0% found this document useful (0 votes)
610 views20 pages

08 Economics of Machining

1) The economics of machining aims to maximize profit by balancing production rate and tool life. High production rates increase costs while long tool life reduces costs. 2) The costs of machining include handling costs, tooling costs, tool setting/changing costs, and machining costs per piece. The optimal cutting speed minimizes total unit cost. 3) Production rate depends on machining time, tool changing time, and non-productive time per piece. The optimal speed maximizes production rate for minimum total time.

Uploaded by

Abhinav Reddy
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
610 views20 pages

08 Economics of Machining

1) The economics of machining aims to maximize profit by balancing production rate and tool life. High production rates increase costs while long tool life reduces costs. 2) The costs of machining include handling costs, tooling costs, tool setting/changing costs, and machining costs per piece. The optimal cutting speed minimizes total unit cost. 3) Production rate depends on machining time, tool changing time, and non-productive time per piece. The optimal speed maximizes production rate for minimum total time.

Uploaded by

Abhinav Reddy
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 20

Machining Science

Economics of Machining

Economics of Machining
Objective of more profit
an Industry
Economics of Machining

manufacturing production rate:


cost: minimum
economical tool life

maximum
Balance has to be
struck to ensure
and production

maximum tool life not


tool life bothered
reduced increased
cutting speed cutting speed
low production high cost of
rate machining

1
Cost Components of Production

 handling cost/piece
Economics of Machining

 tooling cost/piece
 tool setting and changing cost/piece
 machining cost/piece

Cost of Production

R
Economics of Machining

1 – Cost of tooling
2 – Cost of tool
Cost per piece

changing
3 – Cost of handling
2 4 – Cost of machining
R – Total Cost
Min Cp
Minimum cost
1
3
4
Vopt V

2
Economics of Machining Time Components of Production

 machining time/piece
 handling time/piece
 tool setting and changing time/piece

Rate of Production

R
Economics of Machining

3 Minimum time
Time per piece

1 – Tool changing time


2 – Non-productive time
3 – Machining time
Maximum R – Total Time
production
Min Tp
1
2

Vopt V

3
Economics of Machining Economics of Machining

Minimum
cost
Production rate
Cost per piece

Maximum
Hi-E production
range

Vcp Vtp
V

Cost of Production

machining cost/piece
Economics of Machining

+ tool setting cost/piece


Unit cost (Cp)
+ tooling cost/piece

+ handling cost/piece

4
Machining Cost
machining cost/piece =
ℎ ( )
Economics of Machining

ℎ ( )

+ ( / )

+ ℎ
+ ℎ /

= ℎ = =
1000

Tool Setting Cost


tool setting cost/piece =
= ℎ /
Economics of Machining

= ( )

= = ( )

= . /

= = ⁄
1000 1000

5
Economics of Machining Types of Tools

Solid Tool Throw-away Inserts

Tooling Cost

tooling cost/piece =
Economics of Machining

( / )

Solid tool Insert


+( × )
+1

6
Handling Cost

handling cost/piece =
Economics of Machining

= &

 Does not depend on cutting speed

 Constant

Cost of Production
Now, the unit price can be expressed as:
Economics of Machining

= + + +

⇒ = +
1000 1000

+ +

7
Cost of Production

1
=0 ⇒{ −
Economics of Machining

1000
1
+ −1
1000
1
+ −1
1000
+ 0} = 0

Cost of Production

1
⇒ = −1 +
Economics of Machining

⇒ =
1
−1 +

8
Rate of Production

Rate of Production = =
Economics of Machining

machining time/piece
Time of Prodn. (Rp) + tool setting time/piece

+ handling time/piece

Rate of Production

Machining time/piece = =
Economics of Machining

Tool setting time/piece = =

Handling time/piece, = Constant

= + +

9
Rate of Production
1 1
= =
Economics of Machining

+ +
1000 1000 ⁄

to maximize Rp  it is sufficient to
minimize the denominator, tp

⇒ =0

Rate of Production

1
Economics of Machining

=0 ⇒{ −
1000
1
+ −1
1000

+ 0} = 0

10
Rate of Production

1
⇒1= −1
Economics of Machining

⇒ =
1
−1

Exercise Problems
Pb.: A large batch of steel shafts are to be rough turned to 76 mm
diameter for 300 mm length at a feed of 0.25 mm/rev. A solid
HSS type tool is to be used and appropriate constant in Taylor’s
Economics of Machining

tool life equation for the conditions employed are as follows: n =


0.25; measured tool life at the cutting speed of 245 m/min is 60
sec. The initial cost of the machine was Rs. 1,50,000/- and is to
be amortized in 5 years. The operator’s wages are Rs. 20/hour
and the operator and machine overheads are 100%. Tool
changing and resetting time on the machine is 300 sec and the
cost of regrinding the tool is Rs.10/-. The initial cost of the tool is
Rs.50/- and it can be ground 10 times. Non productive time for
each component is 120 sec. Obtain optimum speed for minimum
cost of production and hence obtain the tool life; rate of
production and the cost of producing the component.

11
Exercise Problems
Pb.: A 200 mm long and 300 mm diameter bar is
turned on a lathe with feed = 0.25 mm/rev.
The operating cost is 5 paise/min while the
Economics of Machining

tool cost is Rs. 1/edge. Tool changing time is


1 min. The requirements are such that either
of the two tool materials X or Y can be used.
Compare the machining cost per component
whilst operating under most economical
conditions for the two materials.
Material ‘X’  VT0.1 = 67
Material ‘Y’  VT0.1 = 90

Exercise Problems
Pb.: A 100 mm long 35 mm diameter bar is to be
turned at a feed of 0.26 mm/rev. The
Economics of Machining

operating cost is Rs. 10/min. and the tool


cost is Rs. 75/edge. The tool changing time
is 4 min. A carbide tool is used with two
cutting fluids for which the tool life
equations are given below:
Cutting fluid ‘X’  VT0.22 = 67
Cutting fluid ‘Y’  VT0.32 = 67

12
Exercise Problems
A tool used in a turning operation is of the brazed
carbide tip type. Its cost is Rs. 450/- and on the average,
it can be reground 10 times. The cost of regrinding is
Economics of Machining

Rs. 45/-. The lathe cost is Rs.2 lakhs, used 8 hrs/day, 5


days/week and 50 weeks/year. Its cost is to be amortized
over 10 years. The machine overheads are 100%. The
operator’s wages are Rs. 20/hr. and the operator’s
overheads are 100%. Tool life equation is VT0.25 = 7,
where V is in m/sec and T is the tool life in sec. the tool
changing time is 4 min, and the handling time per
component is 5 min. The workpiece with 50 mm
diameter and 400 mm length is machined at the rate of
0.25 mm/rev. Calculate minimum production cost and
hence obtain minimum production time.

Exercise Problems
Pb.: A 200 mm long and 65 mm diameter bar is to be
turned at a feed of 0.15 mm/rev. The operating
cost is Rs. 0.50/min. and the tool cost is Rs.
Economics of Machining

10/edge. The tool changing time is 2 min. Assume


weight of workpiece as 0.14 kg. The following two
workpiece materials have been used.:
Material ‘X’ (cost Rs.100/kg)  VT0.10 = 67
Material ‘Y’ (cost Rs.120/kg)  VT0.16 = 90
Calculate tool life and optimum cutting velocities
for min. cost with no consideration for material
cost; and maximum production rate criteria for
both the w/p materials. State which material
should be chosen for total minimum cost.

13
Exercise Problems
Pb.: A tool used in a turning operation is of brazed
type. Cost of the tool is Rs. 100 and on average, it
can be reground 10 times. The cost of each
Economics of Machining

regrinding is Rs.5/-. The lathe cost is to be


amortized over 10 years and the machine
overheads are 100%. The lathe cost is Rs.2,00,000
and is used 8 hrs/day, 5 days/week and 50
weeks/yr. The tool life relationship is VT0.25 = 400.
Tool changing time is 4 min, handling time per
component is 5 min, cutting distance per
component is 200 m. Calculate minimum
production cost and time.

Exercise Problems
Pb.: Illustrate in a sketch graph the economic factors
involved in metal cutting and show that cutting
Economics of Machining

speed has an optimum value.


When finish turning a 50 mm diameter, 130 mm
long bore in a high-tensile steel at a feed of 0.13
mm/rev. The tool life equation was VT0.12 = 146.
The cost of regrinding the tool was Rs. 8 and the
tool changing time was 10 min. If the inclusive
cost of operating the machine is Rs. 13.5/hr,
determine (a) the economic machining time per
component, (b) the number of components to be
produced between tool changes.

14
Exercise Problems
Pb.:An automatic lathe is to be used to machine brass
components 75 mm long X 50 mm diameter using a
depth of cut 1.25 mm. Select the speed that
Economics of Machining

minimizes the machining cost and calculate the


corresponding tool life. Also estimate the cutting
speed for minimum tool life of production. Assume:
Labor + overhead rate Cm = Rs. 5/hr.
Reconditioning cost of the tool edge = Rs 0.25/edge
Loading and unloading time of the work = 15 Sec.
Tool change time = 5 min.
Tool life relationship: VT0.25 = 300

Exercise Problems
Pb.: A 1.0 m long cut is to be given on a 100 mm
diameter steel bars on an engine lathe. The depth of
cut is 6 mm and the feed rate is 0.5 mm/rev. the
Economics of Machining

following cost data are available for this operation:


machine labor: Rs.20/hr; machine burden rate:
400% of labor; tool cost: Rs. 180; tool changing
time: 2 min.; regrinds available: 5/tool; grinding
time: 6 min/edge; tool grinding labor: Rs.30/hr;
tool grinding burden: 500% of labor; loading time:
5 min/component; Tool life equation: VT0.25 = 200.
Obtain optimum speed for minimum cost of
production and hence obtain the tool life, rate of
production and the cost producing a component.

15
Exercise Problems
Pb.: A 200mm long and 30 mm diameter bar is to be
turned on a lathe with a feed rate of 0.25 mm/rev.
Economics of Machining

The rpm is 200. The operating cost is 5 paise/min


while the tool cost is Rs. 1/edge. The design
provisions indicate that either of the following
two materials may be used. State which material
should be chosen for minimum cost.
Material cost/kg tool life eqn.
X Rs. 2.00 VT0.10 = 67
Y Rs. 3.00 VT0.16 = 90

Exercise Problems
Pb.: A 600 mm long cut is to be made on a 150 mm dia
bar on a lathe with a depth of cut of 1.5 mm and
feed of 0.25 mm/rev. The tool life equation is VT0.25
Economics of Machining

= 475. For the above operation, two types of tools


may be used: (i) brazed tool and (ii) throw away
carbide inserts. The following cost data have been
collected:
(a) Machine costs: machining cost = Rs 1/hr;
machine overhead = 100%; grinding cost =
Rs.1.5/hr; grinding machine overhead = 200%;
idle time = 5 min.

Contd….

16
Exercise Problems
b) Tool costs:
 brazed tools – initial cost = Rs.80/-; grinding
Economics of Machining

time – 5 min/edge; tool changing time = 2


min; 9 grinds/tool before salvage.
 Throw-away inserts: cost – Rs.300; tool
change time = 1.5 min; cutting edges = 8
i. Plot the cost/piece as a function of cutting speed
and hence find the cutting speed for minimum cost
for each case.
ii. Compute and compare the tool life for minimum
cost/piece for maximum production rate both for
brazed and inserted type cutting tools.

Extended Taylor’s Tool Life Equation


Economics of Machining


= ⁄ ⁄

17
Cost of Production
The unit price is expressed as:
Economics of Machining

= + + +

⇒ = +
1000 1000

+ +

Cost of Production
=0
1
Economics of Machining

⇒{ −
1000
1
+ −1
1000
1
+ −1
1000
+ 0} = 0

18
Cost of Production

1
Economics of Machining

⇒ = −1 +

⇒ =
1
−1 +

Cost of Production
=0
1
Economics of Machining

⇒{ −
1000

+ −1
1000
+ −1
1000
+ 0} = 0

19
Cost of Production

⇒ = −1 +
Economics of Machining


⇒ =
−1 +

A. Venu Gopal ME 353 :: Machining Science 39

References

 Manufacturing Engineering, D.K. Singh, CRC Publishers


Economics of Machining

 Manufacturing Processes, J.P. Kaushish, PHI


 Manufacturing Technology, Vol.II, P.N. Rao, TMH
 Machining & Machine Tools, AB Chattopadhyay, Wiley
 Fundamentals of Machining and Machine Tools,
G. Boothroyd, Int. McGraw Hill
 Manufacturing Science, Amitabha Ghosh and Ashok
Kumar Malik, East West Press Pvt. Ltd.

20

You might also like