PRODUCTIVITY RATES FOR FORMWORKS

Item No. CREW SIZE Hourly Production


Production Rate Per 8 hrs.
Square Meters Square Meters
FW FORMWORK
FW01 Formwork to footings 2 CARPENTERS, 1 HELPER 1.2 sq.m per day 9.6 sq.m per day
FW02 Formwork to isolated footings 2 CARPENTERS, 1 HELPER 1.6 sq.m per day 12.8 sq.m per day
FW03 Formwork to rafts 2 CARPENTERS, 1 HELPER 1.4 sq.m per day 11.2 sq.m per day
FW04 Formwork to rafts D>0.75m 2 CARPENTERS, 1 HELPER 1.8 sq.m per day 14.4 sq.m per day
FW05 Formwork to tie beams 2 CARPENTERS, 1 HELPER 1.0 sq.m per day 8 sq.m per day
FW06 Formwork to high level tie beams D>0.45M 2 CARPENTERS, 1 HELPER 1.2 sq.m per day 9.6 sq.m per day
FW07 Formwork to Neck Columns 2 CARPENTERS, 1 HELPER 4 sq.m per day
FW08 Formwork to U/G Water tank 2 CARPENTERS, 1 HELPER 6 sq.m per day
FW09 Formwork to basement retaining walls 2 CARPENTERS, 1 HELPER 9 sq.m per day
FW10 Formwork to columns (small size) 2 CARPENTERS, 1 HELPER 7 sq.m per day
FW11 Formwork to Columns (large size) 2 CARPENTERS, 1 HELPER 9 sq.m per day
FW12 Formwork to D/S beam internal (shallow) 2 CARPENTERS, 1 HELPER 6 sq.m per day
FW13 Formwork to D/S beam external (Deep) 2 CARPENTERS, 1 HELPER 7 sq.m per day
FW14 Formwork to D/S beam external (Shallow) 2 CARPENTERS, 1 HELPER 4 sq.m per day
FW15 Formwork to D/S beam external (Deep) 2 CARPENTERS, 1 HELPER 6 sq.m per day
FW16 Formwork to lift walls single core 2 CARPENTERS, 1 HELPER 6 sq.m per day
FW17 Formwork to lift walls multi core 2 CARPENTERS, 1 HELPER 8 sq.m per day
FW18 Formwork to slab decking (10ft) hourdi 2 CARPENTERS, 1 HELPER 1.6 sq.m per day 12.8 sq.m per day
FW19 Formwork to slab decking (>10ft) hourdi D/S beams 2 CARPENTERS, 1 HELPER 1.2 sq.m per day 9.6 sq.m per day
FW20 Formwork to slab decking (>10ft) hourdi 2 CARPENTERS, 1 HELPER 1.2 sq.m per day 9.6 sq.m per day
FW21 Formwork to slab decking (>10ft) hourdi 2 CARPENTERS, 1 HELPER 1.0 sq.m per day 8 sq.m per day
FW22 Formwork to staircase (non spiral) 2 CARPENTERS, 1 HELPER 4 sq.m per day
FW23 Formwork to balcony parapets 2 CARPENTERS, 1 HELPER 6 sq.m per day
FW24 Formwork to roof parapets 2 CARPENTERS, 1 HELPER 8 sq.m per day

D = DEPTH
U. GR. = UNDERGROUND
D/S = DECK - SLAB
> = GREATER THAN
< = LESS THAN

PRODUCTIVITY RATES FOR FOWMWORKS

Item No. CREW SIZE Hourly Production


Production Rate Per 8 hrs.
FW 25 shutter Manufacture for pile caps 1 CARPENTER + 1 HELPER 2 sq.m per hour 16 sq.m per day
FW 26 shutter Fix for pile caps I CARPENTER + 1 HELPER 1.5 sq.m per hour 12 sq.m per day
FW 27 Deshutter footings/pile caps 1 HELPER 6 sq.m per hour 48 sq.m per day
FW 28 Shutter make column necks 1 CARPENTER + 1 HELPER 1.5 sq.m per hour 12 sq.m per day
FW 29 Shutter fix column necks 1 CARPENTER + 1 HELPER 1.2 sq.m per hour 9.6 sq.m per day
FW 30 Deshutter Column necks 1 HELPER 4.8 sq.m per hour 38.4 sq.m per day
FW 31 Shutter make tie beams 1 CARPENTER + 1 HELPER 1.2 sq.m per hour 9.6 sq.m per day
FW 32 shutter fix tie beams 1 CARPENTER + 1 HELPER 1 sq.m per hour 8 sq.m per day
FW 33 Column shutter making 1 CARPENTER + 1 HELPER 1.2 sq.m per hour 9.6 sq.m per day
FW 34 Column shutter fixing 1 CARPENTER + 1 HELPER 1 sq.m per hour 8 sq.m per day
FW 35 Column deshuttering 1 HELPER 4 sq.m per hour 32 sq.m per day
FW 36 Walls shutter making 1 CARPENTER + 1 HELPER 1.5 sq.m per hour 12 sq.m per day
FW 37 Walls shutter fixing 1 CARPENTER + 1 HELPER 0.8 sq.m per hour 6.4 sq.m per day
FW 38 De shutter Tie beam shutter 1 HELPER 4 sq.m per hour 32 sq.m per day
FW 39 Wall formwork deshuttering 1 HELPER 3.2 sq.m per hour 25.6 sq.m per day
FW 40 Staircase formwork making 1 CARPENTER + 1 HELPER 0.8 sq.m per hour 6.4 sq.m per day
FW 41 staircase formwork fixing 1 CARPENTER + 1 HELPER 0.8 sq.m per hour 6.4 sq.m per day
FW 42 Staircase formwork deshuttering 1 HELPER 1.6 sq.m per hour 12.8 sq.m per day
FW 43 Drop beams formwork making 1 CARPENTER + 1 HELPER 1 sq.m per hour 8 sq.m per day
FW 44 Drop beams formwork fixing 1 CARPENTER + 1 HELPER 0.8 sq.m per hour 6.4 sq.m per day
FW 45 Drop beams formwork stipping 1 HELPER 3.2 sq.m per hour 25.6 sq.m per day
FW 46 suspended slab formwork fixing 1 CARPENTER + 1 HELPER 1.2 sq.m per hour 9.6 sq.m per day
FW 47 suspended slab formwork deshutter 1 HELPER 5 sq.m per hour 40 sq.m per day
FW 48 Formwork fixing for sunshades 1 CARPENTER + 1 HELPER 0.7 sq.m per hour 5.6 sq.m per day
FW 49 Parapet formwork making 1 CARPENTER + 1 HELPER 1.2 sq.m per hour 9.6 sq.m per day
FW 50 Parapets formwork fixing 1 CARPENTER + 1 HELPER 1 sq.m per hour 8 sq.m per day
FW 51 Parapets formwork stripping 1 HELPER 4 sq.m per hour 32 sq.m per day
FW 53 Fixing of lintle formwork 1 CARPENTER + 1 HELPER 0.5 sq.m per hour 4 sq.m per day
FW 54 Deshutter lintle formwork 1 HELPER 2 sq.m per hour 16 sq.m per day
FW 55 Deck formwork fixing 1 CARPENTER + 1 HELPER 1.5 sq.m per hour 12 sq.m per day
FW 56 Deck Formwork deshuttering 1 HELPER 6 sq.m per hour 48 sq.m per day
FW 57 Pipe scaffolding erection for slab 1 SCAFFOLDER 0.85 sq.m per hour 6.8 sq.m per day
FW 58 inverted beam shutter fixing 1 CARPENTER + 1 HELPER 1 sq.m per hour 8 sq.m per day
FW 59 De-Shuttering Manholes, square - circular (Timber) 1 CARPENTER + 1 HELPER 4 sq.m per hour 32 sq.m per day
FW 60 Manhole Shutter erection - square or circular(Timber) 1 CARPENTER + 1 HELPER 1.5 sq.m per hour 12 sq.m per day
FW 61 Metal Shutter for Manholes 1 CARPENTER + 1 HELPER 1 sq.m per hour 8 sq.m per day
FW 62 Metal Shutter for Precast Beams 2 CARPENTERS + 2 HELPERS 3 sq.m per hour 24 sq.m per day
FW 63 Metal Shutter for Pile caps 2 CARPENTERS + 2 HELPERS 3 sq.m per hour 24 sq.m per day
FW 64 Metal Shutters for Pile cap Beams 2 CARPENTERS + 2 HELPERS 3 sq.m per hour 24 sq.m per day