LAND
Consistency with land Current land use w/in 1km radius See attached proof of compatibility
use (as per zoning ordinance): with land use
Residential Limit project activities to what is
Commercial/ Institutional compatible to the land use
Industrial
Others, specify
Agricultural/ Recreational
Protected Areas
Others, specify
Land tenure / Identify Land tenure / compatibility Obtain appropriate clearances/ Regularly monitor
compatibility issue issues: permits from concerned agencies presence/absence of
CARP Provide relocation/disturbance
complaints
Disturbance to wildlife Existing vegetation in the area: Comply with conditions of DENR/LGU Annual inspection of area
due to vegetation Forestland SLUP, Tree Cutting Permit, ROW, replanted/re-vegetated
clearing
PCA Permit Others, specify
Pest/disease infestation
Marshland Limit land clearing as much as
Grassland possible
Mangrove Provide temporary fencing for
Wetland vegetation that will be retained
Others, specify
Employ Integrated Pest Management
System
Promote restoration of damaged or
destroyed vegetation where possible
(e.g., tree planting)
WATER
Increased siltation due Specify nearest/receiving water Set-up proper and adequate sanitary Regular (ocular) inspection of:
to project activities body: facilities Drainage / canal systems
Water quality Strictly require the contractor and its Water treatment facility (i.e.,
degradation workers to observe proper waste grease trap, septic tank,
Others, specify
disposal and proper sanitation etc.)
Strictly observe proper waste handling Regular monitoring of the following:
Parameter
and disposal Frequency
Distance to nearest/receiving Provide wastewater treatment facility pH Annual
water body: (e.g., septic tank, oil and water Semi-annual
0 to less than 0.5 km separator, etc.) Quarterly
0.5 to 1 km Provide biogas generator or similar Monthly
More than 1 km
waste treatment measures
TSS Annual
Set up silt trap/settling ponds to concentratio
Semi-annual
Classification of nearest water minimize downstream siltation n
body: Others, specify Quarterly
Freshwater Marine/ coastal Monthly
water BOD Annual
AA SA Semi-annual
A SB
Quarterly
Monthly
B SC
Color Annual
C SD Semi-annual
D Quarterly
Monthly
Project Name: ____________________________________________________
Page 4 of 8
Initial Environmental Examination (IEE) Checklist Report Form for Livestock / Poultry Projects
Deep well
Water district/LGU
Surface water
Others, specify
AIR / NOISE
Nuisance due to Distance to nearest community: Properly operate and maintain all Regular monitoring for
generation of 0 to less than 0.5 km emission sources (e.g. vehicles, presence/absence of
obnoxious/unpleasant 0.5 to 1 km generator, etc) complaints
odor
More than 1 km Strictly enforce good housekeeping
Regular (ocular) inspection of:
Air quality degradation practices Absence of white or black
Nuisance due to noise Is the wind direction blowing Control vehicle speed to lessen
smoke from vehicles,
generator, etc.
generation suspension of road dust
Project Name: ____________________________________________________
Page 6 of 8
Initial Environmental Examination (IEE) Checklist Report Form for Livestock / Poultry Projects
PEOPLE
Reduced employment
Conduct prior consultation and
coordination to minimize disruption of
and/or livelihood
daily domestic activities and to ensure
opportunities
respect for IP rights and cultural
Increased revenues for practices