Pce8 78 82
Pce8 78 82
Pce8 78 82
78
Special Conditions of Contract
GCC Clause
1.17 The Intended Completion Date is Two Hundred Forty calendar days
from the start date indicated in GCC Clause 1.28.
NOTE: The contract duration shall be reckoned from the start date and
not from contract effectivity date.
1.22 The Procuring Entity is the Department of Budget and Management
(DBM) with address at General Solano St., San Miguel, Manila.
1.23 The Procuring Entity’s Representative is:
Director Ryan S. Lita
Administrative Service (AS)
Department of Budget and Management
1.24 The Site is located at Arcache Building, General Solano St. cor.
Nepomuceno St., San Miguel, Manila.
1.28 The Start Date shall be seven (7) calendar days from the date of receipt
of the Notice to Proceed.
1.31 The Works consist of:
1. General Requirements:
a. Permit to Construct (PTC)
b. Permits (Building permit, Electrical Permit, Sanitary
Permit, mechanical Permit, Zoning Permit, Fire Permit,
etc.)
c. Project Billboard
2. Temporary Facilities and Facilities for the Engineer
3. Demolition Works
4. Earth Works
5. Structural Works
79
6. Architectural Works
7. Site and Landscape Architectural Works
8. Sanitary/Plumbing Works
9. Electrical Works
10. Electrical Auxiliaries Works
11. Mechanical Works – Elevator, VAC
12. Fire Protection Works
13. Architectural Interior Design Works
2.2 Completion of the Works is within Two Hundred Forty (240) calendar
days beginning seven (7) calendar days from receipt of the Notice to
Proceed.
5.1 The Procuring Entity shall give possession of so much of the Site to the
Contractor after a pre-construction meeting between the authorized
representatives of UP, the DBM and the Contractor.
6.5 The Contractor shall employ the following Key Personnel:
NOTE: The names of the Key Personnel and their designation shall be
filled out by winning contractor prior to contract signing.
7.4(c) No further instructions.
7.7 No further instructions.
8.1 No further instructions.
10 The site investigation reports are:
80
13 If applicable, all partners to the joint venture shall be jointly and
severally liable to the Procuring Entity.
18.3(h)(i) No further instructions.
21.2 The Arbiter is:
81
of the warranty shall be a ground for suspension and/or blacklisting of
the contractor.
51.1 The date by which “as built” drawings are required is ten (10) calendar
days after issuance of final acceptance.
51.2 The amount to be withheld for failing to produce “as built” drawings
and/or operating and maintenance manuals by the date required is 1/50
of 1% of contract value.
82