0% found this document useful (0 votes)
60 views1 page

Suspension of Work at Site Request

This document is a request for the suspension of work at a construction site. It requires information such as the plot number, permit number, consultant, and contractor. The requester must provide the reason for suspension and submit supporting documents, including a letter from the consultant explaining the site status and suspension procedure, and an undertaking letter from the owner. The requester and various stakeholders like the owner, consultant, and master developer must provide their contact details and signatures to authorize the suspension request.

Uploaded by

vijay
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
60 views1 page

Suspension of Work at Site Request

This document is a request for the suspension of work at a construction site. It requires information such as the plot number, permit number, consultant, and contractor. The requester must provide the reason for suspension and submit supporting documents, including a letter from the consultant explaining the site status and suspension procedure, and an undertaking letter from the owner. The requester and various stakeholders like the owner, consultant, and master developer must provide their contact details and signatures to authorize the suspension request.

Uploaded by

vijay
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

SUSPENSION OF WORK AT SITE REQUEST

Plot Number Permit Number


Consultant
Contractor

Reason for Suspension of


Work at Site

Submission Details Initial Submission


(Tick Appropriate Box) Re-submission

DOCUMENTS REQUIRED

1. Letter from Consultant explaining the status at site and the method/procedure of implementing the suspension
2. Undertaking Letter from owner (Template No. ZA-DC-F-66)

Terms and Conditions


• I hereby certify that the information, data and documents provided with this application are true, genuine and correct to the best
of my knowledge. In case of default/failure to comply with any of the aforesaid conditions or the documents submitted by us is
found false/forged, our application will be rejected forfeiting any applicable fees paid.
• I hereby undertake the full liability for the suspended construction works at the site including HSE measures.

REQUESTER DETAILS

Contractor Consultant

Contact Person Contact Person

Contact No. Contact No.

Date Date

Signature & Signature &


Stamp Stamp

Owner Master Developer (if applicable)

Contact Person Contact Person

Contact No. Contact No.

Date Date

Signature & Signature &


Stamp Stamp

PO Box 478844, Dubai, UAE


T +971 800-4-DDA (332)
F +971 4 427 2449
ZA-DC-F-65 Issue 6, Rev 1, Dated: 20.21.2018 dda.gov.ae