0% found this document useful (0 votes)
70 views3 pages

2012 Exam

1. A testing system was used to determine friction loss coefficients for tendons in straight and curved concrete elements. The loads measured at load cells were 95.7% and 89.9% of jacking loads, respectively. The values of friction coefficient μ and its rate of change k need to be determined. 2. A 3m prestressed concrete member subjected to axial tension is given. The new length needs to be evaluated assuming negligible crack width and given material properties and stresses. 3. Stresses in a pretensioned box girder carrying steam pipes need to be estimated at midspan on a cold winter day, given temperatures, material properties, geometry, and self-weight.

Uploaded by

Jagannathan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
70 views3 pages

2012 Exam

1. A testing system was used to determine friction loss coefficients for tendons in straight and curved concrete elements. The loads measured at load cells were 95.7% and 89.9% of jacking loads, respectively. The values of friction coefficient μ and its rate of change k need to be determined. 2. A 3m prestressed concrete member subjected to axial tension is given. The new length needs to be evaluated assuming negligible crack width and given material properties and stresses. 3. Stresses in a pretensioned box girder carrying steam pipes need to be estimated at midspan on a cold winter day, given temperatures, material properties, geometry, and self-weight.

Uploaded by

Jagannathan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

The University of Western Ontario - Faculty of Engineering

Department of Civil and Environmental Engineering

Final Examination - April 2012

CEE 9628b – Prestressed Concrete Dr. M.A. Youssef, P.Eng. Page 1/3

Problem 1: (9 marks – 15 minutes)


Load
A post-tensioning supplier has developed a Jack
Cell
testing system to determine experimentally the
friction loss coefficients (μ and k) for different 9m
tendon systems. Two concrete elements have

R 23 m
been cast, one being straight and the other
being a circular arc with radius of 23 m, Fig. 1.
The loads measured at the shown load cells
Load
were 95.7% and 89.9% of the jacking loads for Jack
Cell
the straight and circular tendon shapes,
respectively. Determine the values of μ and k. 9m

Fig. 1 Determination of Friction Coefficients

Problem 2: (18 marks – 30 minutes)

A three meter long prestressed concrete member (original length, i.e. when εc=0), Fig. 2, is subjected to
an axial tensile force N. If the stress in the deformed reinforcing bars is equal to 300 MPa at a crack
location, evaluate the new length of the member assuming that width of cracks is almost zero. Given:
* Δεp = 0.006, fc’ = 30 MPa, fcr = 2 MPa, fsy = 400 MPa, fspy = 1600 MPa, Es = Ep = 200,000 MPa
* For concrete in tension, you have to consider tension stiffening.
* For steel bars and prestressing strands, assume a bilinear stress-strain relationship (f = fy for ε ≥ εy).
.

50 mm (typ.)

2 No. 15M bars


300 mm

2-15 mm seven wire


150 mm

strands

2 No. 15M bars

100 100
300 mm

Figure 2 Prestress Concrete Member


The University of Western Ontario - Faculty of Engineering
Department of Civil and Environmental Engineering

Final Examination - April 2012

CEE 9628b – Prestressed Concrete Dr. M.A. Youssef, P.Eng. Page 2/3

50 mm
150 mm
Problem 3: (30 marks – 50 minutes)

The pretensioned box girder, Fig. 3, is simply 2-13 mm Seven Wire


supported with a span of 20 m. It is used to carry the Strands
steam pipes shown. Assuming uncracked elastic
response, estimate the concrete stresses at midspan on

900 mm
a cold winter day. Steam
Pipes

150 mm

50 mm
Given:
* Δεp = 0.0065, w = 10 kN/m,
* Temperature at casting = 20 oC, 6-13 mm Seven Wire
Strands
* Ec eff =10,000 MPa, Ep eff = 194000 MPa
* εsh = -0.4×10-3, αc=αp= 10×10-6 / oC 150 mm 150 mm
* Temperature of shaded area = +30 oC 600 mm
* Temperature of remaining areas = -20 oC
Figure 3 Pretensioned Box Girder

Problem 4: (27 marks – 45 minutes) P


Horizontally e
A prestressed concrete column, Figure 4, contains four size 15 seven wire Restrained

strands that were pretensioned to 1350 MPa. After the column was loaded with
an axial compression P at end eccentricities e, the concrete strains were
measured at points A and B and found equal to -3.16×10-3 and +0.5×10-3,
respectively. Given that fc’=65 MPa, εo=-0.002 and fpy=0.85fpu, estimate the axial
load P and the end eccentricity e.
Stress

B A
4m

fpu
f 40 mm (typ.)
py
2m
240 mm

Ep
Strain
Horizontally
0.05 Restrained
e
240 mm P

Figure 4 Eccentrically Loaded Column


The University of Western Ontario - Faculty of Engineering
Department of Civil and Environmental Engineering

Final Examination - April 2012

CEE 9628b – Prestressed Concrete Dr. M.A. Youssef, P.Eng. Page 3/3

Problem 5: (24 marks – 40 minutes)

The prestressed concrete beam, shown in Fig. 5, is fixed at the left end and roller-supported at the right.
It is post-tensioned with a single tendon with a parabolic profile.
(1) Calculate the primary, secondary, and total moments due to prestressing.
(2) What minor adjustment could be made in the tendon profile to produce a concordant tendon?
250 mm

600 mm
300 mm
150 mm

6000 mm 6000 mm

Fig. 5 Prestressed Concrete Beam

You might also like