REKAPITULASI PENGIRIMAN MATERIAL

PT TATA GUNA PRATAMA


RUSUNAWA PARAMEDIS GORONTALO UTARA

NO HARI TANGGAL MATERIAL SAT VOLUME KETERANGAN

1 Kamis 12-May-22 Bata Ringan Blesscon ( 10 x 20 x 60) Bh 2016


2 Kamis 12-May-22 Drymix Plester D200 zak/40 Kg 500
3 Kamis 12-May-22 Drymix Aci BB-300 zak/40 Kg 500
4 Sabtu 14-May-22 Kusen Allexindo 3" Btng/6 M 200
5 Sabtu 14-May-22 Spigot Allexindo Btng/6 M 200
6 Senin 16-May-22 Rangka Baja Ringan Taso (TS) 150-C 75.75 Btng/6 M 200
7 Senin 16-May-22 Reng Rangka baja Ringan Taso (TR) 110-R32.45 Btng/6 M 150
8 Senin 16-May-22 Karet Putih ( Kusen jendela Kaca) Rol/20 M 16
9 Senin 16-May-22 Cassment Jendela Kecil Psng 165
10 Senin 16-May-22 Cassment Jendela Besar Psng 142
11 Senin 16-May-22 Granito HT Indogress (60 x 60) Dos 1420
12 Senin 16-May-22 Rangka Metal Stud Kencana Partisi C73 TCTO 45 3 M Btng/3 M 200
13 Selasa 17-May-22 Pasir Truk/ 6 m3 2
14 Selasa 17-May-22 Split Truk/ 6 m3 2
15 Rabu 18-May-22 Split Truk/ 6 m3 1
16 Kamis 19-May-22 Pasir Truk/ 6 m3 1
17 Kamis 19-May-22 Semen Tonasa zak/50 Kg 200
18 Sabtu 21-May-22 Split Truk/ 6 m3 3
19 Sabtu 21-May-22 Pasir Truk/ 6 m3 2
20 Minggu 22-May-22 Split Truk/ 6 m3 3
21 Minggu 22-May-22 Pasir Truk/ 6 m3 3
22 Minggu 22-May-22 Semen Tonasa zak/50 Kg 400
23 Senin 23-May-22 Split Truk/ 6 m3 3
24 Senin 23-May-22 Pasir Truk/ 6 m3 1
25 Senin 23-May-22 Besi D 19 Btng 102
Besi D 16 Btng 418
Besi D 13 Btng 627
Besi D 10 Btng 729
Besi Ø 8 mm Btng 254
26 Selasa 24-May-22 Split Truk/ 6 m3 1
27 Selasa 24-May-22 Pasir Truk/ 6 m3 1
28 Selasa 24-May-22 Semen Tonasa zak/50 Kg 200
29 Selasa 31-May-22 CBM Hollow 16 x 32 Btng/4m 100
30 Selasa 31-May-22 CBM Hollow 32 x 32 Btng/4m 100

Dibuat Tanggal, 25 Mei 2022

EBEN HAEZER
REKAPITULASI BETON MANUAL
PT TANJONG HARAPAN
PONPES ISLAMIYAH GUNUNG RAYA, KAB. PADANG LAWAS UTARA

CAMPURAN DI LOKASI Jadwal Test Kubus


No Silinder
NO HARI TANGGAL MUTU BETON Umur URAIAN KEGIATAN KETERANGAN
Slump Beton Umur Umur
Jam 14
(cm) 7 hari 28 hari
hari
MTS NEGERI 2 PURBALINGGA (KEC BOBOTSARI)

1 27-Jul-20 Senin K.225 10±2 09.00 MTSN1_P_1 3-Aug-20 Cor Pondasi Tangky Air K.225 SITE MIX
2 27-Jul-20 Senin K.225 10±2 09.00 MTSN1_P_2 10-Aug-20 Cor Pondasi Tangky Air K.225 SITE MIX
3 27-Jul-20 Senin K.225 10±2 09.00 MTSN1_P_3 24-Aug-20 Cor Pondasi Tangky Air K.225 SITE MIX
4 31-Jul-20 Jumat K.225 10±2 10.00 MTSN1_P_4 7-Aug-20 Cor Kolom Tangky Air K.225 SITE MIX
5 31-Jul-20 Jumat K.225 10±2 10.00 MTSN1_P_5 14-Aug-20 Cor Kolom Tangky Air K.225 SITE MIX
6 31-Jul-20 Jumat K.225 10±2 10.00 MTSN1_P_6 28-Aug-20 Cor Kolom Tangky Air K.225 SITE MIX

MAN PURBALINGGA (KECAMATAN PURBALINGGA)

1 17-Aug-20 Senin K.225 10±2 09.00 MAN_P_1 24-Aug-20 Cor Pondasi Tangky Air K.225 SITE MIX
2 17-Aug-20 Senin K.225 10±2 09.00 MAN_P_2 31-Aug-20 Cor Pondasi Tangky Air K.225 SITE MIX
3 17-Aug-20 Senin K.225 10±2 09.00 MAN_P_3 14-Sep-20 Cor Pondasi Tangky Air K.225 SITE MIX
4 24-Aug-20 Senin K.225 10±2 10.00 MAN_P_4 31-Aug-20 Cor Kolom Tangky Air K.225 SITE MIX
5 24-Aug-20 Senin K.225 10±2 10.00 MAN_P_5 7-Sep-20 Cor Kolom Tangky Air K.225 SITE MIX
6 24-Aug-20 Senin K.225 10±2 10.00 MAN_P_6 21-Sep-20 Cor Kolom Tangky Air K.225 SITE MIX

MAN 2 BANJARNEGARA

1 30-Jul-20 Kamis K.225 10±2 09.00 MAN2_B_1 6-Aug-20 Cor Pondasi Tangky Air K.225 SITE MIX
2 30-Jul-20 Kamis K.225 10±2 09.00 MAN2_B_2 13-Aug-20 Cor Pondasi Tangky Air K.225 SITE MIX
3 30-Jul-20 Kamis K.225 10±2 09.00 MAN2_B_3 27-Aug-20 Cor Pondasi Tangky Air K.225 SITE MIX
4 6-Aug-20 Kamis K.225 10±2 10.00 MAN2_B_4 13-Aug-20 Cor Kolom Tangky Air K.225 SITE MIX
5 6-Aug-20 Kamis K.225 10±2 10.00 MAN2_B_5 20-Aug-20 Cor Kolom Tangky Air K.225 SITE MIX
6 6-Aug-20 Kamis K.225 10±2 10.00 MAN2_B_6 3-Sep-20 Cor Kolom Tangky Air K.225 SITE MIX

MAN 3 KUTOWINANGUN KEBUMEN

1 30-Jul-20 Kamis K.225 10±2 09.00 MAN3_K_1 6-Aug-20 Pondasi telapak K.225 SITE MIX
2 30-Jul-20 Kamis K.225 10±2 09.00 MAN3_K_2 13-Aug-20 Pondasi telapakK.225 SITE MIX
3 30-Jul-20 Kamis K.225 10±2 09.00 MAN3_K_3 27-Aug-20 Pondasi telapak K.225 SITE MIX
4 13-Aug-20 Kamis K.225 10±2 10.00 MAN3_K_4 20-Aug-20 Sloof K.225 SITE MIX
5 13-Aug-20 Kamis K.225 10±2 10.00 MAN3_K_5 27-Aug-20 Sloof K.225 SITE MIX
6 13-Aug-20 Kamis K.225 10±2 10.00 MAN3_K_6 10-Sep-20 Sloof K.225 SITE MIX
7 21-Aug-20 Jumat K.225 10±2 09.00 MAN3_K_7 28-Aug-20 kolom K.225 SITE MIX
8 21-Aug-20 Jumat K.225 10±2 09.00 MAN3_K_8 4-Sep-20 kolom K.225 SITE MIX
9 21-Aug-20 Jumat K.225 10±2 09.00 MAN3_K_9 18-Sep-20 kolom K.225 SITE MIX
10 4-Sep-20 Jumat K.225 10±2 10.00 MAN3_K_10 11-Sep-20 Ring Balok K.225 SITE MIX
11 4-Sep-20 Jumat K.225 10±2 10.00 MAN3_K_11 18-Sep-20 Ring Balok K.225 SITE MIX
12 4-Sep-20 Jumat K.225 10±2 10.00 MAN3_K_11 2-Oct-20 Ring Balok K.225 SITE MIX