Seatwork No. 3
Seatwork No. 3
Seatwork No. 3
3
Critical Path Analysis
INSTRUCTIONS: Compute the following Activity Duration using the 3-Point Estimate’s PERT
Distribution. Show your solutions.
A. Planning 2 3 6 3 days
D= 7
2
A=3 J=
H=
B=5 E= G= L=
1 3 5 6 8 10
C=4 I= K=
F=
4 9
Path 1 : A-D-G-H-J-L | 3+10+18+2+10+2 = 45 days
Path 2 : A-D-G-I-K-L| 3+10+18+3+3+2 = 39 days
Path 3 : B-E-G-H-J-L | 5+8+18+2+10+2= 45 days
Path 4 : B-E-G-I-K-L| 5+8+18+3+3+2 = 39 days
Path 5 : C-F-G-H-J--L | 4+7+18+2+10+2 = 43 days
Path 6 : C-F-G-I-K-L| 4+7+18+3+3+2 = 37 days