The document outlines the work breakdown structure for installing a potable drinking water line system with cooling and heating dispensers across the campus of Technological University of the Philippines-Visayas. The project involves 7 stages: 1) evaluating suitable locations for the water tank, pumps, lines and dispensers, 2) designing the water line system, 3) procuring necessary piping, fittings, pumps, tanks and dispensers, 4) installing the equipment, 5) testing and modifying the system, 6) establishing operation procedures, and 7) creating maintenance procedures to ensure ongoing functionality.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0 ratings0% found this document useful (0 votes)
128 views1 page
Work Breakdown Structure (WBS)
The document outlines the work breakdown structure for installing a potable drinking water line system with cooling and heating dispensers across the campus of Technological University of the Philippines-Visayas. The project involves 7 stages: 1) evaluating suitable locations for the water tank, pumps, lines and dispensers, 2) designing the water line system, 3) procuring necessary piping, fittings, pumps, tanks and dispensers, 4) installing the equipment, 5) testing and modifying the system, 6) establishing operation procedures, and 7) creating maintenance procedures to ensure ongoing functionality.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1
Installation of Potable Drinking Water Line System with Cooling-and-Heating Dispenser in
Different Areas in Technological University of the Philippines-Visayas
Work Breakdown Structure (WBS) I. Site Evaluation a. Investigation of campus geography/landscape and determination of possible locations for tank, pumps, water lines and dispensers II. Designing of the Water Line System a. Design Review and Assessment b. Final Design and Drawings III. Procurement a. Pipings, elbows, and fittings i. Delivery and Inspection b. Pedestal style bottle filling stations i. Delivery and Inspection c. Centrifugal pump i. Delivery and Inspection d. Water Tank (4200L) i. Delivery and Inspection IV. Installation a. Tank and pump installations b. Pipe fitting i. Pipe cutting, elbows and fittings preparation ii. Pipe laying iii. Piping installations c. Dispenser installations V. Testing and Modifications a. Pressure/head testing b. Water quality assessment (Temperature, pH, Turbidity, TDS, Coliform, etc.) c. Leakage detection d. Duty cycle VI. Operation Procedures a. Pump priming b. Tank pressure operation and monitoring c. Dispenser start-up VII. Maintenance Procedures a. Monthly preventive maintenance i. Water analysis ii. Pump maintenance iii. Pipings, elbows, and fittings inspection