Seatwork No. 3

Download as docx, pdf, or txt
Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1/ 2

Seatwork No.

3
Critical Path Analysis

Name: Karylle M. Manrique Score: ____________


Yr. and Section: BSI/T 3B Date: _____________

INSTRUCTIONS: Compute the following Activity Duration using the 3-Point Estimate’s PERT
Distribution. Show your solutions.

Activity (in days) O. Estimate M. Estimate P. Estimate Actual Duration

A. Planning 2 3 6 3 days

B. Requirement Analysis 3 5 8 5 days

C. Data Gathering 2 4 6 4 days

D. Design Interface 5 10 14 10 days

E. System Design 6 8 12 8 days

F. Data Modelling 4 7 9 7 days

G. Program Coding 14 18 24 18 days

H. Initial Validation 1 2 3 2 days

I. Final Testing 1 3 4 3 days

J. Design Final Prototype 5 10 12 10 days

K. Final Adjustment and Validation 3 4 5 3 days

L. Software Installation 1 2 3 2 days


II. COMPLETION
Directions: Complete the Network Diagram by supplying the corresponding duration of each activity based on the
results of the PERT analysis above. Then identify the most critical path using the Citical Path Analysis/Method by
encircling the Path number. (23pts.)

D= 7
2
A=3 J=
H=
B=5 E= G= L=
1 3 5 6 8 10

C=4 I= K=
F=
4 9
Path 1 : A-D-G-H-J-L | 3+10+18+2+10+2 = 45 days
Path 2 : A-D-G-I-K-L| 3+10+18+3+3+2 = 39 days
Path 3 : B-E-G-H-J-L | 5+8+18+2+10+2= 45 days
Path 4 : B-E-G-I-K-L| 5+8+18+3+3+2 = 39 days
Path 5 : C-F-G-H-J--L | 4+7+18+2+10+2 = 43 days
Path 6 : C-F-G-I-K-L| 4+7+18+3+3+2 = 37 days