Untitled
Untitled
ABC Carpentry Workshop produces a product called “chair’ which passes through three
processes A, B and C. During October 2021, the following took place in that company.
Process A - data
- 12,000 kg of material 1 were injected into the production process and each kg was valued
at Shs. 6,500/=
- Direct labour cost was 8,500 labour hours used in the production process and each hour
was at Shs 3,500/=
- Actual output turned out to be 9,500 units.
- Process loss was scrapped at Shs. 6,000/= per unit and was paid for by cheque.
Process B - data
- 4,000 kg of materials were added to the production process and each kg was valued at
Shs. 7,000/=
- Direct labour amounted to Shs. 14,000,000 (14m)/=
- Actual output turned out to be 10,500 units and the process loss was scrapped at Shs.
9,000/= per unit.
Process C –data
- Additional materials totaling 1,000 kg valued at Shs. 5,000/= per kg were introduced in
the production process.
- Direct labour amounted to Shs. 12,000,000
- Actual output was 11,500 units while process loss was scrapped at Shs. 9,000/= per unit.
Additional information
Required;
Question 2
a) Poly fibre Ltd located in Namanve produces customized polythene bags used by different
manufacturers to pack their products. The following information relates to the month of
April 2019:
- Production 40,000 polythene bags
- sales 30,000 polythene bags
Item Ugx
Production costs:
Required: