Variance Analysis CW Questions
Variance Analysis CW Questions
Material Variance
Example – 1
Simple case :
In a factory, standard estimates for material for the manufacture of 1,000 units of
Product Zee is 400 kgs at Rs. 2.50 per kg. When 2,000 units of product Zee are
produced it is found that 825 kgs of materials are consumed at Rs. 2.70 per kg.
Calculate material variances.
Original Std – 1000 Actual output – 2000 Std for Actual output-2000
units units units
Qty Price Amount Qty Price Amount Qty Price Amount
400 Rs. 825 2.70 2227.50 (400/1000) Rs. Rs.
kgs 2.50 kg x 2000 = 2.50 2000
800 kgs
For producing 10 units – 4 kgs of B is required. So for producing 1000 units of output
how much B is required = (4/10) x 1000
Example – 2
Modern Tiles Ltd makes plastic tiles of standard size of 6” x 6” x 1/8”. From the
following information you are required to calculate for direct materials:
(i) Cost variance in total;
(ii) Cost variance sub-divided into (a) Price and (b) Usage;
(iii) The usage variance analysed to show (a) mix and (b) yield
A Standard mix of the compound required to produce an output of 20,000 square
feet of tiles with 1/8” thickness is as under:
Direct Material Quantity (kg) Price per kg
A 600 Re. 0.90
B 400 0.65
C 500 0.40
During December, eight mixes were processed and actual materials consumed
were:
Example – 3
Common Brass is an alloy consisting of 70% Copper and 30% Zinc. In melting and
processing it is expected that a 4% loss of metal will occur. Standard prices are
Rs.40,000 per tonne for Copper and Rs. 15,000 per tonne for Zinc. From the
following information calculate (a) MPV (b) MUV (c) MMV (d) MYV and (e) MCV.
Standard Actual
Details
Quantity Rate (Rs.) Quantity Rate (Rs.)
Copper 700 40000 600 50000
Zinc 300 15000 600 10000
Actual Loss 144
Example – 4
Standard Actual
Raw Material Share of Total Cost (Rs. Per Cost (Rs. Per
Quantity (Kg)
input (%) Kg) Kg)
A 40 50 42,000 48
B 30 80 31,000 80
C 20 90 18,000 92
D 10 100 9,000 110
Output obtained for the month 92,000 Kg
Calculate (a) MPV (b) MUV (c) MMV (d) MYV and (e) MCV. Calculate up to two
decimals.
Example – 5
From the following information calculate (a) MCV, (b) MPV and (c) MUV
Example – 6
From the following information calculate (a) MCV, (b) MUV and (c) MPV
Compute the missing data indicated by the question mark from the following:-
Particulars A B
Standard price per unit Rs. 12 Rs. 15
Actual Price per unit Rs. 15 Rs. 20
Standard Input (in Kgs) 50 ?
Actual Input ? 70
Material Price Variance ? ?
Material Usage Variance ? Rs.300 (A)
Material Cost Variance ? ?
Material Mix Variance Rs. 45 (A)
A company produces Product X using raw materials A and B. The standard mix of A
and B is 1:1 and the standard loss is 10% of input. You are required to compute the
missing information indicated by “?” based on the data given below:
Particulars A B Total
Standard price (Rs. per kg) 24 30
Actual Input (kg) ? 70
Actual Output (kg) ?
Actual price (Rs. Per kg) 30 ?
Standard input quantity (kg) ? ?
Yield variance 270 (A)
Mix variance ?
Usage variance ? ? ?
Price Variance ? ? ?
Cost Variance 0 ? 1300(A)
Solution:
Hence Revised Actual quantity should be equal to 110 kgs but in the proportion of 55
and 55 (1 : 1proportion)
SP AP AQ SQ RSQ
A 24 30 40 50 55
B 30 40 70 50 55
110 100 110
Missing Numbers
Following data is extracted from books of A Ltd for the month of Feb 2021.
Solution
RM Cost Variance = SC – AC
2975 = (SQ x SR) – (59825)
Therefore (SQ x SR) = 59825 + 2975 = 62800
If total MCV = 62800 and MCVB = 18000; then MCVA = 62800 – 18000 = 44800
Therefore, Price of A = 44800 / 800 = 56
If MCV = 2975 and MPV = 175; MUV should be 2975 – 175 = 2800 (F)
MUV = (SQ – AQ) SR
A – (800 – 900) x 56 = 5600(A)
B – (600 – AQ) x 30 = ?????
Sum of A + B = 2800 (F); therefore MUVB = 5600 + 2800 = 8400 (F)
Example – 8
Following was the composition of the gang of workers in a factory during a particular
month in one of the production departments. The standard composition of workers
and wage rate per hour were as under:
The standard output of the gang was four units per hour of the product. During the
month the actual composition of the gang and hourly rates paid were as under:
Solution:
Employees Std Act Rate Act Hours Act Hrs Std Hrs Revised
Rate paid Worked Std Hrs
Skilled 20 20 400 376 405 376
Semi-skilled 12 14 600 564 810 752
Unskilled 8 10 1000 940 810 752
2000 hrs 1880 hrs 2025 hrs 1880 hrs
(Actual Hrs worked / Std qty of workers) x Std qty of each category of worker
Example – 9
Two hours were lost in the week due to machine breakdown. Actual
production was 960 units in the week.
Find out (i) Labour rate variance; (ii) Labour mix variance; (iii) Labour idle time
variance; (iv) Labour yield variance; (v) Labour efficiency variance and (vi) Labour
Cost variance.
Solution
S - 7200(A)
SS - 880(F)
US - 2820(F) 3500(A)
S - 1300(F)
SS - 400 (A)
US - 300 (F) 1200 (F)
S - 8500 (A)
SS - 1280 (F)
US - 2520 (F) 4700(A)
S - 1625 (A)
SS - 320 (A)
US - 210 (A) 2155(A)
S - 250 (F)
SS - 80(F)
US - 70(F) 400(F)
S - 7125(A)
SS - 1520(F)
US - 2660(F) 2945(A)
Example – 10
In a factory, 100 workers are engaged and average rate of wages is Rs. 5 per hour.
Std working hours per week are 40 hours and the standard output is 10 units per
hour. During a week in December, wages were paid for 50 workers @ Rs. 5 per
hour, 10 workers @ Rs. 7 per hour and 40 workers @ Rs. 4 per hour. Actual output
was 380 units, The factory did not work for 5 hours due to breakdown on machinery.
Calculate Labour cost variance, Labour rate variance, Labour efficiency variance and
Idle time variance.
Example – 11
Standard hours for producing two products A and B are 15 hours and 20 hours per
unit respectively. Both products require identical type of labour and the standard
wage rate is Rs. 5 per hour. In a year 10,000 units of A and 15,000 units of B were
produced. The total labour hours actually worked were 4,50,500 and actual wage bill
came to Rs. 23,00,000. This included 12,000 hours paid for at Rs. 7 per hour and
9,400 hours paid for @ Rs. 7.50 per hour; the balance having been paid @ Rs. 5 per
hour.
You are required to compute Labour Cost variance, labour rate variance and labour
efficiency variance.
Example – 12
SB Ltd operates a system of standard costing. For one unit of product the std
material input is 20 liters at a std price of Rs. 2 per liter. The std wage rate is Rs. 6
per hour and 5 hours are allowed to produce one unit. Fixed production overhead is
absorbed at the rate of 100% of direct wages cost.
During the month just ended the following occurred:
Actual price paid for purchase of material - Rs. 1.95 per liter
Total direct wages cost - Rs. 1,56,000
Fixed production overhead incurred - Rs. 1,58,000
Required :-
(i) Budgeted output in units
(ii) Number of liters purchased
(iii) Number of liters used above standard allowed
(iv) Actual units produced
(v) Actual hours worked
(vi) Actual wage rate per hour
Example – 13 (a)
Discuss if Actual hours of 4,500 includes 300 hours of Abnormal Idle Time. Budgeted
hour= 20(std)
Example – 13 (b) *300= 6000
SR=
Calculate Variable Overhead variances from the following information: 7800/6000
Example – 14
From the following information of GSN Ltd., calculate variable overhead variances
Example – 15
Following information was obtained from the records of a manufacturing unit using
standard costing system.
Standard Actual
Production 4,000 units 3,800 units
Working days 20 21
Machine hours 8,000 hours 7,800 hours
Fixed overhead Rs.4,00,000 Rs. 3,90,000
Variable overhead Rs. 1,20,000 Rs. 1,20,000
You are required to calculate the following Actual foh= 390000; Budgeted foh= 400000;
(a) Fixed overhead variances Bud Adj= 400000/20*21 (for days)
Bud Adj for time= 400000/8000*7800
Bud Adj for output= 400000/4000*3800
(b) Variable overhead variances
Example – 16 (a)
In department X of a plant, the following data are submitted for a particular week:
Standard output for 40 hours per week 1,400 units
Budgeted Fixed Overhead ₹ 1,400 Actual foh= 1500; budgeted
Actual Output 1,200 units foh=1400;
Actual hours worked 32 Bud adj for days= 1400/0=0
Actual Fixed Overhead ₹ 1,500 Bud adj for time= 1400/40*32
Calculate variances Bud adj for output=
1400/1400*1200
Example – 16 (b)
Eajjie Ltd has furnished the following information for the month of August
Budget Actual
Output (Units) 30,000 32,500
Hours 30,000 33,000
Fixed Overhead (₹) 45,000
Variable overhead (₹) 60,000
Total Factory Overhead (₹) --- 1,12,500
Homework
A company operates a standard costing system and showed the following data for a
particular month:
Actual Budgeted
No of working days 22 20
Man-hours 4,300 4,000
Overhead rate per hour ---- ₹ 0.50
Hours per unit of output ----- 10
Fixed overhead incurred ₹ 1,800 -----
No of units produced 425 ----
Calculate (a) Overhead cost variance (b) Budget/Expenditure Variance (c) Volume
Variance (d) Capacity Variance (e) Calender Variance and (f) Efficiency Variance
[Ans – (a) 325 (F); (b) 200 (F); (c) 125 (F); (d) 50(A); (e) 200 (F); (f) 25(A)]
Example – 17
From the following information calculate (i) Total Sales Variance; (ii) Sales Price
Variance; (iii) Sales Volume Variance; (iv) Sales Mix Variance and (v) Sales Qty
Variance.
Standard Actual
Product
Units Rate (Rs) Units Rate (Rs)
A 5000 5 6000 6
B 4000 6 5000 5
C 3000 7 4000 8
Example : Class Practice
Standard Actual
Product
Units Rate (Rs) Units Rate (Rs)
X 600 10 650 9
Y 400 15 450 13
Example – 18
A Company uses standard costing system. The sales data for a particular period are
as under:
Compute the missing data indicated by the question marks from the following:
Sales Mix variance for both the products together was Rs. 450 (F).