MANIPULATIVE INTERPRETATION Research Dox
MANIPULATIVE INTERPRETATION Research Dox
MANIPULATIVE INTERPRETATION Research Dox
AVTAR SINGH
Contra proferentem Where the words used in an exclusion clause are
capable of two constructions, a wider construction and a limited
construction, then the limited construction would be preferred, for the
rule of law is that "every exception clause is to be interpreted, in case of
ambiguity, contra proferentem"1. This means that "if there is any doubt
as to the meaning and scope of the excludeing or limiting term, the
1
Professor Brian Coote, Breach and exception Clauses, (1970) Camb LJ at p. 238., Avtar Singh on Law of Contracts
ambiguity will be resolved against the party who has inserted it... These
principles were applied by the Court of Appeal in Hollier v Rambler
Motors AMC Ltd.
In Bank of India v K Mohandas, (2009) 5 SCC 313, in case of unclear
term or expression, interpretation against the party is to be preferred who
used such expressions,
This doctrine applies in the case of a commercial contract since the
clauses of the contract are bilateral and mutually agreed upon.
In Henry Kendall & Sons v William Lillico & Sons Ltd.^^° In this case
during the past three years three or four times in every month goods
were supplied on oral orders followed by signature on sold notes which
excluded liability for latent defects. It was held that this practice was a
sufficient notice of the terms. Distinguishing this case from the present
the court said that that was a typical case where a consistent course of
dealing between the parties made it imperative for the court to read into
the contract the terms printed on the sold notes.
Cotton threads delivered under a contract were found to be 6 per cent
shorter than they should have been and the seller sought to get rid of the
liability for short delivery by sheltering himself .under the exemption
clause which said that the goods actually delivered would be taken to be
in accordancewith the contract in all respects unless the sellerswere
informed within 14 days of delivery of somethingwrong. The buyers
discovered the shortage when they put the threads to actual use and that
was much later than 14 days. The court did not permit the seller to use
his clause for creating this phenomenon that goods not delivered should
be taken to have been delivered. There was no warrant for an implication
to the effect that non-delivery in length or small measure was included
in the objections which should, within the time-limit, be made to goods
delivered. Beck & Co v Szymanowski & Co, 1923AC 43 (HL).