Or Individual Assignment 2023
Or Individual Assignment 2023
Instructions
1. Simplex method
Find the initial simplex tableau for the craft brewery LPP.
Max Z = 10X1 +8X2
St: X1+X2 ≤ 50
2X1+4X2 ≤ 400
3X1+5X2 ≤300
X1, X2≥ 0
2. Solve the following LPP using Simplex method
Max Z = 12X1 +15X2+9X3
St: 8X1+16X2+12X3 ≤ 250
4X1+8X2 +10X3 ≥400
7X1+9X2+8X3 =105
X1, X2, X 3 ≥ 0
C 5 6 4 0 0 0
BV X1 X2 X3 S1 S2 S3 Q
S3 0 0 4 0 -2 7 1 80
X3 4 0 2 1 -1 3 0 30
X1 5 1 0 0 1 -2 0 20
Zj 5 8 4 1 2 0 220
Cj -- Zj 0 -2 0 -1 -2 0
Answer the following questions based on the above given information:
4. Transportation
A concrete company transports concrete from three plants to three construction sites.
The supply capacities of the three plants, the demand requirements at the three sites,
and the transportation costs per ton are as follows:
REQUIRED
1. Determine the linear programming model formulation for this problem and
2. solve it by North-west corner method, minimum cost and VAM
3. test the optimality by stepping stone and MODI
5. Assignment Model
The Omega pharmaceutical firm has five salespersons, whom the firm wants to assign to five
sales regions. Given their various previous contacts, the salespersons are able to cover the
regions in different amounts of time. The amount of time (days) required by each salesperson
to cover each city is shown in the following table:
Plant Construction site
A B C D
1 17 10 15 16
2 12 9 16 9
3 11 16 14 15
4 14 10 10 18
5 13 12 9 15
REQUIRED
6. Project Model
Suppose a civil engineering firm has to bid for the construction of a dam. The activities and
time estimates are given below. Do the next requirements.
Activity a m b
1-2 (a) 1 3 4
1-3 (b) 2 4 6
1-4 (c) 2 3 5
2-5 (d) 3 4 5
3-6 (e) 3 5 7
4- 7 (f) 5 7 9
5-8 (g) 2 3 6
6-8 (h) 4 6 8
7-8 (I) 3 4 6
Required:
b) Compute the expected time for each activity and the expected duration for each path.
e) Compute the variance for each activity and the variance for path
REQUIRED: Determine the earliest and latest times, the total float for each activity,
the critical activities, the slacks of the events and the project completion time.