Gantt Chart

The document outlines a project timeline with phases for planning, analysis, design, implementation, and system/security support. It includes dates for activities like forming project teams, defining requirements, designing systems, writing code, and documentation. Key deliverables are scheduled such as submitting reports on start and project definition, requirements, design, testing, and the final project report.

Uploaded by

Ahmad Daniel
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
51 views2 pages

Gantt Chart

The document outlines a project timeline with phases for planning, analysis, design, implementation, and system/security support. It includes dates for activities like forming project teams, defining requirements, designing systems, writing code, and documentation. Key deliverables are scheduled such as submitting reports on start and project definition, requirements, design, testing, and the final project report.

Uploaded by

Ahmad Daniel
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 2

Start

Planning Phase 3/27/2023


Formulation Organisation 29-Mar
Analyze Organisation And Current System 31-Mar
Define Proposed System Process 3-Apr
Define roles for group member 7-Apr
Create schedule for plan 11-Apr
Documentation 14-Apr
Submit Report SDP 17-Apr

Analysis phase 19-Apr


Define Product Perspective and Function 20-Apr
Research on User Characteristic 22-Apr
Identify on their Operating Enviroment 22-Apr
Define General Constraint 22-Apr
Research External Interface Requirements 29-Apr
Plan The Interface For The System 1-May
Research Functional Requirements 4-May
Research Other Nonfunctional Requirement 4-May
Plan the Requirements 4-May
Documentation 7-May
Submit Report SRS 8-May

Design Phase 10-May


Define The Purpose And Scope 11-May
Develop the Diagram 15-May
Develop Database Design 19-May
Develop ERD and Data Dictionary 27-May
Documentation 9-Jun
Submit SDD 12-Jun

Implementation Phase 13-Jun


Do the Document Purpose 13-Jun
Write Server Coding 15-Jun
Write System Coding 22-Jun
Write Interface Coding 1-Jul
Documentation 9-Jul
Submit STD 10-Jul

System And Security Support Phase 1-Jul


Write User manual 1-Jul
Write Admin manual 3-Jul
System Presentation 10-Jul
Submit Final Report 10-Jul
END
17-Apr
31-Mar
2-Apr
6-Apr
10-Apr
15-Apr
16-Apr
17-Apr

8-May
21-Apr
27-Apr
27-Apr
27-Apr
30-Apr
3-May
6-May
6-May
6-May
8-May
8-May

12-Jun
14-May
18-May
26-May
8-Jun
11-Jun
12-Jun

10-Jul
14-Jun
21-Jun
30-Jun
8-Jul
10-Jul
10-Jul

10-Jul
3-Jul
7-Jul
10-Jul
10-Jul