Chapter 6
Chapter 6
Chapter 6
Chapter 6
In these spreadsheets, you will learn how to use the following Excel fu
VDB
Solver
SLN
eadsheets:
equire that
Chapter 6 - Section 2
The Baldwin Company: An Example
Because capital budgeting requires numerous repetitive cash flows, it is an ideal application for Excel. When doing a
no calculations on your own, but rather let Excel do the calculations for you. We will begin with the Baldwin Compan
We will start off with some preliminary work, including the depreciation each year, sales price, and unit costs:
The change in net working capital for each year is the beginning net working capital for each year minus the net wor
working capital each year is:
Now we can calculate the pro forma income statement for each year (Table 6.1), which will be:
With this, the incremental cash flows each year, NPV for different interest rates, and IRR for the project are (Table 6
NPV
4% $ 155,809
10% $ 78,533
15% $ 28,968
18.54% $ -
20% $ (10,682)
There are actually six MACRS schedules: three-, five-, seven-, 10-, 15-, and 20-year schedules. The MACRS schedule
balance method, and switching to straight-line depreciation when it is more advantageous. The three-, five-, seven-
double declining balance depreciation amount, while the 15- and 20-year schedules use a factor of 1.5 (150%). Exce
Below, we have constructed a MACRS table with all six schedules.
Equipment Life (Years)
Year 3 5 7
1 33.33% 20.00% 14.29%
2 44.44% 32.00% 24.49%
3 16.67% 19.20% 17.49%
4 5.56% 12.60% 12.49%
5 10.80% 9.54%
6 5.40% 8.68%
7 8.68%
8 4.34%
9
10
11
12
13
14
15
16
17
18
19
20
21
Finally, note that the MACRS schedule we calculated can vary slightly from the table presented in the textbook. The
schedule we used in the textbook. However, you are allowed to calculate the schedule on your own based on the ru
the table in the textbook (or the table published by the IRS!). In the future, we will use the table in the textbook for
or Excel. When doing a capital budgeting problem, as in most Excel uses, you should do few or
th the Baldwin Company project. We have the following projections for the project:
Year 4 Year 5
10,000 6,000
11.52% 11.52%
Year 4 Year 5
$ 11,520 $ 11,520
82,720 94,240
17,280 5,760
21.22 21.65
212,242 129,892
13.31 14.64
133,100 87,846
year minus the net working capital investment at the end of the year. So, the change in net
$ 24,970 $ 21,224
21,224 -
$ 3,745 $ 21,224
he aftertax salvage value, which is:
e:
$ 212,242 $ 129,892
133,100 87,846
11,520 11,520
$ 67,622 $ 30,526
14,201 6,410
$ 53,421 $ 24,115
The MACRS schedule is calculated using the depreciation according to the double declining
he three-, five-, seven-, and 10-year schedules use a factor of 2 (200%) when calculating the
tor of 1.5 (150%). Excel has a function, VDB, which can be used to construct a MACRS table.
Equipment Life (Years)
10 15 20
10.00% 5.00% 3.75%
18.00% 9.50% 7.22%
14.40% 8.55% 6.68%
11.52% 7.70% 6.18%
9.22% 6.93% 5.71%
7.37% 6.23% 5.28%
6.55% 5.90% 4.89%
6.55% 5.90% 4.58%
6.55% 5.90% 4.46%
6.55% 5.90% 4.46%
3.28% 5.90% 4.46%
5.90% 4.46%
5.90% 4.46%
5.90% 4.46%
5.90% 4.46%
2.95% 4.46%
4.46%
4.46%
4.46%
4.46%
2.23%
ucting the MACRS table is tricky because of the half-year convention. Below you will see what
a percentage rather than a dollar amount. Salvage is the salvage value, which is zero. Life is
d locked the row. This allows us to copy and paste the formula further down the table was
reciation. With the half-year convention, we used the year and subtracted 1/2. To calculate
ar minus one-half, or the life of the asset. In most years we could have taken the next year
ot work for the first year since there is no prior year. So, for the first year, we eliminated the
h the inputs in this case. We used a factor of two for the three-, five-, seven-, and 10-year
ed in the textbook. The reason is that the IRS publishes a MACRS schedule, which is the
ur own based on the rules outlined by the IRS. If you do so, you will get the table above, not
ble in the textbook for our calculations.
Chapter 6 - Section 4
Some Special Cases of Discounted Cash Flow Analysis
To find the equivalent annual cost (EAC), we find the net present value of the project, then find the annuity that rep
Suppose we have two different options for a pollution control system, a filtration system or a precipitation system. T
Filtration Precipitation
system system
Equipment $ 1,100,000 $ 1,900,000
Operating cost $ 60,000 $ 10,000
Life (years) 5 8
Income Statements
Filtration Precipitation
system system
Operating cost $ 60,000 $ 10,000
Depreciation 220,000 237,500
EBIT $ (280,000) $ (247,500)
Tax (58,800) (51,975)
Net income $ (221,200) $ (195,525)
So, using the bottom-up approach, the OCF for each alternative is:
In the final analysis, we should choose the system that is the least expensive, which is the filtration system.
Setting a Bid Price: A Capital Budgeting Extension
Suppose the company you work for is entering a competitive bidding process for a new project. How do you determ
for the project? We know that you would not want to lose money on the project from a financial perspective. From
project has a zero NPV, we make exactly the required return on the project. So, the minimum bid price we should su
all of the cash flows of the project such as the initial investment, salvage value, net working capital, etc., we can set
results in a zero NPV. While doing this by hand is possible, it can often result in tedious calculations. Fortunately, Exc
easier.
We are bidding on the following project. The contract will last for four years, and the equipment will be depreciated
bid price we could submit?
Equipment $ 3,300,000
Pretax salvage value $ 75,000
Units per year 125,000
Price per unit $ 21.92
VC as a percentage of sales 45%
Fixed costs $ 425,000
MACRS Year 1 33.30%
MACRS Year 2 44.40%
MACRS Year 3 14.80%
MACRS Year 4 7.40%
Immediate NWC $ 80,000
Tax rate 21%
Required return 10%
We entered a price in the appropriate cell above. As we will show later, it does not really matter what price we ente
the project with our hypothetical price. This will be:
To find the aftertax salvage value, we need to calculate the taxes. We get:
Pretax salvage value $ 75,000.00
Taxes on sale (15,750.00)
Aftertax salvage value $ 59,250.00
The total cash flows for each year of the project are:
NPV $ -
The minimum bid price is the price at which the NPV of the project is zero. We can use Solver to find this unit price (
We restored the original unit price so you could use Solver on this problem for practice.
NOTE: There is a bug in Solver that will occur occasionally. In some cases, Solver will not launch, or if you try to save
unexpected internal error or available memory was exhausted" pop up. In this case, the solution is to uninstall Solve
1) Go to the File tab on the top left, click Excel options, choose Add-Ins, select Excel Add-Ins in the pulldown m
2) Uncheck the Solver add-in and click OK.
3) Go to the File tab on the top left, click Excel options, choose Add-Ins, select Excel Add-Ins in the pulldown m
repeat of Step 1.
4) Check the Solver add-in and select OK.
oject, then find the annuity that represents the annual cost based on the life of the project.
system or a precipitation system. The relevant numbers for each alternative are:
the equipment will be depreciated on a three-year MACRS schedule. What is the minimum
ot really matter what price we entered. Next, we need to calculate the cash flows and NPV for
4
$ 905,806
80,000
59,250
$ 1,045,056
oblem are:
ecific value, in this case, the NPV cell. Since the lowest bid price is the price that results in a
he cell we would like to change in order to set the target cell equal to the value we chose. In
d for the unit price is irrelevant: Solver will change the value when it solves the problem. Note
you can see the answer report generated by Solver. In this case, the bid price that results in a
will not launch, or if you try to save one or more of the reports, you may see "Solver: An
se, the solution is to uninstall Solver and re-install it. To do this:
ct Excel Add-Ins in the pulldown menu near the bottom of the box, and click on Go.
ct Excel Add-Ins in the pulldown menu near the bottom of the box, and click on Go. This is a
Microsoft Excel 15.0 Answer Report
Worksheet: [CF 12th edition Chapter 06 Excel Master.xlsx]Section 6.5
Report Created: 10/19/2021 4:54:40 PM
Result: Solver found a solution. All Constraints and optimality conditions are satisfied.
Solver Engine
Engine: GRG Nonlinear
Solution Time: 0 Seconds.
Iterations: 1 Subproblems: 0
Solver Options
Max Time 100 sec, Iterations 100, Precision 0.000001
Convergence 0.0001, Population Size 100, Random Seed 0, Derivatives Forward, Require Bounds
Max Subproblems Unlimited, Max Integer Sols Unlimited, Integer Tolerance 5%, Solve Without Integer Constraints
Variable Cells
Cell Name Original Value Final Value Integer
Constraints
Cell Name Cell Value Formula Status Slack
$C$92 NPV: Project Cash Flows $ - $C$92=0 Binding 0
ut Integer Constraints
Chapter 6 - Section 5
Inflation and Capital Budgeting
Inflation should always be considered in any long-term project. As long as inflation is correctly handled, the NPV of t
project proposed by Altshuler, Inc.
With these projections, we can generate the following nominal cash flows and NPV:
NPV @ 5% $426.55
When dealing with any cash flows, it is irrelevant whether you use real cash flows with the real interest rate or nom
value will always be the same.
n is correctly handled, the NPV of the project will be the same. For example, consider the
ct. David Altshuler prefers to work in nominal terms, while Marissunta Giannetti prefers real
de the initial cost by the life of the equipment, or we can use the built-in Excel function SLN
and Life, which is the life of the asset. In general, we usually find it easier just to divide the
n, but it is available if you prefer.
PV:
s with the real interest rate or nominal cash flows with the nominal interest rate, the present
Chapter 6 - Master It!
For this Master It! assignment, refer to the Goodweek Tires, Inc., case at the end of Chapter 6. For your conven
such as the price, variable cost, etc. on the next page. For this project, answer the following questions:
d. At what OEM price would Goodweek Tires be indifferent to accepting the project? Assume the replacement m
e. At what level of variable costs per unit would Goodweek Tires be indifferent to accepting the project?
the end of Chapter 6. For your convenience, we have entered the relevant values in the case
swer the following questions:
OEM market:
Price $ 41
Variable cost $ 29
Automobile production 6,200,000
Growth rate 2.50%
Market share 11.00%
Replacement market:
Price $ 62
Variable cost $ 29
Market sales 32,000,000
Growth rate 2.00%
Market share 8.00%
Replacement market:
Total tires sold in market
SuperTread tires sold
Price
Revenue:
OEM market
Replacement market
Total
Variable costs:
OEM market
Replacement market
Total
Revenue
Variable costs
Marketing and general costs
Depreciation
EBT
Tax
Net income
OCF
NPV
IRR
Profitability index