Chapter 1. Introduction To Power Systems: December 2019
Chapter 1. Introduction To Power Systems: December 2019
Chapter 1. Introduction To Power Systems: December 2019
net/publication/337931908
CITATIONS READS
0 42,235
1 author:
Francisco Gonzalez-Longatt
University of South Eastern Norway
463 PUBLICATIONS 3,850 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
Unbalanced Power Flow Analysis in Distribution Systems Using TRX Matrix: Implementation Using DIgSILENT Programming Language View project
All content following this page was uploaded by Francisco Gonzalez-Longatt on 14 December 2019.
1.1 Objective
This chapter presents a general introduction to power system and its main elements.
1.2 Introduction to Power Systems a brief history1
In 1882 Edison inaugurated the first central generating station in the USA. The Edison plant fed a load of 400 lamps,
each of them consuming the power of 83 W. At about the same time the Holborn Viaduct Generating Station in London
was the first in Britain to cater for consumers generally, as opposed to specialised loads. This scheme used a 60-kW
generator driven by a horizontal steam engine; the voltage of generation was 100V direct current (DC).
The first major alternating current (AC) station in Great Britain (GB) was at Deptford, where power was generated
by machines of 10 000 h.p. and transmitted at 10 kV to consumers in London (see Fig. 1.1).
Fig. 1.1. Deptford Power Station built 1887. It was the first major station to use the new-fangled high voltage AC. It was rebuilt a
number of times before it was decommissioned in 1983 and demolished in 1992. See more at https://londonist.com/2012/03/the-
history-of-londons-power-stations
During this period the battle between the advocates of AC and DC, it was the War of Currents era (sometimes, War
of the Currents or Battle of Currents). George Westinghouse and Thomas Edison became adversaries due to Edison's
promotion of DC for electric power distribution against AC advocated by several European companies and
Westinghouse Electric based in Pittsburgh, Pennsylvania, which had acquired many of the patents by Nikola Tesla.
Owing mainly to the invention of the transformer the supporters of AC prevailed and steady development of local
electricity generating stations commenced with each large town or load centre operating its own station.
In 1926, in Britain, an Act of Parliament set up the Central Electricity Board (CEB) was created with the object of
interconnecting the best of the 500 generating stations then in operation with a high-voltage network known as the
Grid. The act tried to link the Britain most efficient power stations with consumers via a ‘national gridiron’. The CEB
established the Britain first synchronised AC grid, running at 132 kilovolts (kV) and 50 Hertz (Hz), which by 1933
was a collection of local grids, with emergency interlinks, covering most of England.
Nationalisation of the electricity supply industry under terms of the Electricity Act 1947 comes into effect in 1948.
The Electricity Act 1947 nationalised 505 separate electricity generation and supply organizations in GB on 1 April
1948, both privately owned and state-owned, and consolidated them into 14 area electricity boards of the new Central
Electricity Authority that the Act created (also known as the British Electricity Authority), which subsequently became
the Central Electricity Generating Board. Two organisations were set up:
1. The Area Boards, which were mainly concerned with distribution and consumer service; and
2. The Generating Boards, which were responsible for the generation and the operation of the high-voltage
transmission network or grid.
The electricity supply industry was in public ownership from 1948 to 1990. All of this changed radically in 1990 when
the British Electricity Supply Industry was privatized.
For the first 80 years of electricity supply, the growth of the load was rapid at around 7% per year, implying a doubling
of electricity use every ten years and this type of increase continues today in rapidly industrialising countries.
However, in the USA and other industrialised countries, there has been a tendency, since the oil shock of 1973, for
the rate of increase to slow with economic growth no longer coupled closely to the use of energy. In the UK, growth in
electricity consumption has been under 1% per year for a number of years.
A traditional objective of energy policy has been to provide secure, reliable and affordable supplies of electrical energy
to customers. This is now supplemented by the requirement to limit greenhouse gas emissions, particularly of CO2,
and so mitigate climate change. Hence there is increasing emphasis on the generation of electricity from low-carbon
sources that include renewable, nuclear and fossil fuel plants fitted with carbon capture and storage equipment. The
obvious way to control the environmental impact of electricity generation is to reduce the electrical demand and
1 Source: B. M. Weedy, B. J. Cory, N. Jenkins, Janaka B. Ekanayake, Goran Strbac. (2012). Power Systems. Wiley
Chapter 1
increase the efficiency with which electrical energy is used. Therefore, conservation of energy and demand reduction
measures are important aspects of any contemporary energy policy.
1.3 Power System Definition
An electric power system is a network of electrical components used to supply, transmit and use electric power (see Fig.
1.2).
Fig. 1.3. Structure of a power system with special emphasis on voltage level used in GB.
Now a formal definition of the power system
(1) (generating stations electric power system) The electric power sources, conductors, and equipment required to
supply electric power. (PE/EDPG) IEEE 505-1977r2.
(2) (electric) The generation resources and/or transmission facilities operated as an entity to meet load and/or
interchange commitments. (PE/PSE) 94-1991w3
(3) The generation resources and/or transmission facilities operated under common management or supervision
to meet load and interchange commitments. (PE/PSE) 858-1993w4 [3]
For more definitions, check: (2000). "IEEE 100 The Authoritative Dictionary of IEEE Standards Terms Seventh
Edition." IEEE Std 100-20005.
The traditional power system is arranged as a hierarchy (see Fig. 1.3). Generators feed into a high voltage
transmission system that facilitates bulk transfers of power over large distances. Connected to the transmission
system are medium voltage distribution networks that take power from grid supply points and deliver it to the
customers who are supplied a low voltage.
1.4 The structure of an electric power system
For a lot of its history, the electricity supply industry has operated as a set of vertically integrated monopolies within
certain geographic areas. Many countries, notably but not only, the UK, have sought to bring competition to this
industry in order to provide better value to consumers. The approach in the UK has been to unbundled the various
functions within the industry and then use a combination of market mechanisms, and regulation are then used to
enhance economic efficiency.
2 IEEE Standard Nomenclature for Generating Station Electric Power Systems, ANSI/IEEE 505-1977
3 IEEE Recommended Definitions of Terms for Automatic Generation Control on Electric Power Systems, ANSI/IEEE 94-1991
4 ANSI/IEEE 858-1993, IEEE Standard Definitions in Power Operations Terminology
5 Direct link: https://ieeexplore.ieee.org/document/4116787
Fig. 1.4. Voltage levels and it uses inside a power system. Source: https://www.parliament.uk/documents/post/pn163.pdf
6 https://www.thebigbangfair.co.uk/media/49868/ngrid_be-the-source_how-electricity-made-transmitted-v2.pdf
Page 3 of 18 Chapter_1_Intro_to_PS_v2.docx Dr. F. Gonzalez-Longatt
Chapter 1
system. The transmission lines connect the neighbouring power systems at transmission levels, thus forming a grid.
The grid is the network of multiple generating resources and several layers of the transmission network.
Fig. 1.5. A demonstrative example of the transmission system, using GB voltages. National Grid transmits electricity at high
voltage throughout England and Wales on a system made up of 7,000 kilometres of overhead lines, 600 kilometres of underground
cables and some 300 substations7.
Fig. 1.6. Typical distribution system structure showing the GB voltage levels. Distribution Network companies distribute the
energy in their licence areas throughout England and Wales7.
A power system operates in a normal state if the following conditions are satisfied:
The bus voltages are within the prescribed limits.
The system frequency is within the specified limits.
The active and reactive power balance exists in the system.
However, the system load varies continuously and hence, in order to ensure satisfactory system operation, proper
controls have to be provided in a power system.
1.5 Characteristics Influencing Generation and Transmission
There are three main characteristics of electricity supply that, however obvious, have a profound effect on the manner
in which the system is engineered. They are as follows:
Electricity, unlike gas and water, cannot be stored and the system operator traditionally has had limited control
over the load. The power balance between generation and demand must be carefully enforced. However, this
aspect has been changing the recent time with more and more penetration of energy storage devices in the
power network. A short discussion of that will be presented in future sections.
The electricity sector creates major environmental impacts that increasingly determine how a plant is
installed and operated.
The generating stations are often located away from the load resulting in transmission over considerable
distances.
1.6 Generation Sector and Energy conversion
The national electrical load consists of a base plus a variable element, depending on the time of day and other factors.
In thermal power systems, the base load should be supplied by the most efficient (lowest operating cost) plant which
then runs 24 hours per day, with the remaining load met by the less efficient (but lower capital cost) stations. In hydro
systems, water may have to be conserved, and so some generators are only operated during times of peak load.
7 https://www.thebigbangfair.co.uk/media/49868/ngrid_be-the-source_how-electricity-made-transmitted-v2.pdf
Dr. F. Gonzalez-Longatt Chapter_1_Intro_to_PS_v2.docx Page 4 of 18
Three-Phase Systems
Fig. 1.7. Hourly demand profile (2018. Year on hourly average) in the GB system. Minimum: 30.429 GW maximum: 47.041 GW
average: 40.869 GW. Source: http://gridwatch.co.uk/
Coal, uranium, oil, gas, hydro, wind and solar are the main sources of energy used in the generation of electricity in
England and Wales. Much of the electricity is produced in thermal power stations.
Electricity generation in the UK in 20178 was broadly stable compared to the previous two years at 336 TWh, with a
continuation of the shift in fuel mix away from coal. Unlike previous years, this shift has tended towards growth in
renewable generation aided by the increase in renewable capacity.
In 2017, the share of renewables’ generation increased to 29.3% from 24.5% in 2016. This increase resulted from a
12.8% increase in renewables’ generation capacity in 2017, reaching 18.3 GW (de-rated to reflect intermittency),
accounting for 22% of generating capacity.
Low carbon electricity’s share of generation increased from 45.6% to a record 50.1%. This increase was driven by the
increase in renewables generation, as nuclear generation decreased by 1.9% compared to 2016.
Total electricity supply fell by 1.0% to 353 TWh, as net imports decreased by 16.8% to 14.8 TWh. The UK remained a
net importer of electricity in 2017, with net imports contributing 4.2% of electricity supply – this was slightly lower
than the 5.0% of supply in 2016. Final consumption decreased by 1.0% to 301 TWh in 2017, largely as a result of
decreases in the domestic and commercial sectors due to warmer weather.
Fig. 1.8. Shares of electricity generation, by fuel8. A historical series of fuel used in the generation on a consistent, energy
supplied, fuel input basis is available at Table 5.1.1 on the BEIS section of the GOV.UK website and accessible from the Digest of
UK Energy Statistics home page: www.gov.uk/government/collections/digest-of-uk-energy-statisticsdukes
Source:
8
https://assets.publishing.service.gov.uk/government/uploads/system/uploads/attachment_data/file/736152/Ch5.pdf
Page 5 of 18 Chapter_1_Intro_to_PS_v2.docx Dr. F. Gonzalez-Longatt
Chapter 1
Fig. 1.9. Illustrative map showing the geographical location of the major power stations in the UK (operational May 2018).
Fig. 1.10. Schematic diagram showing the main component in view of a coal-fired steam generating station.
A steam power-station operates on the Rankine cycle, modified to include superheating, feed-water heating, and steam
reheating. High efficiency is achieved by the use of steam at the maximum possible pressure and temperature. Also,
for turbines to be constructed economically, the larger the size, the less the capital cost per unit of power output. As
a result, turbo-generator sets of 500 MW and more have been used. With steam turbines above 100 MW, the efficiency
Dr. F. Gonzalez-Longatt Chapter_1_Intro_to_PS_v2.docx Page 6 of 18
Three-Phase Systems
is increased by reheating the steam, using an external heater, after it has been partially expanded. The reheated
steam is then returned to the turbine where it is expanded through the final stages of blading.
Drax power station is large biomass and coal-fired power station in North Yorkshire, England, capable of co-firing
petcoke9. It has a 2.6 GW capacity for biomass and 1.3 GW capacity for coal. Its name comes from the nearby village
of Drax. It is situated on the River Ouse between Selby and Goole. Its generating capacity of 3,906 megawatts (MW)
is the highest of any power station in the United Kingdom, providing about 6% of the UK's electricity supply.
1.6.2 Energy Conversion Using Water
Perhaps the oldest form of energy conversion is by the use of water power. The technology behind hydropower is fairly
simple, but taming the power of water is a major challenge. In a hydroelectric station, the energy is obtained free of
cost. This attractive feature has always been somewhat offset by the very high capital cost of construction, especially
of the civil engineering works. Hydropower plants are expensive to build but inexpensive to operate.
Unfortunately, the geographical conditions necessary for hydro-generation are not commonly found, especially in
Britain. As of 201710, hydropower accounts for around 1.8% of Britain’s total electricity supply and 18% of our
renewable energy. This makes it our fourth most-generated renewable energy source after wind power, bioenergy and
solar power. The vast majority of hydropower in the UK is generated in Scotland and Wales in hydroelectric power
plants, located within reservoirs and dams across the Scottish Highlands and Welsh countryside. Dinorwig Power
Station in north-west Wales is the largest hydropower plant in the UK by far. It has a total capacity of 1,728
megawatts which is enough to power a whopping 2.5 million homes. In Scotland, the Cruachan Power Station in
Argyll and Bute can generate 440 megawatts of hydroelectric power and power up to 225,000 homes.
In most developed countries, all the suitable hydroelectric sites are already fully utilised. The Three Gorges Dam in
Hubei, China, has the world's largest instantaneous generating capacity (22,500 MW), with the Itaipu Dam in
Brazil/Paraguay in second place (14,000 MW). Despite the large difference in installed capacity these two power
stations generate nearly equal amounts of electrical energy during the course of an entire year - Itaipu 103.1 TWh in
2016 and Three Gorges 98.8 TWh in 2014, because the Three Gorges experiences six months per year when there is
very little water available to generate power, while the Paraná River that feeds the Itaipu has a much lower seasonal
variance in flow. The power output of the Three Gorges reaches 125 TWh in years of high feed availability.
There still exists great hydroelectric potential in many developing countries but large hydro schemes, particularly
those with large reservoirs, have a significant impact on the environment and the local population.
The difference in height between the upper reservoir and the level of the turbines or outflow is known as the head.
The water falling through this head gains energy which it then imparts to the turbine blades. Impulse turbines use a
jet of water at atmospheric pressure while in reaction turbines the pressure drops across the runner impart significant
energy.
Fig. 1.11. Schematic diagram showing the main components in a typical hydropower station.
9 Petcoke (petroleum coke) is the coke that, in particular, derives from a final cracking process—a thermo-based chemical engineering process that
splits long chain hydrocarbons of petroleum into shorter chains—that takes place in units termed coker units. (Other types of coke are derived
from coal.)
10 https://theswitch.co.uk/renewable-energy/hydroelectric-power
Page 7 of 18 Chapter_1_Intro_to_PS_v2.docx Dr. F. Gonzalez-Longatt
Chapter 1
Fig. 1.12. Schematic diagram showing the main components of a combined-cycle gas turbine (CCGT) power station.
Combined efficiencies of new CCGT generators now approach 50-60%. That is, from an overall efficiency of say 34%
(simple cycle), to possibly an overall efficiency of 62% (combined cycle), 84% Theoretical efficiency (Carnot cycle).
The advantages of CCGT plant are the high efficiency possible with large units and, for smaller units, the fast start
up and shut down (2–3 min for the gas turbine, 20 min for the steam turbine), the flexibility possible for load following,
the comparative speed of installation because of its modular nature and factory-supplied units and its ability to run
on light oil (from local storage tanks) if the gas supply is interrupted. Modern installations are fully automated and
require only a few operators to maintain 24-hour running or to supply peak load if needed.
Pembroke CCGT power plant is located in west Wales, UK. It was built with an estimated investment of £1bn and
was officially opened on 19 September 2012. With a total generating capacity of 2,160MW and thermal efficiency of
60%, it is one of the largest and the most efficient CCGT power plants in the UK. Pembroke power station is owned
and will be operated by RWE npower, an integrated energy company based in the UK.
1.6.4 Nuclear Power
Energy is obtained from the fission reaction which involves the splitting of the nuclei of uranium atoms. Compared
with chemical reactions, very large amounts of energy are released per atomic event. Uranium metal extracted from
the base ore consists mainly of two isotopes, U238 (99.3% by weight) and U235 (0.7%). Only U235 is fissile, that is when
struck by slow-moving neutrons its nucleus splits into two substantial fragments plus several neutrons and 11 J of
kinetic energy. The fast-moving fragments hit surrounding atoms producing heat before coming to rest.
The neutrons travel further, hitting atoms and producing further fissions. Hence the number of neutrons increases,
causing, under the correct conditions, a chain reaction. In conventional reactors, the core or moderator slows down
the moving neutrons to achieve more effective splitting of the nuclei.
As of 23 April 2014, the IAEA report there are 450 nuclear power reactors in operation operating in 31 countries.
Nuclear power in the UK generates around a quarter of the country's electricity as of 2016, projected to rise to a third
by 2035.
The UK has 15 operational nuclear reactors at seven plants (14 advanced gas-cooled reactors (AGR) and one
pressurised water reactor (PWR)), as well as nuclear reprocessing plants at Sellafield and the Tails Management
Facility (TMF) operated by Urenco in Capenhurst. The UK reactors are generating about 21% of its electricity but
almost half of this capacity is to be retired by 2025.
EDF Energy owns and manages the seven currently operating reactor sites, with a combined capacity of about 9 GW.
Six new plants are proposed to be built in the next few decades. All nuclear installations in the UK are overseen by
the Office for Nuclear Regulation.
PWRs constitute the large majority of the world's nuclear power plants (notable exceptions being Japan and Canada)
and are one of three types of light water reactor (LWR), the other types being boiling water reactors (BWRs) and
supercritical water reactors (SCWRs). An Advanced Gas-cooled Reactor (AGR) is a type of nuclear reactor designed
and operated in the United Kingdom. These are the second generation of British gas-cooled reactors, using graphite
as the neutron moderator and carbon dioxide as coolant. They have been the backbone of the UK's nuclear generation
fleet since the 1980s.
Hinkley Point C nuclear power station (HPC) is a project to construct a 3,200 MWe nuclear power station with two
EPR reactors in Somerset, England. The proposed site is one of eight announced by the British government in 2010,[4]
and in November 2012 a nuclear site licence was granted. On 28 July 2016 the EDF board approved the project, and
on 15 September 2016, the UK government approved the project with some safeguards for the investment. The plant,
which has a projected lifetime of sixty years, has an estimated construction cost of between £19.6 billion and £20.3
billion.
http://www.world-nuclear.org/information-library/country-profiles/countries-t-z/united-kingdom.aspx
11
https://www.renewableuk.com/news/425522/Energy-storage-capacity-set-to-soar-300-UK-based-companies-involved-in-new-sector.htm
12
Two-winding
transformer
Three-winding
transformer
Reactence
Impedance
Synchronous Machine
Rotating machine- M M
general
Load
Fuse
Circuit breaker
Fig. 1.16. Symbols for representing the components of a three-phase power system.
1 5 L1 3 1 5 3
L1
G1 Load 1 G1 Load 1
T1
L2 L3 T1 L2 L3
4 4
T2 T2
2 2
G2 G2
(a) ANSI (b) IEC
Fig. 1.17. An illustrative example of a single-line diagram of a simple power system: two synchronous generators (G1 and G2),
two two-winding power transformers (T1 and T2), one load (Load 1), three transmission lines (L1, L2, L3) and six circuit breakers.
13http://std.iec.ch/iec60617
14https://ieeexplore.ieee.org/document/985670
15https://www.nationalgrid.com/sites/default/files/documents/37783-ETYS%202014%20Appendix%20E%20-%20Technology.pdf
Fig. 1.20. Schematic diagram of the constituent networks of a supply system. USA voltages in parentheses.
1.9.1 Interconnections
Interconnection allows an alternative path to existing between generators and bulk supply points supplying the
distribution systems. This provides security of supply should anyone path fail.
The interconnections of power systems offer the following advantages.
(a) Quality: The voltage profile of the transmission network improves as more generators contribute to the
system, resulting in an increased total system capability. This also improves the frequency behaviour of the
system following any load perturbation due to increased inertia of the system.
(b) Economy: In interconnected systems, it is possible to reduce the total set of generating plants required to
maintain the desired level of generation reserve. This results in the reduction of operational and investment
Fig. 1.22. An illustrative diagram of a typical arrangement of supply to an urban network–British practice.
Electricity distribution networks carry electricity from the high voltage transmission grid to industrial, commercial
and domestic users. There are 14 licensed distribution network operators (DNOs) in Britain, and each is responsible
for a regional distribution services area. The 14 DNOs are owned by six different groups.
The DNO groups and individual DNOs are16:
Electricity North West Limited
Northern Powergrid: Northern Powergrid (Northeast) Limited, Northern Powergrid (Yorkshire) plc
Scottish and Southern Energy: Scottish Hydro Electric Power Distribution plc, Southern Electric Power
Distribution plc
ScottishPower Energy Networks: SP Distribution Ltd, SP Manweb plc
UK Power Networks: London Power Networks plc, South Eastern Power Networks plc, Eastern Power
Networks plc
Western Power Distribution:
o Western Power Distribution (East Midlands) plc
o Western Power Distribution (West Midlands) plc
o Western Power Distribution (South West) plc
o Western Power Distribution (South Wales) plc
Fig. 1.23. Electricity distribution map of GB, showing the geographical area of each company17.
https://www.ofgem.gov.uk/electricity/distribution-networks/gb-electricity-distribution-network
16
http://www.energynetworks.org/info/faqs/electricity-distribution-map.html
17
Fig. 1.24. Typical demand profile (MW) during 24-hours in GB. Seasonal variation is depicted.
The system operator must plan for unusual demand patterns such as "television pick-up"18. This is the sudden increase
in load when a popular television programme ends. This can provoke a rise of 1,000 MW in demand in a matter of a
few minutes. Major television events create even larger changes. The largest events are over 2,000 MW. Most TV
events can be predicted reasonably well based on previous experience. It is highly unusual events that cause problems.
It would also seem that the more diverse TV and entertainment market that now exists means that the TV pick-up is
less severe because the audience for each TV programme is less. The largest ever TV pick-up in the UK was 2,800
MW of demand after the penalty shootout in an England v. Germany world cup semi-final in 1990.
Fig. 1.25. An example of the phenomenon of “TV pickup” a very British problem, in this case, the 1990 World Cup England v’s
Germany match19. 2,800MW – equivalent to 1,120,000 kettles (based on 1MW = 400 kettles).
An example of a highly unusual event causing the system operator to work hard to maintain a stable system was the
two-minute silence at 11:00 am on 14th September 2001 in remembrance of the deaths on 11th September. In the
minutes before and during the silence, some 2,500 MW of load was switched off. This requires two large power stations
to be removed from the system very quickly. We can tell that this was not achieved quickly enough because the grid
frequency rose above its target range. When generation exceeds demand, the excess energy builds up in the inertia of
the generators and the frequency rises. The “missing” 2,500 MW of load reappeared over the next 5 minutes and
because there was now a shortage of generation the frequency briefly dipped below its target range.
18 TV pickup is a term used in the United Kingdom to refer to a phenomenon that affects electricity generation and transmission networks.
19 https://daryanenergyblog.wordpress.com/2013/09/24/blackout-paranoia/
Dr. F. Gonzalez-Longatt Chapter_1_Intro_to_PS_v2.docx Page 16 of 18
Three-Phase Systems
Fig. 1.26. Power demand during the Remembrance Day: 11:00 am on 14 September 2001.
A more recently, National Grid seems to have done a remarkably good job of managing some difficult demand pick-
up and drop-off associated with the Royal Wedding. They would have looked back in the records more than 10 years
for the last similar wedding but would have found direct comparison tricky because of the changes in TV viewing
habits over ten years and the fact that this time a bank holiday was declared and last time it was a normal workday.
Nonetheless, they managed to stop any large frequency excursions occurring despite swings in demand of more than
3,000 MW over an hour (actually a lot slower than a 2-minute silence).
Fig. 1.27. Frequency and demand during the Royal Wedding 29 April 2011. Electricity demand: 1,600MW – 640,000 kettles.
https://www.drax.com/technology/7-of-the-biggest-tv-moments-in-uk-electricity-history/
20