How's That?: How To Achieve A SCORS A Rating
How's That?: How To Achieve A SCORS A Rating
How to achieve a
SCORS A rating
Concrete-encased
steel frames
Timber-sheathed
steel-framed structures
How’s that?
Complex steelwork, the cricket
calendar and Covid-19 were no match
for the project team behind two
striking new stands at Lord’s
CM
MY
CY
CMY
thestructuralengineer.org/jobs
The Structural Engineer Jobs is the official jobs board
for The Institution of Structural Engineers.
The perfect place to find the latest
350
structural engineering vacancies.
posted on
jobs average
every month
Features
10 Optimising the structural design of modular housing
by combining timber and lightweight steel framing
Climate emergency
14 How to achieve a SCORS A rating using current
38
materials and technology
Professional guidance
16 Collaborative Reporting for Safer Structures:
Basement excavation under a semi-detached house
causes collapse
Technical
18 Concrete-encased steel frames, 1900–70:
considerations in their assessment and
refurbishment
Project focus
26 Design and construction of the Compton and Edrich
stands, Lord’s Cricket Ground redevelopment
10
Opinion
34 Viewpoint: Could sustainability be advanced through
simplification of codes of practice?
38 Book review: Why do buildings collapse in
earthquakes?
4
40 Verulam
At the back
Volume 100 │ Issue 5 │May 2022
43 Diary dates
46 Spotlight on Structures
48 Services Directory
46
50 TheStructuralEngineer Jobs
COVER: CLARE ADAMS/MCC
18
3
thestructuralengineer.org | May 2022
34
CONTENTS_TSE May 2022_The Structural Engineer.indd 3 21/04/2022 09:15
Embodied carbon basics
for structural engineers
on-demand course
Learn how to undertake embodied carbon calculations Module 1: Definitions, the
calculation, scope
for every project and aspect of structural design. This
Module 2: Using the results,
new course is essential undertaking for all engineers reuse and refurbishment
and contributes to your CPD.
Module 3: Steel, concrete,
Features four captivating modules you can follow at your timber, brick and masonry
own pace. Module 4: Other materials,
environmental product,
––– declarations
Book now:
www.istructe.org/resources/training/
embodied-carbon-basics-on-demand-course
21144_embodied_carbon_FP.indd
TSE.May22_004.indd 4 1 21/02/2022
19/04/20224:27 pm
16:55
Editorial Upfront
PRESIDENT
Jane Entwistle
BSc(Hons), CEng, FIStructE, MICE
CHIEF EXECUTIVE
Martin Powell
EDITORIAL
HEAD OF PUBLISHING
Lee Baldwin
MANAGING EDITOR
Robin Jones
t: +44 (0) 20 7201 9822
e: [email protected]
Robin Jones Managing Editor
EDITORIAL ENQUIRIES
Hitting a top
Noha Ali
t: +44 (0) 20 7201 9152
e: [email protected]
ADVERTISING
DISPLAY SALES
SCORS rating
t: +44 (0) 20 7880 7632
e: [email protected]
RECRUITMENT SALES
t: +44 (0) 20 7880 6235
e: [email protected]
DESIGN
SENIOR DESIGNER
Nicholas Daley
PRODUCTION AS SPRING ARRIVES at HQ in London, and we In the Technical section, Nicholas Bill looks at
PRODUCTION DIRECTOR
Jane Easterman
feel the warmth of the sun again, many people’s the historic use of concrete encasement for steel
thoughts will be turning to cricket. Despite the frames, aiming to provide some guidance on the
EDITORIAL ADVISORY GROUP
Will Arnold MIStructE
recent trials and tribulations of the England men’s unusual characteristics of such structures and
Premma Makanji MIStructE team, thousands of people up and down the how these should be considered when planning
Allan Mann FIStructE
Chris O’Regan FIStructE country will be turning out to follow their counties. refurbishment works (page 18). Assessment of
Angus Palmer MIStructE
Simon Pitchers FIStructE
So, what better way to mark the start of the season concrete-encased steel frames requires a thorough
Eleana Savvidi MIStructE than with an article describing the design and understanding of the materials used and knowledge
Subscription prices construction of a pair of striking new stands at of the design practice at the time of construction.
Institutional: £479
Personal (print only): £110
Lord’s – the ‘Home of Cricket’ Other content this month
Personal (online only): £110 (page 26)? includes a CROSS report on
Personal (Student Member): £45
The authors discuss the a basement excavation that
Single copies: £25 (incl. p&p) design of the steel-framed
structures, with a secondary
OFF-SITE led to the collapse of a semi-
detached house (page 16),
CONSTRUCTION
Printed by
Warners Midlands plc
timber beam network for as well as our usual Verulam
CAN ALLOW
The Maltings, Manor Lane Bourne,
Lincolnshire PE10 9PH the canopies, along with (page 40), Diary dates
United Kingdom
5
thestructuralengineer.org | May 2022
6
May 2022 | thestructuralengineer.org
The Institution’s History Study Group has opened up an entirely new way of assessing
value of made available a ‘technical autobiography’ that stability.
developments of Jacques Heyman, former Professor and He also recognised that maintaining
Head of the Department of Engineering at compatibility wasn’t essential, as it is for an
with
the University of Cambridge. First published elastic theory, as the natural state of masonry
sustainable in the Peterhouse Annual Record in 2019, is to be cracked.
design ‘Skeletons: A Technical Autobiography Written He first applied this approach to masonry
A report by for Instruction and Entertainment’, charts bridges, but was soon asked to apply it to the
engineering consultancy Patrick Parsons, based the course of Professor Heyman’s long and more complex structures of Gothic churches.
on research with 100 senior executives of UK illustrious career, Jacques Heyman is the author of 14 books
construction firms, reveals that they are seeing Jacques Heyman was one of the people and co-author of two others, and has written
significant commercial benefits from using who recognised the limitations of the elastic numerous articles on the plastic design of steel
sustainable design and engineering to build theory of structural mechanics and developed structures, masonry construction, general
developments with a lower carbon footprint and the plastic theory to better predict the failure structural theory, and the history of structural
water use, and to reduce waste and materials of structures. engineering. He is a Fellow of the Society of
used. His early work applied plastic theory to the Antiquaries, of the Institution of Civil Engineers
In the report, Sustainable by design, two- prediction of the strength of steel structures and of the Royal Academy of Engineering.
thirds (66%) of respondents said sustainable and that work has changed how we picture Jacques Heyman has been a member of
design is adding value to current developments their behaviour and assess their strength and the IStructE History Study Group for many
and 83% said that projects designed with green stability. years and in 1992 gave the ‘Star’ (now
credentials have given them a competitive He then perceived that plastic theory could Sutherland) history lecture on ‘Rib vaults and
advantage. Furthermore, 68% expect the value be applied to masonry structures, recognised flying buttresses – the structure of Gothic’.
of developments with sustainable design to that the central problem was usually the
increase by between 10% and 20%, and 18% stability of their equilibrium, rather than Download the biography at www.
expect values to increase by between 20% and their strength, which was the focus of most istructe.org/get-involved/study-
50% over the next three years, demonstrating approaches and of all codes of practice, and groups/history-of-structural-engineering/.
the significant premium placed on sustainable
construction. Industry news
The research also highlighted that the most New Dutch bridge tests flax-based bio-composite material
important aspect of sustainably designed
developments is that they can be adapted to An EU project entitled ‘Smart Circular project is investigating options for the building
meet future environmental and social challenges. Bridge’ is showing what is possible with an material after the bridges have reached the
innovative new bio-composite based on end of their life. These include mechanical,
Read the report at www.patrickparsons. flax. The project involves the development chemical, or even biological recycling with
co.uk/wp-content/uploads/Sustainable- of three bridges using the material, the first fungi.
by-Design-Report-Web.pdf. of which has been unveiled at the Floriade ‘These materials have a great future,’
international horticulture exhibition in Almere, said project leader, Professor Rijk Blok, from
the Netherlands. TU Eindhoven. ‘In particular, the intensive
Institution news The bridge, which has a span of 15m, cooperation between science, industry and
Have you considered joining the has been developed by an international communities has given a big push to materials
consortium of 15 partners led by Eindhoven development.’
IStructE Expert Witness register?
University of Technology. The project team
The IStructE Expert Witness register helps consists of five universities, seven innovative Find out more about the project at
Chartered Members kickstart their careers as companies, and three municipalities. www.nweurope.eu/projects/project-
Expert Witnesses, by promoting their skills and As well as 100% natural flax fibres, the bio- search/smart-circular-bridge-scb-for-
specialisms to legal firms and other interested resin will also use non-fossil sources as much pedestrians-and-cyclists-in-a-circular-
parties. as possible. The proportion of bio-resin in the built-environment/.
Unlike other registers, the IStructE register first bridge is 25%, but will reach 60% or more
includes details of your specialist structural in the next two bridges. This will be achieved
engineering knowledge, helping clients and legal by using waste products from bio-diesel
professionals access the expertise they require production and recycled PET bottles.
quickly and effectively. The bridge will be systematically monitored
Successful applicants will also gain in real time. Almost 100 sensors provide
membership of The Academy of Experts (TAE), data on the material’s behaviour in everyday
with all membership benefits available for the year use. A structural health monitoring system
at no additional charge (including technical advice with optical glass fibre sensors provides
and guidance, information services and practical information on material strains, and
SMART CIRCULAR BRIDGE
assistance in relation to their work as an Expert acceleration sensors detect even the finest
Witness). vibrations caused by wind. Evaluation of data
from the sensors is carried out with the help
Find out more or express your interest at of artificial intelligence to recognise patterns
www.istructe.org/get-involved/become- in material behaviour. The data can be viewed
istructe-expert-witness/. on a dashboard at
dashboard.smartcircularbridge.eu/.
With the circular economy in mind, the
8
May 2022 | thestructuralengineer.org
PROFESSIONAL INDEMNITY
INSURANCE SOLUTIONS
Always Happy to Talk Run-Off Cover available when you cease trading
Structural Engineers and Associated Fast Quote Turnaround with
Property Professionals Efficient Expert Service
Great Rates for Established Firms and Pro-active Claims Service
New Start Up Practices Interest Free Instalments Available
Exclusive In-House Scheme with a Complimentary Legal Review Service Available
Major UK Insurer Surveying Equipment And Office Insurance
Wide Choice of other Insurers available to quote Public Liability and Employers Liability Insurance
When the Insurance Market changes, find your port in a storm. Anchorman Insurance at your service.
Specialist Professional Indemnity Insurance Brokers focussed on Sole Trader,
Small to Medium Sized Enterprises and New Start Up Practices since 1998.
10
May 2022 | thestructuralengineer.org
| A
series of 32 tensile tests was use of cement particleboards at the largest forces, while the screws
performed on coupons longitudinally the bottom of the shear wall as an around the openings and in the top and
cut from the webs and flanges of aboveground waterproofing measure bottom stripes of the wall experience
C-section profiles. Testing was were scrutinised. A typical shear wall forces of lower amplitude.
completed in accordance with BS configuration in the first-floor front Accordingly, the screw density
EN ISO 6892-1 (2016)6. Figure 2a facade of ilke Homes’ modular house and the sheathing board layout were
shows the BS EN ISO-dictated is shown in Fig. 2d. optimised by positioning screws in
coupon dimensions for steel sheet | O
ptimisation of the wall materials optimal positions and making the fewest
thickness (1.6 mm) used in the tests. in terms of CFS cross-sections, cuts possible to boards, although fire
| T
hirty-three tests on screws sheathing board cuts and the number design requirements in terms of screw
connecting sheathing boards to of sheathing-to-CFS screws was spacing had to be met as well.
CFS profiles were carried out. carried out using FEA. Figure 5a shows the failure mode in
The experiments investigated the | A
set of design guidelines for the the shear wall represented by damage in
sheathing type and thickness, as well sheathing layout, screw distribution the OSB corners around the openings.
as the distance between the screw’s and stud cross-section dimensions A similar trend was obtained from the
longitudinal axis and the edge of the has been drafted. FEA simulation (Fig. 5b), where the grey
sheathing (i.e. the edge distance). areas in the von Mises stress contour
The test set-up as designed and Results show parts of the boards that are under
implemented in the laboratory is The lateral load-versus-displacement stresses higher than their nominal
shown in Fig. 2b. curves from monotonic tests on full-scale strength (7MPa).
| F
orty-one FEA models of different shear walls are plotted in Figure 3 along
CFS-framed shear wall configurations with FEA results. The FEA modelling Benefits
were established in Abaqus/CAE protocol developed accurately simulates The above results have brought several
2017 (Fig. 2c). the lateral behaviour (strength and benefits and improvements to the design
| F
ifteen CFS-framed shear walls stiffness) of the tested walls. of ilke Homes’ modules:
were designed and tested under Assessment of the shear force on | R elying on OSB-to-CFS screw shear
monotonic lateral loads (i.e. the sheathing-to-CFS screws at peak strength and stiffness to develop
wind loads). The influence of the strength of the wall (Figure 4) revealed lateral capacity in the external walls,
area, number and position of the that the screws at the vertical straight instead of K-bracing or X-strap
openings, screw spacing, and the edges of the sheathing boards endure bracing, led to a 5% reduction in steel
11
thestructuralengineer.org | May 2022
a) Coupon
testing for CFS
characterisation
b) OSB-to-CFS screw shear tests
c) FEA modelling of
CFS shear wall
80% OF ENGLAND
simulated lateral load
vs displacement
12
May 2022 | thestructuralengineer.org
ëFIGURE 4: Screw
force vector diagram
at peak load
a) Tested b) Numerical
ìFIGURE 5: Model deformation at peak load showing localised failure of sheathing boards
REFERENCES
per module (minimum saving of £405 have common long walls in the 1) Kechidi S., Banks N. and Iuorio O. (2021) ‘Contribution of
and a reduction in embodied energy). ground-floor module. In addition, the OSB Sheathing to Racking Capacity of Cold-Formed Steel
| T
he strength and stiffness obtained reduction in the CP boards’ height Frames’, ce/papers, 4, pp. 393–400; https://doi.org/10.1002/
for the tested shear walls made it enabled the sheathing layout to be cepa.1308
possible to change to a generic designed with off-the-shelf OSB 2) Iuorio O., Kechidi S. and Banks N. (2021) ‘Experimental
design that covers 80% of England, dimensions, which significantly helped investigation into the performance of cold-formed steel walls
considering wind speed, distance to in reducing material waste. sheathed with OSB and cement-based panels’, ce/papers, 4,
shore and altitude above sea level. | F
ull board layouts can be pp. 525–529; https://doi.org/10.1002/cepa.1325
| S
heathing-to-framing screw density accommodated on the HSPL with 3) Kechidi S. and Iuorio O. (2022) ‘Numerical investigation
is now under the ‘takt time’ of an a cut at each end. Previously, these into the performance of cold-formed steel framed shear
automated high-speed panel line required trimming or packing out on walls with openings under in-plane lateral loads’, Thin-
(HSPL) – 600 screws per cycle for the HSPL bed. Walled Struct., 175, 109136; https://doi.org/10.1016/j.
one pair of walls – allowing ilke’s | S
heathing board arrangements are tws.2022.109136
production target to be reached. now common across floors and 4) British Standards Institution (2005) BS EN 1993-1-
| A
voidance of triangular insulation house types. 1:2005+A1:2014 Eurocode 3. Design of steel structures.
cuts due to the absence of K-bracing General rules and rules for buildings, London: BSI
in the external walls of the modules These improvements in design and 5) British Standards Institution (2006) BS EN 1993-1-
resulted in a significant reduction manufacturability have been reviewed 3:2006 Eurocode 3. Design of steel structures. General
in labour time. In addition, loose fill and accepted by consultant structural rules. Supplementary rules for cold-formed members and
insulation is enabled as well. engineers, as well as being accepted for sheeting, London: BSI
| C
ement particle (CP) board strips warranties and accreditation by the key 6) International Organization for Standardization (2016)
have been reduced from 600mm reviewing bodies SCI, NHBC and BLP/ ISO 6892-1:2016 Metallic materials – Tensile testing – Part 1:
to 300mm, making it possible to BOPAS. Method of test at room temperature, Geneva: ISO
13
thestructuralengineer.org | May 2022
3. Lean design
The science is now unequivocal – climate change | worries about errors (‘sleep at night’ this quickly) and then engage with the contractor
is happening, and human activities are the main factors): designers overdesign structures so to understand if/where it is beneficial to put
cause; we must act now to mitigate the worst that there is excess capacity to ameliorate any material back in.
consequences. Structures are responsible mistakes that occur in calculation, draughting,
for a significant amount of embodied carbon manufacture or installation. Challenge load allowances (10% saving)
emissions: current practice in buildings results in Imposed loads for London offices are still
upfront carbon emissions of 300–600kgCO2e/m2 While both behaviours are understandable and often set at 4+1 = 5kN/m2, whereas Eurocode
for the structure1–3. However, there are significant stem from good intentions, they add unnecessary recommends 2–3kN/m2. Research has shown
reductions that can be made using current carbon emissions. the lower values to be more than sufficient for
materials and technology if we: A more efficient approach would be to design most scenarios7 – and using them would reduce
| design more efficiently targeting 100% utilisation (using software to do carbon by 10%8.
| construct more efficiently.
Designing efficiently
We have a duty to our clients and to society to
apply our skills and abilities to make best use of
materials and design efficiently. As a profession,
we design conservatively to keep people safe;
however, there is evidence that we are over-
conservative in places in our assumptions
about loading, serviceability requirements and
appropriate utilisation.
14
May 2022 | thestructuralengineer.org
Table 1: Estimated carbon savings as applied to typical building an estimate of the savings potential; the latter
two columns apply these reductions to a
Values for a typical building structure typical 500kgCO2e/m2 (average of sources
CO2e savings
Change 1–3) structure to show the absolute and
estimate kgCO2e/m2 % percentage values.
As can be seen, the net effect is a sizeable
None (current practice) – 500 100% 75% reduction, resulting in a typical building
structure of just 123kgCO2e/m2 – less than the
Challenge load allowances 10% 450 90%
150kgCO2e/m2 required to achieve a SCORS
A rating1. SCORS sets this target for 2030,
Reassess serviceability 25% 337 68%
but fortunately we can achieve it immediately.
Target high utilisation 30% 236 47% So, what’s stopping us?
Engineers can also be overzealous when diameters, lengths and pitches to closely match
allowing for future loads: while having long- steel provision to that required, or fabricating 1) Arnold W., Cook M., Cox D., Gibbons O.
life structures is also required to minimise steel beams with variable thicknesses or depths, and Orr J. (2020) ‘Setting carbon targets: an
introduction to the proposed SCORS rating
future emissions, allowing for adaptability (e.g. reducing material by 30% in some examples10, all scheme’, The Structural Engineer, 98 (10), pp.
enabling future addition of extra members or while increasing build quality. 8–12
strengthening) can be a more resource-efficient
2) London Energy Transformation Initiative
way of achieving it9. Material partial factors (20% saving) (2020) LETI Embodied Carbon Primer [Online]
Design codes assume a traditional level of Available at: www.leti.london/ecp (Accessed:
Reassess serviceability (25% saving) workmanship and inspection in construction; in March 2022)
Serviceability limits, such as for deflection, the Eurocodes these are included in the material 3) UK Green Building Council (2015) Tackling
often govern structural design, yet too often partial factor values. Placement tolerances and embodied carbon in buildings, London:
UKGBC
are excessively conservative. Engagement with material properties (e.g. concrete strength) can
clients and the supply chain at appropriate points be more closely controlled off site, resulting in a 4) Gibbons O. and Orr J. (2020) How to
in the design process can mitigate this by: reliably more accurate construction. Eurocode calculate embodied carbon, London: IStructE
Ltd
| u nderstanding what limit is appropriate for the clauses enable this increased quality to be
end user, e.g. could span/360 deflection limits reflected in a reduction in the material partial 5) Moynihan M.C. and Allwood J.M. (2014)
‘Utilization of structural steel in buildings’,
be relaxed to span/250? Is a response factor factors11. Applying this reduction to columns Proc. R. Soc. A., 470, 20140170; https://doi.
of 4 absolutely necessary for an office floor or on a UK project resulted in a 20% reduction in org/10.1098/rspa.2014.0170
would 6 or 8 suffice? embodied carbon. 6) Orr J., Copping A., Drewniok M., Emmitt
| a djusting slab-edge deflection limits when the S. and Ibell T. (2018) MEICON: Minimising
cladding supplier is appointed and can advise Reduced waste (2% saving) Energy in Construction Survey of Structural
the specific capabilities of their system. Building products for multiple projects on a Engineering Practice Report; https://doi.
org/10.17863/CAM.35178
single production line offers the opportunity to
Furthermore, given it is a serviceability limit use offcuts from one project on the next and 7) Drewniok M and Orr J. (2018) MEICON:
Demonstrating Floor Loading Report [Online]
state, stiffness contributions from partition walls eliminate the need to over-order materials to de- Available at: www.meicon.net/floor-loading
or secondary steelwork/concrete could be added risk construction. On-site construction commonly (Accessed: March 2022)
into deflection analyses to augment the response features abortive work and rework caused 8) Hawkins W., Peters A. and Mander T.,
of the primary structure. It is estimated that by trades working in close proximity or out of (2021) ‘A weight off your mind: floor loadings
coupling these contributions with relaxing limits by sequence; by contrast, factory work typically and the climate emergency’, The Structural
30–50% could give a 25% carbon reduction. eliminates such issues. These effects can reduce Engineer, 99 (5), pp. 18–20
waste from the 5% typically seen on site4. 9) Field C. (2020) ‘Lean yet resilient – designing
Constructing efficiently for the future’, The Structural Engineer, 98 (8),
pp. 15–17
While many structures are still built in a 1950s, Using 56+ day strengths (5% saving)
in situ manner, modern methods of construction Twenty-eight-day concrete strengths are 10) Allwood J.M., Cullen J.M., Carruth
A.M. et al. (2011) Going on a metal diet
(MMC) are becoming increasingly attractive as specified; however, particularly for off-site
[Online] Available at: www.uselessgroup.org/
a way to enhance quality and safety while also manufacture, the concrete is often more mature publications/reports/wellmet-2050-going-
offering the potential to significantly reduce than this when it is loaded. Fifty-six-day strengths metal-diet (Accessed: March 2022)
material (Figure 1). Factory environments are are 15–20% higher12, and could therefore enable 11) Institution of Structural Engineers (2021)
more controlled workplaces with the potential to lower cement mixes to be used, potentially Reduced reinforcement through reduced
leverage economies of scale, while automated reducing carbon contents by ~5%. material partial factors [Online] Available
at: www.istructe.org/resources/guidance/
systems offer the ability to more closely tailor
reduced-reinforcement-material-partial-factors/
manufacturing output to design requirements. Summation (Accessed: November 2021)
Obviously, the above savings cannot be
12) British Standards Institution (2008) BS EN
Optimised manufacture (30% saving) arithmetically summed – instead, they compound 1992-1-1:2004+A1:2014 Eurocode 2: Design of
Robots can manufacture complex arrangements in the order shown in Table 1. The first two concrete structures. General rules and rules for
efficiently, e.g. changing reinforcement bar columns list the changes described above with buildings, London: BSI
15
thestructuralengineer.org | May 2022
16
May 2022 | thestructuralengineer.org
What is CROSS?
BASEMENT CONSTRUCTION
IS SPECIALIST HIGH-RISK Collaborative Reporting for Safer Structures
17
thestructuralengineer.org | May 2022
70: considerations in
buildings. While no comprehensive study has ever
been undertaken to quantify these structures, the
inclusion of encased sections within contemporary
literature produced by steel manufacturers is
refurbishment
especially, London.
18
May 2022 | thestructuralengineer.org
connections.
FIGURE 2: Typical beam-to-column connections before 1970
Batho and Lash further investigated the
effects of encasement on semi-rigid connections,
finding that the strength and stiffness of various
specimens were enhanced until the concrete
in tension cracked (Figure 3)7. The improved
behaviour was dependent upon the arrangement
of reinforcement within the encasement.
However, the cases without reinforcement
were also found to have significant improvements.
In these cases, local passive stresses develop
within the encasement surrounding the flange
and web cleats, creating a confining effect.
Hence, the flexure of the cleats is reduced and
therefore the rotation of the beam, resulting in a
higher yielding moment (Figures 3 and 4). Once
cracks form in the concrete encasement, the
effects of confinement reduce (especially around
the top cleat) and the curve roughly follows that of
the bare steel specimen.
Batho and Lash’s conclusions concurred
with Baker. They recommended that for beam
design, the increase in restraining moments
provided by the encasement should be ignored.
However, for column design, stiffening should
FIGURE 3: Moment-angle curves for encased connections be considered to calculate the worst-case
actions.
The extent to which the stiffening effects
of the encasement were subsequently
considered in analysis is difficult to determine,
as the approach is absent from contemporary
textbooks. Indeed, when presenting the design
of the Red Road Towers of Glasgow (1967),
then Europe’s tallest residential buildings,
McClusky noted that the determination of such
properties had been the subject of argument for
years8, indicative of a varied design approach.
Moreover, the author has encountered buildings
REPRODUCED AND ADAPTED FROM BATHO AND LASH, 1936
19
thestructuralengineer.org | May 2022
‘Incombustible’
1930 London C.C. Act 116 (7.5) 116 (7.5) As previous As previous As previous
1939 London C.C. Act 124 (8) 124 (8) As previous As previous As previous
1948 BS 449:1948 154 (10) 139 (9) 1:2:4 mix and adequately 4.76mm (3/16in.) dia. I-section with single web
reinforced by binding or bars in the form of
stirrups stirrups or binding at
not more than 6in.
Casing to be at least 4in. (152.4mm) pitch, and
wider than flanges and so arranged as to pass
provide 2in. cover through the centre of the
covering to the edges
and soffit of the lower
flange
1959 BS 449:1959 162 (10.5) 147 (9.5) 1:2:4 mix As previous I-section with single web
(Combined BS 154 (10) 139 (9) 9.53mm (3/8in.) aggregate C-section back-to-back,
449 and CP113) t>19mm t>19mm not more than 1½in. apart
Works strength >20.68MPa
(3000lb/sq.in.) at 28 days Steel to be unpainted
Materials used in construction more than 40mm apart) were considered by such measurements rarely identify the correct
Steel frame members: sizes and steel British codes to be enhanced structurally. section. The only certain way to determine the
quality Approximate sizes of the steel members can section is to locally break out the encasement
Practically any section could be encased for fire be cautiously deduced from measurements and take measurements of the steel.
purposes, but only single I-sections (including of the encasement. However, considering the With these structures typically appearing
those with additional riveted flange plates) and encasement can be oversized and compound after 1900, rolled sections should conform to
twin channel sections (fixed back-to-back, no sections were commonly used for columns, standard sizes. Most can be identified in the
20
May 2022 | thestructuralengineer.org
21
thestructuralengineer.org | May 2022
Technical Concrete-encased steel frames
22
May 2022 | thestructuralengineer.org
23
thestructuralengineer.org | May 2022
REFERENCES
1) Humphrey R.L. (1912) ‘Fireproofing’, Transactions 9) British Constructional Steelwork Association 18) Batho C., Lash S.D. and Kirkham R.H.H. (1939)
and Notes of The Concrete Institute, 4 (3), pp. 316–396 (1991) Historical Structural Steelwork Handbook, ‘The properties of composite beams, consisting of
London: BCSA steel joists encased in concrete, under direct and
2) Andrews E.S. (1924) ‘Structural steelwork
sustained loading’, J. ICE, 11 (4), pp. 61–114
reinforced with concrete’, The Structural Engineer, 2 10) Molesworth H.R. (1902) ‘American workshop
(7), pp. 290–291 methods in steel construction’, Min. Proc. ICE, 19) British Constructional Steelwork Association
148, pp. 58–74 (1950) Safe Load Tables, London: BSCA
3) Institution of Structural Engineers (1964) Report
on composite construction in structural steel and 11) Beal A.N. (2011) ‘A history of the safety 20) Wilson H.C. (1939) Building Design and
concrete, London: IStructE factors’, The Structural Engineer, 89 (2), pp. 20–26 Construction, London
4) Bussell M. (1997) P138: Appraisal of existing 12) BCSA, Historical Structural Steelwork 21) Joint Committee on Fire Grading of Buildings
iron and steel structures, Ascot: Steel Construction Handbook, pp. 9–10 (1946) Post-War Buildings Studies No. 20. Fire
Institute, p. 44 Grading of Buildings. Part 1: General Principles
13) Results published in 1924 by Redpath, Brown
and Structural Precautions, London: HMSO
5) British Standards Institution (1969) BS 449-2:1969 & Co. In: BCSA, Historical Structural Steelwork
The use of structural steel in building, London: BSI Handbook, p. 73. 22) Malhotra H.L. and Stevens R.F. (1964) ‘Fire
resistance of encased steel stanchions’, Proc. ICE,
6) Baker J.F. (1936) ‘The rational design of steel 14) Faber O. (1956) ‘Savings to be effected by
27 (1), pp. 77–98
building frames’, J. ICE, 3 (7), pp. 127–210 the more rational design of cased stanchions as
a result of recent full-size tests’, The Structural 23) Malhotra H.L., Stevens R.F., Creasy L.R. et al.
7) Batho C. and Lash S.D. (1936) Further
Engineer, 34 (3), pp. 88–109 (1964) ‘Discussion. Fire resistance of encased steel
investigations on beam and stanchion connections
stanchions’, Proc. ICE, 29 (2), pp. 446–459
encased in concrete. Together with laboratory 15) Jones R. and Rizk A.A. (1963) ‘An investigation
investigation on a full-scale steel frame, Final Report, on the behaviour of encased steel columns under 24) Bailey C.G. and Newman G.M. (1998) ‘The
Steel Structures Research Committee, Department load’, The Structural Engineer, 41 (1), pp. 21–33 design of steel framed buildings without applied
of Scientific and industrial Research, London: HMSO, fire protection’, The Structural Engineer, 76 (5), pp.
16) Stevens R.F. (1965) ‘Encased stanchions’, The
pp. 276–363 77–81
Structural Engineer, 43 (2), pp. 59–66
8) McClusky H. (1967) ‘Thirty-one-storey flats in 25) British Constructional Steelwork Association
17) Virdi K.S. and Dowling P.J. (1973) ‘The ultimate
structural steelwork’, The Structural Engineer, 45 (3), (1965) Prefabricated Floors for Use in Steel Frame
strength of composite columns in biaxial bending’,
pp. 111–130 Buildings, Publication No. M2.1964, London: BCSA
Proc. ICE, 55 (1), pp. 251–272
24
May 2022 | thestructuralengineer.org
26
May 2022 | thestructuralengineer.org
Project credits
Client Marylebone Cricket Club
Architect: WilkinsonEyre
Structural, building services, Buro Happold
fire and ground engineering;
Acoustics; Energy consulting;
People movement; Sustainability;
Transport and mobility; Technology;
Waste management and logistics:
Main contractor: ISG
Steelwork contractor (steelwork Severfield
connection design, detailing,
fabrication, supply, erection,
installation of metal decking, steel
stairs and precast seating units):
Demolition subcontractor: J Coffeys
Piling: Frankie
Groundwork: J Coffeys
Membrane supplier: ArchitenLandrell
CLARE ADAMS/MCC
27
thestructuralengineer.org | May 2022
FERGUS McCORMICK beverage concessions, two new restaurants, ground level, with the outer perimeter of the
MSt, MSc, MA, CEng, FIStructE, FICE new washrooms and a high-level connecting stands conceived as a lighter colonnade with
Partner, Buro Happold, Bath, UK walkway for improved crowd circulation. slim columns. The structural framing of each
In contrast to the previous stands, the top stand developed to a moment frame solution in
level is partially covered with a steel-framed roof, each direction.
TIM SULLIVAN which complements the subtle curvature and In the cross-section, the main part of the
form of the design while creating a distinctive main frames was generally supported on two
IEng, AMIStructE
silhouette, helping to heighten the sense of main columns with two further supports for the
Technical Director, ISG, London, UK drama of sporting events. lower tier (Figure 3). The rear columns became
A key requirement was to develop a coherent, pin-ended, enabling a transparent welcoming
IAIN HILL integrated structural design and construction elevation with a refined aesthetic; the lateral
strategy respecting the high-quality aesthetic strength and stiffness was focused on an
BEng, CEng, FIStructE, FICE
that the client and architect required. inner main column coupled with the bending
Associate Director, Severfield, Bolton, UK This article describes how Buro Happold resistance of main grid-line rakers. Lateral
considered all materiality for the frame design, resistance in the longer directions was also from
PAUL EDDLESTON before selecting steel after an extensive moment action, with the main front column
construction programming study. The design again providing the key strength and stiffness.
MSc, BSc, CEng, MICE
diagram of the steel moment frame in each The main supporting columns were some of
Senior Structural Engineer, Buro Happold, Bath, UK direction was chosen to suit the required the largest elements in each of the two stands:
openness, but the frame was designed with pin- typically 1400mm × 500mm box sections, with
MICK SLACK ended columns on the outer perimeter to enable 100mm thick base plates fixed with Macalloy
a light colonnade elevation and stiffer columns bar anchor assemblies. There are nine of these
BEng, CEng, MIStructE
on an inner line. The moment connections of the columns in the Compton stand and seven in the
Engineering Manager, Severfield, Bolton, UK frame were key details, with Severfield providing Edrich stand. Positioned on grid line B, which
important design input for the final choice. is in the middle of each stand, the columns sit
RAJAN MISTRY The article also discusses some of the towards the back of the lower tier, support the
challenges of working within the existing site 7m cantilevering seating area of the second
BSc (Hons)
and the unprecedented demands imposed by tier, and also support the underside of the
Engineering Technician, Buro Happold, Bath, UK Covid-19, explaining how ISG approached and uppermost seating level.
worked through these. The steel section types, depths and
Introduction connections give a clear legibility to the framing
Marylebone Cricket Club (MCC) has led the Design challenges diagram of the design (Figure 4). The lower
game of cricket for over 200 years and helped Design diagram tier was not included in the radial lateral stability
take it from a national pastime in England to The layout and organisation of floors and system as a low-level prop, because of its
a global obsession. At its heart is Lord’s, the seating tiers responded to the functional needs variable relationship to the main frame around
‘Home of Cricket’, where MCC is dedicated to of the buildings, with the overall form and shape the stands and because its optimum design
growing its reputation as the most celebrated developed to complement the JP Morgan choice for construction was uncertain for some
venue in cricket. Lord’s has been at its current Media Centre. Each stand, including its roof, time. Eventually, the lowest part of the lower tier
location in St John’s Wood, northwest London was spatially offset from the Media Centre to was generally formed of in situ concrete and the
for over 200 years. allow each part of the new elevation to be read whole of the tier was laterally isolated from the
Responding to an increasingly competitive individually, but also so that all three separate remainder of the main frame.
sporting environment, the Ground has building blocks – the Compton stand, the Edrich The frame was designed to the dynamic
been undergoing upgrade work to steadily stand and the Media Centre – could be read as criteria and method of the IStructE guide1.
improve facilities in accordance with a staged a single new composition. The cantilevers are long, but the frame is not
masterplan. MCC Chief Executive and The key structural design challenge was designed for concert events, which significantly
Secretary, Guy Lavender, has stated: ‘MCC is to maintain a light, airy feeling to the whole reduces the spectator excitation and, hence,
committed to ensuring Lord’s remains the best development and very open circulation at demand on the cantilevers.
place in the world at which to watch and play
cricket.’
The latest phase of the masterplan
FIGURE 2: View from Nursery
encompasses redevelopment of the Compton Ground (west) during later stages
and Edrich stands, which are situated either of construction showing new
stands, either side of JP Morgan
side of the distinctive aluminium JP Morgan
Media Centre
Media Centre at the famous Nursery End of
the Ground (Figure 1). The previous stands
were dated and lacking in facilities. The new
stands transform the Nursery End, providing
world-class facilities, opening up views both
to the Pavilion and back towards the Nursery
STEVE MACEY/BURO HAPPOLD
28
May 2022 | thestructuralengineer.org
Compton and Edrich stands, Lord’s Cricket Ground Project focus
Site constraints
Phased developments can allow continued
29
thestructuralengineer.org | May 2022
FIGURE 5: Thumbnail sketches used to explore different materiality options. Blue = steel, dark grey = in situ concrete, light grey = precast concrete
BURO HAPPOLD
the southwest side of the Ground almost FIGURE 6: Revit
2.5m lower than the northwest side. In model of stand
showing steel,
matches, it causes deviation to the ball when foundations and
bowling; for the project, it resulted in different shallow tunnel in
lengths of the lower tiers all the way through red. Half-toned
pink elements are
the Compton and Edrich stands. existing pile caps
30
May 2022 | thestructuralengineer.org
FIGURE 7:
Sketches for
developing
canopy design
FERGUS McCORMICK/BURO HAPPOLD
As well as demolition and groundworks, times. Inevitably, some members of the supply assembly. The three subassemblies were then
the first phase also included the erection of chain had to contend with Covid impacts, which dimensionally checked and welded together to
the main steel frames of the stands along affected productivity levels. form the single assembly, prior to painting and
with precast floor and terrace units. Work loading for delivery to site.
on the new structures began in January/ Steel frame fabrication and erection The grid line B box columns form the
February 2020, before concrete started to Severfield’s steelwork package involved some backbone of the primary structural stability
be placed in March/April. The project was complex fabrication, partly due to the effect system for the stands, incorporating moment
maintaining programme despite one of the of significantly varying geometries through the connections in both the transverse and
wettest winters in the past decade. WCC stands; this was especially true for the columns longitudinal directions. Not surprisingly, these
was supportive in allowing weekend working (Figure 8) and plate girder rakers (Figures 9 are among the most heavily engineered
for a four-month period. and 10), which provide support to the precast steelwork details on the project.
At this point, the Covid-19 pandemic hit, concrete terraces. The final connection details reflect Buro
with a lockdown imposed in March 2020. As part of the fabrication method, each Happold’s original concept very closely, with
ISG rapidly put a Covid plan into operation raker component was split into three individual the columns split above and below the primary
and site works continued safely with between subassemblies. This made turning, handling rakers at levels 2 and 3, effectively enabling
100 and 125 operatives on site each day, and machining in the factory a lot easier than the cantilever terrace rakers to be continuous
adhering to social distancing measures at all if the rakers had been fabricated as a single through the column, while facilitating moment
31
thestructuralengineer.org | May 2022
MICK SLACK/SUK
used four mobile cranes working concurrently
FIGURE 11: 3D – allowing both stands to be constructed at
model view of adopted
detail for typical raker–
the same time. (For further details, see article
column connection in NSC5.)
The longest upper-tier rakers were up to
20m long. This is marginally over a commonly
accepted transport limit of 18m, but Severfield
transfer between rakers/columns. FIGURE 12: MEP installation, with pre-detailed service established that it would be beneficial to
holes in steelwork
The detail was developed collaboratively fabricate and transport these as single-raker
between all parties; it involved widening the units rather than include site splices. The
top/bottom flanges of the raker local to the weights were up to 22t, requiring an additional
column, enabling the upper and lower column 300t capacity crane. During March 2020 there
assemblies to bolt directly to the raker section was a fifth crane on site – a self-erecting tower
(Figure 11). The increased flange width was crane – installing the steel stairs.
achieved by locally inserting a wider, ‘thicker’
flange plate – facilitated by virtue of the raker June 2020 onwards: roof fabrication and
sections being ‘fabricated’ plate girders, giving erection
greater flexibility for local thickening of material Building works continued through what had
where required. been anticipated to be the 2020 summer
The widened flange plates were specified cricket season and into the next closed season
to be slightly thicker than required, enabling from September. The phases after the main
FERGUS McCORMICK/BURO HAPPOLD
the plates to be machined flat after completion frame erection included blockwork installation,
of all welding (thus accounting for potential dry lining and MEP fit-out (Figure 12). The
‘distortions’ due to welding processes), to final construction phases included bar and
provide a suitable bearing fit-up between the restaurant fit-out, and the erection of the
rakers and columns. stands’ steel-framed roofs and the steel link
The column section was effectively replicated bridge.
within the depth of the raker, ensuring a direct The first major challenge in developing the
load path with minimal internal stiffening. steelwork connection details for the canopy
The principles of this detail were adopted as was to ensure accurate location of the roof
standard at levels 2, 3 and 4 on all primary cantilever tip, in elevation and on plan. This
frame gridlines, maximising rationalisation, and was required both for the structural fit-up of the
CHS leading-edge members with the cantilever
tip and for ensuring a smooth, continuous
FIGURE 13: View from curve and smooth aesthetic to the members
upper tier of Edrich stand (Figure 13).
looking north across rear
of Media Centre towards The challenge was addressed by designing
canopy of Compton and incorporating sufficient scope for
stand adjustment to accommodate potential building
tolerances. Several measures were adopted,
including a packing facility incorporated within
each connection of the canopy rib to the back
STEVE MACEY/BURO HAPPOLD
32
May 2022 | thestructuralengineer.org
Conclusion
Lord’s Cricket Ground required stands of
significant merit that would integrate with the
Ground’s character. The team worked to deliver
the complex engineering solutions required
for this high-quality project, and to overcome
MICK SLACK/SUK
Acknowledgements
Fergus McCormick thanks Monica McCormick
MICK SLACK/SUK
33
thestructuralengineer.org | May 2022
Viewpoint
Could sustainability
be advanced through
simplification of codes
of practice?
Alasdair Beal sets out his views on how changes to codes
of practice could enable engineers to achieve more efficient
designs with lower embodied carbon.
Ideas for reducing the carbon footprint and realised in practice because, in the real ratios for individual members but is less
improving the sustainability of structural commercial world, engineers on tight fee economical than a good manual design.
engineering have attracted attention in recent budgets may make conservative assumptions The potential useful life of a structure can
articles in The Structural Engineer. However just to ‘get the job done’ rather than spending also be extended by careful consideration of
there is little scope for reducing safety factors time honing a code-perfect design. serviceability and detailing for durability and
(the safety margin for structural steel has been There is also the risk that over-complex code low maintenance, often for little or no extra
reduced by about 40% since 1984). clauses may be misunderstood by material. If buildings are designed to last
Similarly, while overspecification of floor inexperienced engineers, leading to errors and longer, fewer will need to be demolished and
loadings should be avoided, reducing code designs which are either over-conservative or fewer will need to be constructed, reducing
imposed loadings would be a two-edged else dangerous – and potential extra costs far waste, energy and material use. The creativity
sword: possible small savings in initial cost and exceeding the theoretical benefits envisaged by and care of a good engineer can make a big
materials would have to be balanced against code writers. difference here3,4.
the potential loss of flexibility of use and So, simplifying codes is not just a ‘nice idea’.
consequent shortening of future useful life of If codes are made clearer and simpler to use, Code changes: six easy wins
buildings1–4, which could lead to long-term engineers are more likely to interpret them While there may be little scope for
costs and material waste far exceeding any correctly in practice and have the confidence to economising by cutting code safety factors or
initial savings. design consistently to code limits, improving loadings, other changes could be made which
However, there are other aspects of design the quality and economy of ‘real world’ designs. would significantly reduce material use and
and construction where changes could lead to carbon footprint without any need for fancy
significant ‘real world’ improvements in ‘Nice calculations, shame about calculations or compromising safety.
economy, material use and carbon emissions. the structure’
Excessive focus on code strength calculations 1) Structural steel grades
Simpler codes can distract attention from other important Several years ago, UK steel manufacturers
Current codes of practice for structural design matters. Lest we forget, good conceptual stopped producing UBs, UCs and PFCs in
are complicated and often difficult to design, efficient load paths and detailing for grade S275 and standardised on grade S355
understand. Given the continuing squeeze on ease of construction can have a major effect on steel, but this was not widely publicised in
structural design fees, most engineers would economy in cost and materials. technical journals, so some engineers still
welcome codes which are easier to understand However, for this to happen, engineers need design to grade S275 stresses. Structural steel
and use – but there is more to it than that. a good understanding of structural behaviour use could be significantly reduced simply by
Complexity is unavoidable in some aspects and time to think about the structural scheme publicising this change more widely.
of design, but many current code clauses could before starting detailed calculations5. This is However, in some other sections caution is
be made simpler without any significant effect particularly important when using 3D computer needed: grade S355 used to be standard for
on economy. Also, the theoretical economy analysis6. If this is not done, the result may be most steel tubes, but many are now produced
offered by a complex code clause may not be an inefficient structure which has high utilisation in S235. Also, although European sections are
34
May 2022 | thestructuralengineer.org
available in grade S355, they are also produced codes11, would improve safety and economy
in S275 and S235. where a full second-order analysis is not carried
out; it would also help initial sizing of columns
2) Specifying concrete ENDING OVER- and provide a ‘sense check’ on the results from
Most commercial buildings have concrete SPECIFICATION complex computer analysis.
floors and it is common for the concrete grade
to be specified as RC30/37 or RC32/40. OF CONCRETE Also, the EC3 clauses on sway frame
columns are complex, confusing and over-
However, unless the concrete is to be exposed COULD REDUCE conservative: in addition to wind loads, the rules
as a wearing surface this is rarely necessary –
RC20/25 is adequate for strength and
CEMENT USE BY require lateral loads representing imperfections
to be applied, even though these imperfections
durability in an indoor slab. Ending UP TO 20% have already been allowed for in the standard
overspecification of concrete could reduce column allowable stresses12. Furthermore, while
cement use by up to 20%. it is a good idea to specify minimum lateral
reasonably accurate span-to-depth rules which loads on a structure to ensure robustness,
3) Concrete cover can be applied at the start of the design. This requiring these to be added to the wind load is
For indoor concrete slabs, Eurocode 2 and BS can be done if accurate span-to-depth ratios unnecessarily conservative.
8500-1 generally require at least (15 + 10mm =) are calculated for different types of slab (e.g. Revising these EC3 clauses would simplify
25mm nominal reinforcement cover and some simply supported, continuous, flat slab), with design – and also improve economy.
engineers specify even more. However, fully stressed reinforcement supporting various
throughout most of the 20th century, UK codes values of total (dead + live) load; the results can Construction quality
only required 13mm or 15mm cover and the be presented in a simple table7. An ultra-refined design is worthless if it is not
resulting structures have stood for many Similar tables can be prepared for EC2 and constructed in accordance with the engineer’s
decades without problems. The reason is BS 81108. Adding such a table to EC2 would drawings and specification. Investigations
simple: even if carbonation reaches the steel allow engineers to determine accurate slab following the Grenfell Tower disaster revealed
surface, significant corrosion will not occur if the depths at the start of design, removing the need widespread errors and poor construction,
concrete is kept dry and does not contain for conservative assumptions in scheme indicating inadequate supervision and checking
chlorides. designs. This could lead to significant material of site work. Sadly, this is commonplace, with
Reducing nominal cover in indoor floor slabs savings in practice. adverse effects on strength, durability and
from 25mm to 15mm would reduce slab energy efficiency.
thicknesses by 10mm, typically reducing 5) Concrete columns Many factors have contributed to this,
concrete volume by 5–10% and also reducing Concrete column sizes also usually need to be including cut fees and ‘design only’ contracts
dead load, saving on reinforcement and agreed early in the design process. The EC2 for engineers and architects, as well as Local
foundations. column design method is very complex, so Authority Building Control being under-
(Note that greater cover may be required for again scheme designs are often conservative. resourced and having to compete for work with
higher fire resistance but overspecification Although it is theoretically possible to reduce private approved inspectors. (Current tax
should still be avoided. However, it is important column sizes later, in practice this often does incentives for contractor-led design-and-build
not to skimp on concrete quality or cover for not happen. contracts are also relevant.)
concrete in outdoor or corrosive environments.) A new slender column design method which If we want buildings to last longer and to
gives safe, reasonably accurate results, but is have a lower environmental footprint, current
4) Slab span-to-depth ratios much simpler than Eurocode 2 was recently arrangements for supervision and checking of
Slab thickness affects the volume of concrete presented in Concrete magazine9. (In some site construction need to be radically changed.
and the deadweight of a structure. As it common situations, it is actually more accurate
determines floor zone depth, it must be decided than EC2. It is also simpler and more accurate Existing structures
early in the design process. It is usually than BS 8110.) The number of new buildings constructed each
controlled by span-to-depth ratio to limit Including this method in EC2 would allow year is a very small percentage of the whole
deflection, but unfortunately the EC2 ‘simple’ engineers to determine column sizes more building stock, so most of the buildings which
ratios are crude and conservative and the depth accurately at the start of design, and in most will be present in future already exist. Engineers
required by the ‘accurate’ method can only be structures more complicated analysis would be can make a major contribution to reducing
calculated after reinforcement percentage and unnecessary. It would also enable more energy and material use in construction by
stress are known, i.e. when structural design is accurate initial sizing of column sizes for applying their imagination and skill to help
almost complete. computer analysis and allow simple checking of clients extend the useful lives of existing
Increasing the slab thickness at this stage the results of more complex calculations. structures13–17. (Taxation changes would also
can cause trouble, so engineers commonly help: at present in the UK, VAT applies to work
base their scheme designs on conservative 6) Steel columns to save and reuse an existing building, but
assumptions. In theory, the design should then EC3 includes tables for steel column allowable demolition and reconstruction is tax-free.)
be refined and optimised later, but with limited stress based on slenderness ratio, similar to Training courses for structural engineers
time and fees this often does not happen, so previous codes. However, there is no guidance generally focus on the design of new structures
slabs are commonly thicker than strictly on ‘buckling length’ factors. SCI publication rather than assessing existing structures. There
necessary. P360 gives some limited guidance10. Fuller is more to this than ‘put it into the computer
To solve this problem, engineers need simple, guidance on effective lengths, as in previous UK and see if it complies with the current code’.
35
thestructuralengineer.org | May 2022
Firstly, the construction of the existing structure, codes, making them easier to use, changing
the materials used and their condition must be some detailed requirements and ending
assessed. Then the engineer must try to unnecessary overspecification of materials.
understand the design and work out what the Engineers can also make a difference by
original assumed loadings and allowable designing new buildings to last longer. Changes Alasdair N. Beal
stresses were. (Remember Bob Dylan’s advice: are needed, too, in the way that site construction BSc, CEng, FIStructE, FICE
‘don’t criticise what you can’t understand’.) is supervised and checked, to ensure that Alasdair Beal is a retired civil and structural
This is essential when assessing allowable structures are actually built in accordance with
engineer formerly with Perega Ltd, Leeds, UK
floor loadings, etc., the feasibility of a change of the design drawings and specification.
(previously known as Thomasons Ltd). He has
use and the possible need for strengthening18,19. However, the biggest savings of all in
written technical papers on a variety of
In addition to the information in the BCSA’s materials and carbon footprint may come not
subjects, including limit state design, reinforced
Historical Structural Steelwork Handbook20, from changes to the design rules for new
historical material properties and design buildings, but from engineers using their skills concrete and structural steel design, codes of
stresses for reinforced concrete were and creativity to extend the useful life of existing practice, Eurocodes, engineering history, quality
summarised in Concrete in 199021. A corrected structures. assurance, and health and safety.
and updated summary of these was published
in The Structural Engineer in 201122.
Although engineers in the past did not have REFERENCES
modern computer analysis, they knew more
about the materials in their structures (e.g. the
origin and species of timbers, the source and 1) Hughes A. (2021) ‘Letter to Verulam’, The 13) Fernandez S. (2020) ‘An introduction to
quality of cast iron) than we can establish today. Structural Engineer, 99 (5), p. 42 refurbishment. Part 1: Identifying opportunities
Also, load testing was used more often than at the feasibility stage’, The Structural
2) Beal A.N. (2021) ‘Letter to Verulam’, The
today. Engineer, 98 (11), pp. 14–18
Structural Engineer, 99 (5), pp. 42–43
In Salts Mill in Saltaire, calculated stresses in 14) Tayler H. (2020) ‘A short guide to reusing
the cast iron floor beams were found to be 3) IStructE Safety, Health and Wellbeing
foundations’, The Structural Engineer, 98 (11),
Panel (2021) ‘Structural safety when designing
much higher than usually permitted, but pp. 20–23
lean in the climate emergency’, The Structural
valuable information about its construction was
Engineer, 99 (1), pp. 16–17 15) Fernandez S. (2021) ‘An introduction
found in a book by noted Victorian engineer to refurbishment. Part 2: Maximising the
Fairbairn including the fact that every beam was 4) Chapman T. and Firth I. (2021) ‘Low-carbon
opportunities at the design stage’, The
load tested before installation. outcomes in the built environment’, The
Structural Engineer, 99 (1), pp. 10–14
Structural Engineer, 99 (5), pp. 16–17
On the other hand, the trusses found on site
16) Cobb F. (2021) ‘Understanding existing
were different from the design drawings – and 5) Gholam B. (2020) ‘What do we mean by
buildings – five studies to complete before
badly distorted; they needed to be strengthened efficiency? A holistic approach to reducing
design work starts’, The Structural Engineer,
to prevent failure. ‘Work not carried out in embodied carbon’, The Structural Engineer, 98
99 (3), pp. 10–13
(10), pp. 14–17
accordance with the engineer’s drawings’ is not
17) Pattison J. (2021) ‘Vertical extensions:
a new problem. 6) Hairsine R.C. (2010) ‘Simplified 3D analysis
technical challenges and carbon impact’, The
Sometimes increasing the imposed load on of portal structures – observations, problems
Structural Engineer, 99 (5), pp. 12–15
an existing structure can be justified by careful and solutions’, The Structural Engineer, 88 (3),
pp. 25–33 18) Mathew M. (2021) ‘Analysing existing
analysis and materials testing, and/or reducing
structures: a brief introduction’, The Structural
dead load. If strengthening is needed, this is 7) Institution of Structural Engineers (1991)
Engineer, 99 (6), pp. 14–17
usually by adding columns or beams, but Recommendations for the permissible
sometimes more radical and innovative stress design of reinforced concrete building 19) Foster J. (2021) ‘What can you do if you
solutions are necessary. structures, London: IStructE Ltd are convinced a structure will work but can’t
prove it to code?’, The Structural Engineer, 99
In a Nottingham office block, overstressed 8) Beal A.N. (2009) ‘Eurocode 2: Span/depth
(6), pp. 18–22
high-alumina cement (HAC) roof beams were ratios for RC slabs and beams’, The Structural
strengthened by adding steel beams and Engineer, 87 (20), pp. 35–40 20) Bates W. (1984) Historical Structural
hangers above and applying controlled Steelwork Handbook, London: BCSA
9) Beal A.N. (2019) ‘Concrete column design:
preloading to these to de-stress the HAC simplifying Eurocode 2’, Concrete, May, pp. 21) Steel Reinforcement Commission (1990)
beams23. The same technique was later used in 52–55 ‘UK Reinforcement Standards, 1938–1990’,
combination with dead load reduction in a mill Concrete, 24 (3), pp. 40–41
10) Gardner L. (2011) SCI Publication P360:
at Dean Clough, Halifax to de-stress existing Stability of steel beams and columns, Ascot: 22) Beal A N. (2011) ‘A history of the safety
cast iron beams and allow increased floor Steel Construction Institute, pp. 73–77 factors’, The Structural Engineer, 89 (20), pp.
loading for an office conversion. A leaning 11) British Standard Institution (2000) BS
20–26
masonry viaduct in Adel (Leeds) was stabilised 5950-1:2000 Structural use of steelwork in 23) Beal A.N. (1996) ‘Skyhooks at 18 foot
by post-tensioning steel cables inserted through building, London: BSI (withdrawn), Cl. 4.7.3 centres: strengthening a precast OPC/
the structure24. and Appendix D (Appendix E should only be HAC concrete frame at Hattersley Heaton,
used for rigid-jointed frames) Nottinghamshire’, The Structural Engineer, 74
Conclusions 12) Beal A.N. (2006) ‘Columns, sway frames
(1/2), pp. 6–8
Significant ‘real world’ economies in materials and BS 5950-1:2000’, The Structural Engineer, 24) Beal A.N. (2002) ‘The leaning towers of
and the carbon footprint of new construction 84 (21), pp. 40–42 Adel: stabilising the Seven Arches Aqueduct’,
could be achieved by simplifying over-complex The Structural Engineer, 80 (9), pp. 27–33
36
May 2022 | thestructuralengineer.org
21179_concrete_conference_FP.indd
TSE.May22_037.indd 37 1 19/04/2022
19/04/20224:22 pm
17:02
Opinion Book review
Review
The key value of this book is in reminding readers of the non-technical qualities, such as
cultural sensitivity and communication skills, that seismic safety advocates must embody,
concludes Damian Grant.
Why do buildings THIS BOOK STARTS with the conundrum posed Engineering Research Institute (EERI). This again
collapse in
in its title: given that engineers and seismologists reflects the emphasis of the book on the role of non-
have taken such huge strides over the last five or six engineering stakeholders, and non-technical solutions
CLIMATE PLAYS IN
Database. of engineers’ focus, particularly since the 2011
The book also covers common construction Christchurch earthquake, towards resilience-based
CONSTRUCTION materials and typologies used around the world, and design and a ‘functional recovery’ seismic design
TYPOLOGIES how these different construction types typically fare
in earthquakes. An important lesson – especially for
objective – beyond the typical ‘life safety’ objective
we’ve targeted for four or more decades.
THAT ARE FOUND the reviewer, a smug engineer from temperate New And seismic-resistant technologies that can help us
IN A REGION Zealand – is the role that climate plays in construction
typologies that are found in a region. For example,
achieve these stretch goals, such as base isolation,
supplemental damping devices and unbonded post-
thick mud or stone walls, valuable for their thermal tensioning systems, are also given only a few passing
mass in arid climates, are heavy and brittle – terrible mentions.
properties when considering seismic resistance. That said, there are many books on the market
Of course, unfavourable climate is not the covering these innovative technical solutions to
only feature contributing to building collapses in the earthquake problem. The value of this book is
earthquakes. After extolling the successes of building in reminding us of many other important qualities
code development, particularly over the past half that seismic safety advocates, including engineers,
century, the authors discuss how codes have had must embody: cultural sensitivity, flexibility, empathy,
less success in reducing risk in the developing world. communication skills, persistence and bravery. To this
They cite gaps in the codes themselves, such as end, the nine individuals profiled in the book – and the
not accounting for culturally appropriate and locally two authors – are edifying role models.
available materials, and implementation hurdles, such
as corruption and failure to enforce the codes, as
examples of what has gone wrong.
Another novel feature of this book is the inclusion Damian Grant
of biographical profiles of nine people (seven PhD, CEng
individuals and one couple) who have all made
Damian Grant is an Associate Director at Arup, and
strong contributions to seismic risk reduction in their Seismic Skills Leader for Arup’s UKIMEA region. He
communities. Interestingly, of the nine, only two are co-authored the 4th edition of Earthquake Design
engineers. For what it’s worth, only one (Dr Lucy Practice for Buildings for ICE Publishing, and is
Jones, an eminent California-based seismologist) has current Vice Chair of the Society for Earthquake and
been recognised with awards from the US Earthquake Civil Engineering Dynamics (SECED) committee.
38
May 2022 | thestructuralengineer.org
Comprehensively revised
references, code amendments and
recently published guidance
Visit:
www.istructe.org/shop/manuals
Verulam
Send letters to…
HAVE All contributions to Verulam should be
YOUR submitted via email to: [email protected]
concrete
Peter Debney
40
May 2022 | thestructuralengineer.org
41
thestructuralengineer.org | April
May 2022
I hope the topic will generate much more compatibility wasn’t essential, as it is for an A few years ago he wrote ‘Skeletons:
discussion, benefiting all those that find the elastic theory, as the natural state of A Technical Autobiography Written for
subject of interest. masonry is to be cracked. Instruction and Entertainment’, which was
He first applied this approach to published in the Peterhouse Annual
As Martin points out, designing (in masonry bridges, but was soon asked to Record in 2019, of which he kindly sent
the widest sense) even a trench fill apply it to the more complex structures of me a copy.
foundation is not that straightforward Gothic churches. His work linked modern Jacques Heyman has been a member
and the foundation depth below structural mechanics, which seeks to of the IStructE History Study Group for
ground is a function not just of the predict the distribution of structural forces many years and in 1992 gave the ‘Star’
ground bearing capacity required, but when in equilibrium with the applied loads, (now Sutherland) history lecture on ‘Rib
a depth to assure long-term moisture back to medieval ‘tacit’ understanding, vaults and flying buttresses – the structure
stability. While discussion is based on the masons’ experience of of Gothic’.
welcome, undoubtedly Will was just weight, their observation of the movement Knowing that many engineers, and not
trying to point out that if you have of temporary supports and sense of just members of the Group, would be
confidence in the ground capability correct proportion: his work has interested to read his autobiographical
(via a site investigation) you may well reconnected these two long-separate ways essay, Rob Thomas, the Institution’s
be able to save a good amount of of thinking, greatly broadening our Librarian, and I have been working with
carbon. understanding. Prof. Heyman and Dr Pattenden, the
I do not think it any exaggeration to say Editor of the Peterhouse Record, to
that his work in this field, largely single- publish the autobiography on the
Jacques
handed at first, has transformed how not Institution’s website, as we wish this
just engineers, but many others, picture the essay to be available to the many
Heyman and
structural action of historic masonry. He engineers and others who have
has advised on the structure of many appreciated and benefited from his
plastic theory
historic masonry buildings – cathedrals and teaching, research and practice.
churches in particular. To it, we have appended as full a list of
His work has inspired a younger Prof. Heyman’s publications as we could
ANDREW SMITH generation of engineers, both practising assemble. Together, the article and the
Professor Jacques Heyman’s teaching, and academic, and led to novel structural publications list are a vivid testament to
research and practice will be known to forms which use modern materials and his work and its substantial and
many members. Jacques was one of the construction techniques designed using continuing influence on the thinking and
people who recognised the limitations of developments of his thinking about imagination of engineers and the
the elastic theory of structural mechanics plasticity, equilibrium, shells and lines of structures to which we contribute.
and developed the plastic theory to better thrust. The article is available at www.istructe.
predict the failure of structures. Stimulated by his work on historic org/get-involved/study-groups/
His early work applied plastic theory to masonry, Jacques has also researched the history-of-structural-engineering/.
the prediction of the strength of steel development of engineering understanding
structures and that work has changed how and design over time. He has published a Professor Heyman was indeed an
we picture their behaviour and assess their great many papers and a number of original thinker, and it pays to reflect
strength and stability. books, many of lasting influence, in each of on the principles he espoused.
He then perceived that plastic theory these fields. Nowadays, when using
could be applied to masonry structures, For a very long time, though earlier on computerised stress analysis, we
recognised that the central problem was interspersed with periods spent elsewhere, seem to have sort of defaulted back
usually the stability of their equilibrium, Prof. Heyman worked in the Engineering to elastic theory and equate big
rather than their strength, which was the Department of Cambridge University, of elastic stress to ‘failure’. As Andrew
focus of most approaches and of all codes which he was the Head of Department records, rather it pays to truly
of practice, and opened up an entirely new from 1983 until his ‘retirement’ in 1992, understand how real structures
way of assessing that stability. and for much of that time he has been a behave, taking account of ‘plasticity,
He also recognised that maintaining Fellow of Peterhouse, Cambridge. equilibrium and lines of thrust’.
42
May 2022 | thestructuralengineer.org
Diary dates
charge to attend. Registration
is not typically required.
Meetings may be online or in
person.
For Regional Group events,
check the website for the
latest information. Note that more current information may be available from
the Institution website: www.istructe.org/events
CONFERENCE LECTURE
5–7 July 18 May SPONSORED WEBINARS
Using concrete in a changing environment Christchurch Town Hall: repairing and
conference strengthening an iconic heritage space 12 May
13:30–16:30 Presenter: Mark Browne How to reliably protect buildings
Day 1: Concrete construction solutions 18:00–19:15 from vibrations with Getzner
Day 2: Reusing concrete buildings Price: Free Speakers: Ben van Breda and Dr Ulrich
Day 3: Material efficiency and novel materials Register: www.istructe.org/events/hq/ Gerhaher
Price (early booking): Members: £155 + VAT; christchurch-town-hall-repairing-and- 09:00–10:00
Standard: £245 + VAT; Student: £45 + VAT strengthening/ Price: Free
Booking: www.istructe.org/events/hq/using- Register: www.istructe.org/events/
concrete-conference HISTORY STUDY GROUP hq/2022/how-to-reliably-protect-
16 May buildings-from-vibrations/
WORKSHOPS A window on Soviet era timber engineering
19 May – wooden structures and the Derevyagin 24 May
Digital design & computation workshop beam Structural design and analysis:
10:00–17:30 Paul Bell tackling workflow and complexities
Price: Members: £175.00 + VAT; Standard: – with SCIA
£275.00 + VAT; Student: £175.00 + VAT 14 June Presenters: Christopher Daly and Keith
Booking: www.istructe.org/events/hq/digital- Dee Bridge collapse of 1847 Wan
design-computation-workshops/ Alan Hayward 10:00–11:45
Price: Free
1 June CPD COURSES Register: www.istructe.org/events/
Design of steel and composite buildings Tuesdays, 3–24 May hq/2022/structural-design-and-analysis-
against progressive collapse Conceptual design for structural engineers: tackling-workflow-a/
Presenters: Prof. Jean-François Demonceau, an introduction
Prof. Florea Dinu, Prof. Ahmed Elghazouli, Eng. Presenter: Oliver Broadbent 21 June
Zeyad Khalil and Prof. David Nethercot Price: Members: £295 + VAT; Standard: £395 + The significance of Structural
IStructE HQ VAT Thermal Breaks in high rise
11:30–17:30 Booking: www.istructe.org/events/hq/2022/ fire design and building energy
Price: Free conceptual-design-introduction-may/ performance
Register: www.istructe.org/events/hq/2022/ Presenter: Chris Lister
design-of-steel-and-composite-buildings- 4–5 May Price: Free
against-pr/ Moving into engineering management Booking: www.istructe.org/events/
Presenter: Penny Taylor hq/2022/farrat-sponsored-webinar-21-
10:00–17:30 june-2022/
Price: Members: £625 + VAT; Standard: £835 +
SPONSORED COURSE VAT
Booking: www.istructe.org/events/hq/2022/
25 May moving-into-engineering-management/
Rothoschool on tour 18 May
Presenters: Kelly Harrison and Joachim Wednesdays, 4–25 May Component-based finite element method
Schmid Drawing gym for engineers (CBFEM) for steel connections & members
IStructE HQ Presenter: Trevor Flynn Presenter: Costis Hatzopoulos
09:00–18:00 10:00–12:00 12:00–16:00
Price: £150 + VAT Price: Members: £295 + VAT; Standard: £395 + Price: Free
Booking: www.istructe.org/events/ VAT Register: www.istructe.org/events/hq/2022/
hq/2022/rothoblaas-industry-briefing/ Booking: www.istructe.org/events/hq/2022/ component-based-finite-element-method-
drawing-gym-for-engineers/ (cbfem)/
43
thestructuralengineer.org | May 2022
44
May 2022 | thestructuralengineer.org
–––
With this course, you will learn to:
� Plan your own preparation for the exam
� Recognise what is required to pass each module
� Create viable solutions to exam questions
� Use conceptual tools to develop answers
� Identify any gaps in your preparation Buy now for
12 months access
www.istructe.org/onlineexamprep
Professional Review
Interview on-demand
preparation course
New practical online course to help you
maximise your interview preparation, build
your portfolio and increase your chances of
success in an accessible and flexible way.
Price: £295 + VAT
–––
With this course, you will learn to:
� Develop your portfolio
� Understand how to prepare for the interview
� Learn valuable interview techniques and advice
� Grow your confidence for interview
� Identify any gaps in your preparation
Buy now for
12 months access
www.istructe.info/PRI-course
Editor’s Featured Machine learning (ML) has become ambitious and comprehensive review
the most successful branch of on the growing applications of ML
Article artificial intelligence (AI). It provides a algorithms for structural engineering. An
Machine learning for structural unique opportunity to make structural overview of ML techniques for structural
engineering: A state-of-the-art engineering more predictable due engineering is presented with a
review to its ability in handling complex particular focus on basic ML concepts,
Huu-Tai Thai nonlinear structural systems under ML libraries, open-source Python codes,
Department of Infrastructure extreme actions. Currently, there is a and structural engineering datasets.
Engineering, The University of boom in implementing ML in structural The review covers a wide range of
Melbourne, Australia engineering, especially over the last structural engineering applications of
five years thanks to recent advances ML including: (1) structural analysis and
in ML techniques and computational design, (2) structural health monitoring
capabilities as well as the availability of and damage detection, (3) fire resistance
large datasets. This paper provides an of structures; (4) resistance of structural
members under various
actions, and (5) mechanical
properties and mix design
of concrete. Both isolated
members and whole systems
made from steel, concrete
and composite materials are
explored. Findings from the
reviewed literature, challenges
and future commendations
are highlighted and discussed.
With available databases
and ML codes provided, this
review paper serves as a
useful reference for structural
engineering practitioners
and researchers who are not
familiar with ML but wish to
enter this field of research.
46
May 2022 | thestructuralengineer.org
47
thestructuralengineer.org | May 2022
48
May 2022 | thestructuralengineer.org
QUIKFRAME
STRAP software for analysis and
design of cold formed, concrete, steel
and pre & post-tensioned structures.
THE FASTEST, EASIEST
Fine GEO5 geotechincal software for
soil structure interaction, slope stability,
2D ANALYSIS PROGRAM
earth pressure, sheeting & pile design.
STRUCTURAL DESIGN & CAD DRAWING STRUCTURAL DESIGN & CAD DRAWING
Au t o CAD D r a u g h t i n g S e r v i c e s
Established in 1988, we are a team of
professional technicians with ofces in
Weston super Mare, providing an efcient
on-demand service for our clients
- RC Detailing Specialists -
- Structural Drawing GAʼs & Details -
- Bespoke Drawings for all Applications -
49
thestructuralengineer.org | May 2022
Kier
Professional
Services
are Kier’s in-house team of consulting engineers,
providing permanent and temporary designs and
technical advice to Kier’s Construction, Highways
Infrastructure, Property and Utilities businesses.
50
May 2022 | thestructuralengineer.org
Jobs
Attract the right candidate for less -
Advertise for just £379
Only The Institution of Structural Engineers can provide such a dedicated and receptive audience, whose
experience and creative abilities are sufficiently diverse to fill any vacancy, regardless of seniority.
Our five options offer various levels of targeting and visibility. These include:
£379 £879
DIGITAL DIGITAL & PRINT
Job board ad live for 1 month, Job board ad live for up to 3 months,
with logo with logo
Featured in top section of search
results
“
We managed to fill all the posts we advertised with
the IStructE, and wish to thank you for the support
and advice you provided during the process. I was
really pleased with the spread and quality of
responses we received — and have even managed to
”
find a suitable candidate for a European office as
well as filling the UK roles.
51
thestructuralengineer.org | May 2022