BQ With Priced (Water Tank)
BQ With Priced (Water Tank)
BQ With Priced (Water Tank)
PILING WORKS
GENERALLY
The rates set down by the Contractor against each item in the
Provisional Bills of Quantities, after adjustment if necessary by
the S.O. to his reasonableness, shall become the basis of
valuation for interim payments and variation works.
The Contractor shall also note that the prices inserted against
the items for provision, mobilisation and de-mobilisation of all
necessary equipment, plant, tools and ancillaries are on lump
sum basis and are not adjustable whatsoever.
The payable length for driving shall be measured from the toe
of pile to the commencing surface of driving.
TO COLLECTION -
PW/2/1
BILL NO. 2 - PILING WORKS (ALL PROVISIONAL)
Item Description Unit Qty Rate (RM) Amount (RM)
PILING WORKS….Cont'd
GENERALLY….Cont'd
A Allow for the provision of all temporary works including ITEM 2,000.00 2,000.00
staging etc. for piles to be installed on slopes, edges of
building platforms and the like.
B Allow for the protection, maintenance and removal of all ITEM 2,000.00 2,000.00
existing services, pipes, chutes, sewers, manholes, mains,
underground and overhead cables, street lights etc. during the
execution of the Works.
C Allow for provision of all necessary piling equipment, plant, ITEM 15,000.00 15,000.00
cranes, tools and ancillary equipment and for their
transportation to site, at various formation levels, handling,
assembling, erecting, dismantling and removal on completion
of piling works.
D Allow for moving and handling piling equipment, plant, cranes, ITEM 7,000.00 7,000.00
tools and ancillary equipment about the site as often and
whenever necessary for the execution of the whole piling
operation etc. including all idling time and any excavation and
earthwork support for the movement of the piling frames plant,
equipment and tools and any necessary filling in and
compaction including the provision of any hardstanding and
platform and staging required for moving the piling equipment,
plant, cranes, tools and ancillary equipment from differing
levels of the site.
PILING RECORDS
E Allow for the submission of piling results as described duly ITEM 2,000.00 2,000.00
signed by the Contractor and S.O.'s representatives and
delivering same to the S.O. as work proceeds. The Contractor
should submit one set of as-built tracings on polyester film on
piling completion including of as built works on autocad
diskette when directed by the S.O.
F Allow for the submission of piling setting out drawings as ITEM 4,500.00 4,500.00
described duly signed by licensed surveyor before proceeding
with other works.
Soil Investigation
G To carried out mackintosh probe on site all as per Engineer NO 5 3,000.00 15,000.00
approval and instructions.
PW/2/2
BILL NO. 2 - PILING WORKS (ALL PROVISIONAL)
Item Description Unit Qty Rate (RM) Amount (RM)
TO COLLECTION 47,500.00
PILING WORKS….Cont'd
PDA TEST
A Provide Pile Driving Analysis (PDA) integrity test using sonic NO 4 950.00 3,800.00
logging method and providing all necessary materials,
equipments, labour, records and submission of records.
Provide all equipment, kentledge, etc. And test all intial test
pile up to twice working load as required before commencing
the piling works and subsequent removal from site all
materials, equipment and knowledge and reinstate all
temporary excavation necessary for the execution and
complete of the loading
B Static maintain load test on 300mm x 300mm pile working NO 2 10,000.00 20,000.00
load test as approved by engineer
PW/2/3
BILL NO. 2 - PILING WORKS (ALL PROVISIONAL)
Item Description Unit Qty Rate (RM) Amount (RM)
TO COLLECTION 216,200.00
PILING WORKS….Cont'd
B Prepare surfaces of 300mm x 300mm precast concrete pile NO 110 5.00 550.00
head as required to receice pile cap.
TO COLLECTION 2,750.00
COLLECTION
PW/2/4
BILL NO. 2 - PILING WORKS (ALL PROVISIONAL)
Item Description Unit Qty Rate (RM) Amount (RM)
TOTAL CARRIED TO SUMMARY OF TENDER 266,450.00
PW/2/5
BILL NO. 3 - ELEVATED WATER TANK (ALL PROVISIONAL)
Item Description Unit Qty Rate (RM)
SUBSTRUCTURE
EXCAVATION WORK
CONCRETE WORK
H Pilecap M3 60 310.00
EWT/3/1/6
BILL NO. 3 - ELEVATED WATER TANK (ALL PROVISIONAL)
Item Description Unit Qty Rate (RM)
TO COLLECTION
CONCRETE WORK...(CONT'D)
In ground beam
In pilecap
In ground beam
In ground slab
EWT/3/1/7
BILL NO. 3 - ELEVATED WATER TANK (ALL PROVISIONAL)
Item Description Unit Qty Rate (RM)
TO COLLECTION
ANTI-TERMITE TREATMENT
A ITEM 1,000.00
The Contractor and specialist firm shall guarantee the
effectiveness of anti-termite treatment for a period of five (5)
years and undertake to carry re-treatment without charge
should infestation of sub-terranean termites occur at any time
during the warranty period.
TO COLLECTION
COLLECTION
EWT/3/1/8
BILL NO. 3 - ELEVATED WATER TANK (ALL PROVISIONAL)
Item Description Unit Qty Rate (RM)
EWT/3/1/9
R TANK (ALL PROVISIONAL)
Amount (RM)
1,020.00
100.00
2,410.00
3,492.00
747.00
882.00
2,619.00
18,600.00
4,650.00
18,290.00
13,640.00
EWT/3/1/10
R TANK (ALL PROVISIONAL)
Amount (RM)
66,450.00
4,900.00
4,095.00
16,660.00
1,504.80
5,293.40
1,580.80
771.40
31,125.80
5,802.60
6,691.80
2,614.40
5,403.60
6,125.60
8,702.00
1,309.50
EWT/3/1/11
R TANK (ALL PROVISIONAL)
Amount (RM)
102,580.70
1,000.00
290.50
343.00
1,018.50
2,652.00
66,450.00
102,580.70
2,652.00
EWT/3/1/12
R TANK (ALL PROVISIONAL)
Amount (RM)
171,682.70
EWT/3/1/13
BILL NO. 3 - ELEVATED WATER TANK (ALL PROVISIONAL)
Item Description Unit Qty Rate (RM)
FRAME
A Column M3 54 310.00
Column
Suspended beam
Column
EWT/3/2/14
BILL NO. 3 - ELEVATED WATER TANK (ALL PROVISIONAL)
Item Description Unit Qty Rate (RM)
TO COLLECTION
FRAME.... Cont'd
Suspended beam
Wall Tank
TO COLLECTION
COLLECTION
EWT/3/2/15
BILL NO. 3 - ELEVATED WATER TANK (ALL PROVISIONAL)
Item Description Unit Qty Rate (RM)
EWT/3/2/16
R TANK (ALL PROVISIONAL)
Amount (RM)
16,740.00
34,720.00
27,900.00
10,150.00
10,220.00
23,485.00
6,370.00
25,200.00
5,810.20
22,594.80
136.80
22,610.00
EWT/3/2/17
R TANK (ALL PROVISIONAL)
Amount (RM)
205,936.80
7,170.60
11,073.20
4,016.60
5,407.40
25,273.80
18,270.40
10,138.40
81,350.40
205,936.80
81,350.40
EWT/3/2/18
R TANK (ALL PROVISIONAL)
Amount (RM)
287,287.20
EWT/3/2/19
BILL NO. 3 - ELEVATED WATER TANK (ALL PROVISIONAL)
Item Description Unit Qty Rate (RM)
UPPER FLOOR
Suspended slab
EWT/3/3/20
BILL NO. 3 - ELEVATED WATER TANK (ALL PROVISIONAL)
Item Description Unit Qty Rate (RM)
TOTAL CARRIED TO SUMMARY
EWT/3/3/21
R TANK (ALL PROVISIONAL)
Amount (RM)
57,660.00
21,595.00
20,246.40
EWT/3/3/22
R TANK (ALL PROVISIONAL)
Amount (RM)
99,501.40
EWT/3/3/23
BILL NO. 3 - ELEVATED WATER TANK (ALL PROVISIONAL)
Rate Amount
Item Description Unit Qty
(RM) (RM)
ROOF
In roof slab
In roof beam
TO COLLECTION 79,550.40
EWT/3/4/24
BILL NO. 3 - ELEVATED WATER TANK (ALL PROVISIONAL)
Rate Amount
Item Description Unit Qty
(RM) (RM)
In roof beam
-----------------------------
TO COLLECTION 14,831.00
COLLECTION
EWT/3/4/26
BILL NO. 3 - ELEVATED WATER TANK (ALL PROVISIONAL)
Item Description Unit Qty Rate (RM)
Risers; undercut
EWT/3/5/27
BILL NO. 3 - ELEVATED WATER TANK (ALL PROVISIONAL)
Item Description Unit Qty Rate (RM)
TOTAL CARRIED TO SUMMARY
EWT/3/5/28
R TANK (ALL PROVISIONAL)
Amount (RM)
930.00
620.00
364.00
595.00
420.00
330.75
657.40
437.00
156.00
93.60
72.00
1,050.00
595.00
330.75
735.00
EWT/3/5/29
R TANK (ALL PROVISIONAL)
Amount (RM)
7,386.50
EWT/3/5/30
BILL NO. 3 - ELEVATED WATER TANK (ALL PROVISIONAL)
Rate Amount
Item Description Unit Qty
(RM) (RM)
WALL FINISHES
EXTERNAL
INTERNAL
Construction Joints
J Construction joint size 38m x 25m x 200mm for elevated M 102 30.00 3,060.00
water tank wall including 25mm x 25mm plastic joint with
approved polysulphate sealant or equivalent as per S.O
approval.
Water Stop
EWT/3/6/31
BILL NO. 3 - ELEVATED WATER TANK (ALL PROVISIONAL)
Rate Amount
Item Description Unit Qty
TOTAL CARRIED TO SUMMARY (RM) (RM)
EWT/3/6/32
BILL NO. 3 - ELEVATED WATER TANK (ALL PROVISIONAL)
Rate Amount
Item Description Unit Qty
(RM) (RM)
FLOOR FINISHES
EXTERNAL
INTERNAL
Water Stop
Construction Joints
E Construction joint size 38m x 25m x 200mm for elevated M 102 30.00 3,060.00
water tank wall including 25mm x 25mm plastic joint with
approved polysulphate sealant or equivalent as per S.O
approval.
EWT/3/7/34
BILL NO. 3 - ELEVATED WATER TANK (ALL PROVISIONAL)
Rate Amount
Item Description Unit Qty
(RM) (RM)
SUNDRIES
Railings
Cat Ladder
Netlon CE 161
----------------------------
E Supply and install complete approved lightning protection as ITEM 3,000.00 3,000.00
per Engineer detail drawing.
EWT/3/8/36
BILL NO. 3 - ELEVATED WATER TANK (ALL PROVISIONAL)
Rate
Item Description Unit Qty
(RM)
ELEMENT 13 - SUNDRIES
Cat Ladder
Water Stop
Construction Joints
Inlet Pipe
Excavation not exceeding 2.0m deep and get out, part return,
fill in and ram and remove surplus excavated material to
Contractor's own dump site for :-
PP/6/13/37
BILL NO. 3 - ELEVATED WATER TANK (ALL PROVISIONAL)
Rate
Item Description Unit Qty
(RM)
TO COLLECTION
PP/6/13/38
ANK (ALL PROVISIONAL)
Amount
(RM)
PP/6/13/39
ANK (ALL PROVISIONAL)
Amount
(RM)
-
PP/6/13/40
BILL NO. 3 - ELEVATED WATER TANK (ALL PROVISIONAL)
SUMMARY
SUM/EWT-3/41
BILL NO. 4 - EXTERNAL WORKS (ALL PROVISONAL)
SITE CLEARANCE
A Clear the areas of the site affected by the proposed works of M2 3,100 2.00 6,200.00
all grass, weeds, shrubs, bushes including grubbing up roots,
etc., filling cavities with surplus excavated material and
ramming and removing all debris off the site, construct all
temporary works such as cut off drains, earth drain, dykes and
all other precautionary measure, etc., incidental or deemed
necessary for the proper execution of the whole contract works
and maintain same and removing on completion as directed by
the S.O. (0.74 acres)
EARTHWORKS
GENERAL
B Provide for all temporary works required for the carrying out of ITEM 1,000.00 1,000.00
the earthworks out such as cut-off drains, earth drains, bunds,
silt trap, dykes, and all other precautionary measures,
dewatering etc and including make good land slips erosions
and subsidences as may be required as directed by the
S.O.incidental or deemed necessary for the proper execution
of the whole contract works and maintain same for the
duration of the contract and removal including making good all
existing works disturbed at the end of the contract period.
D Extra over excavation for cutting through rock at any depth, M3 100 50.00 5,000.00
breaking up and removing off site as described
E Cart away surplus excavated materials to Contractor's own M3 1,700 10.00 17,000.00
dump removing off site as described
TO COLLECTION 44,050.00
EW/4/1/42
BILL NO. 4 - EXTERNAL WORKS (ALL PROVISONAL)
TURFING
A Close turfing to slope surfaces including any necessary M2 450 4.50 2,025.00
pegging as specified
TO COLLECTION 2,025.00
COLLECTION
EW/4/1/43
BILL NO. 4 - EXTERNAL WORKS (ALL PROVISONAL)
EW/4/1/44
2 UNIT KILANG INKUBATOR GMP DI BANDAR TENGGARA
SITE CLEARANCE
EARTHWORKS
GENERAL
B Provide for all temporary works required for the carrying out of ITEM
the earthworks out such as cut-off drains, earth drains, bunds,
dykes, and all other precautionary measures, dewatering etc
and including make good land slips erosions and subsidences
as may be required as directed by the S.O.incidental or
deemed necessary for the proper execution of the whole
contract works and maintain same for the duration of the
contract and removal including making good all existing works
disturbed at the end of the contract period.
TURFING
IW/4/1/45
2 UNIT KILANG INKUBATOR GMP DI BANDAR TENGGARA
IW/4/1/46
BILL NO. 4 - EXTERNAL WORKS (ALL PROVISONAL)
Item Description Unit Qty Rate (RM) Amount (RM)
ROADWORKS
B 50mm (finished) thick bed of sand rolled to required chambers M2 2100 3.00 6,300.00
and gradients to receive base course
Crusher run base in two layers, each layers 150mm thick laid
to required falls and cambers, blinded by quarry waste laterite
or dust, well rolled with a power roller and compacted as
specified
Supply and spray tack coats uniformly over the full prepared
surfaces at the rate of not less than 0.326 ( litre/m2) as
specified
EW/4/2/47
BILL NO. 4 - EXTERNAL WORKS (ALL PROVISONAL)
Item Description Unit Qty Rate (RM) Amount (RM)
TO COLLECTION 127,050.00
KERB
A Supply and lay precast concrete kerb overall size 150mm x M 220 25.00 5,500.00
300mm high all cast in 600mm length as shown on drawing
including all necessary round, corner, angle, junction, bedding,
excavation, backfilling, cement mortar joint, etc. and concrete
bedding to kerb overall size 375mm wide x 100mm thick
including haunhing back of kerb similiar concrete with 150mm
wide x 150mm high to receive kerb including all necessary
formwork, reinforcement, excavation, backfiling, remove
surplus excavated material to contractor's own dump.
D Construct 150mm diameter PVC scupper holes with concrete NO 40 45.00 1,800.00
surround 310mm x 310mm high discharge drain at 6000mm
centres along road side table complete with all necessary
excavation, backfilling pipeworks and connections to kerbs
and drains average 2000mm long.
G EXTRA OVER for outlet opening size 300mm x 100mm high NO 40 15.00 600.00
overall at 6.00m centre.
TO COLLECTION 8,950.00
COLLECTION
EW/4/2/48
BILL NO. 4 - EXTERNAL WORKS (ALL PROVISONAL)
Item Description Unit Qty Rate (RM) Amount (RM)
TO COLLECTION 136,000.00
EW/4/2/49
BILL NO. 4 - EXTERNAL WORKS (ALL PROVISONAL)
Item Description Unit Qty Rate (RM) Amount (RM)
E Block drain, cast in 300mm wide x 600mm lengths laid to fall M 160 40.00 6,400.00
and grouted in and pointed in cement and sand (1:3) with and
including a layer of BRC No A6 and grouted and pointed in
cement and sand (1:3) including 1500mm high plastered
brickwall with 100mm x 100mm strut and forming all bends,
stopped ends, junctions, weepholes,cascades, etc as
directed
F Block drain, cast in 450mm wide x 600mm lengths laid to fall M 57 45.00 2,565.00
and grouted in and pointed in cement and sand (1:3) with and
including a layer of BRC No A6 and grouted and pointed in
cement and sand (1:3) including 1500mm high plastered
brickwall with 100mm x 100mm strut and forming all bends,
stopped ends, junctions, weepholes,cascades, etc as
directed
BRICK SUMP
EW/4/3/50
BILL NO. 4 - EXTERNAL WORKS (ALL PROVISONAL)
Item Description Unit Qty Rate (RM) Amount (RM)
TO COLLECTION 32,158.00
GRATINGS
--------------------------
D M2 320 -
Supply and constructed of 300mm thick (average) approved
rubble pitching wall complete with 75mm diameter weephole,
50mm thick concrete capping including all neccessary
excavation, lean concrete, hardcore, concrete base, and
reinforcement all as per Engineer detail drawing.
TO COLLECTION 325.00
COLLECTION
EW/4/3/51
BILL NO. 4 - EXTERNAL WORKS (ALL PROVISONAL)
Item Description Unit Qty Rate (RM) Amount (RM)
TO COLLECTION 32,483.00
EW/4/3/52
2 UNIT KILANG INKUBATOR GMP DI BANDAR TENGGARA
Excavation not exceeding 2.0m deep and get out, part return,
fill in and ram and remove surplus excavated material to
Contractor's own dump site for :-
G Supply and install extra 150mm diameter end cap including all NO
necessary fittings.
H Supply and install extra 150mm diameter 'S bend including all NO
necessary fittings.
TO COLLECTION -
IW/4/4/53
2 UNIT KILANG INKUBATOR GMP DI BANDAR TENGGARA
Valve Chamber
A Sluice valve NO
Pipe Marker
Bulk Meter
IW/4/4/54
2 UNIT KILANG INKUBATOR GMP DI BANDAR TENGGARA
TO COLLECTION -
A Allow for testing, cleaning and disinfecting the whole water ITEM
reticulation system to the requirements of the Local Authorities
and make good all defects.
TO COLLECTION -
COLLECTION
IW/4/4/55
2 UNIT KILANG INKUBATOR GMP DI BANDAR TENGGARA
IW/4/4/56
BILL NO. 4 - EXTERNAL WORKS (ALL PROVISONAL)
Main Gate
B Overall size 8000mm x 3000mm high double swing gate NO 1 2,500.00 2,500.00
comprising of 2 nos each size 4000mm x 1800mm high.
EW/4/4/57
BILL NO. 4 - EXTERNAL WORKS (ALL PROVISONAL)
EW/4/4/58
2 UNIT KILANG INKUBATOR GMP DI BANDAR TENGGARA
B 50mm (finished) thick bed of sand rolled to required chambers M2 60 3.00 180.00
and gradients to receive base course
Crusher run metal in two layers, each layers 4.5" thick laid to
required falls and cambers, blinded by quarry waste laterite or
dust, well rolled with a power roller and compacted as
specified
Supply20)and
(ACW apply
premix asphaltic
macadam concrete
well rolled wearing roller
with approved course to
required falls,
IW/4/6/59
2 UNIT KILANG INKUBATOR GMP DI BANDAR TENGGARA
TO COLLECTION 3,936.00
KERB
A Supply and lay precast concrete kerb overall size 150mm x M 135 28.00 3,780.00
300mm high all cast in 600mm length as shown on drawing
including all necessary round, corner, angle, junction, bedding,
excavation, backfilling, cement mortar joint, etc. and concrete
bedding to kerb overall size 375mm wide x 100mm thick
including haunhing back of kerb similiar concrete with 150mm
wide x 150mm high to receive kerb including all necessary
formwork, reinforcement, excavation, backfiling, remove
surplus excavated material to contractor's own.
D Construct 150mm diameter PVC scupper holes with concrete NO 28 30.00 840.00
surround 310mm x 310mm high discharge drain at 6000mm
centres along road side table complete with all necessary
excavation, backfilling pipeworks and connections to kerbs
and drains average 2000mm long
H 150mm wide x 300mm length x 300mm gap give way line M 100 2.50 250.00
marking
IW/4/6/60
2 UNIT KILANG INKUBATOR GMP DI BANDAR TENGGARA
TO COLLECTION 6,620.00
TURFING
TO COLLECTION 1,245.00
COLLECTION
IW/4/6/61
2 UNIT KILANG INKUBATOR GMP DI BANDAR TENGGARA
IW/4/6/62
PUSAT SUKAN UNIVERSITI TUN HUSSEIN ONN MALAYSIA
SITE CLEARANCE
A Clear the areas of the site affected by the proposed works of M2 40,560 2.00 81,120.00
all grass, weeds, shrubs, bushes including grubbing up
roots,cut, fell and remove in bulk all trees irrespective of
diameter and heights all trees including trees unless otherwise
stated except trees marked by the S.O, etc., filling cavities with
surplus excavated material and ramming and removing all
debris off the site, construct all temporary works such as cut
off drains, earth drain, dykes and all other precautionary
measure, etc., incidental or deemed necessary for the proper
execution of the whole contract works and maintain same and
removing on completion as directed by the S.O. (10.0 acres)
B Strip 150mm thick vegetation top soil stockpile to designated M2 40,560 2.00 81,120.00
area by the Employer for re-use and depose of unsuitable
material off site to Contractor's own dump (Approx 10.00
acres)
DEMOLITION WORKS
EARTHWORKS
TO COLLECTION 171,390.00
IW/6/1/63 (R)
PUSAT SUKAN UNIVERSITI TUN HUSSEIN ONN MALAYSIA
EARTHWORKS...(Cont'd)
A Provide for all temporary works required for the carrying out of ITEM 5,000.00
the earthworks out such as cut-off drains, earth drains, bunds,
dykes, and all other precautionary measures, dewatering etc
and including make good land slips erosions and subsidences
as may be required as directed by the S.O.incidental or
deemed necessary for the proper execution of the whole
contract works and maintain same for the duration of the
contract and removal including making good all existing works
disturbed at the end of the contract period .
C Allow for approved imported material for platform surcharge M3 29,022 10.00 290,220.00
including all necessary levelling, temporary works and carting
away all in accordance to Engineer's details and instruction
TO COLLECTION 413,720.00
COLLECTION
IW/6/1/64 (R)
PUSAT SUKAN UNIVERSITI TUN HUSSEIN ONN MALAYSIA
Crusher run base in two layers, each layers 135mm thick laid
to required falls and cambers, blinded by quarry waste laterite
or dust, well rolled with a power roller and compacted as
specified
IW/6/2/65
PUSAT SUKAN UNIVERSITI TUN HUSSEIN ONN MALAYSIA
KERB
A Overall size 250mm x 300mm high chamfered top edge on M 1916 35.00 67,060.00
one side (Type A)
C EXTRA OVER for outlet opening size 125mm x 250mm high NO 256 20.00 5,120.00
overall at 7.50m centre
F 100mm wide x 1000mm length x 1700mm gap center line M 710 2.00 1,420.00
IW/6/2/66
PUSAT SUKAN UNIVERSITI TUN HUSSEIN ONN MALAYSIA
TO COLLECTION 254,483.00
TURFING
H Close turfing to slope surfaces including any necessary M2 4,314 4.50 19,413.00
pegging as specified
IW/6/2/67
PUSAT SUKAN UNIVERSITI TUN HUSSEIN ONN MALAYSIA
TO COLLECTION 47,953.00
COLLECTION
IW/6/2/68
PUSAT SUKAN UNIVERSITI TUN HUSSEIN ONN MALAYSIA
IW/6/2/69
UNIVERSITI TUN HUSSEIN ONN MALAYSIA, BATU PAHAT
ELEMENT 3 - WALKWAY
A Supply and lay 80mm thick interlocking paver as described M2 835 65.00 54,275.00
driveway including all necessary excavation, concrete edging,
50mm compacted sand and including make good to all
disturbed works to manufacturer's details colour & pattern to
Architect approval.
EW/4/3/70
UNIVERSITI TUN HUSSEIN ONN MALAYSIA, BATU PAHAT
EW/4/3/71
PUSAT SUKAN UNIVERSITI TUN HUSSEIN ONN MALAYSIA
A Exceeding 1.00m but not exceeding 2.00m deep M3 2,325 8.00 18,600.00
D Edges of slab exceeding 250m not exceeding 500mm high ; M 4,296 17.50 75,180.00
base slab
J Overall size 225mm x 225mm x 225mm to side of drain wall NO 1594 10.00 15,940.00
K 300mm diameter half round channel cast in 600mm length ; laid M 2,148 130.00 279,240.00
to fall all as per Engineer's detail drawing
TO COLLECTION 1,309,378.60
IW/6/4/72 (R)
PUSAT SUKAN UNIVERSITI TUN HUSSEIN ONN MALAYSIA
D Allow for drainage system connection to existing drain or sump ITEM 500.00
including hacking, excavation and make good upon completion
to the S.O. satisfaction
E Test and commission the whole drainage systems as described ITEM 1,000.00
and make good all defects, retest and leave whole in perfect
working order to the satisfaction of the S.O. and the Authorities
(Note : Method of testing shall in accordance with the
S.O/Authority requirement)
IW/6/4/73 (R)
PUSAT SUKAN UNIVERSITI TUN HUSSEIN ONN MALAYSIA
COLLECTION
IW/6/4/74 (R)
PUSAT SUKAN UNIVERSITI TUN HUSSEIN ONN MALAYSIA
IW/6/4/75 (R)
PUSAT SUKAN UNIVERSITI TUN HUSSEIN ONN MALAYSIA
Bedding
D 600mm wide x 250mm deep bedding extending halfway down M3 48 222.00 10,656.00
to sides of pipe
E 300mm diameter ; pipe laid and jointed to falls in trench M 349 250.00 87,250.00
TO COLLECTION 104,466.00
IW/6/5/76 (R)
PUSAT SUKAN UNIVERSITI TUN HUSSEIN ONN MALAYSIA
Manhole
Manhole Cover
IW/6/5/77 (R)
PUSAT SUKAN UNIVERSITI TUN HUSSEIN ONN MALAYSIA
B Allow for testing and cleaning the whole of the sewerage ITEM 1,000.00
system to the requirement of the Local Authorities and
Superintending Officer including arranging all necessary
documents and obtaining the test certificates.
C Allow for testing and inspection by Local Authorities based ITEM 2,000.00
on CCTV method from manhole to manhole, all to the
requirements and approval of Local Authorities
TO COLLECTION 3,699.40
COLLECTION
IW/6/5/78 (R)
PUSAT SUKAN UNIVERSITI TUN HUSSEIN ONN MALAYSIA
IW/6/5/79 (R)
BILL NO. 4 - EXTERNAL WORKS (ALL PROVISO
Rate
Item Description Unit Qty
(RM)
WATER RETICULATION
Excavation not exceeding 2.00m deep and get out, part return, fill
in and ram and remove surplus excavated material to
Contractor's own dump site for :-
B Scour Pipe M 16
D Mass concrete ( Grade 15) as specified thrust block including all M3 264 180.00
necessary formwork and excavation
TO COLLECTION
EW/4/5/80
BILL NO. 4 - EXTERNAL WORKS (ALL PROVISO
Rate
Item Description Unit Qty
(RM)
WATER RETICULATION...Cont'd
C Supply and install 250mm diameter sluice valve including double NO 19 500.00
flanged joints and rubber gaskets
D Supply and install 150mm diameter scour valve including flanged NO 4 550.00
joints and rubber gaskets
E Supply and install with 50mm diameter double air valve at NO 5 250.00
300mm centres including flanged joints and rubber gaskets
F Supply and install 100mm diameter double outlet pillar hydrant NO 1 3,000.00
an including tee off, duck foot, short piece and all necessary
fittings as per authority's requirement.
G Supply and install extra 250mm diameter end cap including all NO 3 350.00
necessary fittings
H Supply and install extra 150mm diameter tee including all NO 5 3,000.00
necessary fittings
J Supply and install extra 150mm diameter 'S' bend at culvert NO 5 150.00
crossing including all necessary fittings, special joints and valves
in accordance to engineer's detail.
EW/4/5/81
BILL NO. 4 - EXTERNAL WORKS (ALL PROVISO
Rate
Item Description Unit Qty
(RM)
TO COLLECTION
WATER RETICULATION...Cont'd
F NO 1 50,000.00
Altitude Valve Chamber overall size 4120mm x 2400mm x
2000mm deep internally constructed of 200mm thick concrete
(grade 25) as specified base reinforced with a layer BRC A6 and
225mm thick reinforced concrete wall, 50mm thick screed,
chequre plate (6mm thick) cover complete with pad lock, 12mm
diameter mild steel bar at 100 centre to centre including all
necessary excavation, formwork, backfill and all as per
Engineer's detail drawing.
Valve Chamber
J Air valve NO 5
EW/4/5/82
BILL NO. 4 - EXTERNAL WORKS (ALL PROVISO
Rate
Item Description Unit Qty
(RM)
TO COLLECTION
WATER RETICULATION...Cont'd
Pipe Marker
Bulk Meter
E Approved 150mm diameter bulk meters hydrant including all the NO 1 3,000.00
necessary pipe fittings, valves, concrete platform, thrust block,
etc, all as shown in Engineer's detail drawing.
F ITEM 4,000.00
Allow for road crossing including cutting of existing premix road
using diamond or other approved method, removal of premix
elements, concrete pavers, kerbs, etc. And make good
replacement of all disturbed works to the existing standard and
condition upon completion to the S.O.'s satisfaction.
G ITEM 7,000.00
Supply labour and materials to construct hot tapping connection
between new and existing main supply pipe including ductile iron
alloy saddle, brass ferrule/off take tee, adaptors, concrete base
slab, reducer, stop cock and all necessary temporary works such
as sheet pile, strutting and including excavation, compacted
backfilling etc. all to the S.O.'s satisfaction.
H Allow for testing, cleaning and disinfecting the whole water ITEM
reticulation system to the requirements of the Local Authorities
and make good all defects.
J Allow for hydraulic test (pressure and leakage) as specified and ITEM
as directed by the S.O
EW/4/5/83
BILL NO. 4 - EXTERNAL WORKS (ALL PROVISO
Rate
Item Description Unit Qty
(RM)
TO COLLECTION
COLLECTION
EW/4/5/84
BILL NO. 4 - EXTERNAL WORKS (ALL PROVISO
Rate
Item Description Unit Qty
(RM)
EW/4/5/85
BILL NO. 4 - EXTERNAL WORKS (ALL PROVISONAL)
Amount
(RM)
47,520.00
398,600.00
588,000.00
5,500.00
6,500.00
1,046,120.00
EW/4/5/86
BILL NO. 4 - EXTERNAL WORKS (ALL PROVISONAL)
Amount
(RM)
6,400.00
6,000.00
9,500.00
2,200.00
1,250.00
3,000.00
1,050.00
15,000.00
750.00
200.00
400.00
EW/4/5/87
BILL NO. 4 - EXTERNAL WORKS (ALL PROVISONAL)
Amount
(RM)
45,750.00
20,000.00
50,000.00
95,000.00
2,000.00
EW/4/5/88
BILL NO. 4 - EXTERNAL WORKS (ALL PROVISONAL)
Amount
(RM)
167,000.00
570.00
120.00
150.00
30.00
3,000.00
4,000.00
7,000.00
EW/4/5/89
BILL NO. 4 - EXTERNAL WORKS (ALL PROVISONAL)
Amount
(RM)
14,870.00
1,046,120.00
45,750.00
167,000.00
14,870.00
EW/4/5/90
BILL NO. 4 - EXTERNAL WORKS (ALL PROVISONAL)
Amount
(RM)
1,273,740.00
EW/4/5/91
BILL NO. 4 - EXTERNAL WORKS ( ALL PROVISIONAL )
Rate Amount
Item Description Unit Qty
(RM) (RM)
GUARD HOUSE
A NO 1 60,000.00 60,000.00
EW/4/6/93
PUSAT SUKAN UNIVERSITI TUN HUSSEIN ONN MALAYSIA
Excavation not exceeding 2.0m deep and get out, part return,
fill in and ram and remove surplus excavated material to
Contractor's own dump site for :-
L Supply and install extra 150mm diameter end cap including all NO
necessary fittings
H Supply and install extra 150mm diameter 'S bend including all NO
necessary fittings.
TO COLLECTION -
IW/6/6/94 (R)
PUSAT SUKAN UNIVERSITI TUN HUSSEIN ONN MALAYSIA
WATER RETICULATION…..(CONT'D)
Valve Chamber
A Sluice valve NO
B Scour valve NO
C Air Valve NO
Pipe Marker
Bulk Meter
IW/6/6/95 (R)
PUSAT SUKAN UNIVERSITI TUN HUSSEIN ONN MALAYSIA
WATER RETICULATION…..(CONT'D)
B Allow for testing, cleaning and disinfecting the whole water ITEM
reticulation system to the requirements of the Local Authorities
and make good all defects.
TO COLLECTION -
COLLECTION
IW/6/6/96 (R)
PUSAT SUKAN UNIVERSITI TUN HUSSEIN ONN MALAYSIA
IW/6/6/97 (R)
BILL NO. 4 - EXTERNAL WORKS ( ALL PROVISIONAL )
SUMMARY
SUM/=W-4/98
BILL NO. 5 - PROVISIONAL SUMS
PROVISIONAL SUM
Signages
PRO/5/100
2 UNIT KILANG INKUBATOR DI BANDAR TENGGARA
SUMMARY OF TENDER
BIL DESCRIPTION PAGE NO AMOUNT (RM)
1 PRELIMINARIES 1 - 52 100,000.00
…………….……………………………………… ……………..………………………………………
(Signature of Tenderer) (Signature of Witness)
Name :……………..……………………………. Name : …………………………………………...
…………….……………………………………… …………….………………………………………
Name and Address of Firm Tendering Name and Address Witness
Date : …………………………... Date : …………………………...
SOT/107(R)
CADANGAN PEMBINAAN TANGKI AIR DI BANDAR MAS, KOTA TINGGI, JOHOR DARUL TAKZIM
SUMMARY OF TENDER
ITEM DESCRIPTION PAGE NO AMOUNT (RM)
……………………………………………………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………………………………………………
............................................................ ............................................................
Signature of Tenderer Signature of Witness
Address : ......................................................................
......................................................................
......................................................
Chop .....................................................................
SOT-1/107
PUSAT SERENTI KOTA TINGGI
ELEMENT 1 - SUBSTRUCTURE
EXCAVATION WORK
BW/3/1/103
PUSAT SERENTI KOTA TINGGI
SUBSTRUCTURE …..Cont'd
J Edges of apron slab ; not exceeding 250mm thick M 132 7.00 924.00
In ground beam
In pilecap
BW/3/1/104
PUSAT SERENTI KOTA TINGGI
TO COLLECTION 110,893.40
SUBSTRUCTURE …..Cont'd
In ground beam
In ground slab
In apron slab
H The Contractor and specialist firm shall guarantee the ITEM 1,000.00
effectiveness of anti-termite treatment for a period of five (5)
years andundertake to carry re-treatment without charge
should infestation of sub-terranean termites occur at any time
during the warranty period
BW/3/1/105
PUSAT SERENTI KOTA TINGGI
TO COLLECTION 100,482.80
SUBSTRUCTURE …..Cont'd
Perimeter Drain
C 230mm diameter half round channel cast in 610mm length M 155 40.00 6,200.00
laid to fall; grouted and pointed in cement and sand (1:3)
including all necessary excavation, formwork, 150mm thick
concrete base (Grade 25), 50mm thick mass concrete
bedding, concrete hunching, 1 layer BRC A10, one brickwall
complete with plastering to all exposed surfaces and forming
bend, stopped end, juctions, weepholes, cascades, etc
TO COLLECTION 10,701.00
COLLECTION:
BW/3/1/106
PUSAT SERENTI KOTA TINGGI
BW/3/1/107