
18) Access to all cancelled payroll checks, or bank statements showing payroll wire
deposits
22) Access to all equipment rental and materials invoices and equipment time cards
23) Access to subcontractor and vendor and other billings with supporting documentation.
24) Copy of subcontract/vendor status reports showing contract balances (as applicable) at
the end of the job and total amounts paid to each subcontractor/vendor
25) Access to original bid, proposal, budgetary quotes, purchase orders and procurement
process support documentation
26) Access to all cancelled checks and check vouchers (labour, subcontractors, vendors and
others)
28) Access to project correspondence, meeting minutes, notes, observation reports etc.
Please note that the above list is merely indicative. Additional information requests may be made
based on actual audit work.
Purpose:
This program is to ensure that Contract employees that are potentially exposed to workplace hazards
above the recommended exposure limits undergo periodic monitoring to measure and follow-up on
markers of health effects.
Triggers:
The Medical Surveillance Program is aimed at protecting workers exposed to physical or chemical agents
above a specified threshold (frequency and intensity of exposure) for which medical screening exist.
Potential hazards include:
Noise
Benzene
Hydrogen sulfide
Lead
Asbestos
Man-made mineral fibers
Program for Respirator users
These are stewarded under the guidance of specific programs. Contractors are expected to develop their
programs which should contain the same key elements as the ExxonMobil templates.
For instance, surveillance for Noise exposure requires annual audiometry for their employees thus
exposed. Contractors shall ensure that abnormal results are followed up by an appropriate medical
specialist.
Company’s Medical and Occupational Health Unit (“MOH”) should be contacted for more information
on this.
Process
Contractor
1) Completes Exposure Monitoring of work site and identify workgroups requiring medical
surveillance.
2) As in most cases, where contract employees work alongside ExxonMobil employees in the same
group, and such monitoring has been carried out by MOH (Industrial Hygiene) the contractor
makes use of this information to place their employees in that group under the surveillance
program.
3) Submits lists of employees that have undergone the relevant medical surveillance to the
ExxonMobil Supervisor or Business owner for documentation.
Site Supervisor
1) Identifies workers within the workgroups, sends the list of the affected contract employees in
the index group to the respective contractors and informs the contract employees to follow up
with their respective companies for the examination.
2) Verifies that the contractor employees have undergone the monitoring with their employers.
3) Receives lists of Contractor employees that have undergone the relevant medical surveillance
and documents them.
MOH
1) Ensures that the result of Exposure Assessments with the worker groups are available to the
facility supervisor so that those contractors whose employees require surveillance will be
informed.
2) Advises the ExxonMobil supervisor and SHE contact on matters connected with Medical
Surveillance
Job Specification
SECTION G
Revision 1
September 2022
INTRODUCTION
Scope
This section covers Engineering information and definitions required for the engineering and construction
of MPN facilities
Hierarchy
The effective editions and dates of applicable regulations, codes, standards, recommended practices and
specifications, in some cases, may not be clear or may even be in apparent conflict. Any such conflicts are
to be resolved as follows: In the case of government of Nigeria regulations, it is MPN's intent to comply
with the latest applicable regulations. This includes industry or technical society standards, which may
have acquired the force of law through legislation or regulations. For codes, standards and specifications
which do not have the force of law, the effective edition and date are to be determined in one of two
ways:
(1) If the GP Supplements cites a particular edition, that edition is the one applicable.
(2) If GP Supplements cites the "latest edition", then the edition in effect at the time design commences is
the one which is applicable. Use of subsequent editions issued after design commences shall be reviewed
by the project team on a case-by-case basis.
Company Engineering
Documents listed in this section are furnished by COMPANY for the purpose of defining the
FACILITIES. COMPANY documents have been developed to various levels of definition and therefore
changes to these documents require different levels of COMPANY approval.
The following levels are defined:
A. Level 1 - CONTRACTOR is expected to comply with the requirements of these documents.
B. Level 2 - COMPANY has developed these documents to a high level of completion. They have
been through several levels of functional review. CONTRACTOR shall follow the philosophy,
general concepts and methodology. CONTRACTOR shall verify and complete development of
the design. Modifications generated during design development and/or proposed by the
CONTRACTOR must be approved by COMPANY.
C. Level 3 - Documents accurately reflect the desired concept to be carried forward in design
development. CONTRACTOR may modify the details of the documents as required without
COMPANY pre-approval. Any changes to the concept must be pre-approved by COMPANY.
D. Level 4 - Documents provided to assist the CONTRACTOR in providing a bid and provide a
starting basis for design development. CONTRACTOR may make changes to these documents
with COMPANY's approval. Change orders for such changes will not be accepted without pre-
approval by COMPANY.
G. DEFINITIONS
GP and GPS - ExxonMobil Global Practices and Global Practices Supplements
PDB – Project Design Basis
IFB - Issue for Bid
IFC - Issue for Construction
AFC - Approved for Construction
H. STANDARDS
Global Practices
All WORK performed by the CONTRACTOR shall be conducted in accordance with the COMPANY’S
Global Practices (GP) and Global Practices Supplements (GPS) as listed in Appendix [E-1] to this
Section.
Project Standards
In addition to the COMPANY’S GPs all projects shall adopt a number of additional relevant industry
standards as listed in Appendix [E-1].
Total compliance with the GP’s and the above specifications is required of the CONTRACTOR, and of
lower tier vendors. The scope of compliance with the GP’s and the above specifications, their order of
precedence among various projects and engineering documents, how this compliance is evaluated, along
with an explanation for identifying the need for waivers and instructions for following waiver procedures,
is fully explained in GP 00-00-02, latest edition.
The GP GPS are generated by COMPANY to include all the phases of the project (including Design and
Construction) considering the CONTRACTOR as the services provider to COMPANY.
I. DOCUMENTATION
Numbering
All CONTRACTOR documentation shall be numbered and revision controlled in accordance with the
COMPANY’S GPs. The CONTRACTOR will be allocated numbers by the COMPANY.
As-Built Documents
CONTRACTOR shall be responsible for producing all As Built documentation for the WORK. As Built
documentation shall be updated electronically on the electronic copies provided by the COMPANY. All
such updates shall use the same standards as used by the COMPANY.
CONTRACTOR shall submit the updated native file (electronic) copies, plus the original paper mark-ups,
and a scanned (Adobe PDF) copy of the site mark-ups.
Handover Documentation
CONTRACTOR shall comply with the Handover documentation specified in the GPs and in Section F –
Coordination Procedure
DESIGN BASIS
Design Parameters
The tank revamp design and repair activities shall be conducted in accordance with API
653 and API 650 (latest editions)
For purposes of calculations, crude oil shall be assumed to have the following properties:
crude oil
BS&W =0.5% maximum
API Gravity = 36.0-36.4 0API
Viscosity = Low
Salt Content = from 1.5 to 2.0 /MB crude
Pour Point = typically about 500F / 100C
Condensate
For purposes of calculations, the environmental conditions shall be assumed to have the
following properties:
Design Reviews
At 60% of Detailed Engineering Design, MPN will arrange for a Design Review, Risk
Assessment and Constructability Review with Operations, Maintenance, MPN Design
Engineering Services, Loss prevention etc. And at 100% completion, a final Design review will
also be carried out. Contractor will present his design in each of the reviews to the Stakeholders,
record and incorporate comments and suggestions. After completion of these reviews Contractor
will revise the documents and resubmit to MPN as “Approved for Detailed Design” status.
K. Regulatory Approvals
Apart from the fundamental regulatory requirement for petroleum facility construction work, the
key regulatory requirement impacted by this project will be the re-calibration of the tank.
Operatives of the Department of Petroleum Resources (DPR) will be involved in the calibration
QA/QC activities. DPR approval after re-calibration will be obtained prior to commissioning of
tank.
Contractors working on MPN premises will be required to display identification. Entry will be
controlled via established security procedures approved by MPN. The construction readiness
review will include a representative from the security department, and require that approved
security procedures are in place before commencing construction. The security procedures will
address contractor security and access to the MPN work site, and the protection of MPN
personnel and property through unauthorized or uncontrolled access. Security considerations will
be documented during any other review (pre-mobilization, MOC, transportation of persons or
materials, de-mob., etc.) affecting the project execution, any change in the project, or change in
the work procedures at the work site.
Appendix E-1
Table 1
Page 361 of 407
JOB SPECIFICATION Section G
QIT & BRT Crude/Pentane Plus Storage
and
Settling Tanks Revamp (SSTR)
Design Basis Document
Applicable References
International Codes & Standards: As referenced within the Upstream Nigeria (UN) Global Practices
Job Specification
Revision 1
September 2022
Section H
Page 364 of 407
JOB SPECIFICATION Section H
QIT & BRT Crude/Pentane Plus Storage
and
Settling Tanks Revamp (SSTR)
Design Development Document
NOT APPLICABLE
Job Specification
COMPANY-Provided Items
Revision 1
September 2022
NOT APPLICABLE
Revision 1
September 2022
1. General
For this document, the terms defined in Article 1 of the PRINCIPAL DOCUMENT, Exhibit A, and the
following Table J1-6 apply.
Table J1-6: Definitions
Term Description
3LP Multi-Layer Polyethylene/Polypropylene
AIWOCS Alternative Installation and Workover Control System (aka: Alternative Intervention
and Workover Control System)
AUT Automated Ultrasonic Testing
CP Cathodic Protection
CRA Corrosion Resistant Alloy
EPC Engineering, Procurement, and Construction
ESD Emergency Shutdown
FBE Fusion Bonded Epoxy
HIPPS High-Integrity Pressure Protection System
HYD Hydraulic
IWOCS Installation and Workover Control System (aka: Intervention and Workover Control
System)
MLI Multi-Layer Insulation
MODU Mobile Offshore Drilling Unit
MQC Multibore Quick Connector
PFI Polyurethane Foam Infill
PLC Programmable Logic Controller
Product Result of an Activity or Process whether Tangible or Intangible, or a Combination of
Both; Including Goods (Hardware and Processed Materials), Services, and Software
ROV Remotely Operated Vehicle
VIV Vortex-Induced Vibration
Note: Singular or plural forms of a term shall have the same definition.
2. CONTRACTOR's Responsibilities
CONTACTOR's responsibilities include the following:
Appendices
2. Organization
A. Ownership
Company is established as a:
Corporation Proprietorship
Partnership Joint Venture
Affiliate National Oil Company
3. Financial Information
Financial Data:
Annual Sales volume (each of the last three years)
Year: Sales Volume ($)
NOTE: THIS IS A GENERIC SURVEY FORM, AND, AS SUCH, SOME OF THE QUESTIONS WILL
NOT APPLY FOR YOUR FACILITY. PLEASE ANSWER ALL QUESTIONS THAT DO APPLY. FOR
THOSE QUESTIONS THAT DO NOT APPLY, INDICATE "N/A."
2. Plant Officials (complete list below or attach an organization chart showing same
information.)
Chairman Of The Board:
President:
Vice-President:
Sales Manager:
Purchasing Manager:
Chief Engineer:
Production Manager:
Quality Assurance Manager:
Telephone:
Quality Control Manager:
Telephone
Chief Inspector:
Telephone:
Customer Contact:
Telephone:
3. Plant data
A. Size of facilities (indicate proper unit of measure - square foot or square meters)
Buildings (covered) work area
Open work area
5. List the national codes and standards (ASME, API, NEMA, etc.) To which you are authorized
to design, fabricate, and/or test.
Type of stamp (symbol) Serial number Expiration date
6. Engineering department
A. Engineers: Licensed/Professional:
University Graduate:
Technical School Graduates:
Draftsmen
B. Does the engineering department prepare working drawings from the customer's
specifications and outline drawings?
E. Identify the design analysis (stress, flexibility, etc.). Which are performed using computer
programs?
7. Manufacturing Department
A. Who reviews and approves manufacturing procedures?
B. Who verifies that the manufacturing procedures welding procedures and drawings being
used are the proper revision?
D. Is fabrication completed at this plant site, or is some fabrication performed at dockside or the
customer's site due to space/shipping limitations?
D. Does the quality control department approve the procedures for: (yes or no)
Receiving Inspection Welding
Fabrication Heat Treatment
NDE Identify others
E. Does the QC/inspection department review and approve reports/certifications for: (yes or no)
Incoming materials Heat Treatment
NDE certification Final documentation
F. Can the QC/inspection department stop production if quality standards are not being met?
How?
H. Does quality control perform (1) no inspection, (2) sample inspection, (3) first piece
inspection, (4) 100% inspection, or (5) a combination of these for the areas listed below:
Receiving inspection In-process inspection Final Inspection Final Test
Are these inspection plans documented?
Are they available for review by the customer?
I. Are there written procedures for control of material that has been
rejected or is to be repaired?
How are these materials identified?
K. Under what conditions would the customer be contacted regarding use of non-conforming
material or material substitutions?
9. Supplier Control
A. Does this plant survey its suppliers prior to use to evaluate their ability
to supply acceptable material?
E. Are chemical and physical test results included as a part of the final documentation to the
customer?
11. Welding
A. Does this plant employ a welding engineer?
Name (s):
E. Weld procedures:
Number of
Material welded (Yes/no) Number of welders qualified
procedures
Carbon steel
Low alloy steel
High chrome alloy steel
Austenitic stainless
Alloy clad steel
Aluminum
Others
G. Welding positioners:
Number available Size capacity Other information
B. Ultrasonics
Does this facility do its own ultrasonic testing?
C. Liquid Penetrants
Does this facility do its own liquid penetrant inspection?
If no, to whom is it subcontracted?
If liquid penetrant inspection is subcontracted, who determines
if the results are acceptable?
D. Magnetic Particle
Does this facility do its own magnetic particle inspection?
If no, to whom is it subcontracted?
If magnetic particle inspection is subcontracted, who
determines if the results are acceptable?
If this facility does its own magnetic particle inspection, list the
number and types of equipment used for each method
including amperage/voltage ranges.
Is dry powder or wet fluorescent used?
E. Other
List the hardness testing equipment used.
List the types and number of eddy current equipment used.
List the types of halogen leak testing equipment used.
List other non-destructive testing equipment used including
electrical test equipment.
F. Please indicate the numbers of NDE technicians for each range of years experience shown
below (note that an individual may be included in more than one NDE discipline):
Number of technicians per years of experience
NDE Discipline Qualification Per
0-2 2-10 10 or more
Radiography
Ultrasonics
Liquid Penetrant
Magnetic Particle
Others
17. Major Customers: List some of the major customers and types of equipment supplied to
them:
Revision 1
September 2022
Section K
CONTRACTOR’s Execution Basis
TO BE PROVIDED BY BIDDERS